ML110660635

From kanterella
Jump to navigation Jump to search
NextEra Energy Seabrook, LLCs Answers to Friends of the Coast and New England Coalition Motion for Leave to File for Reconsideration of Memorandum and Order LBP-11-02
ML110660635
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 03/07/2011
From: Hamrick S
NextEra Energy Seabrook
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 19760, 50-443-LR, ASLBP 10-906-02-LR-BD01, LBP-11-02
Download: ML110660635 (11)


Text

March 7, 2011 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of

)

)

NextEra Energy Seabrook, LLC

)

Docket No.

50-443-LR

)

(Seabrook Station)

)

)

ASLBP No. 10-906-02-LR (Operating License Renewal)

)

NextEra Energy Seabrook, LLCs Answer to Friends of the Coast and New England Coalition Motion for Leave to File For Reconsideration of Memorandum and Order LBP-11-02 NextEra Energy Seabrook, LLC (NextEra) hereby answers and opposes the Motion for Leave to File for Reconsideration of Memorandum and Order LBP-11-02 (Motion) filed by Friends of the Coast and the New England Coalition (NEC), dated February 25, 2011. In its Motion, NEC seeks leave of the Board to file a motion for reconsideration of the Boards Memorandum and Order (Ruling on Petitions for Intervention and Requests for Hearing). LBP-11-02, 73 NRC __ (February 15, 2011).

NEC has not explicitly sought reconsideration of LBP-11-02, only leave to file a motion seeking such relief. Regardless, NEC has failed to show circumstances that would compel the Board to reconsider its decision.

I.

BACKGROUND On September 17, 2010, the Secretary of the Commission granted NEC a 30-day extension of time, until October 20, 2010, to file a request for hearing in the Seabrook

2 license renewal proceeding.1 NEC filed its hearing request on October 21, 2010.2 On October 22, 2010, NEC filed a retroactive request for extension of time, blaming the NRCs E-Filing System for its untimely filing.3 NextEra and the NRC Staff filed timely answers to NECs hearing request on November 15, 2010.4 Any NEC reply was due on November 22. NEC filed its reply on November 23, 2010.5 Later that day it filed another retroactive request for an extension of time.6 At the prehearing conference, in response to criticism from the Board on this point, NECs representative pledge[d...]

to be certain to file a day in advance of the deadline in order to avoid this problem.7 On February 15, 2011, the Board issued its ruling in LBP-11-02, admitting several contentions for hearing, but declining to admit NEC Contention 3 and portions of NEC Contention 4. Under NRC rules, any motion for reconsideration of LBP-11-02 was due within ten days of its issuance, or by February 25. 10 C.F.R. § 2.323(e). On Saturday, February 26, NEC filed its Motion and also filed a retroactive request for an extension of time without conferring with the other parties, as is required by 10 C.F.R. 1 NextEra Energy Seabrook, LLC (Seabrook Station) (Sept. 17, 2010) (unpublished order).

2 Friends of the Coast and the New England Coalition, Petition for Leave to Intervene, Request for Hearing, and Admission of Contentions (Oct. 20 [sic], 2010).

3 Friends of the Coast/New England Coalitions Request for Extension of Time (Oct. 22, 2010).

4 NextEra Energy Seabrook, LLCs Answer Opposing the Petition to Intervene and Request for Hearing of Friends of the Coast and the New England Coalition (Nov. 15, 2010); NRC Staffs Answer to Petitions to Intervene and Requests for Hearing Filed By (1) Friends of the Coast and New England Coalition and (2) Beyond Nuclear, Seacoast Anti-Pollution League and New Hampshire Sierra Club (Nov.

15, 2010).

5 Friends of the Coast and New England Coalition Reply to NextEra and NRC Staff Answers (Nov.

22, [sic] 2010).

6 Friends of the Coast/New England Coalitions Request for Extension of Time (Nov. 22, 2010).

7 Transcript of Proceedings; NextEra Energy Seabrook, Seabrook Station, Unit 1; Oral Argument, at

61.

3

§ 2.323(b).8 NEC conferred with the other parties on Monday, February 28 and supplemented its extension request with a certification to that effect.9 II.

