Letter Sequence RAI |
|---|
CAC:MF3829, (Approved, Closed) EPID:L-2014-TOP-0004, Final Safety Evaluation for Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Approved, Closed) |
|
MONTHYEARML17356A2372017-05-25025 May 2017, 10 January 2018 Audit Report for the May 16 to May 18, 2017 Audit in Support of the Review of ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Non-proprietary Version) Project stage: Request ML17356A2542017-05-25025 May 2017 Trip Report for May 16 to May 18, 2017, Audit in Support of the Review of Topical Report ANP-10332P (AURORA-B LOCA) (Non-Proprietary Version) Project stage: Other ML19095B7612017-10-24024 October 2017 Request for Additional Information Regarding Areva Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios Project stage: Request ML19095B7642017-10-24024 October 2017 Transmittal of Request for Additional Information Regarding Areva Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Set 1, Non-Proprietar Project stage: RAI ML19095B7672017-10-24024 October 2017 Request for Additional Information Regarding Areva Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Set 1, Non-Proprietary) Project stage: RAI ML17356A2502018-01-10010 January 2018 NRC Staff Post-Acceptance Review Feedback and Questions, Areva'S Response Approach, and Subsequent NRC Staff Audit Comments for May 16 to May 18, 2017 Audit Supporting the Review of ANP-10332P (AURORA-B LOCA) Project stage: Acceptance Review ML17356A2472018-01-10010 January 2018 Audit Report for the May 16 to May 18, 2017 Audit in Support of the Review of ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Non-Proprietary Version) Project stage: Approval ML17356A2432018-01-10010 January 2018 Transmittal of Audit Report for the May 16 to May 18, 2017 Audit in Support of the Review of ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Non-Proprietar Project stage: Approval ML19095B7692018-01-19019 January 2018 Request for Additional Information Regarding Areva Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Set 2) Project stage: Request ML19095B7702018-01-19019 January 2018 Transmittal of Request for Additional Information Regarding Areva Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Set 2, Non-Proprietar Project stage: RAI ML17360A2072018-01-19019 January 2018 Transmittal of Request for Additional Information Regarding Areva Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios Project stage: RAI ML19095B7732018-01-19019 January 2018 Request for Additional Information Regarding Areva Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Set 2, Non-Proprietary) Project stage: RAI ML18122A2302018-04-30030 April 2018 ANP-10332Q1NP, Rev 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios Responses to NRC Request for Additional Information Project stage: Response to RAI ML18122A2292018-04-30030 April 2018 Framatome, Inc., Response to Request for Additional Information Regarding Topical Report ANP-10332P, Revision 0, AURORA-8: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios Project stage: Response to RAI ML18171A3082018-07-17017 July 2018 Request for Withholding Information from Public Disclosure in April 30, 2018, Response to Request for Additional Information Regarding Topical Report ANP-10332P, Revision 0 (CAC No. MF3829; EPID L-2014-TOP-0004) Project stage: RAI ML18242A4262018-08-31031 August 2018 Draft Safety Evaluation for Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios, (Non-Proprietary) Project stage: Draft Approval ML18323A5592018-12-18018 December 2018 Request for Withholding Information from Public Disclosure in October 31, 2018, Revised Response to Request for Additional Information Regarding Topical Report ANP-10332P, Revision 0 Project stage: RAI ML19052A5722019-03-26026 March 2019 Final Safety Evaluation for Framatome, Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios (Non-Proprietary Version) Project stage: Approval ML19057A5552019-03-26026 March 2019 Transmittal of Final Safety Evaluation for Framatome Inc. Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios. Project stage: Approval ML19057A5512019-03-26026 March 2019 Final Safety Evaluation for Topical Report ANP-10332P, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios Project stage: Request ML19071A2952019-03-26026 March 2019 Resolution of Comments on Draft Safety Evaluation for Topical Report ANP-10332P, Revision 0 Project stage: Draft Approval ML19183A0102019-07-25025 July 2019 Verification Review Letter for Topical Report ANP-10332P-A, Revision 0, AURORA-B: an Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios Project stage: Other 2018-12-18
[Table View] |
Text
December 18, 2018 Mr. Gary Peters, Director Licensing and Regulatory Affairs Framatome, Inc.
3315 Old Forest Road Lynchburg, VA 24501
SUBJECT:
REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE IN OCTOBER 31, 2018, REVISED RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING TOPICAL REPORT ANP-10332P, REVISION 0, AURORA-B: AN EVALUATION MODEL FOR BOILING WATER REACTORS; APPLICATION TO LOSS OF COOLANT ACCIDENT SCENARIOS (CAC NO. MF3829; EPID L-2014-TOP-0004)
Dear Mr. Peters:
By letter dated October 31, 2018 (Agencywide Documents Access and Management System Accession (ADAMS) Accession No. ML18309A246), Framatome Inc. (Framatome) submitted an October 31, 2018, affidavit executed by Alan B. Meginnis, Product Licensing Manager. The affidavit requested that the information contained in the revised response to the U.S. Nuclear Regulatory Commission (NRC) staff request for additional information regarding Topical Report ANP-10332P, Revision 0, be withheld from public disclosure under Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Hearing Requests, Petitions to Intervene, Requirements for Standing, and Conditions.
A nonproprietary copy of the response has been placed in the NRC Public Document Room and added to the NRC Library in ADAMS as Accession No. ML18309A248.
The Framatome affidavit detailed the reasons for withholding the information.
The NRC staff has reviewed the Framatome application and the material in accordance with the requirements of 10 CFR 2.390. On the basis of the statements in the affidavit, the NRC staff has determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure under 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, the NRC staff may send copies of this information to its consultants working in this area. The agency will, of course, ensure that the NRC staff consultants have signed the appropriate agreements for handling proprietary information.
G. Peters If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC.
You also should understand that the NRC staff may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC staff makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I can be reached at 301-415-4053 or via e-mail at Jonathan.Rowley@nrc.gov.
Sincerely,
/RA/
Jonathan G. Rowley, Project Manager Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation Docket No. 99902041
ML18323A559 *concurred via email NRR-106 OFFICE NRR/DLP/PLPB/PM NRR/DLP/PLPB/LA* NRR/DSS/SNPB/BC NAME JRowley DHarrison RLukes DATE 11/19/2018 12/4/2018 12/18/2018 OFFICE NRR/DLP/PLPB/BC NRR/DLP/PLPB/PM NAME DMorey JRowley DATE 12/18/2018 12/18/2018