UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, IL 60532-4352
March 29, 2017
Mr. Bryan C. Hanson
Senior VP, Exelon Generation Company, LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2 - REQUEST FOR INFORMATION
FOR AN NRC DESIGN BASES ASSURANCE INSPECTION (PROGRAM):
IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM
INSPECTION REPORT 05000373/2017008; 05000374/2017008
Dear Mr. Hanson:
On June 26, 2017, the U.S. Nuclear Regulatory Commission (NRC) will begin a triennial
baseline Design Bases Assurance Inspection (Program) at the LaSalle County Station,
Units 1 and 2. This inspection will be performed in accordance with NRC Baseline
Inspection Procedure 71111.21N, Attachment 1.
The Design Bases Assurance Inspection will focus on the implementation of the electrical
equipment environmental qualification (EQ) program to verify you are maintaining the qualified
status of equipment during the life of the plant. The EQ components to be reviewed during this
baseline inspection will be identified during the inoffice preparation week that occurs prior to the
onsite inspection week.
The inspection will include a bagman trip to support selection of components and 2 weeks of
onsite inspection. The inspection team will consist of three NRC inspectors. The current
inspection schedule is as follows:
Bagman trip onsite week:
June 5, 2017
Preparation week:
June 19 - 23, 2017
Onsite inspection weeks:
June 26 - 30, 2017; and
July 10 - 14, 2017.
Experience with previous baseline design inspections of similar depth and length has shown
that this type of inspection is extremely resource intensive, both for the NRC inspectors and the
licensee staff. In order to minimize the inspection impact on the site and to ensure a productive
inspection for both parties, we have enclosed a request for information needed for the
inspection.
B. Hanson
-2-
It is important that all of these documents are up-to-date and complete in order to minimize the
number of additional documents requested during the preparation and/or the onsite portions of
the inspection. Insofar as possible, this information should be provided electronically to the lead
inspector. The information request has been divided into four groups:
The first group lists information necessary for our initial inspection scoping
activities. This information should be provided to the lead inspector no later than
May 8, 2017. Prior to the bagman trip, on May 22, 2017, the lead inspector will
communicate the initial selected set of approximately 12 EQ components.
The second group of documents requested is those items needed to support the
bagman trip. This set of documents should be available to the lead inspector
onsite on June 5, 2017.
The third group of documents requested is those items needed to support our
in-office preparation activities for the selected set of 6 - 9 EQ components. This
set of documents should be provided to the lead inspector at the Regional Office
no later than June 16, 2017. During the in-office preparation activities, the team
may identify additional information needed to support the inspection.
The last group includes the additional information above as well as plant specific
reference material. This information should be available to the team onsite on
June 26, 2017. It is also requested that corrective action documents and/or
questions developed during the inspection be provided to the lead inspector
as the documents are generated.
The lead inspector for this inspection is Mr. George M. Hausman. We understand that our
licensing contact for this inspection is Ms. Dwi Murray of your organization. If there are any
questions about the inspection or the material requested in the enclosure, please contact the
lead inspector at (630) 829-9743 or via e-mail at George.Hausman@nrc.gov.
This letter does not contain new or amended information collection requirements subject to
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number
3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond
to, a request for information or an information collection requirement unless the requesting
document displays a currently valid Office of Management and Budget Control Number.
B. Hanson
-3-
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
George M. Hausman, Senior Reactor Engineer
Engineering Branch 3
Division of Reactor Safety
Docket Nos. 50-373; 50-374
Enclosure:
Design Bases Assurance Inspection
EQ Program Document Request
cc: Distribution via LISTSERV
B. Hanson
-4-
Letter to Bryan C. Hanson from George M. Hausman dated March 29, 2017
SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2 - REQUEST FOR INFORMATION
FOR AN NRC DESIGN BASES ASSURANCE INSPECTION (PROGRAM):
IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM
INSPECTION REPORT 05000373/2017008; 05000374/2017008
DISTRIBUTION:
RidsNrrDorlLpl3
RidsNrrPMLaSalle
RidsNrrDirsIrib Resource
Cynthia Pederson
DRPIII
DRSIII
ADAMS Accession Number: ML17088A624
OFFICE
RIII
E RIII
RIII
RIII
NAME
GHausman:jw
DATE
03/29/17
OFFICIAL RECORD COPY
DESIGN BASES ASSURANCE INSPECTION EQ PROGRAM DOCUMENT REQUEST
Enclosure
Inspection Report: 05000373/2017008; 05000374/2017008
Bagman Date:
June 5, 2017
Inspection Dates:
June 26 - 30, 2017, and
July 10 - 14, 2017
Inspection Procedure:
IP 71111.21N, Design Bases Assurance Inspection (Program),
Attachment 1, Environmental Qualification (EQ) under 10 CFR
50.49 Programs, Processes, and Procedures
Lead Inspector:
George M. Hausman, Senior Reactor Engineer, DRS
630-829-9743
George.Hausman@nrc.gov
I.
