ML16341G522

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/92-09 & 50-323/92-09 on 920310-17. Violations Noted.Major Areas Inspected:Licensee Implementation of QA Program for Procurement of Generator Portion of Sixth EDG Unit
ML16341G522
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 04/07/1992
From: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16341G520 List:
References
50-275-92-09, 50-275-92-9, 50-323-92-09, 50-323-92-9, NUDOCS 9204240022
Download: ML16341G522 (34)


See also: IR 05000275/1992009

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report Nos:

Docket Nos:

License

Nos:-

Licensee:

50-275/92-09

and 50-323/92-09

50-275

and 50-323

DPR-80 and

DPR-82

Pacific Gas

and Electric Company

77 Beale Street,

Room 1451

San Francisco,

California

94106

Facility Name:

Diablo Canyon Units

1 and

2

Inspected At:

Corporate Office, San Francisco,

California

. Inspection

Conducted:

March 10-11,

1992 at Corporate office

Harch 16-17,

1992 in

RV office

Inspectors:

Approved By:

D. Kirsch, Chief, Reactor

Safety Branch

R.. Huey,

Enforcement Officer

S; Matthews,

gA Specialist,

VIB, NRR

srsc

,

se

,

eac or

a ety

rane

e

>gne

Summary:

s ection from March 10-17

1992

e ort Nos.

50-275 92-09

and 50-323 92-09

Safet

Issues

Mana ement

S stem

SIMS

Items:

None

Jesuits:

General

Conclusions

on Stren ths

and Weaknesses:

Strengths

In preparation

for the inspection,

the licensee

assembled

a

comprehensive

history of PGIl.E activities regarding the purchase

of the

sixth generator.

The history candidly identified the weaknesses

observed

in the procurement

processes.

Weaknesses

. The licensee's

corrective actions to resolve

a

nonconformance

report,

issued

in 1989, regarding

inadequate

supplier

audits failed to assess

the adequacy of the audits of NEI Peebles

Electric Products

Inc. - Cleveland,

and Peebles

Electric Hachines-

Scotland,

and. recognize

the potential

impact on the sixth generator

procurement.

In addition, the quality assurance

organization failed to

9204240022

92040S

PDR

ADOCK 05000275

G

PDR

0

identify certain irregularities in the procurement

process

such

as

supplier audit inadequacy,

the issuance

of a purchase

order to a

supplier who was not listed on the Qualified Suppliers List, and

performance of commercial

grade procurement

oversight

by a contractor

who had not developed

an adequate

commercial

grade procurement

and

dedication

program.

S fet

Si nificant Matters:

None

S mmar

of Violations and Oeviations:

This inspection identified two apparent violations of NRC requirements:

2.

Failure to comply with approved

procedures for dispositioning of

draft supplier audit findings.

Failure to implement appropriate corrective actions for inadequate

supplier

audits.'ll

t

t

This inspection

opened three

new open items.

getails

1. ~Ct

d

  • M.'H. Fujimoto, Vice President,

Nuclear, Technical

Services

  • R. C. Anderson,

Manager,

Nuclear Engineering

and Construction

.

Services

(NECS)

  • H. R. Tressler,

Diablo Canyon Project Engineer,

NECS

J. A. Sexton,

Manager, guality Assurance

  • J. C. Young, Director, Procurement guality Assurance

(P(A)

  • U. A. Farradj,

Group Leader,

NECS

  • J. E. Tompkins, Director, Nuclear Regulatory Affairs
  • E. R. Kahler,

Group Leader,

Replacement

Parts

Engineering

(RPE)

  • E. 'Walters,

Engineer,

RPE

  • T. M. Packy,

Lead Auditor, P(A

C. Patrick,

Lead Auditor,

PgA

  • H. 'S. Dobrzensky,= Senior Supervisor,

P(A

  • -Attended the Exit Interview on Harch ll, 1992

2.

ur ose of Ins ection

The purpose of the inspection

was to

Assess

whether the licensee

had defined

and implemented

an

appropriate quality assurance

program for the procurement of the

generator portion of the sixth Emergency Diesel

Generator

(EDG)

unit,

Assess

whether the licensee's

quality assurance

and engineering

organizations

had acted responsibly in dealing with the generator

procurement-

and the problems identified,

~

Assess

whether the corrective actions in response

to

Nonconformance

Report

number DCO-89-gA-N007 were adequately

implemented for the generator

procurement,

and

~

Determine the circumstances

which contributed to the omission of

an audit finding, regarding

an undeveloped

commercial

grade

dedication

program

on the part of NEI Peebles - Electric Products,

Inc.

(P-EP) of Cleveland,

Ohio, from the final audit report

and

which remained

unresolved

by the licensee.

