Other: AEP-NRC-2013-13, Redacted Version of Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Events (Order Number EA-12-049), AEP-NRC-2013-14, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), AEP-NRC-2013-71, First Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies, AEP-NRC-2013-72, Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), AEP-NRC-2014-16, Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licensees with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), AEP-NRC-2014-17, Second Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events., AEP-NRC-2014-66, Third Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), AEP-NRC-2014-67, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), AEP-NRC-2014-89, Compliance with March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events, AEP-NRC-2014-91, Update to Communications Assessment Implementation Actions and Timeline - Fukushima Dai-ichi Near-Term Task Force Recommendation 9.3, Emergency Preparedness, AEP-NRC-2015-13, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), AEP-NRC-2015-22, Compliance with March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), AEP-NRC-2015-23, Final Integrated Plan Regarding March 12, 2012, U.S. NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), AEP-NRC-2015-83, Of Final Integrated Plan Regarding March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), ML13234A503, ML13337A325, ML13357A325, ML14115A315, ML14140A064, ML14209A122, ML14216A362
|
MONTHYEARAEP-NRC-2013-14, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-02-27027 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other AEP-NRC-2013-13, Redacted Version of Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Events (Order Number EA-12-049)2013-02-27027 February 2013 Redacted Version of Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Events (Order Number EA-12-049) Project stage: Other ML13164A3812013-06-19019 June 2013 Request for Additional Information on the Overall Integrated Plan in Response to Order EA-12-051 Concerning Reliable Spent Fuel Pool Instrumentation Project stage: RAI ML13183A4312013-07-0303 July 2013 Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval AEP-NRC-2013-57, Response to Request for Additional Information Regarding the Overall Integrated Plan in Response to Order EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation2013-07-11011 July 2013 Response to Request for Additional Information Regarding the Overall Integrated Plan in Response to Order EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI AEP-NRC-2013-71, First Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies2013-08-26026 August 2013 First Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies Project stage: Other AEP-NRC-2013-72, Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-26026 August 2013 Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13234A5032013-08-28028 August 2013 Nuclear Regulatory Commission Audits of Licensee Responses to Mitigation Strategies Order EA-12-049 Project stage: Other ML13283A1222013-09-30030 September 2013 WCAP-17762-NP, Revision 1, D. C. Cook Unit 1 Return to Reactor Coolant System Normal Operating Pressure/Normal Operating Temperature Program - Licensing Report, and Enclosures 7 Through 9 Project stage: Request ML13310B4992013-11-13013 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Instrumentation Project stage: RAI ML13357A3252014-01-10010 January 2014 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Donald C. Cook Nuclear Plant, Units 1 and 2, TAC Nos.: MF0766 and MF0767 Project stage: Other ML13337A3252014-01-24024 January 2014 Interim Staff Evaluation and Audit Report Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other AEP-NRC-2014-16, Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licensees with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-27027 February 2014 Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licensees with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other AEP-NRC-2014-17, Second Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events.2014-02-27027 February 2014 Second Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. Project stage: Other AEP-NRC-2014-15, 30 Day Report of Changes to or Errors in an Evaluation Model2014-02-27027 February 2014 30 Day Report of Changes to or Errors in an Evaluation Model Project stage: Request ML14115A3152014-04-28028 April 2014 Plan for the Onsite Audit of Mohr Regarding Implementation of Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-051 Project stage: Other ML14140A0642014-05-21021 May 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML14209A1222014-08-13013 August 2014 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other AEP-NRC-2014-66, Third Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-27027 August 2014 Third Six Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other AEP-NRC-2014-67, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-27027 August 2014 Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML14216A3622014-08-27027 August 2014 Report for the Onsite Audit of Mohr Regarding Implementation of Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-051 Project stage: Other AEP-NRC-2014-89, Compliance with March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events2014-12-16016 December 2014 Compliance with March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other AEP-NRC-2014-91, Update to Communications Assessment Implementation Actions and Timeline - Fukushima Dai-ichi Near-Term Task Force Recommendation 9.3, Emergency Preparedness2014-12-16016 December 2014 Update to Communications Assessment Implementation Actions and Timeline - Fukushima Dai-ichi Near-Term Task Force Recommendation 9.3, Emergency Preparedness Project stage: Other AEP-NRC-2015-13, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-25025 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other AEP-NRC-2015-22, Compliance with March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-06-16016 June 2015 Compliance with March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other AEP-NRC-2015-23, Final Integrated Plan Regarding March 12, 2012, U.S. NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-06-16016 June 2015 Final Integrated Plan Regarding March 12, 2012, U.S. NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other AEP-NRC-2015-83, Of Final Integrated Plan Regarding March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-10-0101 October 2015 Of Final Integrated Plan Regarding March 12, 2012, NRC Order Regarding Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15264A8512015-11-0909 November 2015 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Approval 2014-01-24
[Table View] |
Similar Documents at Cook |
|---|
|
Text
INDIANA Indiana Michigan Power MICHIGAN Cook Nuclear Plant POWER0 One Cook Place Bridgman, MI 49106 A unit ofAmerican Electric Power Indiana MichiganPower.com February 27, 2014 AEP-NRC-2014-15 10 CFR 50.46 Docket No.:
50-315 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Unit 1 30-DAY REPORT OF CHANGES TO OR ERRORS IN AN EVALUATION MODEL
References:
- 1.
