ML12069A387
| ML12069A387 | |
| Person / Time | |
|---|---|
| Site: | Palo Verde |
| Issue date: | 03/09/2012 |
| From: | Thomas Farnholtz Region 4 Engineering Branch 1 |
| To: | Edington R Arizona Public Service Co |
| References | |
| IR-12-003 | |
| Download: ML12069A387 (6) | |
See also: IR 05000528/2012003
Text
March 9, 2012
Randall K. Edington, Executive
Vice President, Nuclear/CNO
Arizona Public Service Company
P.O. Box 52034, Mail Stop 7602
Phoenix, AZ 85072-2034
SUBJECT:
PALO VERDE NUCLEAR GENARATING STATION - NOTIFICATION OF NRC
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
(05000528/529/530/2012003)
Dear Mr. Edington:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission Region IV
staff will conduct a triennial heat sink performance inspection at the Palo Verde Nuclear
Generating Station Units 1, 2, and 3. The inspection will be comprised of two reactor inspectors
(one in training) from the NRC Region IV office. The inspection will be conducted in accordance
with Inspection Procedure 71111.07, "Heat Sink Performance."
The schedule for the inspection is as follows:
Onsite inspection - May 7-11, 2012
Experience has shown that this inspection is resource intensive both for the NRC inspectors
and your staff. In order to minimize the impact to your onsite resources and to ensure a
productive inspection, we have enclosed a request for documents needed for this inspection.
Please note that the documents are requested to be provided by April 30, 2012. We request,
that during the onsite inspection week, you ensure that copies of analyses, evaluations, or
documentation regarding the implementation and maintenance of your heat exchanger program
are available. Of specific interest are those documents that establish that your heat exchanger
program satisfies NRC regulatory requirements and conforms to applicable NRC guidance.
Also, appropriate personnel knowledgeable of safety-related heat exchangers should be
available to support the inspector at the site during the inspection.
We have discussed the schedule for this inspection activity with your staff and understand that
our regulatory contact for this inspection will be Del Elkinton of your licensing organization. If
there are any questions about this inspection or the material requested, please contact the
inspector, Gerond A. George, at 817-200-1562 or by email, Gerond.George@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the
UNITED STATES
NUCLEAR REGULATORY COMMISSION
RE G IO N I V
1600 EAST LAMAR BLVD
ARLINGTON, TEXAS 76011-4511
Randall K. Edington
- 2 -
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Thomas R. Farnholtz, Chief
Engineering Branch 1
Division of Reactor Safety
Dockets: 50-528; 50-529; 50-530
Licenses: NPF-41; NPF-51; NPF-74
Enclosure:
Heat Sink Performance Inspection Document Request
cc: Distribution via ListServ for Palo Verde Nuclear Generating Station
Randall K. Edington
- 3 -
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov )
Deputy Regional Administrator (Art.Howell@nrc.gov )
DRP Director (Kriss.Kennedy@nrc.gov )
DRP Deputy Director (Troy.Pruett@nrc.gov )
DRS Director (Anton.Vegel@nrc.gov )
DRS Deputy Director (Tom.Blount@nrc.gov )
Senior Resident Inspector (Tony.Brown@nrc.gov )
Resident Inspector (Mica.Baquera@nrc.gov )
Branch Chief, DRP/D (Ryan.Lantz@nrc.gov )
PV Administrative Assistant (Regina.McFadden@nrc.gov )
Project Engineer, DRP/D (David.You@nrc.gov )
Project Engineer, DRP/D (Brian.Parks@nrc.gov )
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov )
Project Manager (Lauren.Gibson@nrc.gov )
Acting Branch Chief, DRS/TSB (Ryan.Alexander@nrc.gov )
RITS Coordinator (Marisa.Herrera@nrc.gov )
Regional Counsel (Karla.Fuller@nrc.gov )
Congressional Affairs Officer (Jenny.Weil@nrc.gov )
OEMail Resource
SUNSI Review Completed: ___Y___
ADAMS: Yes
No Initials: _GAG_
Publicly Available Non-Publicly Available Sensitive
Non-Sensitive
R:\\_REACTORS\\PV\\PV 2012003 FRI - GAG
SRI:EB1
C:EB1
G. George
T. Farnholtz
/RA/
/RA/
3/8/12
3/9/12
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
- 1 -
Enclosure
Heat Sink Performance Inspection Document Request
Inspection Dates:
May 7-11, 2012
Inspection Procedures:
IP 71111.07, Triennial Heat Sink Performance
Inspector:
Gerond A. George, Senior Reactor Inspector
T. Gwynne Skaggs-Ryan, Reactor Inspector (Training)
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic
format (ims.certrec.com database or digital media preferred), in care of Gerond A. George, by
April 30, 2012. The inspectors will select specific items from the information requested below
and then request from your staff additional documents needed during the onsite inspection
week. Also, we request that you categorize the documents in your response with the numbered
list below. Please provide requested documentation electronically if possible. If requested
documents are large and only hard copy formats are available, please inform the inspector, and
provide subject documentation during the first day of the onsite inspection. If you have any
questions regarding this information request, please call the lead inspector as soon as possible.