In order to accomplish this purpose

the inspectors

held discussions

with

the licensee's

engineering

and quality assurance

organization

regarding

the generator

procurement intent

and history,

and interviewed members of

the audit staff.

2

3.

enerator

oc rement (Inspection

Procedure

No. 92702)

ack round

i

b.

The inspector discussed,

with responsible

licensee

personnel,

the

philosophy

and intent of the generator

procurement for the sixth

EDG unit.

The licensee

indicated that

a basic premise

was that

the generator for the sixth

EDG would be identical to the

generators

installed

on the other five EDG units,

and the spare

generator,

procured in 1986-87.

The reasons for this desired

commonality primarily involved common spare parts,

common design

of the generator

and control panels,

common test

and maintenance

procedures,

and

common staff knowledge,

among others.

The licensee'tated

that the decision

was

made to procure the

sixth generator

from the

same manufacturer

who had manufactured

the other five generators,

and the spare,

and deal with the

qualification of the prime contractor/supplier

(P-EP)

and

manufacturer,

Peebles

Electrical Hachines

(PEH), of Edinburgh,

Scotland,

separately.

PG&E stated that they had

some confidence

that the generator quality would be acceptable

based

upon

engineering participation in audits

and satisfactory

procurement

and operation of fi.ve installed generators.

The licensee

stated

their belief that if anything

was wrong with the generator it

would be

made evident in the testing

and could be repaired,

and,

further, that their intent was to scrap the generator unit at any

.point that it became clear that the unit could not be deemed

qualified for service

and sufficiently reliable.

These decisions

were dictated

by schedule

considerations

which required having the

generator

tested

as

a unit with the diesel

in Canada

in Hay 1991,

and installed

and operational

by the completion of the

1993 Unit 2

refueling outage.

The licensee

purchased

the generator for the sixth

EDG unit from

P-EP,

a

10 CFR 50, Appendix B, supplier.

P-EP contracted with a

subsidiary,

PEH, located in Scotland, for the manufacture of the

generator.

PEH was not an Appendix

B qualified supplier.

Accordingly,

P-EP would need to assure that appropriate

commercial

grade

procurement

and dedication

processes

were exercised for the

generator

component parts.

Sixth

EDG Procurement

Chronolo

The licensee

supplied

and discussed

the following chronology.

~

In June

1988,

a Gulf States Utilities audit resulted

in

PG&E

removing

P-EP from their Qualified Supplies List (QSL).

~

PG&E conducted audit

(89180S) of P-EP during July,

1989, in

an attempt to qualify P-EP for inclusion

on the

QSL:

Problems

were found, most notably that

a P-EP audit of PEH

was not an adequate

audit.

The audit was not sufficient to

qualify P-EP as

a gSL supplier of the generator.

PGIIE conducted

an audit of PEN during August

1989 in an

attempt to requalify PEN,as

a qualified supplier.

As a

result of problems found, the audit was

deemed

not

sufficient to requalify

PEN and was not listed

on the gSL.

PEN was removed from the gSL in January

1990

as

a result of

corrective action in response

to a nonconformance

report

regarding

inadequate

supplier qualification audits

(NCR

fDC0-89-gA-N007).

PGIIE conducted

another qualification audit (89295S) of P-EP

on December

11,

1989.

An interview with the lead auditor established

that

the audit was originally planned

as

a commercial

grade

procurement

and dedication

survey

and that the audit

was upgraded to an Appendix

B supplier qualification

audit after the audit was completed.

The

NRC

concluded that the upgrade

was not well managed

and

inappropriate.

The auditor indicated that

he only had slightly more

than

a week to plan the audit in addition to several

other duties at the time.

The

NRC concluded that this

seemed

an inadequate

amount of time to plan

an audit

of this scope.

The audit was

a one day audit,

an insufficient amount

of time to conduct

an audit of this scope.

The audit was

based

upon

a draft procurement

specification

(SP-D-Peebles/Rev.

3) which was not

issued until later,

on February 6,

1991.

The audit was conducted

even prior to the issuance

of

specification SP-D-Peebles/Rev.

2 on February

22,

1990.

The audit report was finally issued

on April

17,

1990.

The licensee

asserted

that the procurement

specification

issued

on February

22,

1990 accounted

for resolution of the findings of the audit;

however,

there

was. no documentation of this assertion.

The audit report was delayed

due to a two month

medical

leave

by the lead auditor.

The draft was

available in January

1990;

however,

comments of

licensee

management

were not able to be resolved

by

the lead auditor.

4

P-EP was ultimat'ely listed

on the gualified Suppliers

List on June

1,

1990 based

upon this one day audit.

