Letter Sequence Withholding Request Acceptance |
|---|
EPID:L-2018-LLA-0048, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information (Open) |
Initiation
- Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting
|
MONTHYEARML18079B1402018-02-23023 February 2018 Browns Ferry Nuclear Plant, Units 1, 2, and 3: Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus Project stage: Request CNL-18-042, Proposed Technical Specifications Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus, Supplement 12018-03-0707 March 2018 Proposed Technical Specifications Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus, Supplement 1 Project stage: Supplement ML18059A1072018-03-16016 March 2018 Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Request ML18088A0252018-04-0606 April 2018 Acceptance Review Regarding Proposed Expanded Maximum Extended Load Line Limit Analysis Plus (Mellla+) Project stage: Acceptance Review ML18101A1012018-04-13013 April 2018 Summary of March 16, 2018, Meeting with Tennessee Valley Authority Regarding a License Amendment Request to Implement Maximum Extended Load Line Limit Analysis Plus for Browns Ferry Nuclear Plant Project stage: Meeting CNL-18-099, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 2, Operator Training Results2018-07-23023 July 2018 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 2, Operator Training Results Project stage: Supplement ML18268A0212018-09-27027 September 2018 Regulatory Audit Plan in Support of Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Other ML18317A1642018-11-20020 November 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - Non-Proprietary Project stage: RAI ML18331A5442018-12-0606 December 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - (Non-Proprietary) Project stage: RAI CNL-18-140, Response to Request for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 42018-12-13013 December 2018 Response to Request for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 4 Project stage: Supplement CNL-18-111, Triennial Decommissioning Funding Plans for Independent Spent Fuel Storage Installations (Isfsis)2018-12-13013 December 2018 Triennial Decommissioning Funding Plans for Independent Spent Fuel Storage Installations (Isfsis) Project stage: Request CNL-18-139, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information2018-12-14014 December 2018 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information Project stage: Request CNL-19-007, Response to Requests for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus2019-01-16016 January 2019 Response to Requests for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus Project stage: Response to RAI CNL-19-011, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 6, Additional Operator Training Results2019-01-16016 January 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 6, Additional Operator Training Results Project stage: Supplement CNL-19-017, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 7, Response to Requests for Additional Information2019-01-25025 January 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 7, Response to Requests for Additional Information Project stage: Supplement ML19067A0262019-03-0707 March 2019 Notice of Forthcoming Closed Meeting with Tennessee Valley Authority (TVA) and General Electric-Hitachi (Geh), Regarding Maximum Extended Load Line Limit Analysis Plus (Mella+) License Amendment Request (LAR) for Browns Ferry Nuclear Plant, Project stage: Meeting CNL-19-032, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 8, Additional Operator Training Information2019-03-13013 March 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 8, Additional Operator Training Information Project stage: Supplement CNL-19-045, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 9, Additional Information Regarding Anticipate Transient Without Scram with .2019-04-24024 April 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 9, Additional Information Regarding Anticipate Transient Without Scram with . Project stage: Supplement ML19121A2242019-06-0606 June 2019 Non-Proprietary - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Summary Report for the Audits in Support of License Amendment Request for Operation in the Expand Maximum Extended Load Line Limit Analysis Plus Operating Domain Project stage: Other ML19120A2882019-06-0606 June 2019 Summary of March 19, 2019, Closed Meeting with Tennessee Valley Authority a License Amendment Request to Implement Maximum Extended Line Limit Analysis Plus Project stage: Meeting ML19136A3282019-07-22022 July 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A1342019-07-22022 July 2019 Request for Additional Information from Public Disclosure Project stage: RAI ML19163A0802019-07-22022 July 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19163A1652019-08-0505 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19135A5572019-08-26026 August 2019 Request for Withholding Information from Public Disclosure (EPID L-2018-LLA-00488) Project stage: Withholding Request Acceptance ML19133A1192019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A0582019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A2542019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A2782019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance CNL-19-125, Proposed Technical Specifications (TS) Change 510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 12, Additional License Condition2019-12-19019 December 2019 Proposed Technical Specifications (TS) Change 510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 12, Additional License Condition Project stage: Supplement 05000260/LER-2019-001-01, Traversing In-core Probe Purge Header Check Valve Leak Rate in Excess of Technical Specifications Limits2019-12-19019 December 2019 Traversing In-core Probe Purge Header Check Valve Leak Rate in Excess of Technical Specifications Limits Project stage: Request ML19210C3082019-12-26026 December 2019 Redacted - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Issuance of Amendment Nos. 310, 333, and 293 Regarding Maximum Extended Load Line Limit Analysis Plus Project stage: Approval ML19360A0442019-12-30030 December 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2019-01-16
[Table View] |
Text
Mr. Joseph W. Shea Vice President, Nuclear Regulatory Affairs and Support Services Tennessee Valley Authority Browns Ferry Nuclear Plant 1101 Market Street, LP 4A Chattanooga, TN 37402-2801 UNITED STATES WASHINGTON, D.C. 20555-0001 August 26, 2019
SUBJECT:
BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (EPID L-2018-LLA-0048)
Dear Mr. Shea:
By letter to the U.S. Nuclear Regulatory Commission (NRC), dated February 23, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML180798140), Tennessee Valley Authority (TVA) submitted an affidavit dated February 12, 2018, executed by Mr. Neil Wilmshurst, Vice President and Chief Nuclear Officer at Electric Power Research Institute, Inc. (EPRI), requesting that the information contained in the following document (Attachment 5 of the letter dated February 23, 2018) be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations ( 10 CFR), Part 2, Section 2.390:
GEH Report NEDC-33877P, "Safety Analysis Report for Browns Ferry Nuclear Plant Units 1, 2, and 3 Maximum Extended Load Line Limit Analysis Plus,"
Revision 0, dated February 2018.
