ML103160350

From kanterella
Jump to navigation Jump to search
IR 05000313-10-004 & 05000368-10-004, and Notice of Violation, on 07/01/10 - 09/30/10, Arkansas Nuclear One - NRC Integrated Inspection
ML103160350
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 11/12/2010
From: Clark J
NRC/RGN-IV/DRP/RPB-E
To: Berryman B
Entergy Operations
References
IR-10-004
Download: ML103160350 (72)


See also: IR 05000313/2010004

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

November 12, 2010

EA 10-233

Brad Berryman, Acting Vice President, Operations

Entergy Operations, Inc.

Arkansas Nuclear One

1448 S.R. 333

Russellville, AR 72802

Subject: ARKANSAS NUCLEAR ONE - NRC INTEGRATED INSPECTION

REPORT 05000313/2010004 AND 05000368/2010004

Dear Mr. Berryman:

On September 30, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Arkansas Nuclear One facility. The enclosed integrated inspection report

documents the inspection findings, which were discussed on September 27, 2010, with you and

members of your staff.

The inspections examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

One violation is cited in the enclosed Notice of Violation and the circumstances surrounding it

are described in detail in the subject inspection report. The violation involved the failure to

implement appropriate foreign material exclusion controls in areas designated as Zone 1 foreign

material exclusion areas as required by station procedure (EA-10-233). Although determined to

be of very low safety significance (Green), this violation is being cited in the Notice because

Arkansas Nuclear One failed to restore compliance within a reasonable time after the violations

were identified in NRC Inspection Reports 05000313, 05000368/2008005, 2009004, and

2010003, as specified in Section 2.3.2.a of the NRC Enforcement Policy. You are required to

respond to this letter and should follow the instructions specified in the enclosed Notice when

preparing your response. The NRC will use your response, in part, to determine whether further

enforcement action is necessary to ensure compliance with regulatory requirements.

This report documents eight additional NRC-identified and self-revealing findings of very low

safety significance (Green). Seven of these findings were determined to involve violations of

NRC requirements. However, because of the very low safety significance, and because they

are entered into your corrective action program, the NRC is treating these findings as noncited

violations, consistent with Section 2.3.2.a of the NRC Enforcement Policy. If you contest the

violations or the significance of the noncited violations, you should provide a response within

30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear

Entergy Operations, Inc.

- 2 -

Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with

copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 612 E.

Lamar Blvd, Suite 400, Arlington, TX 76011-4125; the Director, Office of Enforcement, U.S.

Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident

Inspector at the Arkansas Nuclear One facility. In addition, if you disagree with the crosscutting

aspect assigned to any finding in this report, you should provide a response within 30 days of

the date of this inspection report, with the basis for your disagreement, to the Regional

Administrator, Region IV, and the NRC Resident Inspector at Arkansas Nuclear One.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, and its

enclosure, will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Jeffrey A. Clark, P.E.

Chief, Project Branch E

Division of Reactor Projects

Dockets: 05000313; 05000368

Licenses: DPR-51; NPF-6

Enclosures: Notice of Violation

NRC Inspection Report 05000313/2010004; 05000368/2010004

w/Attachment: Supplemental Information

cc w/Enclosures:

Senior Vice President

& Chief Operating Officer

Entergy Operations, Inc.

P.O. Box 31995

Jackson, MS 39286-1995

Thomas Palmisano

Vice President, Oversight

Entergy Operations, Inc.

P.O. Box 31995

Jackson, MS 39286-1995

Entergy Operations, Inc.

- 3 -

Stephanie Pyle, Acting Manager, Licensing

Arkansas Nuclear One

1448 SR 333

Russellville, AR 72802

Joseph A. Aluise

Associate General Counsel - Nuclear

Entergy Services, Inc

639 Loyola Avenue

New Orleans, LA 70113

Senior Manager, Nuclear Safety & Licensing

Entergy Nuclear Operations

P.O. Box 31995

Jackson, MS 39286-1995

Chief, Radiation Control Section

Arkansas Department of Health

4815 West Markham Street, Slot 30

Little Rock, AR 72205-3867

Jim E. Gibson

County Judge of Pope County

100 West Main Street

Russellville, AR 72801

Arkansas Department of Health

Radiation Control Section

4815 West Markham Street, Slot 30

Little Rock, AR 72205-3867

David E. Maxwell, Director

Arkansas Department of Emergency

Management, Bldg. 9501

Camp Joseph T. Robinson

North Little Rock, AR 72199

Chief, Technological Hazards

Branch

FEMA Region VI

800 North Loop 288

Federal Regional Center

Denton, TX 76209

Entergy Operations, Inc.

