ML14044A105

From kanterella
Jump to navigation Jump to search
IR 05000298-13-005; 09/23/2013 12/31/2013; Cooper Nuclear Station, Integrated Resident and Regional Report; Equip Alignment, Maint Risk Assessments & Emergent Work Control, Operability Determinations & Functionality Assessments, Problem Id
ML14044A105
Person / Time
Site: Cooper Entergy icon.png
Issue date: 02/13/2014
From: Allen D
NRC/RGN-IV/DRP/RPB-C
To: Limpias O
Nebraska Public Power District (NPPD)
Allen D
References
EA-13-075, EA-13-225 IR-13-005
Download: ML14044A105 (42)


See also: IR 05000298/2013005

Text

February 13, 2014

EA-13-075

EA-13-225

Mr. Oscar A. Limpias, Vice President-Nuclear

and Chief Nuclear Officer

Nebraska Public Power District

Cooper Nuclear Station

72676 648A Avenue

Brownville, NE 68321

SUBJECT:

COOPER NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT

05000298/2013005 AND NRC INVESTIGATION REPORT NO. 2013-009

Dear Mr. Limpias:

On December 31, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at the Cooper Nuclear Station. On December 20, 2013, the NRC inspectors

discussed the results of this inspection with Mr. R. Penfield, Director of Nuclear Safety

Assurance, and other members of your staff. Inspectors documented the results of this

inspection in the enclosed inspection report.

The NRC inspectors documented four findings of very low safety significance (Green) in this

report. All of these findings involved violations of NRC requirements. Further, inspectors

documented two licensee-identified violations which were determined to be of very low safety

significance in this report. The NRC is treating these violations as non-cited violations (NCVs)

consistent with Section 2.3.2.a of the Enforcement Policy.

One of the licensee identified violations referenced above, resulted in an NRC investigation.

The enclosed report documents the investigation completed on October 1, 2013, by the Nuclear

Regulatory Commission's Office of Investigations. The purpose of this investigation was to

determine whether a fire watch was wilfully inattentive while on duty at Nebraska Public Power

Districts Cooper Nuclear Station, Brownville, Nebraska. Based on the evidence gathered

during the investigation, the NRC concluded that on December 5, 2012, a former contract-

employee deliberately failed to perform a fire watch at the Cooper Nuclear Station. This was

contrary to the fire protection plan that satisfies Criterion 3 of Appendix A of 10 CFR Part 50,

and resulted in a violation.

Since the former contract-employee's violation was wilful, it was evaluated under the NRC's

traditional enforcement process in accordance with the Enforcement Policy. The current

Enforcement Policy is included on the NRC's website at: http://www.nrc.gov/about-

nrc/regulatory/enforcement/enforce-pol.html. After careful consideration of these factors, the

NRC concluded that this violation should be classified at Severity Level IV, based on the

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511

O. Limpias

- 2 -

example provided in Section 6.1.d.1 of the Enforcement Policy. In reaching this decision, the

NRC considered that the event was isolated, it was performed by a low-level, contract-

employee, missing of the fire watch was of short duration, did not result in an actual

consequence, and occurred while the plant was shut-down. In addition, the significance was

mitigated because others were in the area and no actual fire occurred during the time frame that

the fire watch was non-observant.

In accordance with Section 2.3.2 of the Enforcement Policy, and with the approval of the

Director, Office of Enforcement, this issue has been characterized as a non-cited violation,

because (1) the violation was identified by the licensee; (2) the violation involved the act of an

individual, who would not have been considered a licensee official with oversight of regulated

activities as defined in the Enforcement Policy; (3) the violation did not involve a lack of

management oversight and was the isolated action of the former, contract-employee; and

(4) significant remedial action commensurate with the circumstances was taken by the licensee.

Regarding the corrective actions, the Cooper Nuclear Station conducted an internal

investigation to determine the cause and took appropriate corrective actions.

The NRC concluded that information regarding: (1) the reason for the violation, (2) the

corrective actions that have been taken and results achieved, and (3) the date when full

compliance was achieved is already adequately addressed on the docket in the enclosed

inspection report. Therefore, you are not required to respond to this letter unless the description

herein does not accurately reflect your corrective actions or your position.

If you contest the violations or significance of these NCVs, you should provide a response within

30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with

copies to the Regional Administrator, Region IV; the Director, Office of Enforcement,

U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC resident

inspector at the Cooper Nuclear Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the Regional Administrator, Region IV; and the NRC resident inspector at the

Cooper Nuclear Station.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, a copy of this letter, its enclosure, and your

response (if any) will be available electronically for public inspection in the NRCs Public

Document Room or from the Publicly Available Records (PARS) component of the NRC's

Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible

from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic

Reading Room).

Sincerely,

/RA/

Donald B. Allen, Branch Chief

Project Branch C

Division of Reactor Projects

O. Limpias

- 3 -

Docket Nos.: 50-298

License Nos: DPR-46

Enclosure: Inspection Report 05000298/2013005

wAttachment: Supplemental

Information

Electronic Distribution to the Cooper Nuclear Station

O. Limpias

- 4 -

ML14044A105

SUNSI Rev Compl.

Yes No

ADAMS

Yes No

Reviewer Initials

RVA

Publicly Avail.

Yes No

Sensitive

Yes No

Sens. Type Initials

RVA

SRI:DRP/C

RI:DRP/C

C:DRS/EB1

C:DRS/EB2

C:DRS/OB

C:DRS/PSB1

JJosey

CHenderson

TRFarnholtz

GMiller

VGaddy

MSHaire

T-D.Allen for

T-D.Allen for

/RA/

/RA/

/RA/

/RA/

02/13/2014

02/13/2014

02/07/2014

02/12/2014

02/07/2014

02/07/2014

C:DRS/PSB2

C:DRS/TSB

SPE:DRP/C

ACES/C

BC:DRP/C

HGepford

RKellar

RAzua

VCampbell

DAllen

/RA/

/RA/

/RA/

/RA/

/RA/

02/10/2014

02/07/2014

02/06/2014

02/11/2014

02/13/2014

OFFICIAL RECORD COPY

- 1 -

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

05000298

License:

DPR-46

Report:

05000298/2013005

Licensee:

Nebraska Public Power District

Facility:

Cooper Nuclear Station

Location:

72676 648 A Ave

Brownville, NE

Dates:

September 23 through December 31, 2013

Inspectors: J. Josey, Senior Resident Inspector

S. Garchow, Senior Operations Engineer

C. Henderson, Resident Inspector

D. Strickland, Operations Engineer

C. Steely, Operations Engineer

J. Laughlin, Emergency Preparedness Inspector, NSIR

Approved

By:

Donald B. Allen

Chief, Project Branch C

Division of Reactor Projects

- 2 -

SUMMARY

IR 05000298/2013005; 09/23/2013-12/31/2013; Cooper Nuclear Station, Integrated Resident

and Regional Report; Equip Alignment, Maint Risk Assessments & Emergent Work Control,

Operability Determinations & Functionality Assessments, Problem ID & Resolution.

The inspection activities described in this report were performed between September 23, 2013,

and December 31, 2013, by the resident inspectors at the Cooper Nuclear Station, three

inspectors from the NRCs Region IV office, and an inspector from the NRCs Office of Nuclear

Security and Incident Response. Four findings of very low safety significance (Green) are

documented in this report. All of these findings involved violations of NRC requirements.

Additionally, NRC inspectors documented in this report two licensee-identified violations of very

low safety significance or Severity Level IV. The significance of inspection findings is indicated

by their color (Green, White, Yellow, or Red), which is determined using Inspection Manual

Chapter 0609, Significance Determination Process. Their cross-cutting aspects are

determined using Inspection Manual Chapter 0310, Components Within the Cross-Cutting

Areas. Violations of NRC requirements are dispositioned in accordance with the NRCs

Enforcement Policy. The NRC's program for overseeing the safe operation of commercial

nuclear power reactors is described in NUREG-1649, Reactor Oversight Process.

Cornerstone: Mitigating Systems

Green. The inspectors identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion XVI, Corrective Actions, associated with the licensees failure to promptly identify

and correct a condition adverse to quality. Specifically, from July 2010 to present, the

licensee failed to properly evaluate the diesel generator fuel oil storage tank vents to

demonstrate their ability to perform their specified safety function in the event of a tornado

missile. The licensee is in the process of developing corrective actions to restore

compliance for this issue. This issue has been entered into the corrective action program as

Condition Report CR-CNS-2014-00146.

The licensees failure to promptly identify and correct a condition adverse to quality was a

performance deficiency. This performance deficiency is more than minor, and therefore a

finding, because it is associated with the design control attribute of the Mitigating Systems

Cornerstone, and affected the cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable consequences.

Using Inspection Manual Chapter 0609, Appendix A, The Significance Determination

Process (SDP) for Findings At-Power, dated July 1, 2012, inspectors determined this

finding to have very low safety significance (Green) because it: (1) was not a deficiency

affecting the design and qualification of a mitigating structure, system, or component, and

did not result in a loss of operability or functionality; (2) did not represent a loss of system

and/or function; (3) did not represent an actual loss of function of at least a single train for

longer allowed outage time, or two separate safety systems out-of-service for longer than

their technical specification allowed outage time; and (4) did not represent an actual loss of

function of one or more nontechnical specification trains of equipment designated as high

safety-significance in accordance with the licensees maintenance rule program. The finding

has a cross-cutting aspect in the area of human performance associated with decision-

making component because the licensee did not ensure that the proposed action was safe

in order to proceed, rather than unsafe to disapprove the action H.1(b) (Section 1R04).

- 3 -

Green. The inspectors identified a non-cited violation of 10 CFR 50.65(a)(4), Requirements

for Monitoring the Effectiveness for Maintenance at Nuclear Power Plants, for the licensees

failure to implement required risk management actions during maintenance activities

affecting the seismic qualification of the safety-related 4160 Vac Bus F and G when the

cabinet doors are opened during under voltage relay testing. The licensee corrected this

issue by providing procedural guidance for implementation of the required risk management

actions. The licensee entered this deficiency into their corrective action program for

resolution as Condition Report CR-CNS-2013-06870.