RECONSIDERATION REQUIRES COMPELLING CIRCUMSTANCES Under the NRCs Rules of Practice, Motions for reconsideration may not be filed except upon leave of the presiding officer or the Commission, upon a showing of compelling circumstances, such as the existence of a clear and material error in a decision, which could not have reasonably been anticipated, that renders the decision invalid.

10 C.F.R. § 2.323(e).

The Commissions Statements of Consideration for its 2004 rulemaking that amended the adjudicatory provisions in Part 2 described the compelling circumstances standard as intended to permit reconsideration only where manifest injustice would occur in the absence of reconsideration, and the claim could not have been raised earlier.

Final Rule, Changes to Adjudicatory Process, 69 Fed. Reg. 2,182, 2,207 (Jan. 14, 2004). It went on to state that reconsideration should be an extraordinary action and should not be used as an opportunity to reargue facts and rationales which were (or should have been) discussed earlier. Id.

See also Progress Energy Carolinas, Inc.

(Shearon Harris Nuclear Power Plant, Units 2 and 3), CLI-10-9, 71 NRC __ (Mar. 11, 2010) (slip op. at 4).

8 Friends of the Coast and New England Coalition, Inc. Request for Extension of Time-Post-Facto (Feb. 26, 2011).

9 Friends of the Coast and New England Coalition, Inc. Request for Extension of Time, Addenda, Certificate of Counsel (Feb. 28, 2011).

4 III.

NECS MOTION DOES NOT SHOW COMPELLING CIRCUMSTANCES As a threshold matter, NECs motion should be denied because it was not timely filed. 10 C.F.R. § 2.323(e). NEC correctly reported in the addendum to its retroactive request for an extension of time that NextEra takes no position on the filing of its extension request, but unless and until such relief is granted, NECs Motion is late and should not be entertained.10 NECs continued lack of respect for the Commissions pleading deadlines should not be encouraged.11 However, even if the Board were to review the substance of NECs Motion, it falls far short of the Commissions stringent standard for reconsideration set forth in 10 C.F.R. § 2.323(e). Indeed, it makes no effort to show compelling circumstances that could not have been anticipated and instead mischaracterizes the Boards decision and improperly reargues facts and rationales that it raised earlier (or should have). See 69 Fed. Reg. at 2,207.

First, NEC claims that the Board declared moot a portion of its Contention 4 that deals with wind borne radiation dose, based upon NextEras post-Answer submittal of its response to an NRC Staff Request for Additional Information on the effect of the sea breeze on the calculated radiation dose in its Severe Accident Mitigation Alternatives (SAMA) analysis. Motion at 2. NEC provides no citation to LBP-11-02 to support its assertion that the Board found this claim to be moot. See id. In fact, the Board expressly 10 NECs post-motion correspondence does not meet the intent of 10 C.F.R. § 2.323(b), which requires a movant to certify that it has made a sincere effort to contact other parties in the proceeding and resolve the issue(s) raised in the motion, so that Boards need only address issues that the parties cannot resolve themselves. Filing a motion and then asking the other parties if they object to the filing of the motion does not achieve this purpose.

11 It should be noted that the Commission disfavor[s] motions for extensions of time that are themselves filed out-of-time and expect[s] parties to file motions for extensions of time so that they are received by the [NRC] well before the time specified expires. Tennessee Valley Authority (Bellefonte Nuclear Plant Units 1 and 2), CLI-10-26, 72 NRC __, __ (2010) (slip op. at 2)(citing Statement of Policy on Conduct of Licensing Proceedings, CLI-81-8, 13 NRC 452, 455 (1981)).

5 declined to consider NextEras January 14, 2011 submittal and admitted the portion of NEC Contention 4 addressing this issue. LBP-11-02 (slip op. at 19, 50). Obviously, NECs misstatement of the Boards ruling cannot provide compelling circumstances to reconsider the decision.

Second, NEC seeks reconsideration of the Boards decision to deny admission of its Contention 3, related to aging management of buried pipes. Motion at 2-5. In its ruling, the Board found Contention 3 inadmissible for two reasons: it (1) presents an issue that is not within the scope of the proceeding (10 C.F.R. § 2.309(f)(1)(ii)); and (2) is not supported by adequate factual allegations (§ 2.309(f)(1)(v)). LBP-11-02 (slip op. at 38). In reaching this determination, the Board relied on the Commissions finding in the Pilgrim proceeding that the license renewal intended function for buried piping does not include the prevention of radioactive leaks. Id. at 36-37 (citing Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station) CLI-10-14, 71 NRC __ (2010) (slip op. at 15) (Pilgrim II)).