- 4 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Chuck.Casto@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Anton.Vegel@nrc.gov)

DRS Director (Roy.Caniano@nrc.gov)

DRS Deputy Director (Troy.Pruett@nrc.gov)

Senior Resident Inspector (Alfred.Sanchez@nrc.gov)

Resident Inspector (Jeffrey.Josey@nrc.gov)

Resident Inspector (Jeff.Rotton@nrc.gov)

Branch Chief, DRP/E (Jeff.Clark@nrc.gov)

Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)

Project Engineer (William.Schaup@nrc.gov)

Project Engineer (Jim. Melfi@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Kaly.Kalyanam@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

ROPreports

DRS/TSB STA (Dale.Powers@nrc.gov)

OEDO RIV Coordinator (Geoffrey.Miller@nrc.gov)

Executive Technical Assistant (John.Giessner@nrc.gov)

R:\\_REACTORS\\_ANO\\2010\\ANO2010004-RPT-AAS.docx ML

ADAMS: No 5Yes

5 SUNSI Review Complete

Reviewer Initials: JC

5Publicly Available

5 Non-Sensitive

Non-publicly Available

Sensitive

RIV:SRI/DRP/B RI/DRP/B

RI/DRP/B

SPE/DRP/PBE C:DRS/PSB2

C:DRS/EB1

ASanchez

JJosey

JRotton

RAzua

GWerner

TFarnholtz

/RA/ T-Clark

/RA/ T-Clark

/RA/ T-Clark

/RA/ T-Clark

/RA/

/RA/

11/12/2010

11/12/2010

11/12/2010

11/12/2010

11/09/2010

11/08/2010

C:DRS/EB2

C:DRS/TSB

C:DRS/OB

C:DRS/PSB1 SEO:ORA/OE

C:DRP/PBE

NOKeefe

MHay

MHaire

MShannon

RKellar

JClark

/RA/

/RA/

/RA/KClayton for

/RA/

/RA/ T-Azua

/RA/

11/08/2010

11/09/2010

11/09/2010

11/09/2010

11/11/2010

11/12/2010

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

NOTICE OF VIOLATION

Entergy Operations, Inc.

Docket No: 50-313

Docket No: 50-368

Arkansas Nuclear One Station License

No: DPR-51

No: NPF-6

EA 10-233

During an NRC inspection conducted on July 1through September 30, 2010, a violation of NRC

requirements was identified. In accordance with the NRC Enforcement Policy, the violation is

listed below:

Title 10 of the Code of Federal Regulations, Part 50, Appendix B, Criterion V,

Instructions, Procedures, and Drawings, requires, in part, that activities affecting

quality shall be prescribed by documented instructions, procedures or drawings,

of a type appropriate to the circumstances and shall be accomplished in

accordance with these instructions, procedures, or drawings.

Arkansas Nuclear One Procedure EN-MA-118, Foreign Material Exclusion,

Revision 6 requires the establishment of a Foreign Material Exclusion Zone 1

when loss of foreign material exclusion integrity could result in fuel failure,

reduced system safety, station availability, or significant cost for recovery.

Section 5.11, FME Zone 1 Requirements, of the same procedure, states in part

that for Foreign Material Exclusion Zone 1, the Foreign Material Exclusion Monitor

shall control personnel and material access to the Foreign Material Exclusion

zone.