Letter from Westinghouse Electric Company LLC, to Donald C. Cook Nuclear Plant, "D. C. Cook Units 1 and 2 10 CFR 50.46 Report for the HOTSPOT Burst Strain Error Correction," dated January 29, 2014.
- 2.
Letter from J. P. Gebbie, Indiana Michigan Power Company (I&M), to U. S.
Nuclear Regulatory Commission (NRC),
"License Amendment Request Regarding Restoration of Normal Reactor Coolant System Operating Pressure and Temperature Consistent with Previously Licensed Conditions," dated October 8, 2013.
- 3.
Letter from J. P. Gebbie, I&M, to NRC, "Donald C. Cook Nuclear Plant Units 1 and 2, Response to Information Request Pursuant to 10 CFR 50.54(f) Related to the Estimated Effect on Peak Cladding Temperatures Resulting from Thermal Conductivity Degradation in the Westinghouse-Furnished Realistic Emergency Core Cooling System Evaluation (TAC No. M99899)," dated March 19, 2012.
Pursuant to 10 CFR 50.46, Indiana Michigan Power Company (I&M),
the licensee for Donald C. Cook Nuclear Plant (CNP) Unit 1, is reporting significant changes to, or errors in, Emergency Core Cooling System evaluation models (EM), or in the application of such models that affect the calculated peak fuel cladding temperature. By Reference 1, Westinghouse notified I&M of an EM error which significantly affected the Best-Estimate Large-Break Loss-of-Coolant Accident (LBLOCA) analysis for CNP Unit 1. The impact of the errors is not significant to the CNP Unit 2 LBLOCA Analysis Calculated Peak Cladding Temperature (PCT). The CNP Unit 1 and Unit 2 Small-Break LOCA analyses are not affected by this error.
The enclosure to this letter provides a description of each LBLOCA EM error correction and the associated impact to the CNP Unit 1 LBLOCA analysis of record and the analysis performed for the CNP Unit 1 normal operating pressure/normal operating temperature (NOP/NOT) project currently under review, Reference 2. Based on information provided by Westinghouse, an assessment of
U. S. Nuclear Regulatory Commission AEP-NRC-2014-15 Page 2 these errors resulted in a PCT increase of 85°F for Unit 1 for both current operation and at NOP/NOT conditions. By Reference 3, I&M had provided a schedule for a reanalysis resulting from an unrelated error associated with thermal conductivity degradation.
Based on the previously provided schedule for reanalysis, and since the changes from these errors did not lead to PCT temperatures in excess of the limit, there are no additional plans for a reanalysis as a result of these errors. This condition has been entered into CNP's corrective action program.
There are no new or revised commitments in this letter. Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.