A nonproprietary copy of this document is provided in the Attachment 6 of the TVA letter dated February 23, 2018.
The EPRI affidavit dated February 12, 2018, stated that the submitted document contains proprietary information that that should be considered exempt from mandatory public disclosure on the following bases:
Withholding Based Upon Privileged And Confidential Trade Secrets Or Commercial Or Financial Information (see e.g., 10 C.F.R. § 2.390(a)(4):
- a.
The Proprietary Information is owned by EPRI and has been held in confidence by EPRI. All entities accepting copies of the Proprietary Information do so subject to written agreements imposing an obligation upon the recipient to maintain the confidentiality of the Proprietary Information. The Proprietary Information is disclosed only to parties who agree, in writing, to preserve the confidentiality thereof.
J.Shea
- b.
C.
- d. EPRI considers the Proprietary Information contained therein to constitute trade secrets of EPRI. As such, EPRI holds the Information in confidence and disclosure thereof is strictly limited to individuals and entities who have agreed, in writing, to maintain the confidentiality of the Information.
The information sought to be withheld is considered to be proprietary for the following reasons. EPRI made a substantial economic investment to develop the Proprietary Information and, by prohibiting public disclosure, EPRI derives an economic benefit in the form of licensing royalties and other additional fees from the confidential nature of the Proprietary Information. If the Proprietary Information were publicly available to consultants and/or other businesses providing services in the electric and/or nuclear power industry, they would be able to use the Proprietary Information for their own commercial benefit and profit and without expending the substantial economic resources required of EPRI to develop the Proprietary Information.
EPRl's classification of the Proprietary Information as trade secrets is justified by the Uniform Trade Secrets Act which California adopted in 1984 and a version of which has been adopted by over forty states. The California Uniform Trade Secrets Act, California Civil Code §§3426 -
3426. 11, defines a "trade secret" as follows:
'"Trade secret' means information, including a formula, pattern, compilation, program device, method, technique, or process, that:
(1) Derives independent economic value, actual or potential, from not being generally known to the public or to other persons who can obtain economic value from its disclosure or use; and (2) Is the subject of efforts that are reasonable under the circumstances to maintain its secrecy."
- e.
The Proprietary Information contained therein are not generally known or available to the public. EPRI developed the Information only after making a determination that the Proprietary Information was not available from public sources. EPRI made a substantial investment of both money and employee hours in the development of the Proprietary Information. EPRI was required to devote these resources and effort to derive the Proprietary Information. As a result of such effort and cost, both in terms of dollars spent and dedicated employee time, the Proprietary Information is highly valuable to EPRI.
- f.
A public disclosure of the Proprietary Information would be highly likely to cause substantial harm to EPRl's competitive position and the ability of EPRI to license the Proprietary Information both domestically and internationally. The Proprietary Information can only be acquired and/or duplicated by others using an equivalent investment of time and effort.
J.Shea We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, based on the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
Docket Nos. 50-259, 50-260, and 50-296 cc: Neil Wilmshurst, Vice President and Chief Nuclear Officer Electric Power Research Institute 1300 W WT Harris Blvd.
Charlotte, NC 28262 Listserv Sincerely, Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
ML19136A058 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LAiT NAME FSaba KEntz DATE 06/24/19
OFFICE NRR/DSS/SRXB/BC(A)
NRR/DORL/LPL2-2/BC NAME JBorromeo UShoop DATE 07/26/19 08/23/19 NRR/DORL/LPL2-2/LA BClayton (JBurkhardt for) 06/24/19 NRR/DORL/LPL2-2/PM FSaba 08/26/19