In its Motion, NEC challenges this determination, arguing with no citation or support of any kind that the Board must recognize the accident mitigation performance of numerous buried SSCs is to move radioactive water to collection points, sumps, treatment, and storage; thus mitigating or preventing its escape to the human environment. Motion at 3. This argument basically restates NECs position from its initial petition - that buried pipes within the scope of license renewal contain radioactive water and leaks from these pipes could endanger the public. See NEC Petition at 24. But reconsideration is not an opportunity to reargue claims made earlier. To the extent NEC now attempts to tie the prevention of leaks of radioactive water to accident mitigation

6 under 10 C.F.R. § 54.4(a)(1)(iii), it makes a new argument that was not, but should have been, presented in its petition. See generally, NEC Petition at 22-33. In any event, NECs Motion provides no support for the assertions that buried pipes within the scope of license renewal contain radioactive water and would be relied upon to mitigate or prevent the consequences of an accident. See Motion at 4-5.

Appearing to acknowledge that the prevention of leaks is not the intended function of buried pipes, NEC also argues that:

NRC cannot provide adequate assurance of public health and safety; nor can it provide adequate assurance of environmental protection of the biotic community through its ongoing reactor oversight program [process] either in the present or during the proposed period of extended operation because it relies on licensee conducted inspections, which, in many SSCs, inspect primarily for external corrosion and are monitoring to detect leaks only after they have occurred. These failings are at the core of Friends/NECs arguments.... Friends/NEC is at a loss to understand how the adequacy, in terms of protecting the public health and welfare, of anything that is treated in the license renewal application is not within the scope of a proceeding that is convened to settle disputes about the contents of the license renewal application.

Motion at 4.

The Commission rejected this argument in Pilgrim II, explaining that 10 C.F.R.

§ 54.21 does not require each structure and component within the scope of license renewal to be the subject of a far-reaching evaluation encompassing all aspects of the

[current licensing basis (CLB)], but instead requires a demonstration that the effects of aging will be adequately managed so that the intended function(s) will be maintained consistent with the CLB. CLI-10-14, (slip op. at 16). The Boards faithful application of Commission precedent certainly does not warrant reconsideration.

7 Third, NEC asks the Board to reconsider its decision to separately consider each of Contention 4s various subparts. Motion at 5-6, 8. NEC appears to assert that all of the issues it raised in Contention 4 (with the possible exception of its terrorism-related claim, see Motion at 6, n.2) must be considered as a whole. But NEC has failed to offer any compelling circumstances that would justify reconsideration of the Boards decision denying admission of portions of Contention 4. The Board in LBP-11-02 dismissed specific subparts of the contention because it found that those portions were beyond the scope of this proceeding (slip op. at 41, 44), were not adequately supported (id. at 59, 60),

or were immaterial (id. at 61). The Commission recently approved a Boards consideration of a multi-part contention in this manner, analyzing each subpart and finding that some were admissible while others were not. Progress Energy Inc. (Levy County Nuclear Power Plant, Units 1 and 2), CLI-10-02, 71 NRC __, __ (2010)(slip op.

at 4, 7, 10). Regardless of whether the Board considered Contention 4 as a single contention or as several distinct sub-contentions, individual claims that do not meet the Commissions contention admissibility requirements are inadmissible.

NEC only identifies one aspect of Contention 4 the Board declined to admit - its challenge to the use of probabilistic modeling in Contention 4A. Motion at 6. The Board clearly explained in LBP-11-02 that the Commission has stated that the purpose of a SAMA analysis is to assess the probability-weighted consequences of a severe accident.

LBP-11-02 (slip op. at 41) (citing Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station) CLI-10-11, 71 NRC __ (2010)

(slip op. at 13) (Pilgrim I)). The correct application of Commission caselaw is hardly a manifest injustice worthy of reconsideration.