Sincerely, Joel P. Gebbie Site Vice President DB/amp
Enclosure:
Donald C. Cook Nuclear Plant Unit 1 Report of Error Corrections on Westinghouse Large-Break Loss-of-Coolant Analysis Emergency Core Cooling System Evaluation Model c:
J. T. King, MPSC S. M. Krawec, AEP Ft. Wayne, w/o enclosures MDEQ - RMD/RPS NRC Resident Inspector C. D. Pederson, NRC Region III T.J. Wengert, NRC Washington, DC
ENCLOSURE TO AEP-NRC-2014-15 DONALD C. COOK NUCLEAR PLANT UNIT 1 REPORT OF ERROR CORRECTIONS ON WESTINGHOUSE LARGE-BREAK LOSS-OF-COOLANT ANALYSIS EMERGENCY CORE COOLING SYSTEM EVALUATION MODEL Abbreviations:
OF degrees Fahrenheit ECCS emergency core cooling system FAH nuclear enthalpy rise hot channel factor FQ heat flux hot channel factor LOCA loss of coolant accident MWt megawatts - thermal NOP/NOT normal operating pressure/ normal operating temperature PCT peak cladding temperature SGTP steam generator tube plugging Summary:
By Westinghouse letter LTR-LIS-14-44, "D. C. Cook Units 1 and 2 10 CFR 50.46 Report for the HOTSPOT Burst Strain Error Correction," dated January 29, 2014, Westinghouse Electric Company notified Indiana Michigan Power, the licensee for Donald C. Cook Nuclear Plant (CNP) Unit 1, of significant errors in the evaluation model for the Large-Break (LB) LOCA analysis of record for CNP Unit 1. This report contains a summary of changes and errors and their estimated effect on the calculated PCT of CNP Unit 1 LBLOCA analysis of record which also includes a PCT impact associated with the Unit 1 Cycle 25 operating cycle that began in May 2013. Additionally included is the impact of the error for the NOP/NOT project.
The error that has been identified in the HOTSPOT code affected the calculation of the fuel rod burst strain. The equation for the application of the burst strain is given as Equation 7-69 in WCAP-16009-P-A and in WCAP-12945-P-A.
The outer radius of the fuel rod cladding, after burst occurs, should be calculated based on the burst strain, and the inner radius of the fuel rod cladding should be calculated based on the outer radius. The HOTSPOT code was found to have the burst strain applied to the calculation of the fuel rod cladding inner radius.
The cladding outer radius was then calculated based on the inner radius. As such, the fuel rod burst strain was incorrectly applied to the inner radius rather than the outer radius, which impacts the resulting fuel rod cladding geometry at the fuel rod burst elevation (i.e., axial location in the core) after fuel rod burst was calculated to occur following a LBLOCA. The correction of the erroneous calculation results in thinner fuel rod cladding at the burst node (location/elevation) and leads to more fuel relocating into the burst node, leading to an increase in the calculated LBLOCA PCT at the burst node.
Enclosure to AEP-NRC-2014-15 Page 2 Affected Evaluation Models 1996 Westinghouse Best Estimate Large Break LOCA Evaluation Model 2004 Westinghouse Realistic Large Break LOCA Evaluation Model using ASTRUM Estimated Effect As shown in the PCT rack-up tables below, the calculated LBLOCA PCT, with assessments, becomes 2175°F for Unit 1 (i.e., current Cycle 25 operation) which includes a PCT adjustment of +14'F associated with core reload effects. The Unit 1 value for the NOP/NOT program with assessments becomes 2037°F. Thus, it is seen that the 10 CFR 50.46 acceptance criterion of not exceeding 2200°F continues to be satisfied for both CNP units.
References:
- 1. WCAP-12945-P-A, Volume 1, Revision 2, and Volumes 2 through -5, Revision 1, "Code Qualification Document for Best Estimate LOCA Analysis," dated March 1998.
- 2. WCAP-16009-P-A, "Realistic Large-Break LOCA Evaluation Methodology Using the Automated Statistical Treatment Of Uncertainty Method (ASTRUM)," dated January 2005.
- 3. LTR-LIS-14-44, "D. C. Cook Units 1 and 2 10 CFR 50.46 Report the HOTSPOT for Burst Strain Error Correction" dated January 29, 2014.
