ML110280044

From kanterella
Jump to navigation Jump to search
Notification of an NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000416-11-007 and Request for Information
ML110280044
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 01/27/2011
From: O'Keefe N
NRC/RGN-IV/DRS/EB-2
To: Douet J
Entergy Operations
References
IR-11-007
Download: ML110280044 (11)


See also: IR 05000416/2011007

Text

January 27, 2011

James R. Douet

Vice President Operations

Entergy Operations, Inc.

Grand Gulf Nuclear Station

P.O. Box 756

Port Gibson, MS

SUBJECT:

GRAND GULF NUCLEAR STATION - NOTIFICATION OF AN NRC TRIENNIAL

FIRE PROTECTION BASELINE INSPECTION (NRC INSPECTION

REPORT 05000416/2011007 AND REQUEST FOR INFORMATION

Dear Mr. Douet:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),

Region IV staff will conduct a triennial fire protection baseline inspection at your Grand Gulf

facility in April 2011. The inspection team will be comprised of reactor inspectors from the NRC

Region IV office. The team will conduct the inspection in accordance with the baseline

Inspection Procedure 71111.05T, "Fire Protection (Triennial)."

The schedule for the inspection is as follows:

Information gathering visit: March 15-16, 2011

Onsite inspection:

April 4 - 8, 2011

April 18 - 22, 2011

The purpose of the information gathering visit is to obtain information and documentation

needed to support the inspection, to become familiar with the fire protection programs, fire

protection features, post-fire safe shutdown capabilities and plant layout, and mitigating

strategies to address Section B.5.b of the Interim Compensatory Measures Order, EA-02-026,

of February 25, 2002/10 CFR 50.54(hh)(2). Four individuals will participate in the information

gathering visit to select the fire areas for evaluation, identify additional documents needed to

support the inspection, obtain unescorted access, and meet with the key personnel who will

support the inspection. The fire area selection will require a walkdown of candidate fire areas in

company with key personnel from your staff. The enclosure to this letter provides an initial list of

the documents the team will need for their review. We request that your staff transmit copies of

the documents listed in the enclosure to the NRC Region IV office for team use in preparation

for the inspection. Please send this information so that it will arrive in our office in Arlington,

Texas, by the dates listed in the enclosure.

During the information gathering visit, the team will also discuss the following inspection support

administrative details: office space size and location; specific documents requested to be made

available to the team in their office spaces; arrangements for reactor site access; and the

availability of knowledgeable plant engineering and licensing organization personnel to serve as

points of contact during the inspection.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

Grand Gulf Nuclear Station

- 2 -

We request that during the onsite inspection weeks, you ensure that copies of analyses,

evaluations, or documentation regarding the implementation and maintenance of the fire

protection program, including post-fire safe shutdown capability, be readily accessible to the

team for their review. Of specific interest for the fire protection portion of the inspection are

those documents that establish that your fire protection program satisfies the NRC regulatory

requirements and conforms to applicable NRC and industry fire protection guidance. For the

B.5.b portion of the inspection, those documents implementing your mitigating strategies and

demonstrating the management of your commitments for the strategies are of specific interest.

Also, please ensure the availability of appropriate personnel knowledgeable of: (1) plant

systems required to achieve and maintain safe shutdown conditions from inside and outside the

control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant

fire protection systems, and (4) the fire protection program and its implementation should be

available to support the team at the site during the inspection.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number 3150-

0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a

request for information or an information collection requirement unless the requesting document

displays a currently valid Office of Management and Budget control number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Your cooperation and support during this inspection will be appreciated. If you have questions

concerning this inspection or the inspection team's information or logistical needs, please

contact John Mateychick, the team lead inspector, in the Region IV office at (817) 276-6560, or

by email, John.Mateychick@nrc.gov

Sincerely,

/RA/

Neil O'Keefe, Chief

Engineering Branch 2

Division of Reactor Safety

Docket: 50-416

License: NPF-29

Enclosure: Triennial Fire Protection

Inspection Documentation Request List

Grand Gulf Nuclear Station

- 3 -

Senior Vice President

Entergy Nuclear Operations

P.O. Box 31995

Jackson, MS 39286-1995

Senior Vice President and COO

Entergy Operations, Inc

P.O. Box 31995

Jackson, MS 39286-1995

Vice President, Oversight

Entergy Operations, Inc

P.O. Box 31995

Jackson, MS 39286-1995

Chief, Energy and Transportation Branch

Environmental Compliance and

Enforcement Division

Mississippi Department of

Environmental Quality

P.O. Box 2249

Jackson, MS 39225-2249

Interim County Administrator

Claiborne County

Board of Supervisors (James Johnston)