The licensees failure to implement required risk management actions during maintenance

activities was a performance deficiency. This performance deficiency was more than minor,

and therefore a finding, because it was associated with the equipment performance attribute

of the Mitigating Systems Cornerstone and affected the associated objective. Specifically,

by failing to implement required risk management actions to restore 4160 Vac Bus F and G

to their seismically qualified condition, i.e. cabinet doors closed, this thereby affected the

associated objective to ensure availability, reliability, and capability of systems that respond

to initiating events to prevent undesirable consequences. Using Inspection Manual

Chapter 0609, Appendix K, Maintenance Risk Assessment and Risk Management

Significance Determination Process, dated May 5, 2005, Flowchart 2, Assessment of Risk

Management Actions, the inspectors determined the need to calculate a risk deficit to

determine the significance of this issue. A senior reactor analyst performed a bounding

detailed risk evaluation, which determined that the incremental core damage probability

associated with this finding was less than 1 X 10-6, so the finding has very low safety

significance (Green). The finding has a cross-cutting aspect in the area of human

performance associated with the work practices component because the licensee failed to

define and effectively communicate expectations regarding procedural compliance and to

ensure that personnel follow procedures H.4(b)(Section 1R13).

Green. The inspectors identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, Drawings, associated with the licensees failure to

perform an adequate operability determination in accordance with Station

Procedure 0.5OPS, Operations Review of Condition Reports/Operability Determination.

Specifically, the licensee failed to evaluate the effect on operability of taking electrical relays

for the service water pumps out of their seismically qualified configuration. To correct this

issue the licensee directed that the affected service water pump be declared inoperable

during Division II under voltage testing. The licensee entered this deficiency into their

corrective action program for resolution as Condition Report CR-CNS-2014-00122.

The failure to properly assess and document the basis for operability when a degraded or

nonconforming condition was identified was a performance deficiency. The performance

deficiency was more than minor, and therefore a finding, because it was associated with the

equipment performance attribute of the Mitigating Systems Cornerstone and affected the

cornerstone objective to ensure availability, reliability, and capability of systems that respond

to initiating events to prevent undesirable consequences. Specifically, the licensees failure

to properly document and assess the basis for operability resulted in a condition of unknown

operability for a degraded nonconforming condition. Using Inspection Manual

Chapter 0609, Appendix A, Initial Screening and Characterization of Findings,

dated July 1, 2012, inspectors determined that the finding was of very low safety

significance (Green) because the finding: (1) was not a deficiency affecting the design and

qualification of a mitigating structure, system, or component, and did not result in a loss of

- 4 -

operability or functionality; (2) did not represent a loss of system and/or function; (3) did not

represent an actual loss of function of at least a single train for longer than its technical

specification allowed outage time, or two separate safety systems out-of-service for longer

than their technical specification allowed outage time; and (4) did not represent an actual

loss of function of one or more nontechnical specification trains of equipment designated as

high safety-significance in accordance with the licensees maintenance rule program. The

finding has a cross-cutting aspect in the area of human performance associated with

decision-making component because the licensee did not ensure that the proposed action

was safe in order to proceed, rather than unsafe to disapprove the action H.1(b)

(Section 1R15).

Cornerstone: Occupational Radiation Safety

Green. Inspectors reviewed a self-revealing non-cited violation of Technical

Specification 5.4.1.a, associated with a radiation protection technician who failed to follow

the requirements of Radiation Work Permit 2013-001, Radiation Protection Activities,

Revision 1. This radiation work permit did not authorize entry into areas with dose rates

exceeding 80 mrem/hr. The licensee determined that this issue was due to a human

performance error and corrected the issue as such. The licensee entered this issue into

their corrective action program as Condition Report CR-CNS-2013-07506.

The failure to follow radiation work permit requirements was a performance deficiency. The

performance deficiency was more than minor, and therefore a finding, because it was

associated with the program and process attribute of the Occupational Radiation Safety

Cornerstone and affected the associated cornerstone objective to ensure the adequate

protection of the workers health and safety from exposure to radiation from radioactive

material during routine civilian nuclear reactor operation. Specifically, this finding resulted in

a radiation protection technician receiving an unintended and unexpected radiation dose.

Using Manual Chapter 0609, Appendix C, Occupational Radiation Safety Significance

Determination Process, dated August 19, 2008, the inspectors determined that the finding

was of very low safety significance (Green) because: (1) it was not associated with as low

as is reasonably achievable (ALARA) planning; (2) it did not involve an overexposure;

(3) there was no substantial potential for an overexposure; and (4) the licensees ability to

assess dose was not compromised. The finding has a cross-cutting aspect in the area of

human performance associated with the work practices component because licensee

personnel failed to use human error prevention techniques, such as pre-job briefs, self-and-

peer checking, and proper documentation of activities commensurate with the risk of the

assigned task, such that, work activities were performed safely H.4(a) (Section 4OA2).

Licensee-Identified Violations

Violations of very low safety significance or Severity Level IV that were identified by the licensee

have been reviewed by the inspectors. Corrective actions taken or planned by the licensee

have been entered into the licensees corrective action program. These violations and

associated corrective action tracking numbers are listed in Section 4OA7 of this report.

- 5 -

PLANT STATUS

The Cooper Nuclear Station began the inspection period at full power on September 23, 2013,

and remained at essentially full power through the end of the inspection period

December 31, 2013.

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R04 Equipment Alignment (71111.04)

Partial Walkdown

a.

Inspection Scope

The inspectors performed partial system walk-downs of the following risk-significant

systems:

October 11, 2013, 125 Vdc and 250 Vdc, C battery charger to Division 1 and

Division 2 battery

October 13, 2013, 4160 Vac, Bus F

November 12, 2013, Core spray Division I and northeast quad fan coil unit

November 26, 2013, Auxillary steam lines in 4160 switchgear room G, diesel

generator rooms 1 and 2, service water pump room, and control room envelope

high energy line break requirements

The inspectors reviewed the licensees procedures and system design information to

determine the correct lineup for the systems. They visually verified that critical portions

of the systems were correctly aligned for the existing plant configuration.

These activities constituted four partial system walk-down samples as defined in

Inspection Procedure 71111.04.

b.

Findings

Introduction. The inspectors identified a Green, non-cited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Actions, associated with the licensees failure to

promptly identify and correct a condition adverse to quality.

Description. While performing plant walk downs, inspectors noted that the diesel

generator fuel oil storage tank vent lines appeared to be susceptible to tornado missiles.

Specifically, the vent lines were approximately 1 foot apart, and inspectors questioned

whether a single tornado generated missile could render both vent lines incapable of

performing their specified function.

- 6 -

Inspectors reviewed the licensees USAR and noted the following:

Appendix F states that the licensee complies with Draft General Design

Criteria GDC-2, published July 11, 1967, and the Draft General Design

Criteria GDC-2 requires that the systems and components needed for accident

mitigation remain fully functional before, during, and after a tornado event.

USAR Chapter I-5, Section 5.2, defines Class I structures and equipment as,

Structures and equipment whose failure could cause significant release of

radioactivity or which are vital to a safe shutdown of the plant and removal of

decay and sensible heat.

USAR Chapter XII-2, Section 2.1.2.3, identifies the Standby Diesel Generator

System and Auxiliaries as Class I equipment.

Inspectors were not able to locate an evaluation of the vent lines that demonstrated their

ability to withstand a tornado missile impact. Inspectors did, however, note that Station

Procedure 5.1WEATHER, Operations During Weather Watches and Warnings,

Revision 12, Section 7.4, directed that, in the event of a tornado impact to the site,

operators would inspect the vent lines, and if they were damaged, one of the diesel

generator fuel oil tank fill lines was to be opened. Inspectors determined this to be a

compensatory action, and questioned if the vent lines were adequately protected from

tornado generated missiles.

Inspectors informed the licensee of their concerns, and the licensee initiated Condition

Report CR-CNS-2013-03720. In this condition report, the licensee identified that during

the 2010 NRC component design basis inspection, NRC inspectors had similar

questions and Condition Report CR-CNS-2010-05211 had been initiated to address

these questions. The licensee subsequently closed Condition Report

CR-CNS-2013-03720 with no further actions being taken.

Inspectors reviewed Condition Report CR-CNS-2010-05211 and noted that it had been

initiated due to questions about a statement in the licensees design control document

for the diesel generators which dealt with tornado missile protection for the diesel

generator fuel oil storage tank vents. Specifically, the design control document stated, in

part, The vent pipe concerns was satisfactorily resolved during the 1991 EDSFI, and

inspectors had requested the stations evaluation for the diesel generator fuel oil storage

tank vents and fill valves with respect to tornado missile.

The licensee researched the basis for this statement and determined that it most likely

came from their evaluation of a finding at another facility where the NRC had questioned

the adequacy of fill and vent connections with respect to impact from a tornado/tornado

missile. During their review, the licensee determined that an evaluation of the fill and

vent lines ability to withstand a tornado missile impact did not exist.

Corrective action number 2 of Condition Report CR-CNS-2010-05211 was, in part, to

provide a formal analysis of the diesel generator fuel oil storage tank vent lines

pertaining to tornado missile protection. The licensee generated Engineering

Evaluation 10-060, Evaluation of the Diesel Generator Fuel Oil Tanks, in response to

this corrective action.

- 7 -

Inspectors reviewed Engineering Evaluation 10-060 and noted that it did not evaluate

the vent lines with regard to their ability to withstand tornado generated missiles.

Instead, it assumed that the vents were small runs of pipe and if impacted by a missile

there would be no damage to the fueil oil storage tank. The evaluation went on to

discuss manual actions that could be implemented if the vent lines were to be damaged

by a tornado generated missile.

Inspectors determined that the licensees assumptions associated with the vent lines

ability to withstand a missile impact were not adequate. Therefore, the licensee had

failed to correct a previously identified condition adverse to quality. Specifically,

Condition Report CR-CNS-2010-05211 identified that the station did not have an

evaluation that demonstrated the diesel generator vent lines ability to withstand a

tornado missile impact, and the corrective action (corrective action 2) to correct this, did

not because of inadequate assumptions by engineering personnel.

Inspectors informed the licensee of their concern, and the licensee initiated Condition

Report CR-CNS-2014-00146.