. The purchase

order,

SP-D-Peebles/Rev.

2, was issued to

P-EP

on February

22,

1990, well before

P-EP was placed

on the

gSL in June

1990.

A draft Audit Finding Report

(AFR) was issued to P-EP

by the lead auditor on December

11,

1989.

The

AFR

identified that

P-EP

had not fully developed

a

.

commercial

grade dedication

program for PGLE

identified critical- parts.

This AFR was not tracked

to resolution or addressed

by the audit report, facts

which remained

unknown to the licensee until brought

to their attention

by the

NRC on February

20,

1992.

This is an apparent violation of procedure

gAA-WI-305,

which requires that the audit finding report

be

included in the audit package,

and procedure

gAA-WI-

317, which requires that audit finding reports

be

tracked in accor'dance

with procedure

gAA-WI-302.

(Violation, 50-323/92-09-01)

A followup audit was

deemed

necessary

by the audit

team

and was not done until August 1990,

about nine

months after the original audit.

The

NRC had the following conclusions

regarding this

audit and its relationship to future events.

C

The

NRC concluded that the audit was inadequately

planned,

and- inadequately

executed to adequately

address

the intended

scope.

The scope

was

inappropriately

upgraded,

after the audit, to be

an

Appendix

B supplier qualification audit instead of the

more limited commercial

grade survey, originally

planned;

The audit was conducted

using

a draft

procurement specification,

which would not be issued

until February

1991.

The purchase

order to P-EP

was

issued in February

1990, before the qualification

audit report was issued in April 1990,

and before

P-EP

was placed

on the

gSL in June

1990.

The followup

audit was not done until August 1990, after the

purchase

order was issued to P-EP

and after

P-EP was

placed

on the gSL.

The audit finding regarding

P-EP's

inadequate

commercial

grade dedication

program

was

never

adequately

resolved,

even though

PEN (a

subcontractor

to P-EP) procured generator parts

commercially

and supplied these to P-EP

as

a completed

generator.

PEM procured parts for the generator during early 1990.

PG&E had one supplier audit of PEM during this parts

procurement

phase.

A third party audit of P-EP was conducted

by Houston Light

and

Power during late July 1990.

Thirteen Audit Finding

Reports

were issued to P-EP.

An implementation audit of P-EP was conducted

in mid August

1990.

This was

a better planned audit than the December

1989 one day audit

and had,a longer duration.

P-EP was removed

from the

PG&E gSL on September

1,

1990.

The spare generator,

purchased

ear lier and in storage

at the

Diablo Canyon warehouse

was put on hold.

The procurement of

the sixth generator,

however,

continued,

apparently without

PG&E compensatory

measures

to compensate

for the removal of

P-EP from the gSL.

PG&E determined,

in August 1990, that

an Engineering

Evaluation of the sixth generator

was necessary

to determine

the adequacy of the generator

in light of the large

number

of supplier audit findings on P-EP

and

PEM.

The spare

generator

in the warehouse

on site was placed

on hold

pending completion of the Engineering Evaluation.

A joint P-EP/PG&E commercial

grade survey of PEM was

conducted

in October

1990.

The

PG&E team consisted of

quality assurance

and engineering

personnel.

The audit

resulted in six audit finding Reports

and

a request for an

Engineering Evaluation to evaluate

the impact of the

findings on the adequacy of the sixth generator.

Assembly of the generator

occurred at

PEM during the period

of October

1990 through February

1991.

During this period

PG&E had source

inspectors

at

PEM on two occasions

to

monitor the generator quality and testing.

The generator

was shipped in late February

1991.

The final Purchase

Order (SP-D-Peebles/Rev.

3) was issued to

P-EP

on February 6,

1991.

At this time the generator

assembly

was essentially

complete

and testing

was in

progress.

P-EP was reinstated

on the

gSL for a One-Time purchase

on

March 1,

1991, after the generator

was constructed

and

shipped

from PEM.

A verification visit to P-EP

on March 13,

1991 found that

the

P-EP corrective actions applicable to a one-time

purchase

were not acceptably

implemented.

A second

6

verification inspection to P-EP during July 1991 found that

P-EP

had adequately

implemented corrective actions

applicable to a one-time purchase.-

PG&E issued the final Engineering

Evaluation of P-EP

and

PEH

activities

on October 31,

1991, concluding that the spare

and sixth generator

were acceptable.

Com arison of PG&E's Audit

din s at

P-EP

and

P

H to the

RC's

Ins ection F

at

-

d

H (92702)

The

NRC conducted

an inspection of P-EP, in August of 1991, to evaluate

P-EP's production of an emergency

AC power generator for PG&E.