Contrary to the above, between October 31, 2008, and September 2, 2010, Arkansas

Nuclear One failed to ensure Foreign Material was controlled in accordance with the

requirements of Procedure EN-MA-118. Specifically, the inspectors identified multiple

occasions where the licensee personnel failed to implement appropriate foreign material

exclusion controls (e.g., failure to appropriately log material in to and out of the area) in

Foreign Material Exclusion Zone 1 areas around safety-related equipment as required by

station procedure. Additionally, these failures had the potential of having a negative

impact on safety-related components.

This violation is associated with a Green Significance Determination Process finding.

Pursuant to the provisions of 10 CFR 2.201, Entergy Operations, Inc. is hereby required to

submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional

Administrator, Region IV, and a copy to the NRC Resident Inspector at the facility that is the

subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation

(Notice). This reply should be clearly marked as a "Reply to Notice of Violation EA-10-233," and

should include: (1) the reason for the violation, or, if contested, the basis for disputing the

violation or severity level, (2) the corrective steps that have been taken and the results

- 1 -

Enclosure 1

- 2 -

Enclosure 1

achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date

when full compliance will be achieved. Your response may reference or include previous

docketed correspondence, if the correspondence adequately addresses the required response.

If an adequate reply is not received within the time specified in this Notice, an order or a

Demand for Information may be issued as to why the license should not be modified,

suspended, or revoked, or why such other action as may be proper should not be taken. Where

good cause is shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, U. S. Nuclear Regulatory

Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the NRCs document system (ADAMS), accessible from the

NRC website at http://www.nrc.gov/reading-rm/pdr.html or http://www.nrc.gov/reading-

rm/adams.html, to the extent possible, it should not include any personal privacy, proprietary, or

safeguards information so that it can be made available to the public without redaction. If

personal privacy or proprietary information is necessary to provide an acceptable response,

then please provide a bracketed copy of your response that identifies the information that

should be protected and a redacted copy of your response that deletes such information. If you

request withholding of such material, you must specifically identify the portions of your response

that you seek to have withheld and provide in detail the basis for your claim of withholding (e.g.,

explain why the disclosure of information will create an unwarranted invasion of personal

privacy or provide the information required by 10 CFR 2.390(b) to support a request for

withholding confidential commercial or financial information). If safeguards information is

necessary to provide an acceptable response, please provide the level of protection described

in 10 CFR 73.21.

Dated this 12th day of November 2010.

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Dockets:

05000313, 05000368

Licenses:

DPR-51, NPF-6

Report:

05000313/2010004 and 0500368/2010004

Licensee:

Entergy Operations, Inc.

Facility:

Arkansas Nuclear One, Units 1 and 2

Location:

Junction of Hwy. 64 West and Hwy. 333 South

Russellville, Arkansas

Dates:

July 1 through September 30, 2010

Inspectors:

A. Sanchez, Senior Resident Inspector

J. Josey, Resident Inspector

J. Rotton, Resident Inspector

C. Osterholtz, Senior Operations Engineer

K. Clayton, Senior Operations Engineer

T. Pate, Operations Engineer

D. Strickland, Operations Engineer

L. Ricketson, P.E., Senior Health Physicist

C. Graves, Health Physicist

D. Stearns, Health Physicist

Approved By:

Jeff Clark, P.E., Chief, Project Branch E

Division of Reactor Projects

- 1 -

Enclosure 2

SUMMARY OF FINDINGS

IR 05000313/2010004; 05000368/2010004; 07/01-09/30/2010; Arkansas Nuclear One,

Integrated Resident and Regional Report; Licensed Operator Requalification Program;

Operability Evaluations; Plant Modifications; Post Maintenance Testing; Refuel and Other

Outage Activities; Surveillance Testing; Radioactive Solid Waste Processing, and Radioactive

Material Handling, Storage, and Transportation; and Identification and Resolution of Problems.

The report covered a 3-month period of inspection by resident inspectors and announced

baseline inspections by regional inspectors. One Green cited violation, one Green finding and

seven Green noncited violations were identified. The significance of most findings is indicated

by their color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609,

Significance Determination Process. Crosscutting aspects are determined using Inspection

Manual Chapter 0310, "Components within the Cross Cutting Areas." Findings for which the

significance determination process does not apply may be Green or be assigned a severity level

after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 4, dated December 2006.