Analysis. The licensees failure to promptly identify and correct a condition adverse to

quality was a performance deficiency. This performance deficiency is more than minor,

and therefore a finding, because it is associated with the design control attribute of the

Mitigating Systems Cornerstone, and affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences. Using Inspection Manual Chapter 0609,

Appendix A, The Significance Determination Process (SDP) for Findings At-Power,

dated July 1, 2012, inspectors determined this finding to have very low safety

significance (Green) because it: (1) was not a deficiency affecting the design and

qualification of a mitigating structure, system, or component, and did not result in a loss

of operability or functionality; (2) did not represent a loss of system and/or function;

(3) did not represent an actual loss of function of at least a single train for longer allowed

outage time, or two separate safety systems out-of-service for longer than their technical

specification allowed outage time; and (4) did not represent an actual loss of function of

one or more nontechnical specification trains of equipment designated as high safety-

significance in accordance with the licensees maintenance rule program. The finding

has a cross-cutting aspect in the area of human performance associated with decision-

making component because the licensee did not ensure that the proposed action was

safe in order to proceed, rather than unsafe to disapprove the action H.1(b).

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions,

requires, in part, that measures shall be established to assure that conditions adverse to

quality, such as failures, malfunctions, deficiencies, deviations, defective material and

equipment, and nonconformances are promptly identified and corrected. Contrary to

the above, from July 2010 to present, measures established by the licensee failed to

assure that an identified condition adverse to quality was corrected. Specifically, the

licensee failed to evaluate the lack of tornado missile protection for the diesel generator

fuel oil storage tank vents and demonstrate their ability to perform their specified safety

function in the event of a tornado missile strike. The licensee is in the process of

developing corrective actions to restore compliance for this issue. An immediate safety

concern does not exist due to the procedurized compensatory measures. This violation

is being treated as a non-cited violation, consistent with Section 2.3.2.a of the

- 8 -

Enforcement Policy. The violation was entered into the licensees corrective action

program as Condition Report CR-CNS-2014-00146. (NCV 05000298/2013005-01,

Failure to Promptly Identify and Correct a Condition Adverse to Quality)

1R05 Fire Protection (71111.05)

Quarterly Inspection

a.

Inspection Scope

The inspectors evaluated the licensees fire protection program for operational status

and material condition. The inspectors focused their inspection on four plant areas

important to safety:

October 3, 2013, Control rod drive units north, Fire Area I, Zone 2A

October 3, 2013, Residual heat removal heat exchanger 1A, Fire Area I, Zone 2B

October 3, 2013, Standby liquid control pump tanks and access way, Fire Area I,

Zone 5A

October 8, 2013, Diesel generator room 1A, Fire Area IX, Zone 14A

For each area, the inspectors evaluated the fire plan against defined hazards and

defense-in-depth features in the licensees fire protection program. The inspectors

evaluated control of transient combustibles and ignition sources, fire detection and

suppression systems, manual firefighting equipment and capability, passive fire

protection features, and compensatory measures for degraded conditions.

These activities constituted four quarterly inspection samples, as defined in Inspection

Procedure 71111.05.

b.

Findings

No findings were identified.

1R06 Flood Protection Measures (71111.06)

a.

Inspection Scope

On November 6, 2013, the inspectors completed an inspection of a manhole susceptible

to flooding. The inspectors selected a manhole that contained risk-significant or

multiple-train cables whose failure could disable risk-significant equipment:

Manhole 6A

The inspectors observed the material condition of the cables and splices contained in

the manhole and looked for evidence of cable degradation due to water intrusion. The

inspectors verified that the cables met design requirements.

- 9 -

These activities constitute completion of one bunker/manhole sample, as defined in

Inspection Procedure 71111.06.

b.

Findings

No findings were identified.

1R07 Heat Sink Performance (71111.07)

a.

Inspection Scope

On November 12, 2013, the inspectors completed an inspection of the readiness and

availability of risk-significant heat exchangers. The inspectors reviewed the data from a

performance test for the A reactor equipment cooling heat exchanger. Additionally, the

inspectors walked down the A reactor equipment cooling heat exchanger to observe its

performance and material condition and verified that the A reactor equipment cooling

heat exchanger was correctly categorized under the Maintenance Rule and was

receiving the required maintenance.

These activities constitute completion of one heat sink performance annual review

sample, as defined in Inspection Procedure 71111.07.

b.

Findings

No findings were identified.

1R11 Licensed Operator Requalification Program and Licensed Operator Performance

(71111.11)

.1

Review of Licensed Operator Requalification

a.

Inspection Scope

On October 30, 2013, the inspectors observed an evaluated simulator scenario

performed by an operating crew. The inspectors assessed the performance of the

operators and the evaluators critique of their performance.

These activities constitute completion of one quarterly licensed operator requalification

program sample, as defined in Inspection Procedure 71111.11.

b.

Findings

No findings were identified.

.2

Review of Licensed Operator Performance

a.

Inspection Scope

On November 29, 2013, the inspectors observed the performance of on-shift licensed

operators in the plants main control room. The inspectors observed the operators

performance of the following activities:

- 10 -

2.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for the reactor core isolation coolant surveillance brief and run

1.25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br /> for the control rod operability

0.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> for the brief on the solenoid-operated valve replacement for control

rods 18-35 and 22-11

In addition, the inspectors assessed the operators adherence to plant procedures,

including conduct of operations procedure and other operations department policies.

These activities constitute completion of one quarterly licensed operator performance

sample, as defined in Inspection Procedure 71111.11.

b.

Findings

No findings were identified.

.3

Biennial Inspection

a.

Inspection Scope

To assess the performance effectiveness of the licensed operator requalification

program, the inspectors conducted personnel interviews, reviewed the operating tests,

reviewed randomly selected medical and watchstanding proficiency records, and

observed ongoing operating test activities.

The on-site inspection effort occurred from October 21, 2013, to October 24, 2013.

During this time, the inspectors interviewed licensee personnel to determine their

understanding of the policies and practices for administering requalification

examinations. The inspectors also performed observations of portions of the operating

tests. These observations included five job performance measures and five scenarios

that were administered in the current biennial requalification cycle. These observations

allowed the inspectors to assess the licensee's effectiveness in conducting the operating

test to ensure operator mastery of the training program content. The inspectors also

performed an in-office review of overall operator performance on the biennial written

exams as well as the annual operating tests.

The results of these examinations were reviewed to determine the effectiveness of the

licensees appraisal of operator performance and to determine if feedback of

performance analyses into the requalification training program was being accomplished.

The inspectors interviewed members of the training department and reviewed minutes of

the Operations Training Review Group and Training Advisory Committee meetings to

assess the responsiveness of the licensed operator requalification program to

incorporate the lessons learned from both plant and industry events. The inspector also

reviewed a sample of licensed operator annual medical forms and procedures governing

the medical examination process for conformance to 10 CFR 55.53, a sampling of the

licensed requalification program feedback system, and reviewed remediation process

records. In addition to the above, the inspectors reviewed examination security

measures, simulator fidelity, and simulator deficiencies.

- 11 -

From December 1 to December 16, 2013, the inspectors performed an in-office review

of the biennial written examinations and reviewed the overall pass/fail results of the

individual job performance measure operating tests, simulator operating tests, and

written examinations administered by the licensee during the operator licensing

requalification cycles and biennial examination. Final examination results were

assessed to determine if they were consistent with the guidance contained in

NUREG 1021, "Operator Licensing Examination Standards for Power Reactors,

Revision 9, Supplement 1, and NRC Manual Chapter 0609, Appendix I, "Operator

Requalification Human Performance Significance Determination Process." Seven

separate crews participated in simulator operating tests, written examinations, and job

performance measure operating tests, totaling 41 licensed operators. There was one

failure on the written examination, no individual failures on the simulator operating tests,

and no failures on the job performance measure operating tests. The one failure on the

written examination was successfully remediated prior to returning to shift.

The inspectors completed one inspection sample of the biennial licensed operator

requalification program.

b.

Findings

No findings were identified.

1R12 Maintenance Effectiveness (71111.12)

a.

Inspection Scope

The inspectors reviewed two instances of degraded performance or condition of safety-

related structures, systems, and components:

November 19, 2013, 4160 Vac Bus F and G unavailability

November 27, 2013, 10 CFR 50.65(a)(3) evaluation

The inspectors reviewed the extent of condition of possible common cause structure,

system, and component failures and evaluated the adequacy of the licensees corrective

actions. The inspectors reviewed the licensees work practices to evaluate whether

these may have played a role in the degradation of the structure, system, and

component. The inspectors assessed the licensees characterization of the degradation

in accordance with 10 CFR 50.65 (the Maintenance Rule), and verified that the licensee

was appropriately tracking degraded performance and conditions in accordance with the

Maintenance Rule.

These activities constituted completion of two maintenance effectiveness samples, as

defined in Inspection Procedure 71111.12.

b.

Findings

No findings were identified.

- 12 -

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

a.

Inspection Scope

The inspectors reviewed six risk assessments performed by the licensee prior to

changes in plant configuration and the risk management actions taken by the licensee in

response to elevated risk:

October 16, 2013, Appendix R reactor building local auxiliary safe shutdown

control panel availability when reactor temperature rises above 200 degrees

Fahrenheit

November 18, 2013, 4160 Vac Bus F undervoltage relay testing

November 19, 2013, Inclement weather and off site power

December 16, 2013, Replacement of service water booster pump C

December 18, 2013, Control room envelope boundary door seal H305

repair/replacement

December 31, 2013, Temporary steam exclusion boundaries for control building,

903 feet corridor and door D301

The inspectors verified that these risk assessments were performed timely and in

accordance with the requirements of 10 CFR 50.65 (the Maintenance Rule) and plant

procedures. The inspectors reviewed the accuracy and completeness of the licensees

risk assessments and verified that the licensee implemented appropriate risk

management actions based on the result of the assessments.

Additionally, on October 13, 2013, the inspectors also observed portions of one

emergent work activitiy that had the potential to affect the functional capability of

mitigating systems.

Diesel generator 1 unavailable and Yellow risk for jacket water leak to the lube oil

system

The inspectors verified that the licensee appropriately developed and followed a work

plan for these activities. The inspectors verified that the licensee took precautions to

minimize the impact of the work activities on unaffected structures, systems, and

components.

These activities constitute completion of seven maintenance risk assessments and

emergent work control inspection samples, as defined in Inspection Procedure 71111.13.

b.