As a

result of this inspection,

documented

in Inspection Report (IR)

99900772/91-01,

the

NRC issued

a Notice of Nonconformance to P-EP that

identified four areas

where P-EP's activities failed to comply with NRC

51

5

1

App

dt tt

Tttl

15, ftt ~df

d

P t5

tt

CPRP

5T.

TR

RRC

1

d td

inspection of PEH, in September

of. 1991 to evaluate

PEH's manufacture of

the generator for PG&E.

As a result of this inspection,

documented

in

IR 99901065/91-01,

the

NRC issued

a Notice of Nonconformance to

PEH that

identified two areas

where

PEH's activities failed to comply with P-EP's

expectations

necessary

to support certification that the generator

complied with the requirements

of Appendix

B to

10 CFR Part 50.

In its response

to IR 99900772/92-01,

dated

February

12,

1992,

PG&E

provided (1)

an itemization of the NRC's issues identified in IR

99900772/91-01,

(2) the corresponding

PGEE audit findings,

and (3) the

compensatory

actions taken

by PG&E to. resolve the findings.

PG&E's

response

did not address

the NRC's findings 'in IR 99901065/91-01

(PEH).

The team's

review of certain sections of PG&E's response

resulted

in the

observations

described

below.

a.

Section III - Additional Information on

P-EP related

0 en Items

Identified in NRC

R 50-

3 91-202

This section of PG&E's response

discusses

three concerns

related

to the generator identified in the NRC's letter to PG&E, dated

November

15,

1991, which transmitted

IR 50-323/91-202.P

(1)

otor

Po

e

Ha net Mire:

PG&E stated that

P-EP

had reported

that it is evaluating the impact of the varnished-wire that

was

used in the fabrication of the generator's

pole windings

(P-EP

had specified the use of unvarnished wire).

P-EP had

not completed its evaluation at the time of this inspection.

This issue

was identified by the

NRC during its inspection

of PEH.

This issue

was, not identified by PG&E.

(2)

Bakelite Electrical

Se aration

Rin

The commercial

grade

bakelite electrical

separation

ring was

used

as

a load

bearing component-part

of the rotor shaft support

assembly.

(3)

PG&E stated that it agreed that the ring is part of the

support

system of the bearing housing,

due to the sandwich

design,

and lack of any known failure of this design.

The

mechanical

strength

was not considered

a critical design

characteristic.

PG&E, however, did not demonstrate

to the

team

an engineering

evaluation to substantiate

this

conclusion

or that assured

the adequacy of the comaercial

grade item to perform its function in support of the rotor

shaft assembly.

This issue

was identified by the

NRC during

its inspection of PEN.

This issue

was not identified by

PG&E.

c

'c tion o

Cr t ca

o

one ts

PG&E stated that

although the list of 27 critical items, identified in

Revision

3 of its purchase

order

(PO) to P-EP was not

signed-off until after the generator

was completed,

these

items were examined during the October

1990 audit of PEN.

However, not all of the

27 critical items were examined

during the audit; the audit examined only a sample

(seven

items) of the identified 27 critical items.

Revision

1 of PG&E's'O to P-EP incorporated

a list of 14

critical items that, according to PG&E, were identified by

P-EP

as

a list of critical items that ~a

be procured

and

dedicated

by P-EP then supplied to PEN.

However, the

PG&E

auditors that conducted

the

December

1989 audit of P-EP,

the

associated

audi.t documentation,

and associated

correspondence

appeared

to indicate that the critical items

were developed

by PG&E's technical staff that supported

the

December

1989 audit.

This issue

was identified by the

NRC

during its inspections of P-EP

and

PEH.

Section

V Additional Information on 0 en-

tems

denti .ied in

RC Ins ection

Re ort No..99900772

91-01

f

This section of PG&E's response

reviews the nonconformances

and

the unresolved

item identified in IR 99900772/91-01.

onconformance

99900772

91-0 -01:

This nonconformance

identified that

P-EP failed to (1) establish

adequate

measures

to control

changes

in design, materials,

and

.manufacturing

processes

commensurate

with those controls

applied to the original design,

(2) provide for performing

design verification of the changes

in design, materials,

and

manufacturing

processes,

(3) demonstrate

that the changes

in

the design

were controlled commensurate

with the design

controls applied to the original design,

and (4) demonstrate

that the original design basis

had

been correctly translated

into revised specifications,

drawings,

procedures,

and

instructions.

0

8'G&E

stated,

in part, that its audit of P-EP in August

1990

(Audit 90197S) identified corresponding

programmatic

findings, documented

in its audit finding report

(AFR)90-067.