510 Market Street

Port Gibson, MS 39150

Manager, Licensing

Sr. Site Executive

Entergy Nuclear Operations

P.O. Box 31995

Jackson, MS 39286-1995

Senior Manager, Nuclear Safety & Licensing

Licensing /Regulatory Affairs

Entergy Nuclear Operations

P.O. Box 31995

Jackson, MS 39286-1995

Manager, Licensing

Entergy Operations, Inc

Grand Gulf Nuclear Station

P.O. Box 756

Port Gibson, MS 39150

Grand Gulf Nuclear Station

- 4 -

Attorney General

Department of Justice

State of Louisiana

P.O. Box 94005

Baton Rouge, LA 70804-9005

Office of the Governor

State of Mississippi

P. O. Box 139

Jackson, MS 39205-0139

Attorney General

Assistant Attorney General

State of Mississippi

P.O. Box 220

Jackson, MS 39205

State Health Officer

State Health Board

P.O. Box 1700

Jackson, MS 39215

Associate General Counsel

Entergy Nuclear Operations

P.O. Box 31995

Jackson, MS 39286-1995

Louisiana Dept. of Environmental Quality

Radiological Emergency Planning and

Response Division

P.O. Box 4312

Baton Rouge, LA 70821-4312

Chief, Technological Hazards

Branch

FEMA Region VI

800 North Loop 288

Federal Regional Center

Denton, TX 76209

Joseph A. Aluise

Associate General Council - Nuclear

Entergy Services, Inc

639 Loyola Avenue

New Orleans, LA 70113

Grand Gulf Nuclear Station

- 5 -

Chief

Technological Services Branch

FEMA Region IV

3003 Chamblee-Tucker Road

Atlanta, GA 30341

Grand Gulf Nuclear Station

- 6 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov )

Deputy Regional Administrator (Art.Howell@nrc.gov )

DRP Director (Kriss.Kennedy@nrc.gov )

DRP Deputy Director (Troy.Pruett@nrc.gov )

DRS Director (Anton.Vegel@nrc.gov )

DRS Deputy Director (Vacant)

Senior Resident Inspector (Rich.Smith@nrc.gov )

Resident Inspector (Andy.Barrett@nrc.gov )

Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov )

Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov )

Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov )

GG Administrative Assistant (Alley.Farrell@nrc.gov )

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov )

Project Manager (Alan.Wang@nrc.gov )

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov )

RITS Coordinator (Marisa.Herrera@nrc.gov )

Regional Counsel (Karla.Fuller@nrc.gov )

Congressional Affairs Officer (Jenny.Weil@nrc.gov )

OEMail Resource

OEDO RIV Coordinator (James.Trapp@nrc.gov )

DRS/TSB STA (Dale.Powers@nrc.gov )

File located: S:\\DRS\\REPORTS\\GG TFP RFI 2011007 - JMM.docx ML110280044

SUNSI Rev Compl.

X Yes No

ADAMS

X Yes No

Reviewer Initials

JMM

Publicly Avail

X Yes No

Sensitive

Yes X No

Sens. Type Initials

JMM

EB2

C: EB 2

JMateychick

NOKeefe

/RA/

/RA/

1/25/11

1/26/11

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

- 1 -

Enclosure

ENCLOSURE

Triennial Fire Protection Inspection Documentation Request

Please provide the following documentation items 1 - 4 prior to the onsite information-gathering

visit, preferably no later than February 28, 2011. Where practical, please provide copies

electronically.

1. The current version of your fire protection program and fire hazards analysis.

2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate

acceptable plant response.

3. Copies of the licensing basis documents for fire protection (safety evaluation reports,

pertinent sections of the final safety analysis report, exemptions, deviations, letters

to/from the NRC regarding fire protection/fire safe shutdown, etc.).