Findings

Introduction. The inspectors identified a Green, non-cited violation of

10 CFR 50.65(a)(4), Requirements for Monitoring the Effectiveness of Maintenance at

Nuclear Power Plants, for the licensees failure to implement required risk management

actions for safety-related 4160 Vac Bus F and G under voltage relay testing.

- 13 -

Description. The inspectors conducted a walk down of the work area and reviewed the

risk assessment and risk management actions associated with under voltage relay

testing of safety-related 4160 Vac Bus F. Inspectors noted that the cabinet doors were

opened during under voltage relay testing and asked the following questions: (1) Are the

safety-related 4160 Vac Bus F and G switchgear seismically qualified when the cabinet

doors are open? and (2) If the buses are not seismically qualified with the doors open,

what risk management actions are in place, and where are they documented, to ensure

they are returned to their seismically qualified condition and, thereby, maintained

available?

The licensee informed the inspectors that the 4160 Vac Bus F and G had only been

evaluated for seismic qualification with the doors closed, therefore, when the doors were

opened, the switchgear was not seismically qualified. The licensee also stated that

Station Procedure 0.41, Seismic Housekeeping, Revision 9, requires that unsecured

open panel access doors shall be attended by workers at all times and, based on this,

they considered the 4160 Vac Bus F and G available when the doors are open.

The inspectors reviewed Station Procedure 0.41, Seismic Housekeeping, Revision 9,

and Station Procedure 0.49, Scheduled Risk Assessment, Revision 34. Inspectors

noted that Station Procedure 0.49 allowed operators to declare equipment available,

provided that, restoration was directed by a procedure, restoration could be done in a

few simple actions, restoration did not require diagnosis, and the function could be

promptly restored either by an operator in the control room or by a dedicated operator

stationed locally for that purpose. Inspectors also noted that neither Station

Procedure 0.41 nor the work order instructions associated with 4160 Vac Bus G and F

under voltage relay testing contained specific directions to restore the buses to their

seismically qualified condition for event response. The inspectors informed the licensee

of their concern, and to capture this concern in the stations corrective action program,

the licensee initiated Condition Report CR-CNS-2013-06870.

The licensee implemented the required additional risk management action through a

revision to Station Procedure 0.41, which ensured workers are briefed to close panel

access doors in the event of an emergency or as directed by control room personnel.

The inspectors determined that the apparent cause of this finding was that the licensee

had failed to follow the requirements of Station Procedure 0.49 for maintaining

availability of the safety-related 4160 Vac Bus F and G when not in their seismically

qualified condition, i.e. cabinet doors open. Specifically, restoration of the 4160 Vac

buses was not directed by a procedure, work order instruction, or standing order.

Analysis. The licensees failure to implement required risk management actions during

maintenance activities was a performance deficiency. This performance deficiency was

more than minor, and therefore a finding, because it was associated with the equipment

performance attribute of the Mitigating Systems Cornerstone and affected the associated

objective. Specifically, by failing to implement required risk management actions to

restore 4160 Vac Bus F and G to their seismically qualified condition, i.e. cabinet doors

closed, this thereby affected the associated objective to ensure availability, reliability,

and capability of systems that responds to initiating events to prevent undesirable

consequences. Using Inspection Manual Chapter 0609, Appendix K, Maintenance Risk

Assessment and Risk Management Significance Determination Process, dated May 5,

- 14 -

2005, Flowchart 2, Assessment of Risk Management Actions, the inspectors

determined the need to calculate the risk deficit to determine the significance of this

issue. A senior reactor analyst performed a bounding detailed risk evaluation which

determined that the incremental core damage probability associated with this finding was

less than 1 X 10-6, so the finding has very low safety significance (Green). The finding

has a cross-cutting aspect in the area of human performance associated with the work

practices component because the licensee failed to define and effectively communicate

expectations regarding procedural compliance and to ensure that personnel follow

procedures H.4(b).

Enforcement. Title 10 CFR 50.65(a)(4) states, in part, that before performing

maintenance activities, the licensee shall assess and manage the increase in risk that

may result from the proposed maintenance activities. Contrary to the above, until

October 2013, the licensee failed to properly manage the increase in risk that resulted

from proposed maintenance activities. Specifically, measures established by the

licensee failed to implement required risk management actions for the proposed

maintenance activity of under voltage relay testing for the safety-related 4160 Vac Bus F

and G when not in their seismically qualified condition. The licensee corrected this issue

by providing procedural guidance for implementation of the required risk management

actions. This violation is being treated as a non-cited violation, consistent with

Section 2.3.2.a of the Enforcement Policy. The violation was entered into the licensees

corrective action program as Condition Report CR-CNS-2013-06870.

(NCV 05000298/2013005-02, Failure to Implement Risk Management Actions for

Proposed Maintenance Activities)

1R15 Operability Determinations and Functionality Assessments (71111.15)

a.

Inspection Scope

The inspectors reviewed four operability determinations that the licensee performed for

degraded or nonconforming structures, systems, or components:

October 4, 2013, Operability determination of the service water booster pump C

missing bearing

October 9, 2013, Operability determination for incorrect grease in the primary

containment isolation valves RW-AO-AO82, 83, 94, and 95

October 23, 2013, Operability determination of the auxiliary steam piping high-

energy line break affecting safety related structures, systems, and components

outside secondary containment

November 26, 2013, Operability determination of the 4160 Vac, Bus G and

Division II service water pumps

The inspectors reviewed the timeliness and technical adequacy of the licensees

evaluations. Where the licensee determined the degraded structures, systems, and

components to be operable, the inspectors verified that the licensees compensatory

measures were appropriate to provide reasonable assurance of operability. The

inspectors verified that the licensee had considered the effect of other degraded

conditions on the operability of the degraded structures, systems, and components.

- 15 -

These activities constitute completion of four operability and functionality review

samples, as defined in Inspection Procedure 71111.15

b.

Findings

Introduction. The inspectors identified a Green non-cited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, associated with the

licensees failure to perform an adequate operability determination in accordance with

Station Procedure 0.5OPS, Operations Review of Condition Reports/Operability

Determination.

Description. While reviewing material associated with NCV 05000298/2013005-02,

Failure to Implement Risk Management Actions for Proposed Maintenance Activities,

inspectors determined that there were other safety-related relays on the 4160 Vac Bus F

and G cabinet doors and questioned why they were not inoperable with the cabinet

doors open. Inspectors informed operators of their questions.

Operations evaluated the inspectors questions as part of their review documented in

Condition Report CR-CNS-2013-06870. During this review operations department

determined that the relays in question had not previously been evaluated for operability,

so an evaluation was performed and documented in this condition report. Operators

determined that no other relays operability was affected by opening the cabinet doors.

During discussions with operators, inspectors questioned this determination.

Specifically, inspectors questioned why the high pressure trip relay associated with the

auto position of the service water pumps on the G bus, having the potential to change

state during a seismic event and potentially affecting the ability of the pump to start on a

low pressure signal, did not affect operability during testing. Operators responded that

the auto position on the switch was not discussed in the USAR nor the technical

specifications. Therefore, this switch position did not have a credited function. Thus, no

operability concerns existed and no further evaluations were required.

Inspectors subsequently reviewed the USAR and technical specifications. During this

review, they noted that Surveillance Requirement 3.7.2.4 required the licensee to verify

that the service water pumps would start on a low pressure signal when in the auto

position. Inspectors determined that operators had failed to adequately evaluate the

service water pump relays on the G bus cabinet doors for operability. Inspectors

informed the licensee of their concerns and the licensee initiated Condition

Report CR-CNS-2014-00122 to capture this issue in the stations corrective action

program.

Inspectors noted that Station Procedure 0.5OPS, Operations Review of Condition

Reports/Operability Determinations, Revision 46, provided the guidance used by

operations staff at the Cooper Nuclear Station to perform operability determinations.

Section 3.1 required, in part, that the shift manager, document the basis for operability

when a degraded or nonconforming condition exists.

Analysis. The failure to properly assess and document the basis for operability when a

degraded or nonconforming condition was identified was a performance deficiency. The

- 16 -

performance deficiency was more than minor, and therefore a finding, because it was

associated with the equipment performance attribute of the Mitigating Systems

Cornerstone and affected the cornerstone objective to ensure availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, the licensees failure to properly document and assess the

basis for operability resulted in a condition of unknown operability for a degraded

nonconforming condition. Using Inspection Manual Chapter 0609, Appendix A, Initial

Screening and Characterization of Findings, dated July 1, 2012, inspectors determined

that the finding was of very low safety significance (Green) because the finding: (1) was

not a deficiency affecting the design and qualification of a mitigating structure, system, or

component, and did not result in a loss of operability or functionality; (2) did not

represent a loss of system and/or function; (3) did not represent an actual loss of

function of at least a single train for longer than its technical specification allowed outage

time, or two separate safety systems out-of-service for longer than their technical

specification allowed outage time; and (4) did not represent an actual loss of function of

one or more nontechnical specification trains of equipment designated as high safety-

significance in accordance with the licensees maintenance rule program. The finding

has a cross-cutting aspect in the area of human performance associated with the

decision-making component because the licensee did not ensure that the proposed

action was safe in order to proceed, rather than unsafe to disapprove the action H.1(b).

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion V, requires, in part, that

activities affecting quality shall be accomplished in accordance with documented

instructions, procedures, or drawings, of a type appropriate to the circumstances.

Station Procedure 0.5OPS, Operations Review of Condition Reports/Operability

Determination, a procedure that is appropriate to the circumstances of evaluating the

operability of safety-related components, required the licensee to properly assess and

document the basis for operability when a degraded or nonconforming condition was

identified. Contrary to the above, on December 20, 2013, an activity affecting quality

was not accomplished in accordance with a procedure that was appropriate to the

circumstances. Specifically, operators failed to adequately evaluate the effect on

operability of taking electrical relays for the service water pumps out of their seismically

qualified configuration. To correct this issue the licensee directed that the affected

service water pump be declared inoperable during Division II under voltage testing. This

violation is being treated as a non-cited violation, consistent with Section 2.3.2.a of the

Enforcement Policy. The violation was entered into the licensees correction action

program as Condition Report CR-CNS-2014-00122. (NCV 05000298/2013005-03,

Failure to Follow Operability Procedure)

1R19 Post-Maintenance Testing (71111.19)

a.