8 NEC now asserts that it did not raise a challenge to the use of probabilistic modeling per se, but instead presented a challenge to how NextEra used probabilistic modeling. Motion at 6. But nowhere in its Motion does NEC identify its allegedly particularized dispute with the way NextEra employed probabilistic modeling. See Motion at 7-8. Nor did its petition raise anything other than a general challenge to the use of probabilistic modeling. See Pet. at 38-40. NECs attempt to recast its general claim as a particularized challenge to NextEras use of probabilistic modeling is both late and factually incorrect.12 In short, NEC has shown no compelling circumstances that would justify reconsideration of any of the Boards decisions denying the admission of its proposed contentions in this proceeding.

12 NEC also disputes the Boards discussion of SAMAs deemed cost-beneficial in other license renewal proceedings in rejecting NECs claim that the use of probabilistic modeling could reduce the consequences so low as to reject all possible mitigation as too costly. LBP-11-02 (slip op. at 41)(citing Pet. at 39). As this discussion immediately followed the Boards separate determination that NECs challenge to probabilistic modeling is beyond the scope of this proceeding, it cannot provide compelling circumstances for reconsideration. See id. at 41. The Board could also have cited NextEras own application, which identifies two potentially cost-effective SAMAs, in order to demonstrate the baselessness of NECs claim. See Environmental Report at F-187. Regardless, this discussion does not affect the Boards determination that a challenge to probabilistic modeling is beyond the scope of this proceeding.

9 IV.

CONCLUSION For all of the foregoing reasons, the Motion should be denied.

Respectfully Submitted, Signed (electronically) by Steven C. Hamrick Mitchell S. Ross Antonio Fernández NextEra Energy Seabrook, LLC 700 Universe Blvd.

Juno Beach, Florida 33408 Telephone: 561-691-7126 Facsimile: 561-691-7135 E-mail: mitch.ross@fpl.com antonio.fernandez@fpl.com Steven C. Hamrick NextEra Energy Seabrook, LLC 801 Pennsylvania Avenue, N.W. Suite 220 Washington, DC 20004 Telephone: 202-349-3496 Facsimile: 202-347-7076 E-mail: steven.hamrick@fpl.com Counsel for NextEra Energy Seabrook, LLC March 7, 2011

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of

)

)

NextEra Energy Seabrook, LLC

)

Docket No.

50-443-LR

)

(Seabrook Station)

)

)

ASLBP No. 10-906-02-LR (Operating License Renewal)

)

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing NextEra Energy Seabrook, LLCs Answer to Friends of the Coast and New England Coalition Motion for Leave to File For Reconsideration of Memorandum and Order LBP-11-02, were provided to the Electronic Information Exchange for service to those individuals listed below and others on the service list in this proceeding, this 7th day of March, 2011.

Administrative Judge Paul S. Ryerson, Esq., Chair Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Email: psr1@nrc.gov Administrative Judge Dr. Michael Kennedy Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Email: michael.kennedy@nrc.gov Administrative Judge Dr. Richard E. Wardwell Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Email: richard.wardwell@nrc.gov Secretary Attn: Rulemakings and Adjudications Staff Mail Stop O-16 C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 hearingdocket@nrc.gov

2 Office of Commission Appellate Adjudication Mail Stop O-16 C1 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: OCAAMAIL@nrc.gov Mary Spencer, Esq.

Maxwell C. Smith, Esq.

Emily L. Monteith, Esq.

Megan Wright, Esq.

Office of the General Counsel Mail Stop O-15 D21 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: mary.baty@nrc.gov Raymond Shadis New England Coalition Post Office Box 98 Edgecomb, Maine 04556 E-mail: shadis@prexar.com Kurt Ehrenberg New Hampshire Sierra Club 40 N. Main Street Concord, NH 03301 E-mail: Kurt.Ehrenberg@sierraclub.org Paul Gunter, Reactor Oversight Project Beyond Nuclear 6930 Carroll Avenue, Suite 400 Takoma Park, MD 20912 E-mail: paul@beyondnuclear.org Doug Bogen Executive Director Seacoast Anti-Pollution League PO Box 1136 Portsmouth, NH 03802 E-mail: bogen@metrocast.net Signed (electronically) by Steven C. Hamrick Steven C. Hamrick