4. The fire probabilistic risk assessment or portions of the plants individual plant

examination for external events report addressing fire events.

Please provide the following documentation items 5 - 47 during the information-gathering

visit or by March 25, 2011, in order to support inspection preparation. Whenever practical,

please provide copies electronically. However, drawings should be provided as paper

copies of sufficient size that all details are legible.

5. Plant layout and equipment drawings for fire areas that identify: (a) the physical plant

locations of major hot standby and cold shutdown equipment; (b) plant fire area and/or

fire zone delineation; and (c) the locations of fire protection equipment, such as

detection, suppression, and post-fire emergency lighting units; and (d) fire area

boundaries. The specific documents needed to support inspection preparation will be

discussed during the site visit.

6. Fire protection program implementing procedures (e.g., administrative controls, operator

response procedures for fires, fire fighting procedures, etc.).

7. Operating procedures used for achieving and maintaining hot and cold shutdown

conditions from the control room in the event of a fire outside the control room (III.G.2

areas).

8. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas)

capability with or without control room evacuation.

9. A list of equipment used to achieve and maintain hot standby and cold shutdown in the

event of a fire (safe shutdown equipment lists).

10. Piping and instrumentation (flow) diagrams showing the components used to achieve

and maintain hot standby and cold shutdown for normal and alternate shutdown. Please

- 2 -

Enclosure

provide one copy of the piping and instrumentation (flow) diagrams for these systems of

a size sufficient to read all details. These should include the systems used for reactor

coolant system (RCS) makeup, RCS pressure control, decay heat removal, and

reactivity control, including the essential support systems.

11. A listing, with descriptions, of design change packages which were determined to impact

fire protection and post-fire safe shutdowns, performed since the last triennial fire

protection inspection.

12. Copies of fire protection program change evaluations (Generic Letter 86-10 evaluations)

performed since the last triennial fire protection inspection.

13. A listing of open and closed corrective action documents initiated since the last triennial

fire protection inspection, which relate to the fire protection program or equipment,

including corrective actions for fire-induced circuit failures, both single and multiple

spurious actuations. Include Corrective Action Process document number, date, and

subject.

14. A listing of the applicable codes and standards (with the versions/dates) related to the

design of plant fire protection features and evaluations of any code deviations. Copies

of these codes should be available for review.

15. Drawings of the portions of the emergency lighting system which support fire response.

16. Procedures used to remove smoke from safety-related areas and the engineering

studies or calculations which support the design basis.

17. Drawings of communication systems credited in the license basis for firefighting and

plant operations during fires where control room is occupied and/or evacuated.

18. Piping and instrumentation (flow) diagrams for the fire water system and selected

suppression systems (To be determined during information-gathering visit).

19. A listing of maintenance and surveillance testing procedures for alternative shutdown

capability, fire barriers, fire detectors, fire pumps, suppression systems and emergency

lighting. Also, include a list of maintenance and surveillance testing procedures which

verify fuse and breaker coordination in accordance with the post-fire safe shutdown

coordination analysis.

20. Maintenance rule performance criterion, and a summary of the performance history for

systems or functions monitored within the maintenance rule program that support the fire

protection program or involve safe shutdown equipment, over the period since the last

triennial fire protection inspection.

21. A copy of fire protection program requirements (e.g., limiting conditions for operation,

surveillance test requirements) covered by technical specifications, technical

requirements manual, updated final safety analysis report, or similar documents.

- 3 -

Enclosure

22. Copies of internal and external self-assessments, audits, peer-assessments or similar

reviews related to post-fire safe shutdown capability or the fire protection program

completed since the last triennial fire protection inspection.

23. A list of manual actions taken outside the control room which are credited to mitigate the

consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should

group actions by the initiating fire area or zone and indicate where the action must take

place.

24. Corrective action taken or planned associated with NCVs05000416/2008006-01, 05000416/2008006-02, 05000416/2008006-03 and 05000416/2008006-04.

25. Electronic copies of operator study guides (i.e., lesson plan text and graphics) or design

basis documents that describe the purpose/function/operating characteristics of the safe

shutdown systems (RCS makeup, RCS pressure control, decay heat removal, and

reactivity control, including the essential support systems).