PG&E's response

stated,

in part,.that the

evaluation of design

changes

and specifications

and

procedures

equivalency

was not required prior to the

1984

time frame since the issues

requiring this review were

associated

with a lack of formal interface

between

P-EP

and

PEM.

This nonconformance,

however, identified issues. with

P-EP's design control that were independent of the

P-EP

and

PEH interface.

PG&E reported to the team that it had reconsidered this

response

in part because

of the like-for-like guidance

provided by the

NRC in Generic Letter (GL) 91-05,

"Licensee

Commercial-Grade

Procurement

and Dedication Programs."

PG&E

reported that its response,

compensatory

actions,

and

engineering

evaluation will be revised to evaluate

the

changes

in design, material,

and the manufacturing

process

since the original generators

were supplied in 1969.

This evaluation is necessary

to determine if any of these

changes

could impact the functional characteristics

and,

ultimately, the generator's'ability

to perform its required

safety function.

The revised engineering

evaluation will be

evaluated

by the,NRC during

a future inspection.

onconformance

9990077

91-0 -0

This nonconformance

identified that

P-EP failed to:

(1) establish

adequate

measures

to contro1 the activities between it and its sister

organization,

PEM, that consisted of the review, approval,

release,

distribution,

and revision of documents

involving

their respective

design interface,

(2) demonstrate

that the

results of PEM's design translation activities were

equivalent to the design requirements

specified -by P-EP,

(3)

adequately

document the critical requirements

or acceptance

criteria compared during the equivalency evaluation,

and (4)

adequately

document the results of the equivalency

evaluation or other bases

to support

P-EP's

conclusion that

PEM's procedure's

and specifications

were equivalent.

PG&E stated,

in part, that its Audit 90197S identified

corresponding

programmatic findings in AFR 90-068.

However,

this

AFR identified (1) that P-EP's external

audit/evaluation

program used to qualify suppliers (e.g.,

PEH)

was not adequate

to comply with PG&E's specification

and (2) that P-EP's quality program did not include

provisions for the dedication of commercial

grade items.

PG&E did not identify the

P-EP

and

PEH interface

issue

addressed

in this nonconformance until the

P-EP/PG&E audit

of PEM conducted

in October

1991

and documented

in P-EP's

Audit Report 9003.

Audit Report

9003 identified this issue

0

in AFR 9003-4

(P-EP

and

PEN interface)

and

AFR 9003-6

(equivalency of PEM procedures

and specifications to P-EP

procedures

and specifications).

~

PGIIE's response

stated,

in part, that in conjunction with

P-EP, it is formulating

a plan for identifying additional

reviews

and documentation

requirements

needed to ensure

the

adequate

resolution of the NRC's nonconformance.

onco formance

990077

91-01-03:

This nonconformance

identified that

P-EP failed to:

(1) establish

adequate

measures

to provide for the selection

and review for

suitability of the application for materials,

parts,

and

equipment that were procured

as commercial

grade

items

and

were essential

to the generator's ability to perform its

essential

to the generator's ability to perform its intended

design

and safety-related

function; (2) ensure

the

suitability of the stator coil's resistance

temperature

detectors,

slip rings,

adhesives,

and mounting sleeve

insulator for the slip rings;

and (3) ensure

the suitability

of the materials,

parts,

and equipment

PEN procured.

PGEE stated that its Audit 90197S identified corresponding

programnatic findings in AFRs90-068

and 90-069.

However,

PGEE first identified the programmatic

issue

addressed

in

this nonconformance,

that P-EP's quality program did not

include provisions for the dedication of commercial

grade

items, in its December

1989 audit of P-EP,

as documented

in

draft AFR No. 3.

PGKE's utilization of the December

1989

audit

and its results is discussed

in paragraph

3.b of this

report.

The adequacy of PG&E's response

and corrective actions with

regard to the NRC's findings related to certain critical

items (e.g.,

the stator coil's resistance

temperature

detectors,

slip rings, adhesives,

and mounting sleeve

insulator for the slip rings) will be evaluated

by the

NRC

during

a future inspection.

onconformance

9990077

9'-01-04:

This nonconformance

identified that

P-EP failed to establish

adequate

measures

to ensure

(1) that activities affecting quality were

prescribed

by documented

instructions,

procedures,

or

drawings;

(2) that activities affecting quality were

accomplished

in accordance

with these instructions,

procedures,

or drawings;

and (3) that instructions,

procedures,

or drawings include appropriate quantitative or

qualitative acceptance

criteria for determining that

important activities were satisfactorily accomplished.