A.

NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Initiating Events

Green. The inspectors documented a self-revealing finding for station electrical

maintenance personnel's failure to adequately implement station Procedure EN-

WM-102, Work Implementation and Closeout, Revision 4. Specifically, station

personnel performing Work Order 00182908-01, removal/reinstallation of the

C-8A isophase fan motor, did not stop work and get a scope change for the work

order when a condition that was not identified in the work order was discovered.

This issue was entered into the licensee's corrective action program as Condition

Report CR-ANO-1-2010-2260.

The performance deficiency was determined to be more than minor because it

affected the human performance attribute of the Initiating Events Cornerstone,

and it directly affected the cornerstone objective to limit the likelihood of those

events that upset plant stability during power operations. Using Manual

Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings,

the inspectors determined that the finding was determined to have very low

safety significance because it did not contribute to both the likelihood of a reactor

trip and the likelihood that mitigation equipment or function would not be

available. The finding was determined to have a crosscutting aspect in the area

of Human Performance, associated with work practices in that the licensee failed

to communicate human error prevention techniques, such as holding pre-job

briefs, self- and peer-checking, and proper documentation of activities H.4(a)

(Section 1R19).

- 2 -

Enclosure 2

Green. The inspectors documented a self-revealing noncited violation of Unit 1

Technical Specification 5.4.1.a for the failure to follow Procedure EN-OP-102,

Protective and Caution Tagging, Revision 12. Specifically, a maintenance

tagout holder signed off a tagout prior to all work being complete, which led to the

removal of the clearance. This resulted in draining the pressurizer to the

containment basement floor instead of to a drain tank. This issue was entered

into the corrective action program as Condition Report CR-ANO-1-2010-1013.

Failure of station personnel to follow Procedure EN-OP-102, Protective and

Caution Tagging, Revision 12 was a performance deficiency. The performance

deficiency was associated with the Initiating Events Cornerstone. The

performance deficiency was determined to be more than minor because if left

uncorrected it could lead to a more significant safety issue. Specifically, the

continued failure to follow this procedure could lead to the inappropriate release

of systems and equipment to other organizations when these systems or

equipment are not capable of performing their function. This is therefore a

finding. Using NRC Manual Chapter 0609, Significance Determination Process,

Appendix G, "Shutdown Operations Significance Determination," Attachment 1,

the finding was determined to have very low safety significance because the

finding did not affect core heat removal, inventory control, power availability,

containment control or reactivity guidelines. The finding was determined to have

a crosscutting aspect in the area of human performance, associated with work

practices in that the licensee did not ensure supervisory and management

oversight of work activities such that nuclear safety is supported. Specifically,

instead of supplying appropriate guidance and supervision for the workers in the

field, the mechanical war room coordinators actions resulted in the failure to

follow procedure by convincing the mechanical lead to sign off on the tagout

before the work had been completed H.4(c) (Section 4OA2.5).

Green. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, at Unit 2. The violation was associated with the biennial

written exam overlap for the weeks four, five, and six written examinations

administered by the facility during the weeks of July 5-9, 2010, July 12-16, 2010,

and July 19-23, 2010. The issues were documented in licensee-initiated

Condition Report CR-ANO-2-2010-01460, which resulted in the licensee

removing five questions from the week four exam and writing new exams for

weeks five and six and administering them prior to the cycle end date of July 31,

2010.

The excessive overlap of the written exam portion of the Unit 2 2010 biennial

written exams was a performance deficiency in that the licensee failed to follow

their established requalification procedures. Specifically, in 2010 some operators

were tested using requalification written exams that repeated greater that

50 percent of the questions that had already been used in the earlier exam

weeks. This finding was more than minor because if left uncorrected it could

have led to a more significant safety concern, in that, licensed operations

personnel could be returned to licensed duties without receiving a procedurally

- 3 -

Enclosure 2

valid examination. The performance deficiency was associated with the Initiating

Events Cornerstone. The inspectors applied Manual Chapter 0609 Significant

Determination Process, Appendix I, Licensed Operator Requalification

Significance Determination Process, and determined that the finding should be

dispositioned as a Green noncited violation. The finding was assessed as having

very low safety significance because: (1) the overlap issues were found during

the biennial examinations of the operators, (2) there were no actual

consequences due to the inadequate examinations, (3) the applicable crews

were re-evaluated once the issues were found, (4) this issue did not exist on the