26. Two copies of one-line diagrams of the AC and vital DC electrical distribution systems.

These should depict how power gets from the switchyard to the engineered safety

feature loads (480V and 4160V).

27. A list of automatic and manually initiated gaseous fire suppression systems in the plant,

giving location and the key equipment being protected.

28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or

maintain hot shutdown and b) reach and/or maintain cold shutdown.

29. A list of high to low pressure interface valves.

30. A copy of procedures governing the training and operation of the fire brigade.

31. Organization charts of site personnel down to the level of fire protection staff personnel.

32. A contact list of key site personnel who will be supporting this inspection, giving location

of their office and phone number onsite.

33. The team would like to observe an unannounced fire brigade drill in the plant, if possible,

during the week of April 18, 2011. Please put us in contact, during the onsite information

gathering trip, with the appropriate personnel for planning drills.

34. The team would like to perform a walkthrough of the procedure for control room

evacuation due to fire with qualified operators in the plant during the week of April 4,

2011. Please put us in contact, during the onsite information gathering trip, with the

appropriate personnel for planning the walkthrough.

The following documents (items 35 - 48) involve B.5.b mitigating strategies.

- 4 -

Enclosure

35. A copy of the license condition that incorporated the requirements issued to address the

requirements of Section B.5.b of the ICM Order, EA-02-026, dated February 25, 2002,

and 10 CFR 50.54(hh)(2).

36. A list of all modifications to regulatory commitments made to meet the requirements of

Section B.5.b of the ICM Order, EA-02-026, dated February 25, 2002, the subsequently

imposed license conditions, and 10 CFR 50.54(hh)(2).

37. A list of procedures/guidelines which were revised or generated to implement the

mitigation strategies. These could be extensive damage mitigation guidelines (EDMGs),

severe accident management guidelines (SAMGs), emergency operating procedures

(EOPs), abnormal operating procedures (AOPs), etc.

38. A matrix that shows the correlation between the mitigation strategies identified in

Nuclear Energy Institute 06-12 and the site-specific procedures or guidelines that are

used to implement each strategy.

39. A list of engineering evaluations/calculations that were used to verify engineering bases

for the mitigation strategies.

40. Copies of piping and instrumentation diagrams (P&ID) or simplified flow diagrams for

systems relied upon in the mitigation strategies. These could be the type used for

training.

41. A list of modification packages and simplified drawings/descriptions of modifications that

were made to plant systems to implement the mitigation strategies.

42. Copies of procedure(s) used to inventory equipment (hoses, fittings, pumps, etc.)

required to be used to implement the mitigation strategies.

43. A list of B.5.b strategies, if any, which have implementing details that differ from that

documented in the submittals to the NRC and the safety evaluation report.

44. A copy of site general arrangement drawing(s) that show the majority of buildings/areas

referenced in B.5.b documents.

45. Training records/ training matrix/ lesson plans related to B.5.b.

46. Copies of Memoranda of Understanding (MOUs) (e.g., with local fire departments)

required to implement any mitigating strategies.

47. The team would like to perform a walkthrough of the procedure implementing a sample

mitigating strategy (to be selected by the inspector during the information gathering visit)

and the inventory equipment (hoses, fittings, pumps, etc.) required to be used to

implement the mitigation strategies during the week of April 4, 2011. Please put us in

contact with the appropriate personnel for planning the walkthrough during the onsite

information gathering trip

- 5 -

Enclosure

The following documentation needs (items 48 - 50) will be dependent upon sample selections,

and will be finalized during discussions with your staff. Please provide the required documents

prior to the week of April 4, 2011. Whenever practical, please provide copies electronically.

Drawings should be provided as paper copies of sufficient size such that all details are legible.

48. Pre-fire plans for the selected fire areas (areas to be selected by the team during the

information-gathering trip).

49. List of identified fire induced circuit failure configurations (for the selected fire areas) that

could prevent operation or cause maloperation of equipment credited for safe shutdown

in the event of a fire. Include failure configurations associated with hot shorts, open

circuits, or shorts to ground identified as potentially causing spurious or multiple spurious

actuations or maloperations of this equipment.

-

50. Cable routing information for components and equipment, credited for safe shutdown in

the selected fire areas. This information request item will be discussed and finalized with

your staff during the information gathering visit.