P-EP

also failed to demonstrate

that the activities affecting

quality (1)" to fit the dovetail rotor pole assemblies

to the

rotor spider

assembly,

(2) to perform the brazing required

0

10

to fabricate the rotor spider assembly,

and (3) to perform

brazed joint spliced-connections

in the field coil winding

were documented

or accomplished

in accordance

with

instructions,

procedures,

or drawings that contained

quantitative or qualitative acceptance criteria and were

equivalent to those specified

by P-EP..

PG&E stated that its Audit 90197S identified corresponding

programmatic findings in AFRs90-068

and 90-072,

and in

P-EP/PG&E's Audit Report

9003,

AFR 9003-5.

Although AFR

90-068 identified (1) that P-EP's external audit/evaluation

program used to qualify suppliers (e.g.,

PEH) was not

adequate

to comply with PG&E's specification

and (2) that

P-EP's quality program did not include provisions for. the

dedication of commercial

grade items, neither of these

issues

are applicable to the issues

addressed

in this

nonconformance.

AFR

90-072 identified that P-EP's internal.

audit program was not adequate

and, therefore, it also did

not address

the issues

in this nonconformance.

AFR 9003-5

addressed

the failure of PEN's procedure-to

provide for the

calibration of the crimping tool or inspection of the

crimped connections.

PG&E's response

with regard to the

applicability of AFRs90-068,

90-072,

and 9003-5 did not

adequately

address

the issue

addressed

in this

nonconformance.

PG&E also responded

that detailed procedures

were not

required for the activities that affect safety during the

fabrication of the rotor pole spider assembly,

as these

operations

were part of normal

shop practice.

The

NRC team

determined that these operations

were part of normal

shop

practice

when the generators

were manufactured

in P-EP's

facility, however,

these

operations

were not part of PEN's

normal

shop practice, particularly since it was

PEN that

requested

the guidance

from P-EP.

PG&E 'added that if the

rotor pole was not assembled

correctly,

.the result would be

.

excess vibration, particularly during the overspeed

portion

of the test.

The basis for PG&E's conclusion

was not

demonstrated

to the team (i.e., vibration monitoring data

recorded during the overspeed

test

"nd post-test

inspection

documentation of the rotor pole spider assembly).

The adequacy of PG&E's response

and corrective actions with

regard to the NRC's findings related to the welding of the

rotor pole spider

assembly

studs

and spliced connections

in

the field coil windings will be evaluated

by the

NRC during

a future inspection.

Unresolved

tern 99900772

91-0 -05:

This unresolved

item

addressed

the concern that P-EP's original quality assurance

manual

((AN-100), in effect during the design,

manufacture,

and test of PG&E's generator,

did not include measures

to

11

adequately

control all of the activities affecting the

quality and safety-related

function of components

and parts.

Although P-EP's

second quality assurance

manual

((AM-101)

superseded

(AM-100, it contained

several

weaknesses

that

required strengthening

before its implementation.

Because

the team did not evaluate

the implementation of (AM-101,

this concern would be evaluated

in more detail during

a

future inspection.

PG&E's response

that this Unresolved

Item did not impact

their generator,

since

9AM-101 is not applicable to this

PG&E procurement,

is considered

adequate

and

no further

discussion of this issue

by

PG&E is required.

de uac

of PG&E's

n ineerin

Evaluation.

(92702)

Section

V,

"PG&E Engineering

Evaluation of P-EP for Purchase

of Sixth

Generator," of PG&E's response,

dated

February

12,

1991, provided

an

overview of the engineering

evaluation

performed

by

PG&E to quality P-

EP,

and according to

PG&E it includes

(1)

a description of PG&E's

procedural

requirements,

(2)

a summary of the

P-EP

NEMP 12.4 Engineering

Evaluation,

Revision 0,

and (3)

a summary of the additional

information

incorporated into Revision

1 of NEMP 12.4.

The team's

review of certain

sections of PG&E's Engineering

Evaluation resulted in the observations.

described

below.

a

~

Product

Performance

Evaluation

b.

This section of PG&E's Engineering Evaluation provided

an

evaluation of the history of P-EP's generators

in the nuclear

industry.

To determine

whether the history of P-EP's generator

affects the quality of the

new generator,

PG&E reviewed the

following documents:

NPRDS reports,

10 CFR Part 21 reports

and

utility reports, Bulletins, Letters,

SERs,

SCERs,

LERs, Restricted

Equipment List,

NRC IRs,

and

GIDEP reports.

The team's

review of this portion of PG&E's Engineering

Evaluation

determined that where the evaluation related to the

same,

or

similar, parts or component-parts

identified by

PG&E as critical

items,

the evaluation

lacked sufficient detail

addressing

the

correlation of the item reviewed to the item installed in new

generator.

Specifically, the evaluation did not. address

the part

and component-part

issued identified in IR 99900772/91-01

and

IR

99901065/91-01.