last biennial written exams in 2008 and did not occur on any of the Unit 1 biennial

written examinations, and (5) the performance on these new exams was

satisfactory. This finding has a crosscutting aspect in the area of work practices

because the licensee did not ensure that supervisory and management oversight

of work activities supported nuclear safety because the 2010 Unit 2 written exam

overlap issues were not caught during the supervisory review and approval prior

to administration of the examinations or prior to the start of this inspection

H.4(c) (Section 1R11).

Cornerstone: Mitigating Systems

Green. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Action, for the failure of the licensee to

promptly identify and correct a known condition adverse to quality associated

with the susceptibility of the emergency diesel generators heating, ventilating

and air conditioning ducting to loading effects caused by natural phenomena,

such as tornados. Specifically, while performing a review in response to an NRC

generic communication, the licensee determined that they could not demonstrate

the ability of the station's emergency diesel generators' heating, ventilating and

air conditioning ducting to withstand a tornado depressurization event. However

no actions were taken to correct or mitigate this issue at the time of discovery.

The licensee entered this issue in their corrective action program as Condition

Report CR-ANO-C-2009-2296.

Failure to promptly identify and correct a known condition adverse to quality

associated with the susceptibility of the Unit 1 emergency diesel generators'

heating, ventilating and air conditioning ducting to loading effects caused by

natural phenomena, tornados, was a performance deficiency. The performance

deficiency was determined to be more than minor because it was associated with

the protection against external events attribute of the Mitigating Systems

Cornerstone, and affected the associated cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events

to prevent undesirable consequences, and is therefore a finding. Using Manual

Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings,

the finding was determined to have very low safety significance because the

finding: (1) was not a design or qualification issue confirmed not to result in a

loss of operability or functionality; (2) did not represent an actual loss of safety

function of the system or train; (3) did not result in the loss of one or more trains

of nontechnical specification equipment; and (4) did not screen as potentially risk

- 4 -

Enclosure 2

significant due to a seismic, flooding, or severe weather initiating event. The

finding was determined to have a crosscutting aspect in the area of human

performance, associated with decision making in that the licensee failed to use

conservative assumptions in decision making and adopt a requirement to

demonstrate that the proposed action is safe in order to proceed rather than a

requirement to it is unsafe in order to disapprove the action H.1(b)

(Section 1R15).

Green. The inspectors documented a self-revealing noncited violation of 10 CFR

Part 50, Appendix B, Criterion III, Design Control, for the licensees failure to

assure that the applicable design basis for applicable structures, systems, and

components were correctly translated into specifications, procedures, and

instructions. Specifically, during initial plant installation, the licensee failed to

correctly identify the effect redundant protective equipment interlocks could have

on maintaining operability of VCH-4B design requirements upon a loss of normal

non-safety related room cooling. This resulted in VCH-4B, emergency

switchgear chiller, not being able to start and perform its design function due to a

combination of high room temperature due to loss of normal non-safety related

cooling, and normally energized compressor oil heaters which led to a high

compressor oil temperature switch actuation that caused a lockout of the chiller

that would have prevented a chiller start. The licensee entered this issue in their

corrective action program as Condition Report CR-ANO-1-2010-2815.