The following heat exchangers/heat sinks have been selected for inspection:
Unit 1 Train A, Essential Cooling Water Heat Exchanger
Unit 1 Train A, Shutdown Cooling Heat Exchanger
Unit 2 Train B, Essential Chiller Heat Exchanger
Unit 3 Train B, Essential Cooling Water Heat Exchanger
Unit 3 Train B, Diesel Jacket Water Heat Exchanger
For all Generic Letter 89-13 exchangers:
1. List of corrective action program documents (with a short description) associated with
Generic Letter 89-13 heat exchangers, heat sinks, silting, corrosion, fouling, heat
exchanger cavitation, or heat exchanger testing, in the previous three years
2. System health report(s) and maintenance rule system notebooks for all the GL 89-13
heat exchangers
3. Copy of any self-assessments done on any GL 89-13 heat exchangers in the previous
three years
4. Copies of procedures developed to implement the recommendations of Generic Letter 89-13, e.g., the Generic Letter 89-13 Heat Exchanger Program description
5. Copy of your response to Generic Letter 89-13
- 2 -
Enclosure
For the specific heat exchangers selected:
Testing Documents
6. Copies of the two most recent completed tests confirming thermal performance for those
heat exchangers which are performance tested
7. Instrument uncertainties of the instruments used during testing
8. Copy of any operability determinations or other documentation of degradation
associated with the heat exchangers or the systems that support the operation for the
selected heat exchangers
9. Documents that show the as-found results are recorded, evaluated, and appropriately
dispositioned such that the as-left condition is acceptable
Cleaning Documents
10. The cleaning and inspection maintenance schedule for each heat exchanger for the next
five years
11. Copy of the document describing the inspection results for the last two cleaning and
inspection activities completed on each heat exchanger
12. Cleaning procedures with acceptance criteria for the selected heat exchangers
13. Copies of the documents that verify the structural integrity of the heat exchanger, e.g.,
eddy current summary sheets, ultrasonic testing results, and visual inspection results
14. Copies of those documents that describe the methods taken to control water chemistry
in the heat exchangers
Design Documents
15. Copies of the design basis documents and updated final safety analysis report pages for
the selected heat exchangers
16. Provide a list of calculations with a description which currently apply to each heat
exchanger
17. Copies of vendor data sheets and design basis data for the selected heat exchangers
18. Copy of the calculation which establishes the limiting (maximum) design basis heat load
which is required to be removed by each of these heat exchangers
19. Copy of the calculation which correlates surveillance testing results from these heat
exchangers with design basis heat removal capability (e.g., basis for surveillance test
acceptance criteria)
- 3 -
Enclosure
20. Copy of the calculations or documents which evaluate the potential for water hammer or
excessive tube vibration in the heat exchanger or associated piping
21. Copy of the document which identifies the current number of tubes in service for each
heat exchanger and the supporting calculation which establishes the maximum number
of tubes which can be plugged in each heat exchanger
22. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes
which are identified in each heat exchanger
For the ultimate heat sink or safety-related service water system:
23. Dam inspections that monitor the integrity of the ultimate heat sink (if applicable)
24. Copies of calculations and surveillances that determine the ultimate heat sink reservoir
capacity and heat transfer capability (if applicable)
25. Copies of any design changes performed on the ultimate heat sink or safety-related
service water system
26. Copies of procedures for a loss of ultimate heat sink or safety-related service water
system
27. Copies of inspections and/or maintenance related to macrofouling (silt, mussel shells,
debris, etc.) and aquatic life
28. Copies of inspections and/or maintenance related to preventing biotic fouling
29. Copies of procedures and/or test results to survey or monitor interface valves between
the safety-related section of the service water system and the nonsafety related section
30. Copy of the most recent service water flow balance test results, both as-found and as-
left
31. History of any thru-wall pipe leaks on the safety-related service water system
Inspector Contact Information:
Gerond A. George
Senior Reactor Inspector
817-200-1562
Gerond.George@nrc.gov
Mailing Address:
US NRC Region IV
Attn: Gerond A. George
1600 East Lamar Blvd.
Arlington, TX 76011-4511