Information Requested Prior to the Onsite Information Gathering/Bagman Week
The following information is requested by May 8, 2017, or sooner, to facilitate inspection
preparation. If you have any questions regarding this information, please call the team
leader as soon as possible. Please provide the information electronically in pdf files,
Excel, or other searchable formats, preferably on some portable electronic media (e.g.,
CD-ROM, DVD, etc.). The portable electronic media should contain descriptive names,
and be indexed and hyperlinked to facilitate ease of use. Information in lists should
contain enough information to be easily understood by someone who has knowledge
of light water reactor technology).
1.
Risk-ranking of top 250 components required to meet environmental
qualifications from your site-specific probabilistic safety analysis (PSA)
sorted by Fussell Vesely Importance.
2.
PSA listing of top ten risk-significant systems.
3.
U.S. Nuclear Regulatory Commission Safety Evaluation Report(s) associated
with EQ.
4.
Electronic copies of Updated Final Safety Analysis Report (UFSAR), Technical
Specifications, and Technical Specifications Bases. Specifically identify which
UFSAR sections address EQ (including seismic).
5.
Identify the various EQ standards (including year, edition, or revision) that the
station is committed to meet.
DESIGN BASES ASSURANCE INSPECTION EQ PROGRAM DOCUMENT REQUEST
2
6.
Site procedures (i.e., and corporate, if applicable) associated with Title 10 of the
Code of Federal Regulations (10 CFR), Part 50, Section 49, Environmental
qualification of electrical equipment important to safety for nuclear power plants.
Include procedures for procurement of qualified equipment, maintenance of
qualified equipment, modification to qualified equipment (including Equivalency
or Commercial Grade Dedication (CGD) programs), and material storage and
shelf life controls.
7.
Copy of EQ Design Basis Document, if applicable.
8.
Copy of any open licensing commitments related to EQ, if applicable.
9.
Equipment Qualification Master List (EQML). Specific issues to be identified
include: safety classification (safety-related or nonsafety-related), Regulatory
Guide 1.97 instrumentation, EQ qualification (e.g., DOR, NUREG 588,
10 CFR 50.49), original or replaced after implementation of 10 CFR 50.49,
and plant location.
10.
List of any installed equipment removed from the EQML and basis for removal.
11.
List of EQ solenoid valves that are normally continuously energized.
12.
List or drawings of plant areas that are subjected to EQ, identifying design
(limiting) temperature, both normal and accident, high energy line break,
radiation levels, etc. that the associated equipment will have to be qualified to
meet EQ. If unit has obtained a power uprate (greater than 5 percent) provide
same information pre-update (earliest available if multiple uprates).
13.
List of CGD evaluations performed, for which the dedicated parts have been
issued for installation (parts issued for the last 10 years) on EQ applications in
the plant. Include CGD evaluation number, name of part, component ID or
description of the component the part was issued to repair, work order, and
date issued or installed.
14.
List of Corrective Action Documents related to the EQ program or EQ of specific
components for the last 5 years.
15.
Current management and engineering organizational chart.
II.
Information Requested (for the approximate 9 - 12 selected components) to be
Available by the Bagman Trip on June 5, 2017.
1.
EQ summary report for each component/subcomponent.
2.
Qualification Maintenance Requirement Sheet or equivalent.
3.
List of corrective action documents associated with each of the selected
components for the last 5 years.
4.
Photos of any component in containment or high radiation areas, if available.
DESIGN BASES ASSURANCE INSPECTION EQ PROGRAM DOCUMENT REQUEST
3
III.
Information Requested (for the approximate 6 - 9 selected components) to be
Available by June 16, 2017, (will be reviewed by the team in the Regional office
during the week of June 19, 2017).
This information should be separated for each selected component, especially if
provided electronically (e.g., folder with component name that includes EQ files,
Qualification Test Reports, calculations, corrective action documents, maintenance
history, etc.).
1.
EQ file, including associated Qualification Test Reports.
2.
Vendor manual (electronic copy or availability of hard copy during inspection).
3.
Preventive maintenance template.
4.
Last performed work order (WO) for each associated EQ preventive
maintenance.
5.
List of corrective maintenance WOs for the last 10 years. Include WO number,
date performed, and brief one line description.
6.
If repair work (e.g., a motor rewind) was performed under a purchase order,
provide copy of the purchase order.
7.
Thermal life calculation.
8.
Any self-assessments of the EQ program in the last 3 years.
IV.
Additional Information to be Provided on June 26, 2017 Onsite
1.
During the in-office preparation activities, the team may identify additional
information needed to support the inspection. The lead inspector will provide
a list of the additional information needed during the week of June 19, 2017.
V.
Information Requested to be Provided Throughout the Inspection
1.
Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection.
2.
Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily by 2:00 p.m.
during the inspection to each team member).
If you have questions regarding the information requested, please contact the lead inspector.