Failure to ensure that design requirements were correctly translated into installed

plant equipment was a performance deficiency. The performance deficiency was

determined to be more than minor because it was associated with the equipment

performance attribute of the Mitigating Systems Cornerstone, and affected the

associated cornerstone objective to ensure availability, reliability, and capability

of systems that respond to initiating events to prevent undesirable

consequences, and is therefore a finding. Using Manual Chapter 0609.04,

Phase 1 - Initial Screening and Characterization of Findings, the finding was

determined to have very low safety significance because: (1) the finding was not

a qualification deficiency that resulted in a loss of functionality of chiller VCH-4B;

(2) it did not lead to an actual loss of safety function of the system or train; (3) it

did not result in an actual loss of safety function of a single train for greater than

its technical specification allowed outage time; (4) it did not represent an actual

loss of safety function of one or more non- technical specification trains of

equipment designated as risk-significant per 10 CFR 50.65, for greater than

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; (5) it did not screen as potentially risk-significant due to a seismic,

flooding, or severe weather initiating event. The inspectors determined that since

the licensee had not recently re-evaluated the design of the emergency

switchgear room chillers high oil temperature lockout; this finding did not

represent current plant performance, and therefore did not have a crosscutting

aspect associated with it (Section 1R22).

Green. The inspectors documented a self-revealing noncited violation of 10 CFR

Part 50, Appendix B, Criterion XVI, Corrective Action, for the licensees failure

- 5 -

Enclosure 2

to promptly identify and correct a known condition adverse to quality associated

with the improper setup of the dead band of service water flow control

valve CV-6034 for cold weather operation. This resulted in the pressure control

valve not properly modulating in response to pressure control inputs, resulting in

emergency switchgear chiller VCH-4A tripping on high discharge pressure. The

licensee entered this issue in their corrective action program as Condition

Report CR-ANO-1-2009-2212.

Failure to promptly identify and correct a known condition adverse to quality

associated with the improper setup of the dead band of service water flow control

valve CV-6034 for cold weather operation was a performance deficiency. The

performance deficiency was determined to be more than minor because it was

associated with the equipment performance attribute of the Mitigating Systems

Cornerstone, and affected the associated cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events

to prevent undesirable consequences, and is therefore a finding. Using Manual

Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings,

the finding was determined to have very low safety significance because: (1) the

finding was not a qualification deficiency that resulted in a loss of functionality of

chiller VCH-4A; (2) it did not lead to an actual loss of safety function of the

system or train; (3) it did not result in an actual loss of safety function of a single

train for greater than its technical specification allowed outage time; (4) it did not

represent an actual loss of safety function of one or more non-technical

specification trains of equipment designated as risk-significant per 10 CFR 50.65,

for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and (5) it did not screen as potentially risk-significant

due to a seismic, flooding, or severe weather initiating event. The finding was

determined to have a crosscutting aspect in the area of human performance,

associated with decision making in that, although the licensee had identified the

vulnerability of the VCH-4A chiller, decided not to pursue the corrective actions to

adjust the dead band for valve CV-6034 and resulted in the subsequent improper

operation of the valve H.1(b) (Section 1R18).

Green. The inspectors identified a cited violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, associated with the

licensees failure to adequately implement Procedure EN-MA-118, Foreign

Material Exclusion, Revision 5/6. Specifically, between October 31, 2008, and

September 02, 2010, inspectors identified multiple occasions where licensee

personnel failed to implement appropriate foreign material exclusion controls in

Zone 1 areas around safety related equipment (e.g., failure to appropriately log

material in to and out of the zone) as required by station procedure. Each

identified instance was a repeat occurrence of previously identified issues that

were documented as NRC identified violations in previous inspection reports in

2008, 2009, and early 2010. Measures established by Arkansas Nuclear One to

address these previously identified noncited violations failed to restore

compliance within a reasonable time after these violations were identified.

Finally, these failures had the potential of having a negative impact on safety

related components such as fuel failure, safety system reliability and safety

- 6 -

Enclosure 2

related equipment availability. This issue was entered into the licensee's

corrective action program as Condition Reports CR-ANO-1-2010-3155,

CR-ANO-2-2010-1839, and CR-ANO-C-2010-2192.