Inspection Scope

The inspectors reviewed four post-maintenance testing activities that affected risk-

significant structures, systems, or components:

October 13, 2013, Diesel generator 1 emergent work control

October 13, 2013, Service water booster pump C

October 17, 2013, Service water booster pump B maintenance window

October 31, 2013, Service water pump A and SW-MOV-36MV

- 17 -

The inspectors reviewed licensing- and design-basis documents for the structures,

systems, and components and the maintenance and post-maintenance test procedures.

The inspectors observed the performance of the post-maintenance tests to verify that

the licensee performed the tests in accordance with approved procedures, satisfied the

established acceptance criteria, and restored the operability of the affected structures,

systems, and components.

These activities constitute completion of four post-maintenance testing inspection

samples, as defined in Inspection Procedure 71111.19.

b.

Findings

No findings were identified.

1R22 Surveillance Testing (71111.22)

a.

Inspection Scope

The inspectors observed two risk-significant surveillance tests and reviewed test results

to verify that these tests adequately demonstrated that the structures, systems, and

components were capable of performing their safety functions:

In-service test:

October 16, 2013, Division I diesel generator fuel oil transfer pump in-service

flow test

Containment isolation valve surveillance test:

October 3, 2013, North scram discharge volume vent isolation valve,

CRD-AOV-CV38B

The inspectors verified that these tests met technical specification requirements, that the

licensee performed the tests in accordance with their procedures, and that the results of

the tests satisfied appropriate acceptance criteria. The inspectors verified that the

licensee restored the operability of the affected structures, systems, and components

following testing.

These activities constitute completion of two surveillance testing inspection samples, as

defined in Inspection Procedure 71111.22.

b.

Findings

No findings were identified.

- 18 -

Cornerstone: Emergency Preparedness

1EP4 Emergency Action Level and Emergency Plan Changes (IP 71114.04)

a.

Inspection Scope

The NSIR headquarters staff performed an in-office review of the latest revisions of

various Emergency Plan Implementing Procedures (EPIPs) and the Emergency Plan

located under ADAMS accession number ML13336A463 as listed in the Attachment.

The licensee determined that in accordance with 10 CFR 50.54(q), the changes made in

the revisions resulted in no reduction in the effectiveness of the Plan, and that the

revised Plan continued to meet the requirements of 10 CFR 50.47(b) and Appendix E

to 10 CFR Part 50. The NRC review was not documented in a safety evaluation report

and did not constitute approval of licensee-generated changes; therefore, this revision is

subject to future inspection. The specific documents reviewed during this inspection are

listed in the Attachment.

These activities constitute completion of one sample as defined in Inspection

Procedure 71114.04-05.

b.

Findings

No findings were identified.

4.

OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency

Preparedness, Public Radiation Safety, Occupational Radiation Safety, and

Security

4OA1 Performance Indicator Verification (71151)

Mitigating Systems Performance Index: Emergency AC Power Systems (MS06), High

Pressure Injection Systems (MS07), Heat Removal Systems (MS08), Residual Heat

Removal Systems (MS09), and Cooling Water Systems (MS10)

a.

Inspection Scope

The inspectors reviewed the licensees mitigating system performance index data for the

period from the fourth quarter 2012 through the third quarter 2013 to verify the accuracy

and completeness of the reported data. The inspectors used definitions and guidance

contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment

Performance Indicator Guideline, Revision 7, to determine the accuracy of the reported

data.

These activities constituted verification of the mitigating system performance index for

emergency ac power systems, high pressure injection systems, heat removal systems,

- 19 -

residual heat removal systems, and cooling water systems, as defined in Inspection

Procedure 71151.

b.

Findings

No findings were identified.

4OA2 Problem Identification and Resolution (71152)

.1

Routine Review

a.

Inspection Scope

Throughout the inspection period, the inspectors performed daily reviews of items

entered into the licensees corrective action program and periodically attended the

licensees condition report screening meetings. The inspectors verified that licensee

personnel were identifying problems at an appropriate threshold and entering these

problems into the corrective action program for resolution. The inspectors verified that

the licensee developed and implemented corrective actions commensurate with the

significance of the problems identified. The inspectors also reviewed the licensees

problem identification and resolution activities during the performance of the other

inspection activities documented in this report.

b.

Findings

No findings were identified.

.2

Annual Follow-up of Selected Issues

a.

Inspection Scope

The inspectors selected two issues for an in-depth follow-up:

On October 16, 2013, the inspectors reviewed corrective actions associated with

the standby liquid control system test tank seismic II/I evaluation.

The inspectors assessed the licensees problem identification threshold, cause

analyses, extent of condition reviews and compensatory actions. The inspectors

verified that the licensee appropriately prioritized the planned corrective actions

and that these actions were adequate to correct the condition.

On December 16, 2013, the inspectors reviewed corrective actions associated

with an unplanned dose rate alarm

The inspectors assessed the licensees problem identification threshold, cause

analyses, extent of condition reviews and compensatory actions. The inspectors

verified that the licensee appropriately prioritized the planned corrective actions

and that these actions were adequate to correct the condition.

These activities constitute completion of two annual follow-up samples, as defined in

Inspection Procedure 71152.

- 20 -

b.

Findings

Introduction. The inspectors reviewed a self-revealing Green non-cited violation of

Technical Specification 5.4.1.a, associated with a radiation protection technicians failure

to follow the requirements of a radiation work permit.

Description. On November 4, 2013, a radiation protection technician signed into

Radiation Work Permit (RWP) 2013-001, Radiation Protection Activities, Revision 1, to

complete the weekly turbine building high radiation area door and posting inspections.

This radiation work permit had a dose limit of 20 millirem and dose rate limit of

80 millirem per hour, and it did not authorize the access to high radiation areas. The

technician had determined prior to entering the radiologically controlled area that the

performance of this task did not require entry into a high radiation area.

The inspections included the steam jet air ejector room gate posting. When the

technician entered the vestibule to the steam jet air ejector room, the individual failed to

notice the high radiation area posting which was between the individual and the steam

jet air ejector room gate posting. The technician entered the posted high radiation area

to check the posting on the steam jet air ejector room gate and received a dose rate

alarm. Upon receiving the dose rate alarm, the technician realized they had entered an

area that exceeded the dose rates allowed by the radiation work permit. The technician

immediately left the area and reported the alarm to supervision. The licensee

determined that the highest dose rate encountered by the technician was 97 millirem per

hour, and the total dose received was 0.5 millirem. The licensee entered this issue into

their corrective action program as Condition Report CR-CNS-2013-07506.

The licensee subsequently performed an apparent cause evaluation, and determined

that the apparent cause for this event was a personnel performance issue regarding

effective use of human performance tools. Specifically, (1) the technician failed to sign

in on the correct radiation work permit authorizing access to high radiation areas in

accordance with Station Procedure 9.EN-RP-101, Access Control for Radiologically

Controlled Areas, Revision 12; (2) the technician failed to obtain the required brief prior

to entering the high radiation area in accordance with Station Procedure 9.EN-RP-101;

(3) the technician failed to stop and perform a job site review when encountering a

posting change from a radiation area to high radiation area; and (4) the technician failed

to use STAR to engage and question this task prior to entering a high radiation area.

Inspectors reviewed the licensees cause analysis and determined that the identified

apparent cause was reasonable for the unplanned dose rate alarm. Inspectors also

noted that the technicians actions were contrary to the requirements of Station

Procedure 9.ALARA.4, Radiation Work Permits, Revision 17, Section 7.3, which stated

that each individual is responsible for complying with radiation work permits.

Analysis. The failure to follow radiation work permit requirements was a performance

deficiency. The performance deficiency was more than minor, and therefore a finding,

because it was associated with the program and process attribute of the Occupational

Radiation Safety Cornerstone and affected the associated cornerstone objective to

ensure the adequate protection of the workers health and safety from exposure to

radiation from radioactive material during routine civilian nuclear reactor operation.

Specifically, this finding resulted in a radiation protection technician receiving an

- 21 -

unintended and unexpected radiation dose. Using Manual Chapter 0609, Appendix C,

Occupational Radiation Safety Significance Determination Process, dated August 19,

2008, the inspectors determined that the finding was of very low safety significance

(Green) because: (1) it was not associated with as low as is reasonably achievable

(ALARA) planning; (2) it did not involve an overexposure; (3) there was no substantial

potential for an overexposure; and (4) the licensees ability to assess dose was not

compromised. The finding has a cross-cutting aspect in the area of human performance

associated with the work practices component because the individual failed to use

human error prevention techniques, such as pre-job briefs, self-and-peer checking, and

proper documentation of activities commensurate with the risk of the assigned task, such

that, work activities were performed safely H.4(a).

Enforcement. Technical Specification 5.4.1.a requires, in part, implementation of

applicable procedures recommended by Regulatory Guide 1.33, Revision 2, Appendix A,

February 1978. Section 7(e) of Appendix A requires, in part, procedures for access

control to radiation areas including a radiation work permit system. Station

Procedure 9.ALARA.4, Radiation Work Permits, Revision 17, implemented this

requirement, and Section 7.3 of Procedure 9.ALARA.4 stated that each individual is

responsible for complying with radiation work permits. Radiation Work Permit 2013-01,

Radiation Protection Activities, Revision 1, did not authorize entry into a high radiation

area and had a dose limit of 20 mrem and a dose rate limit of 80 mrem/hr. Contrary to

the above, on November 4, 2013, a radiation protection technician entered an area with

dose rates exceeding 80 mrem/hr, a condition not authorized by the radiation work

permit. Specifically, the technician failed to see a high radiation area posting and

entered an area with a dose rate of 97 mrem/hr. The licensee determined that this issue

was due to a human performance error and corrected the issue as such. This finding is

being treated as a non-cited violation, consistent with Section 2.3.2.a of the Enforcement

Policy. The violation was entered into the licensees corrective action program as

Condition Report CR-CNS-2013-07506. (NCV 05000298/2013005-04, Failure to

Implement a Radiation Protection Procedure)

.3 Semiannual Trend Review

a.