Su lier uglification

This section of PG&E's Engineering

Evaluation provided

a technical

evaluation of PG&E's audit findings of P-EP

and

PEM, evaluated

the

qualification of the

new generator

purchase,

and determined

the

acceptability of the stocked

spare.

The list of critical items

were separated

according to what facility procured

them,

because,

12

according to POKE, the items supplied

by

PEN were qualified by the

P-EP/PGKE Audit 9003

and the Engineering Evaluation, while those

items supplied

by P-E were qualified by P-EP's coaeercial

grade

dedication

program

and the Engineering Evaluation.-

The team's evaluation of this section of the Engineering

Evaluation resulted in the following observations:

PGKE's basis for determining that its list of 27 critical

items represented

a complete list of the generator's

critical items was not adequately

demonstrated.

Since the

team believes that there are conflicting versions of how and

who identified the critical items, it is therefore

necessary

to evaluate the engineering

basis for the list of critical

items.

As reported

by PGKE, the technical

evaluation of the Audit

90197S findings relating to design control will be revised

to evaluate

the changes

in design, material,

and the

manufacturing

process

since the original generators

were

supplied in 1969.

~

, The evaluation of P-EP's

and

PEH's commercial

grade

dedication activities for the specific parts

and component-

parts identified in IRs 99900772/91-01

and 99901065/91-01

will be evaluated

in detail during

a future inspection.

GKE's

Com ensator

Actions for NRC's

s ection Findi

s at P-

P and

PEM. (92702)

PG&E's compensatory

actions for all of the NRC's specific findings

related to critical parts

and component-parts

of the generator that were

identified during inspections of P-EP

and

PEN will be evaluated

in

detail

by the

NRC during

a future inspection.

Review of Licensee Actions to Address

Su lier Audit Findin

s (92702)

Previous

NRC inspections of P-EP

and

PEN during August and September

1991, identified several significant deficiencies

in the implementation

of 10 CFR 50, Appendix

B qua'lity assurance

program requirements,

as

w ll

as identifying some specific technical deficiencies

in the products

being supplied.

One of the objectives of these

NRC inspections

was to

evaluate

whether

PG&E had implemented appropriate

measures 'for assessing

the adequacy of its supplier quality assurance

(gA) programs

and

responded

appropriately to any findings resulting from such assessments.

In this regard,

the inspectors

noted that

PGKE had identified supplier

gA program problems in August

1990 that were similar to the programmatic

concerns

subsequently

identified by the

NRC.

Accordingly, the

inspectors

reviewed the actions

taken

by the licensee

in response

to

their August

1990 findings,

as well as evaluating whether the problems

13

identified in August 1990 should

have

been identified earlier in the

procurement

process

(especially in light of significant lessons

identified during

a comprehensive

PG&E review of supplier procurement

problems in 1989).

a 0

'censee

Res

o se to

s

90

S

lie

ud't

d

s

As noted

above,

during an August

1990 audit of P-EP (Audit

, 90197S),

PG&E identified numerous significant programmatic

,

deficiencies in the supplier's

implementation of Appendix

B

quality assurance

requirements.

PG&E recognized that the results

of this audit conflicted with the conclusions of an earlier audit

performed in December

1989 (Audit 89295S),

which served

as the

supplier qualification audit for the February

1990 placement of a

purchase

order with P-EP for a Diablo Canyon diesel

generator.

Accordingly,

PG&E initiated an Action Request

(A0201828) in August

1990 to assess

the reasons for the differences

between the

1989

and

1990 audit results.

This assessment

was subsequently

upgraded

to a safety related guality Evaluation

(f0008302) in January

1991

and

a Nonconformance

Report

(NCR 92-N004) in February

1992.

4

The inspectors

concluded that the scope

and corrective actions

associated

with NCR 92-N004 were too narrowly focused only on, the

specific shortcomings of audit 89295S,

instead of recognizing the

broader

and more generic significance of other potentially

inadequate

audits conducted

between July 1989

and December

1990.

In particular, the inspectors

noted the following:

(1)

PG&E identified that Audit 89295S

and the subsequent

placement of the

P-EP purchase

order were deficient in

several

respects.

In particular: audit planning,

scope

and

specification

bases

were deficient; audi,t conclusions

were

based

on inadequate

objective evidence;

licensee

procedures

for disposition of preliminary audit findings were violated;

and procedures

requiring suppliers to be on

a gualified

Suppliers List prior to purchase

order placement

were

'iolated.

(2)

(3)

Each of the Audit 89295S findings are similar to findings

associated

with an earlier comprehensive

PG&E evaluation of

supplier audit deficiencies

issued

in July 1989

as

an

Nonconformance

Report

(NCR 89-N007).