The performance deficiency was determined to be more than minor because it

was associated with the human performance attribute of the Mitigating Systems

Cornerstone, and affected the associated cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events

to prevent undesirable consequences, and is therefore a finding. Using the

Manual Chapter 0609, Significance Determination Process, Phase 1

Worksheets, the finding was determined to have very low safety significance

because the finding: (1) was not a design or qualification issue confirmed not to

result in a loss of operability or functionality; (2) did not represent an actual loss

of safety function of the system or train; (3) did not result in the loss of one or

more trains of nontechnical specification equipment; and (4) did not screen as

potentially risk significant due to a seismic, flooding, or severe weather initiating

event. The finding was determined to have a crosscutting aspect in the area of

problem identification and resolution, associated with the corrective action

program, P.1(d), in that the licensee takes appropriate corrective actions to

address safety issues and adverse trends in a timely manner, commensurate

with their safety significance and complexity (Section 1R20).

Green. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, for station

planning personnel's failure to adequately implement station

Procedure EN-FAP-WM-011, Work Planning Standard, Revision 0, and

EN WM-105, Planning, Revision 6. Specifically, from August 3-19, 2010,

multiple examples were identified where work orders used to perform

maintenance activities on safety related equipment were incorrectly classified as

reference work orders, referenced technical material that did not contain

guidance for the prescribed task, or did not contain sufficient detail or direction to

accomplish the maintenance activity as written. This issue was entered into the

licensee's corrective action program as Condition Reports CR-ANO-C-2010-

1962, CR-ANO-C-2010-1964, CR-ANO-2-2010-1736, CR-ANO-C-2010-2114,

CR-ANO-C-2010-2119, and CR-ANO-C-2010-2140.

The performance deficiency was determined to be more than minor because if

left uncorrected, the continued practice of generating inadequate work orders for

maintenance activities on safety-related equipment would have the potential to

leave risk significant equipment in a degraded condition without the knowledge

and approval of site management and operations personnel, and is therefore a

finding. The performance deficiency was associated with the Mitigating Systems

Cornerstone. Using Manual Chapter 0609.04, Phase 1 - Initial Screening and

Characterization of Findings, the finding was determined to have very low safety

significance because the finding: (1) was not a design or qualification issue

confirmed not to result in a loss of operability or functionality; (2) did not

represent an actual loss of safety function of the system or train; (3) did not result

- 7 -

Enclosure 2

in the loss of one or more trains of nontechnical specification equipment; and

(4) did not screen as potentially risk significant due to a seismic, flooding, or

severe weather initiating event. The finding was determined to have a

crosscutting aspect in the area of human performance, associated with work

practices H.4(b) in that the licensee defines and effectively communicates

expectations regarding procedural compliance and personnel follow procedures.

(Section 4OA2).

Cornerstone: Public Radiation Safety

Green. The inspectors identified a noncited violation of 10 CFR 20.2006(b) for

failure to ship radioactive waste with an accurate manifest. On May 19, 2009,

the licensee shipped 20 Unit 2 spent fuel pool filters to a waste processor for

segregation. The licensee was notified on June 1, 2009, that dose rate on one

filter was almost twice the licensee reported dose rate (38 rem/hr vice 20 rem/hr).

The total activity of the shipment based on the higher dose rate was

approximately three times more than reported on the shipping manifest. Based

on the inspectors finding, the licensee corrected the shipping manifest and

documented this issue in the corrective action program as Condition

Report CR-ANO-C-2010-1866.

Failure to include the correct total radioactivity on a waste manifest is a

performance deficiency. The finding is greater than minor because it was

associated with the Public Radiation Safety Cornerstone attribute of program and

process (transportation program), and affected the cornerstone objective, in that,

it provided incorrect information as part of hazard communication which could

increase public dose. Using the public radiation safety significance determination

process, the inspectors determined the finding had very low safety significance

because: (1) radiation limits were not exceeded, (2) there was no breach of a

package during transit, (3) it did not involve a certificate of compliance issue,

(4) it was not a low level burial ground nonconformance, and (5) it did not involve

a failure to make notifications or provide emergency information. Additionally,

this finding had a crosscutting aspect in the area of corrective action program

because the licensee did not set a low threshold for identifying and correcting

issues P.1(a) (Section 2RS08).

B.

Other Findings

None.

- 8 -

Enclosure 2

REPORT DETAILS

Summary of Plant Status

Unit 1 operated at 100 percent power for the entire period.