Inspection Scope

The inspectors reviewed the licensees corrective action program, performance

indicators, system health reports, and other documentation to identify trends that might

indicate the existence of a more significant safety issue. The inspectors verified that the

licensee was taking corrective actions to address identified adverse trends. The

inspectors also reviewed the licensees progress in addressing existing cross-cutting

themes in; the resources component of the human performance area H.2(c), the

corrective action program component of the problem identification and resolution

area P.1(c), and the decision making component related to the use of conservative

assumptions in decision making H.1(b).

These activities constitute completion of one semiannual trend review sample, as

defined in Inspection Procedure 71152.

b.

Findings

No findings were identified.

- 22 -

Cross-Cutting Issues Trend Review

(1)

Cross-Cutting Theme in Decision Making H.1(b)

In the 2012 mid-cycle assessment letter, dated September 4, 2012, the NRC identified 8

findings associated with the decision making component of the human performance area

involving the use of conservative decision making H.1(b). The NRC determined that a

substantive cross-cutting issue existed because there was a concern with the licensees

scope of effort and progress in addressing this cross-cutting theme, and this theme

repeated a theme identified in earlier assessment periods.

In the 2012 end-of-cycle assessment letter, dated March 4, 2013, the NRC identified 13

findings associated with the cross-cutting aspect of H.1(b). The NRC maintained this

substantive cross-cutting issue open. The licensee initiated Condition

Report CR-CNS-2013-01740, 2012 NRC Annual Assessment Letter Identified 3

Substantive Cross-Cutting Issues, on March 4, 2013. The licensees investigation

determined that the root causes were:

The stations standards related to the resolution of apparently low significance

regulatory issues were low and did not meet Entergy fleet or industry

expectations. This was evidenced by a lack of urgency to fully understand and

resolve substantive cross-cutting issues and NRC findings of low significance

(Green).

The stations Engineering and Operations departments were not adequately

proficient in the application of the licensing and design basis of the plant. Weak

design basis knowledge together with limited experience related to the

application of the design basis, particularly in engineering, resulted in the

reduced levels of proficiency.

The licensees corrective actions for the identified causes were:

Assign mentors to review key engineering analysis products,

Revise the stations corrective action program for how violations and substantive

cross-cutting issues were evaluated,

Conduct operability training with the operations department, and

Conduct training on the stations design and licensing basis with engineering and

operations departments.

In the 2013 mid-cycle assessment letter, dated September 3, 2013, the NRC recognized

the licensee had implemented some corrective actions and had scheduled other

corrective actions for future completion. On October 8, 2013, the NRC was notified of

the licensees readiness for this inspection.

On October 21, 2013, the licensee initiated Condition Report CR-CNS-2013-07205,

NRC Findings with a CCA of H.1(b), to investigate the most recent findings with

H.1(b). The licensees investigation determined that the root (common) cause of these

- 23 -

findings was that clear standards and expectations for the "burden of proof

requirements" for conservative decision making have not been consistently set and

reinforced. The licensee determined that the contributing cause was that prior to the

changes made by CR-CNS-2013-01740, condition reports that documented NCVs and

other NRC Findings of Low Significance had typically not investigated the underlying

process, program, or organizational factors that caused the event to become an NCV.

The licensee determined that the corrective actions described in Condition

Report CR-CNS-2013-01740 were adequate to address the identified causes.

This baseline inspection semi-annual trend review monitored for sustainable

performance improvements as evidenced by effective implementation of an appropriate

corrective action plan that results in no safety significant inspection findings and a

notable reduction in the overall number of inspection findings with the same common

theme.

To date the NRC has identified 7 findings with the cross-cutting aspect of H.1(b) and

this continues to comprise a cross-cutting theme. The licensee has implemented

corrective actions to address this theme and the inspectors will continue to monitor for

sustained improvement.

(2) Cross-Cutting Theme in Documentation and Procedures H.2(c)

In the 2012 mid-cycle assessment letter, dated September 4, 2012, the NRC identified 4

findings with an associated cross-cutting aspect in the resources component of the

human performance area of failing to provide complete, accurate and up-to-date design

documentation, procedures, and work packages, and correct labeling of components

H.2(c). At the time, the NRC did not identify a substantive cross-cutting issue due to

the licensees scope of effort in addressing the theme, and because it was an emergent

performance trend.

In the 2012 end-of-cycle assessment letter, dated March 4, 2013, the NRC identified 4

findings with the associated cross-cutting aspect of H.2(c). The NRC opened a

substantive cross-cutting aspect because the corrective actions had not been effective in

addressing the issue. The licensee initiated Condition Report CR-CNS-2013-01740.

2012 NRC Annual Assessment Letter Identified 3 Substantive Cross-Cutting Issues, on

March 4, 2013. The licensees investigation determined that the root causes were:

The stations standards related to the resolution of apparently low significance

regulatory issues were low and did not meet Entergy fleet or industry

expectations. This was evidenced by a lack of urgency to fully understand and

resolve substantive cross-cutting issues and NRC findings of low significance

(Green).

The stations Engineering and Operations departments were not adequately

proficient in the application of the licensing and design basis of the plant. Weak

design basis knowledge together with limited experience related to the

application of the design basis, particularly in engineering, resulted in the

reduced levels of proficiency.

The licensees corrective actions for the identified causes were:

- 24 -

Assign mentors to review key engineering analysis products,

Revise the stations corrective action program for how violations and substantive

cross-cutting issues were evaluated,

Conduct operability training with the operations department, and

Conduct training on the stations design and licensing basis with engineering and

operations departments.

This baseline inspection semi-annual trend review monitored for sustainable

performance improvements as evidenced by effective implementation of an appropriate

corrective action plan that results in no safety significant inspection findings and a

notable reduction in the overall number of inspection findings with the same common

theme.

The inspectors have observed sustained improvement in the resources component of

the human performance area as demonstrated by no findings with that theme following

full implementation of appropriate corrective actions.

(3)

Cross-Cutting Theme in Problem Evaluation P.1(c)

In the 2011 mid-cycle assessment letter, dated September 1, 2011, the NRC staff

identified 6 findings associated with the corrective action program component of the

problem identification and resolution area in the aspect of thoroughness of problem

evaluation such that the resolutions address causes and extent of conditions P.1(c).

The NRC determined that a substantive cross-cutting issue did not exist because the

NRC did not have a concern with the licensees scope of effort and progress in

addressing the cross-cutting theme and because it was a recent performance trend.

In the 2011 end-of-cycle assessment letter, dated March 5, 2012, the NRC identified 7

findings with a cross-cutting aspect in P.1(c). The NRC opened a substantive cross-

cutting issue in this cross-cutting theme because the NRC had a concern with the

licensees scope of effort and progress in addressing the issue.

In the 2012 mid-cycle assessment letter, dated September 4, 2012, the NRC identified 8

findings with a cross-cutting aspect of P.1(c) and maintained this substantive cross-

cutting issue open.

In the 2012 end-of-cycle assessment letter, dated March 4, 2013, the NRC identified 8

findings with a cross-cutting aspect of P.1(c) and maintained this substantive cross-

cutting issue open. The licensee initiated Condition Report CR-CNS-2013-01740. 2012

NRC Annual Assessment Letter Identified 3 Substantive Cross-Cutting Issues, on

March 4, 2013. The licensees investigation determined that the root causes were:

The stations standards related to the resolution of apparently low significance

regulatory issues were low and did not meet Entergy fleet or industry

expectations. This was evidenced by a lack of urgency to fully understand and

resolve substantive cross-cutting issues and NRC findings of low significance

(Green), and

- 25 -

The stations Engineering and Operations departments were not adequately

proficient in the application of the licensing and design basis of the plant. Weak

design basis knowledge together with limited experience related to the

application of the design basis, particularly in engineering, resulted in the

reduced levels of proficiency.

The licensees corrective actions for the identified causes were:

Assign mentors to review key engineering analysis products,

Revise the stations corrective action program for how violations and substantive

cross-cutting issues were evaluated,

Conduct operability training with the operations department, and

Conduct training on the stations design and licensing basis with engineering and

operations departments.

This baseline inspection semi-annual trend review monitored for sustainable

performance improvements as evidenced by effective implementation of an appropriate

corrective action plan that results in no safety significant inspection findings and a

notable reduction in the overall number of inspection findings with the same common

theme.

The inspectors have observed sustained improvement in the resources component of

the human performance area as demonstrated by one finding with that theme following

full implementation of appropriate corrective actions.

4OA5 Other Activities

.1

(Closed) Violation 05000298/2013009-01: Failure to Maintain Seismic Qualification of

Standby Liquid Control System (EA-13-075)

The inspectors reviewed the licensees immediate corrective actions and implemented

corrective actions to restore the plant to regulatory conformance. The inspectors noted

that the actions implemented by the licensee involved reviewing the seismic II/I

qualification of the Standby Liquid Control System test tank. The inspectors determined

that these actions have addressed the concerns expressed in the violation. This

violation is closed.

.2

IP 92723, Follow Up Inspection for Three or More Severity Level IV Traditional

Enforcement Violations in the Same Area in a 12-Month Period

a.

Inspection Scope

As announced in the Mid-Cycle Performance Review and Inspection Plan letter

(ML13246A356) and in accordance with IP 92723, the inspectors reviewed the

licensees responses to the three traditional-enforcement violations identified during the

12-month period that ended on June 30, 2013. These violations were non-cited and

were designated as follows:

- 26 -

NCV 05000298/2012004-06, Failure to Obtain Prior NRC Approval for a Change

Regarding the Supplemental Diesel Generator

NCV 05000298/2013009-02, Failure to Notify the NRC within Eight Hours of a

Nonemergency Event

NCV 05000298/2012301-01; Failure to Maintain Both Initial Licensing Examination and

Licensed Operator Examination Integrity

The inspectors reviewed the licensees responses to these violations to verify that the

licensee understood the causes of these violations, identified the extent-of-condition and

extent-of-cause associated with these violations, and had taken corrective actions that

are sufficient to address the causes of the violations.

b.

Findings

No findings were identified.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On October 24, 2013, the inspectors conducted an inspection debrief with Mr. J. Austin,

Training Manager, and other members of the licensee's staff, on the results of the licensed

operator requalification program inspection. The licensee acknowledged the findings presented.

After reviewing the complete biennial requalification cycle examination results, the inspectors

conducted a telephonic exit with Mr. C. Herring, Operations Training Superintendent, on

December 19, 2013. The licensee acknowledged the results as presented.

