ML13009A293

From kanterella
Jump to navigation Jump to search
Summary of Meeting with Tennessee Valley Authority Regarding Bellefonte Nuclear Plant, Unit 1, Fuel and Safety Analyses Methodologies
ML13009A293
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 01/16/2013
From: Justin Poole
Plant Licensing Branch II
To:
Poole, Justin
Shared Package
ML13011A250 List:
References
Download: ML13009A293 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 16. 2013 LICENSEE:

Tennessee Valley Authority FACILITY:

Watts Bar Nuclear Power Plant, Unit 2

SUBJECT:

SUMMARY

OF DECEMBER 10, 2012, MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING BELLEFONTE NUCLEAR PLANT, UNIT 1 On December 10, 2012. a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of this meeting was to discuss upcoming submittals regarding fuel design and safety analyses for Bellefonte Nuclear Plant (BLN), Unit 1. A list of participants is enclosed.

TVA provided a presentation to the NRC staff (Agencywide Documents Access and Management System Accession No. ML13011A338), which provided an overview of methods to be used for BLN, Unit 1 fuel design and safety analyses, and a submittal schedule for related documents. In the presentation, TVA discussed its plan to submit Technical Methodology Reports (TMRs) to the NRC in order to gain early NRC acceptance of methodologies to be used for the analyses in Chapters 4 and 15 of the BLN, Unit 1 Final Safety Analysis Report (FSAR),

to avoid the need for the development of a modified methodology late in the FSAR review process, and to provide a place for details required for regulatory review by the NRC but are more detailed than the standard content of the FSAR. The presentation included a list of Topical Reports (TRs), previously approved by the NRC, which TVA intends to use as part of the licensing basis for BLN, Unit 1. TVA also briefly discussed the need for AREVA to submit two additional TRs for NRC's review and approval, which would be referenced in the BLN, Unit 1 licensing basis. At the end of the presentation, TVA had a projected timeline for submitting the TMRs and the new TRs.

During the presentation, the NRC staff focused its questions and feedback to TVA on what processes are available to handle the review of the TMRs. TVA would like the NRC staff to review the TMRs as part of the BLN, Unit 1 license review, rather than having them submitted under the TR process. The NRC staff and TVA discussed the pros and cons for each process, but no agreement was reached. The NRC staff stated that internal meetings would be held prior to responding to TVA. Both the NRC staff and TVA agreed that further meetings on the topic of fuel design and safety analyses would be beneficial.

No members of the public were in attendance and no Public Meeting Feedback forms were received.

- 2 Please direct any inquiries to me at 301-415-2048 or via e-mail at justin. poole@nrc.gov.

Justin C. Poole, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-438

Enclosure:

List of Attendees cc w/encl: See next page

Tennessee Valley Authority cc:

Mr. K. D. Stinson Vice President, Bellefonte Project Tennessee Valley Authority 2744 Bellefonte Road, OSB-1A Hollywood, Alabama 35752 Mr. M. C. Bryan Manager (Acting), Licensing Bellefonte Nuclear Plant Units 1 and 2 Tennessee Valley Authority 2744 Bellefonte Road, OSB-1A Hollywood, Alabama 35752 Mr. P. D. Swafford Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 1101 Market Street Lookout Place 3R Chattanooga, TN 37402-2801 Mr. J. W. Shea Vice President, Nuclear licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37402-2801 Mr. D. C. Romashko Senior Manager, Quality Assurance Tennessee Valley Authority Bellefonte Nuclear Plant 2744 Bellefonte Road, OSB-1A Hollywood, Alabama 35752 Mr. E. J. Vigluicci Assistant General Counsel Tennessee Valley Authority 400 West Summit Hill Drive West Tower 6A Knoxville, TN 37902 BELLEFONTE NUCLEAR PLANT Mr. A. J. Simonti General Manager Bellefonte Technical Services Tennessee Valley Authority 2744 Bellefonte Road, OSB-1A Hollywood, Alabama 35752 State Health Officer Alabama Dept. of Public Health P.O. Box 303017 Montgomery, AL 36130-3017 Chairman Jackson County Commission Courthouse Scottsboro, AL 35752-0200 Director Alabama Emergency Management Agency P.O. Drawer 2160 Clanton, AL 35045-5160

MEETING ATTENDANCE LIST Licensee: Tennessee Valley Authority Plant: Bellefonte Nuclear Plant. Unit 1

Subject:

Fuels and Safety Analyses Methodologies Date: December 10, 2012 Location: U.S. Nuclear Regulatory Commission Time: 9:00 a.m. 11 :00 a.m.

Headquarters. Room 0-8B6 NAME Justin Poole TITLE Sr. Project Manager ORGANIZATION NRRI DORU Plant Licensing Branch 11-2 Christopher Jackson Branch Chief NRRI DSSI Reactor Systems Branch

! Anthony Mendiola Mathew Panicker Branch Chief Reactor Engineer NRRI DSSI Nuclear Performance and Code Review Branch NRRI DSSI Nuclear Performance and Code Review Branch Jennifer Gall Reactor Systems Engineer NRRI DSSI Reactor Systems Branch Harold Scott Nuclear Engineer NRCI Office of Researchl DSA Martin Bryan Manager, Licensing, Bellefonte TVA Mark Burzynski Bellefonte Engineering TVA David Lafever Bellefonte Engineering TVA Enclosure

- 2 I

TVA Henry Jones Bellefonte Engineering Director, Regulatory AREVAlTVA Pedro Salas Affairs I Jerald Holm AREVA Licensing Engineering AREVAlTVA Jeffery Seals Engineering Manager Non-LOCA Safety AREVA Douglas Brownson I Analysis Supervisor AREVA Fuels EDL AREVA Jeffrey S. Tucker PWR LOCA Manager AREVA Bob Baxter Bert Dunn Adv. Engineering LOCA AREVA Licensing AREVAlTVA INathan Hottle

- 2 Please direct any inquiries to me at 301-415-2048 or via e-mail at justin.poole@nrc.gov.

IRAJ Justin C. Poole, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket No. 50-438

Enclosure:

List of Attendees cc w/encl: See next page DISTRIBUTION:

PUBLIC LPL 2-2 Reading RidsAcrsAcnw MailCTR Resource RidsNrrDorILp12-2 Resource RidsNrrDssSnpb Resource HScott. RES RidsNrrDssSrxb Resource RidsNrrPMBeilefonte1 Resource RidsOpaMaii Resource RidsRgn2MailCenter Resource RidsNrrLABClayton Resource FKeith. NRR TWertz. NRR RidsOgcRp Resource TSantos. OEDO MPanicker. NRR JGail, NRR ADAMS Accession No. PKG ML13011A250 Meetin NoticeML12328A156 Meetin Summa ML13009A293 HandoutsML13011A338 E

DORLfLPL2-2/PM DORLfLPL2-2fLA(IT)

DORLfLPL2-2/LA PL2-2/BC DORLfLPL2-2/PM JPoole FKeith "w/edits*

n o

JPoole 1/14/13 1/11/13 1/16/13