Final corrective

actions associated

with NCR 89-N007 were not signed off as

being fully implemented until December

1990.

Since Audit 89295S,

which occurred in December

1989, clearly

did not implement the lessons of NCR 89-N007, the inspectors

concluded that it is likely that other audits performed

during the August

1989 through

December

1990 time period

may

be similarly flawed.

14

b.

During the exit meeting,

the licensee

agreed with the inspector's

conclusions

and committed to expand the scope of NCR 92-N004

corrective actions to include

a review of -all audits performed

during the August

1989 through

December

1990 time period.

Earlier 0

ortunities to Identif

Su lier Procurement

oblems

As noted

above,

PG&E had identified many of the types of audit

deficiencies

associated

with Audit 89295S several

months prior to

performing the audit.

However, these

lessons

were not factored

into Audit 89295S,

although the audit served

as the basis for

placing

a major, safety related .purchase

order.

Although it is

recognized that full implementation of NCR 89-N007 lessons

were

continuing throughout the July 1989 to December

1990 time period,

PG&E failure to implement

any of those lessons

during Audit 89295S

appeared

to the inspectors

to be

a significant missed opportunity.

This failure precluded timely identification and correction of the

significant problems that were subsequently

identified in July and

August 1990, well after significant portions of the purchase

order

had already

been completed.

As a result of the inadequate

1989

audit,

a safety related

purchase

order was placed with P-EP in

February

1990, which did not meet

10 CFR 50, Appendix

B quality

. assurance

program requirements,

as specified in the purchase

order.

documents.

This deficiency was not identified until receipt of an

audit from Houston Light & Power in July 1990 (disqualifying .P-EP

for safety related procurement),

and

a similarly disqualifying

PG&E audit performed in August 1990.

Failure to implement timely actions to preclude recurrence of the

supplier audit deficiencies

addressed

by NCR 89-N007 for Audit

89295S is an apparent violation of 10 CFR 50, Appendix B,

Criterion

16 (Violation, 50-323/92-09-02).

Failure to ensure

proper implementation of quality assurance

requirements

associated

with the purchase of safety related

equipment

from P-EP is an

apparent violation of 10 CFR 50, Appendix B, Criterion

7 (Non-

cited Violation, 50-323/92-09-03).

This violation will not be the

subject of NRC enforcement

action because

the licensee's

efforts

in identifying and correcting the violation meet the criteria

specified in Section VII.B.2 of the Enforcement Policy.

During the exit meeting,

the inspectors

emphasized

several

points

relating to the similarity of this inspection's

findings with those

described

in Inspection

Reports

50-323/89-22

and 50-323/89-27.

These

similarities appear to indicate that

PG&E has not fully implemented

some

of the lessons that should

have

been learned'rom

the significant

guality Assurance

program deficiencies that were addressed

during those

inspections.

In particular, the inspectors

noted that:

a.

One of the major findings of the

1989

NRC inspections

was that

PG&E had too narrowly limited the scope of their review of

inadequate

supplier audits to only those

performed

by contractors,

rather than also addressing

similar deficiencies

in

PG&E performed

15

b.

audits.

As discussed

above, this inspection

noted that the scope

of PG8E's current review of supplier audit deficiencies

(NCR 92-

N004) was also too narrowly focussed.

Another finding of the

1989'NRC inspections

was that

PGLE audit

personnel

were experiencing difficulty raising concerns to their

gA supervision,

resulting in significant program deficiencies

not

being properly evaluated

and resolved in a timely manner.

During

interviews. with PGLE audit personnel

during this inspection, it

again

appeared

that auditor concerns

associated

with the scope

and

definition of Audit 89295S were not properly evaluated

or resolved

in a timely manner.

Although the interviewed personnel

indicated

that they believe that the circumstances

which resulted in those

problems

have

now been corrected,

the fact that they occurred

warrants continuing

PG&E attention to preclude recurrence.

it

terview

The inspectors

discussed

the findings of the inspection,

as indicated

above, with members of the licensee's staff,

as indicated in paragraph

1, at the conclusion of the inspection

on Harch

11,

1990 at the

Corporate Office.

The licensee

acknowledged

the inspection findings and

again reiterated that their management

had determined

to procure

a

generator alike those already installed at Diablo Canyon,

in full

recognition of the problems

found with the quality paperwork of the

suppliers,

and do whatever

was necessary

to later establish

the quality

and acceptability of the generator

by Engineering

Evaluation

and

testing.

The licensee further stated that, in the event that it became,

or becomes,

apparent at any point that the generator

cannot

be qualified

for service, their intent was to scrap the machine short of accepting

and placing the machine in operation.

0