The inspectors asked the licensee whether any materials examined during the inspection should

be considered proprietary. No proprietary information was identified.

On December 20, 2013, the inspectors presented the inspection results to Mr. R. Penfield,

Director of Nuclear Safety Assurance, and other members of the licensee staff. The licensee

acknowledged the issues presented. The licensee confirmed that any proprietary information

reviewed by the inspectors had been returned or destroyed.

4OA7 Licensee-Identified Violations

The following violations of very low safety significance (Green) or Severity Level IV were

identified by the licensee and are violations of NRC requirements which meets the criteria of the

NRC Enforcement Policy Section 2.3.2.a., for being dispositioned as non-cited violation.

Title 10 CFR 50.65(a)(1), Requirements for monitoring the effectiveness of maintenance

at nuclear power plants, requires, in part, that holders of an operating license shall

monitor the performance or conditions of structures, systems, or components within the

scope of the monitoring program against licensee established goals in a manner

sufficient to provide reasonable assurance that such structures, systems, or components

are capable of fulfilling their intended safety function. Contrary to the above, on

November 6, 2013, the licensee identified that they failed to establish goals in a manner

sufficient to provide reasonable assurance that structures, systems, or components were

- 27 -

capable of fulfilling their intended safety function. Specifically, the licensee failed to

establish goals for the main condenser when it was placed in an (a)(1) status. This

performance deficiency was more than minor, and therefore a finding, because it was

associated with the equipment performance attribute of the Initiating Events

Cornerstone, and affected the associated cornerstone objective to limit the likelihood of

events that upset plant stability and challenge critical safety functions during shutdown

as well as power operations. Using Inspection Manual Chapter 0609, Appendix A, The

Significance Determination Process (SDP) For Findings At-Power, inspectors

determined that the finding was of very low safety significance (Green) because the

finding did not cause a reactor trip and the loss of mitigation equipment relied upon to

transition the plant from the onset of the trip to a stable shutdown condition. This issue

was entered into the licensees corrective action program as Condition

Report CR-CNS-2013-07967 for resolution.

Title 10 CFR 50.48 requires, in part, that licensees must have a fire protection plan that

satisfies Criterion 3 of Appendix A of 10 CFR Part 50. Condition 2.C.(4) of the Cooper

Nuclear Station (CNS) License Number DPR-46 states, in part, that the licensee shall

implement and maintain in effect all provisions of the approved fire protection program

as described in the Updated Safety Analysis Report (USAR) and as approved in the

Safety Evaluation dated November 29, 1977, and subsequent supplements. Chapter 9

of the USAR, Fire Protection System, provides a summary description of the SSCs that

are relied on to meet the requirements of General Design Criterion 3, Fire Protection, in

10 CFR Part 50 Appendix A. USAR Section 9.3.2.6 states that the Service Water Pump

Room is protected by an automatic Halon 1301 fire suppression system. USAR Section

9.6 states that the limiting conditions for operation and surveillance requirements for the

Fire Protection System are provided in the CNS Technical Requirements Manual (TRM).

TRM T 3.11.5, Halon 1301 Fire Suppression System, requires that a continuous fire

watch be established if the Halon 1301 system in the Service Water Pump Room is

inoperable. CNS Administrative Procedure (AP) 0.39.1, Fire Watches and Fire

Impairments, Revision 9, Paragraph 5.1.8, Responsibilities of Compensatory

Continuous Fire Watches, stated, in part, that Fire Watch shall observe the..Affected

Area and be alert for signs of fire, smoke, and changing conditions. Contrary to the

requirement in CNS AP 0.39.1, Paragraph 5.1.8, on December 5, 2012, an individual

assigned to fire watch duty to observe the Affected Area was deliberately not alert for

signs of fire, smoke, and changing conditions. Specifically, an individual assigned to

continuous fire watch duty in the Service Water Pump Room, while the Halon 1301

system was inoperable, was found by a non-licensed operator to be inattentive. This

caused the licensee to be in violation of License Condition 2.C.(4) of License No. DPR-

46. The licensee identified the violation, performed an internal investigation, and took

appropriate corrective actions. This included entering this issue into their corrective

action program as Condition Report CR-CNS-2012-10123 for resolution. These

corrective actions were completed on December 24, 2012. (EA-13-225)

A-1

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

J. Austin, Training Manager

T. Barker, Manager, Engineering Programs and Components

J. Bebb, Staff Health Physicist, Radiation Protection

J. Bednar, Technical Supervisor, Radiation Protection

R. Beilke, Manager, Radiation Protection

D. Buman, Director, Engineering

T. Chard, Manager, Quality Assurance

S. DeRosier, Operator Training Superintendent

J. Dixon, ALARA Supervisor, Radiation Protection

R. Estrada, Manager, Design Engineering

M. Ferguson, Manager, Emergency Preparedness

J. Florence, Simulator Supervisor

C. Herring, Superintendant, Operations Training, Requalification

K. Higginbotham, General Plant Manager, Operations

K. Fike, Plant Chemist, Chemistry

J. Flaherty, Senior Staff Licensing Engineer, Licensing

E. Jackson, Exam Developer

D. Madsen, Senior Staff Engineer, Licensing

R. Morris, Specialist, Radiation Protection

J. Olberding, Licensing Specialist

R. Penfield, Director Nuclear Safety Assurance

J. Stough, Manager, Information Technology

K. Tanner, Radiological Shift Supervisor, Radiation Protection

D. Van Der Kamp, Manager, Licensing

A. Walters, Manager, Chemistry

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed 05000298/2013005-01

NCV

Failure to Promptly Identify and Correct a Condition Adverse to

Quality (Section 1R04)05000298/2013005-02

NCV

Failure to Implement Risk Management Actions for Proposed

Maintenance Activities (Section 1R13)05000298/2013005-03

NCV

Failure to Follow Operability Procedure (Section 1R15)05000298/2013005-04

NCV

Failure to Implement a Radiation Protection Procedure

(Section 4OA2)

A-2

Closed 05000298/2013009-01

VIO

Failure to Maintain Seismic Qualification of Standby Liquid

Control System (EA-13-075)(Section 4OA5)

LIST OF DOCUMENTS REVIEWED

Section 1R04: Equipment Alignment

Miscellaneous Documents

Number

Title

Revision

Engineering Evaluation, Assessment of CNS Compliance

with 10 CFR 50.49

0

PBD-EQ, Cooper Nuclear Station Environmental

Qualification Program Basis Document

5 00-95D

NEDC, HELB EQ - Reactor Building

Pressure/Temperature

1 02-005

NEDC, HELB EQ - Mass and Energy Release

1 02-007

NEDC, Review of MPR Calculation 315-0030-001

1 09-102

NEDC, Internal Flooding - HELB, MELB, and Feedwater

Line Break

0 and 1 13-024

NEDC, Steam Exclusion Barrier for Building Door D301

0 13-036

Engineering Evaluation, Steam Exclusion Boundary for

Controlled Corridor Door D301 and Control Building

(EL 903-06) Corridor and Rooms

0 90-031

Design Change, Smoke/Fire Dampers for Control Room

Ventilation

0 91-119

Design Change, DG-Steam Heating Piping System and HV

Fan Coil Restraints

0 91-227

NEDC, Code Qualification of AS, ACD, and CH Piping

Supports in the CNS Diesel Generator Bldg

1 91-277

NEDC, Diesel Generator Building AS, ACD, and CH Piping

Analysis Problem AS-01

1 92-135

NEDC, Operability Evaluation of Steam Piping in the Cable

Spreading Room

1

2045

Burns and Roe, Sheet 1, Flow Diagram Core Spray System

Cooper Nuclear Station

N58

A-3

Miscellaneous Documents

Number

Title

Revision

3002

Burns and Roe, Sheet 1, Cooper Nuclear Station Auxiliary

One Line Diagram, MCC Z, SWGR Bus 1A, 1B, 1E and

Critical SWGR Bus 1F, 1G

N49

3058

Burns and Roe, Cooper Nuclear Station DC One Line

Diagram

N63

Procedures

Number

Title

Revision

2.2.48.2A

Operations Procedure, Station Heating System Electrode

Boilers C and D Component Checklist

26

2.2.73

Operations Procedure, Standby Gas Treatment System

50

2.2A_125DC.DIV1 Operations Procedure, 125 VDC Power Checklist (Div 1)

7

2.2A_250DC.DIV2 Operations Procedure, 250 VDC Power Checklist (Div 2)

0

2.2A_4160.Div1

Operations Procedure, 4160 VAC Auxilary Power Checklist

(Div 1)

1

2.3_9-3-1

Operations Procedure, Panel 9-3 Annunciator 9-3-1

31

2.3_FP-1

Operations Procedure, Fire Protection-Annunciator 1

11

2.3_R-2

Operations Procedure, Panel R - Annunciator R-2

17

2.3_S-1

Operations Procedure, Panel S - Annunciator S-1

18

2.4HVAC

Operations Procedure, Building Ventilation Abnormal

20

2.4TEC

Operations Procedure, TEC Abnormal

25

5.1Incident

Emergency Procedure, Site Emergency Incident

26

6.1EE.302

Surveillance Procedure, 4160V Bus 1F Undervoltage Relay

and Relay Timer Functional Test (Div 1)

31

Condition Reports (CRs)

CR-CNS-2002-03802

CR-CNS-2005-04427

CR-CNS-2013-07073

CR-CNS-2013-07142

CR-CNS-2013-07358

A-4

Section 1R05: Fire Protection

Miscellaneous Documents

Number

Title

2013-281

Barrier Permit

Procedures

Number

Title

Revision

0.23

Station Procedure, CNS Fire Protection Plan

68

Work Orders

4935603

4978976

4978994

Section 1R06: Flood Protection Measures

Procedures

Number

Title

Revision

2.3_S-1

Operations Procedure, Panel S - Annunciator S-1

18

Condition Reports (CRs)

CR-CNS-2012-05939

CR-CNS-2012-08055

Section 1R07: Heat Sink Performance

Miscellaneouse Documents

Number

Title

Revision

REC-F01

Performance Criteria Basis

2

Procedures

Number

Title

Revision

13.15.1

Performance Evaluation Procedure, Reactor Equipment

Cooling Heat Exchanger Performance Analysis

33

Condition Reports (CRs)

CR-CNS-2013-07610

A-5

Work Orders

4895739

Section 1R11: Licensed Operator Requalification Program and Licensed Operator

Performance

Procedures

Number

Title

Revision

6.CRD.301

Surveillance Procedure, Withdrawn Control Rod Operability

IST Test

29

6.RCIC.102

Surveillance Procedure, RCIC IST and 92 Day Test

31

OTP810

Operations Department Examination Security

16

OTP812

Conduct of Operator Oral Boards

12

OTP809

Operator Requalification Examination Administration

16

OTP808

Open Reference Examination Test Item Development

1

OTP806

Conduct of Simulator Training and Evaluation

16

OTP805

Licensed Operator Requalification Biennial Written Exam

12

OTP804

Requalification Scenario Exercise Guide Development

19

OTP803

Development of Operations Training JPMs

4

OTP813

Annual Operating Requal. Exam Development and Admin.