- 4. AEP-NRC-2013-79, "Donald C. Cook Nuclear Plant Unit 1 Docket No. 50-315 License Amendment Request Regarding Restoration of Normal Reactor Coolant System Operating Pressure and Temperature Consistent with Previously Licensed Conditions," dated October 2013.
- 5. AEP-NRC-2013-68, "Donald C. Cook Nuclear Plant Unit 1 30-Day Report of Changes to or Errors in an Evaluation Model," dated August 2013.
Enclosure to AEP-NRC-2014-15 Page 3 Estimated Effect On The Calculated PCT For CNP Unit 1 Large Break LOCA:
Evaluation Model: ASTRUM (2004)
FQ= 2.15 FAH = 1.55 SGTP = 10%(a)
Break Size: Split Analysis Date: November 20, 2007 LICENSING BASIS Analysis-of-Record PCT = 2128°F MARGIN ALLOCATIONS (Delta PCT)
A.
B.
C.
PREVIOUS 10 CFR 50.46 ASSESSMENTS PLANNED PLANT MODIFICATION EVALUATIONS
- 1. Design Input Changes with Respect to Plant Operation
- 2. PBOT/PMID Evaluation NEW 10 CFR 50.46 ASSESSMENTS
- 1. Revised Input Changes with Respect to Plant Operation
- 2. Error in Burst Strain Application OTHER 3840F(a.)
-381 oF(a) 140F(b)
-550F(c)
D.
850F 0°F PCT = 2175°F LICENSING BASIS PCT + MARGIN ALLOCATIONS Notes:
- a. These assessments are coupled via an evaluation of burnup effects which include thermal conductivity degradation, peaking factor burndown and design input changes (e.g., reduction in the maximum allowed steam generator tube plugging from 10% to 2%
and maximum FdH reduced to 1.545). Evaluation details provided in a letter dated March 19, 2012, (ADAMS Accession No. ML12088A104), and supplemented by letter dated June 11, 2012, (ADAMS Accession No. ML12173A025), and subsequently found acceptable by U. S. Nuclear Regulatory Commission (NRC) letter dated March 7, 2013 (ADAMS Accession No. ML13077A137).
- b. This PCT impact is only applicable to the Unit 1 Cycle 25 operating cycle, which began in May 2013 and is scheduled to end in October 2014.
- c. This impact was due to revised heat transfer multiplier distributions identified in AEP-NRC-2013-68.
Enclosure to AEP-NRC-2014-15 Page 4 Estimated Effect On The Calculated PCT For CNP Unit 1 Large Break LOCA at NOP/NOT Conditions:
Evaluation Model: ASTRUM (2004)
FQ= 2.15 FAH = 1.55 SGTP = 10%(a)
Break Size: Split Analysis Date: November 20, 2007 LICENSING BASIS Analysis-of-Record PCT = 2128°F MARGIN ALLOCATIONS (Delta PCT)
A.
PREVIOUS 10 CFR 50.46 ASSESSMENTS 0F(a.)
B.
PLANNED PLANT MODIFICATION EVALUATIONS
- 1. Design Input Changes with Respect to Plant Operation
-489°F(a) for Return to NOP/NOT Evaluation C.
2013 ECCS MODEL ASSESSMENTS
- 1. Design Input NOP/NOT Including Pellet Thermal Conductivity Degradation and Peaking Factor 404 Burndown
- 2. Revised Heat Transfer Multiplier Distributions
_91(b)
- 3. Error in Burst Strain Application 85 D.
OTHER 0°F LICENSING BASIS PCT + MARGIN ALLOCATIONS PCT = 2037°F Notes:
- a. These assessments are coupled via an evaluation of burnup effects which include thermal conductivity degradation, peaking factor burndown and design input changes (e.g., reduction in the maximum allowed steam generator tube plugging from 10% to 2%
and maximum FdH reduced to 1.545). Evaluation details provided in a letter dated March 19, 2012, (ADAMS Accession No. ML12088A104), and supplemented by letter dated June 11, 2012, (ADAMS Accession No. ML12173A025), and subsequently found acceptable by NRC letter dated March 7, 2013 (ADAMS Accession No. ML13077A137).
- b. The return to NOP/NOT evaluation in AEP-NRC-2013-79 contains revised heat transfer multiplier distribution.