PROPOSED PROJECT PLAN FOR TASK 3 Project Objective:
Develop or enhance U.S. Nuclear Regulatory Commissions (NRCs) internal regulatory framework to accommodate Nuclear Energy Institute (NEIs) alternative proposal on newly developed methods (modified as necessary to meet staff expectations).
Key deliverables that need to be completed prior to end of FY 2019 A. NRC; Generate a document that articulates the regulatory frame work supporting risk-informed initiatives (50.69, Tech Spec 4b, Tech Spec 5b, National Fire Protection Association (NFPA) 805) which enables licensees to self-approve changes to engineering and operation programs. (NRC Action)
B. Develop formal document that that articulates how NRC staff will determine acceptability of newly-developed methods provided to NRC via the NEIs or Owners Groups proposed processes. (NRC Action, Industry will have opportunities to provide feedback via public meetings\\calls)
C. Create process\\training\\communications to Division of Operating Reactor Licensing (DORL) and Region to ensure awareness of the new process that the Division of Risk Assessment (DRA) receive timely notifications upon receiving industry reports on probabilistic risk assessment (PRA) upgrades that include newly developed method (NRC Action. Industry will be kept informed. We will not seek feedback).
D. Language for Admin Section of Tech Spec. This language will be incorporated to a formal document approved by NRC. Licensees who wish to depart from Tech Spec 2.2.2.e of TATF-505 should incorporate this language (by reference, if appropriate) to their Admin Tech Spec (similar to Tech Spec 5b). (Industry Action, NRC will be providing feedback via public meetings\\calls)
E. Develop inputs to IMC-612 (example of minor and more-than minor violations). (NRC Action, Industry will be kept informed).
Longer-Term Deliverables to support the framework Enhance Reactor Oversight Process (ROP) frame work (inspection procedure, supporting guidance documents) to address needs of newly-developed methods as well as need of other Region IIs that enables licensees to self-approve programs.
Risks: Receiving agency alignment (NRR\\DORL, NRR\\DSS\\Tech Spec Branch, NRR\\DIRS, Regionsl, NRR\\DLP, OGC to products created by NRR\\DRA staff)
Task Due Date Deliverable\\Process Remarks\\Responsibility 1
Provide NRCs initial view on characteristics that industry should consider to develop Deliverable 1/4/2019 Email to NEI. Email will be captured into public ADAMS Responsibility: NRC 2
Generate a document that articulates the regulatory frame work supporting risk-informed 1/15/2019 Memo from NRRs Senior Level Advisor in PRA to DRA Division Director Responsibility: NRC
initiatives (50.69, Tech Spec 4b, Tech Spec 5b, NFPA 805) which enables licensees to self-approve changes to engineering and operation programs.
3 Draft a document that articulates how NRC staff will determine acceptability of newly-developed methods (review criteria, timing, etc..).
1/29/2019 An Expectation Memo from DRA Division Director to staff or an Office Instruction Responsibility; NRC Industry will be provided opportunities to comment.
NRC will finalize this document after incorporating industry comments.
4 Draft language for Admin Section of Tech Spec (that an industry document should include for NRC staff approval.)
1/29/2019 Draft proposal from NRC to industry Responsibility: NEI/Industry When finalized and included in an NRC document, future applicants (or applicant who have already submitted LARs for tech Spec 4b as well those who have received SEs) may request for a departure from TSTF Section 2.2.2.e by committing to this TS admin change.
5 Receive internal alignment (management, OGC) endorsement for the Items (2) &
(3) above 3/15/2019 Transmit draft documents on Items (2) and (3) above to NEI and Owners Group representative NRC 5
Hold one or more public meeting to receive industry feedback 4/26/2019 Public meeting NRC. NEI, Owners Groups 6
Industry uses input provided in Item (3) by NRC to draft document for NRC approval and NRC uses industry feedback to revise NRC document.
5/24/2019 NEI Owners Groups NRC 7
Develop regional and DORL interfaces necessary implement proposal 5/24/2019 Communication\\s from NRR\\DRA to NRR\\DORL NRC 8
Prepare inputs to IMC-612 to support implementation of NEI alternative in the ROP 5/24/2019 Communications\\s from NRR\\DRA to NRR\\DIRS NRC 9
Issue SE for the document the document that industry will use to seek departure from TSTF 505 6/24/2019 NRC