2

OTP814

SIMULATOR SCENARIO-BASED TRAINING

May 2, 2012

TPP 201

CNS Licensed Personnel Requalification Program

61

2.0.7

CNS Licensed Operator Requalification Program

6

NTP8.2

Preparation and Submittal of Operator and Senior Operator

License Applications

6

NTP8.1

Administration of Licensed Operator Medical Examination

Program

14

EN-TQ-201-04

SAT - Implementation Phase

2

A-6

Procedures

Number

Title

Revision

EDP-06

Supporting Requirements for Configuration Change Control 46

3.4

Configuration Change Control

55

Miscellaneous Documents

Number

Title

Revision/Date

NA

Steady State Test - 23%, 75%, 100%

August 2, 2013

NA

Transient Performance Test #5

October 21, 2013

NA

Transient Performance Test #9

October 21, 2013

SKL012-06-01

OPS Simulator Introduction

179

NTD120057

Simulation Configuration Update - PTL 1207

December 3, 2012

NTD130005

Simulation Configuration Update - PTL 1301

January 8, 2013

NTD130006

Simulation Configuration Update - PTL 1302

January 21, 2013

NTD130014

Simulation Configuration Update - PTL 1304

February 20, 2013

NA

Report - Simulator Discrepancies by

Due Date

October 21, 2013

SKL034-20-127

JPM

1

SDR 13-0061

2 Parameters Out-of-Spec Steady State Test

July 19, 2013

SDR 13-0043

Feedwater Heater Leaks

March 5, 2013

SMP 13-0010

Implement SPC 2012-92 to Simulator

January 18, 2013

SMP 13-0004

Replace SIM RHR-FR-143

October 10, 2012

SDP 13-0025

Correct Simulator RWCU Pump Trip Logic

February 20, 2013

TQF-210-DD04

Performance Evaluation Reports for 2 ROs

October 23, 2013

TQF-210-DD03

LOR Simulator Crew Performance Eval Reports October 23, 2013

OTP813 Att 12

JPM Evaluation Results for 2 ROs

October 23, 2013

NA

2013 LOR Bienniel Written Exam Week 1

through 6 (RO/SRO)

December 12, 2013

A-7

Miscellaneous Documents

Number

Title

Revision/Date

NA

Five Randomly Selected Licensed Operator

Medical Records

October 22, 2013

Section 1R12: Maintenance Effectiveness

Miscellaneous Documents

Number

Title

Revision

EN-DC-207

Maintenance Rule Periodic Assessment

2C0

PF03A

Engineering Evaluation, Provides Essential 4160 VAC

Power to Critical Station Auxiliary Loads (4160V Division 1

Distribution System

1

PF03B

Engineering Evaluation, Provides Essential 4160 VAC

Power to Critical Station Auxiliary Loads (4160V Division 2

Distribution System

1

Condition Reports (CRs)

CR-CNS-2012-05249

CR-CNS-2012-06254

CR-CNS-2013-06870

CR-CNS-2013-07967

Section 1R13: Maintenance Risk Assessments and Emergent Work Control

Miscellaneous Documents

Number

Title

Revision

EQDP.2.212

Appendix R MOV Local Auxiliary Safe Shutdown Control

Panel Components

1 09-102

NEDC, Internal Flooding - HELB, MELB, and Feedwater

Line Break

1 13-023

NEDC, HVAC Vent Steam Exclusion Boundary

0 13-024

NEDC, Steam Exclusion Barrier for Building Door D301

0 13-027

NEDC, Control Building (EL 903-06)Temperature Rise

due to temporary SEB Barrier Installation

0 13-036

Engineering Evaluation, Steam Exclusion Boundary for

Controlled Corridor Door D301 and Control Building

(EL 903-06) Corridor and Rooms

0

2013-023

Barrier Control Permit

2013-281

Barrier Control Permit

A-8

Miscellaneous Documents

Number

Title

Revision

2013-0368

Barrier Control Permit

2013-0369

Barrier Control Permit

10977008

Technical Evaluation

0

Procedures

Number

Title

Revision

0-Barrier

Station Procedure, Barrier Control Process

7 and 9

0-Barrier-Misc

Station Procedure, Miscellaneous Buildings

3

0.41

Station Procedure, Seismic Housekeeping

9 and 10

0.49

Station Procedure, Schedule Risk Assessment

34

6.1EE.302

Surveillance Procedure, 4160V Bus 1F Undervoltage Relay

and Relay Timer Functional Test (Div 1)

31

Condition Reports (CRs)

CR-CNS-2013-00281

CR-CNS-2013-02682

CR-CNS-2013-06870

CR-CNS-2013-06949

CR-CNS-2013-06954

CR-CNS-2013-06979

CR-CNS-2013-07022

Work Orders

4889242

4910617

4910701

4920901

4922893

4921123

4935603

4941332

4945830

4945831

4958736

4978976

4978994

Section 1R15: Operability Determinations and Functionality Assessments

Miscellaneous Documents

Number

Title

Revision

71

Book, Calculations, Crane Runway Beam

0

71

Book, Calculations, 2 Ton Overhead Crane

0 91-119

Design Change, DG-Steam Heating Piping System and HV

Fan Coil Restraints

0

A-9

Procedures

Number

Title

Revision

0.5OPS

Station Procedure, Operations Review of Condition

Reports/Operability Determination

44

2.3_B-3

Operations Procedure, Panel B - Annunciator B-3

30

2.3_FP-1

Operations Procedure, Fire Protection-Annunciator 1

11

2.3_R-1

Operations Procedure, Panel R - Annunciator R-1

14

5.1Break

Emergency Procedure, Pipe Break Outside Secondary

Containment

14

Condition Reports (CRs)

CR-CNS-2012-07142

CR-CNS-2013-06843

CR-CNS-2013-06870

CR-CNS-2013-06916

CR-CNS-2013-07073

Section 1R19: Post-Maintenance Testing

Procedures

NUMBER

TITLE

REVISION

2.20.2

Station Procedure, Operation of Diesel Generators from

Diesel Generator Room

57

6.SW.202

Surveillance Procedure, Service Water Power Operated

Valve Operability Test

18

6.1SW.101

Surveillance Procedure, Service Water Surveillance

Operation (Div 1)(IST)

42

6.2SWBP.101

Surveillance Procedure, RHR Service Water Booster Pump

Flow Test and Valve Operability Test (Div 2)

23

7.0.5

Maintenance Procedure, Post Maintenance Testing

45

7.2.53.3

Maintenance Procedure, Diesel Engine Maintenance

34

Condition Reports (CRs)

CR-CNS-2013-07035

CR-CNS-2013-07041

CR-CNS-2013-07042

CR-CNS-2013-07047

CR-CNS-2013-07056

CR-CNS-2013-07060

CR-CNS-2013-07061

CR-CNS-2013-07063

CR-CNS-2013-07137

CR-CNS-2013-07397

CR-CNS-2013-07442

A-10

Work Orders

4895484

4895569

4895654

4895870

4921123

4932446

4954675

4958736

4978976

Section 1R22: Surveillance Testing

Miscellaneous Documents

Number

Title

Revision

Appendix A Valve Stroke Time Summary

223

Engineering Evaluation, Reconfiguration DGDO-V-19 from

Open to Close

0 01-081

Engineering Evaluation, Determination of Fuel Oil Specific

Gravity for Use in Diesel Fuel Oil Transfer Pump IST

Testing

0

Procedures

Number

Title

Revision

3.9

Engineering Procedure, ASME OM Code Testing of Pumps

and Valves

27

6.CRD.201

Surveillance Procedure, North and South SDV Vent and

Drain Valve Cycling, Open Verification, and Timing Test

20

6.DG.603

Surveillance Procedure, Diesel Fuel Oil Incoming Truck

Sample

21

6.1DG.401

Surveillance Procedure, Diesel Generator Fuel Oil Transfer

Pump IST Flow Test (Div 1)

31

Condition Reports (CRs)

CR-CNS-2013-06774

Work Orders

4908790

Section 1EP4: Emergency Action Level and Emergency Plan Changes

Number

Title

Revision

EPIP 5.7.1

Emergency Classification

49

A-11

Section 4OA1: Performance Indicator Verification

Miscellaneous Documents

Title

Revision

Mitigating Systems Performance Index (MSPI) Basis

Document

7

Procedures

Number

Title

Revision

0-EN-LI-114

Entergy Procedure, Performance Indicator Process

5C0

Condition Reports (CRs)

CR-CNS-2013-07693

Section 4OA2: Problem Identification and Resolution

Miscellaneous Documents

Number

Title

Revision 13-009

Engineering Evaluation, Evaluation of the SLC Test,

Storage, and Mix Tanks for Seismic

1 13-010

NEDC, CNS SLC Storage, Test, and Mix Tanks Seismic

Qualification

1

2013-01

Radiation Work Permit, RP Activities

1

2013-078

Radiation Work Permit, RP Activities in SWP Areas

1

Procedures

Number

Title

Revision

9.ALARA.4

RAD Protection Procedure, Radiation Work Permits

17

9.EN-RP-100

RAD Protection Procedure, Radiation Worker

Expectations

3

9.EN-RP-101

RAD Protection Procedure, Access Control For

Radiologically Controlled Areas

12

Condition Reports (CRs)

CR-CNS-2012-10636

CR-CNS-2013-02328

CR-CNS-2013-03572

CR-CNS-2013-07205

CR-CNS-2013-07506