Unit 2 began the inspection period operating at 100 percent power. On August 23, 2010, Unit 2

performed a technical specification required shutdown to affect repairs to emergency diesel

generator 2. On September 4, 2010, Unit 2 returned to 100 percent power and remained at

100 percent for the rest of the period.

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and

Emergency Preparedness

1R04 Equipment Alignments (71111.04)

.1

Partial Walkdown

a.

Inspection Scope

The inspectors performed partial system walkdowns of the following risk-significant

systems:

August 4-5, 2010, Unit 2, train B containment spray pump while train A was out

of service for maintenance activities

August 12, 2010, Unit 2, emergency diesel generator 1 and alternate AC

generator when Unit 2 emergency diesel generator 2 was out of service for

extended maintenance activity

August 23, 2010, Unit 1, motor-driven emergency feedwater pump P-7B while

turbine-driven emergency feedwater pump P-7A was out of service for planned

maintenance

September 13, 2010, Unit 1, train A low pressure safety injection pump while

train B was out of service for planned maintenance activities

September 23, 2010, Unit 2, motor-driven emergency feedwater pump 2P-7B

while turbine-driven emergency feedwater pump 2P-7A was out of service for

planned maintenance

The inspectors selected these systems based on their risk significance relative to the

reactor safety cornerstones at the time they were inspected. The inspectors attempted

to identify any discrepancies that could affect the function of the system, and, therefore,

potentially increase risk. The inspectors reviewed applicable operating procedures,

system diagrams, Safety Analysis Report, technical specification requirements,

administrative technical specifications, outstanding work orders, condition reports, and

- 9 -

Enclosure 2

the impact of ongoing work activities on redundant trains of equipment in order to identify

conditions that could have rendered the systems incapable of performing their intended

functions. The inspectors also inspected accessible portions of the systems to verify

system components and support equipment were aligned correctly and operable. The

inspectors examined the material condition of the components and observed operating

parameters of equipment to verify that there were no obvious deficiencies. The

inspectors also verified that the licensee had properly identified and resolved equipment

alignment problems that could cause initiating events or impact the capability of

mitigating systems or barriers and entered them into the corrective action program with

the appropriate significance characterization. Specific documents reviewed during this

inspection are listed in the attachment.

These activities constitute completion of five (5) partial system walkdown samples as

defined in Inspection Procedure 71111.04-05.

b.

Findings

No findings were identified.

.2

Complete Walkdown

a.

Inspection Scope

During the month of April 2010 (during Refueling Outage 1R22) and week of

September 26, 2010, the inspectors performed a complete system alignment inspection

of the Unit 1 low pressure injection/decay heat removal systems to verify the functional

capability of the system. This system was selected because it was considered both

safety significant and risk significant in the licensees probabilistic risk assessment. The

inspectors walked down the system to review mechanical and electrical equipment line

ups, electrical power availability, system pressure and temperature indications, as

appropriate, component labeling, component lubrication, component and equipment

cooling, hangers and supports, operability of support systems, and to ensure that

ancillary equipment or debris did not interfere with equipment operation. A review of a

sample of past and outstanding work orders (WOs) was performed to determine whether

any deficiencies significantly affected the system function. In addition, the inspectors

reviewed the corrective action program database to ensure that system equipment

alignment problems were being identified and appropriately resolved. Documents

reviewed are listed in the attachment.

On September 5, 2010, the inspectors performed a complete system alignment

inspection of the Unit 1 reactor building spray system to verify the functional capability of

the system. The inspectors selected this system because it was considered both safety-

significant and risk-significant in the licensees probabilistic risk assessment. The

inspectors walked down the system to review mechanical and electrical equipment line

ups, electrical power availability, system pressure and temperature indications, as

appropriate, component labeling, component lubrication, component and equipment

cooling, hangers and supports, operability of support systems, and to ensure that

ancillary equipment or debris did not interfere with equipment operation. The inspectors

- 10 -

Enclosure 2

reviewed a sample of past and outstanding work orders to determine whether any

deficiencies significantly affected the system function. In addition, the inspectors

reviewed the corrective action program database to ensure that system equipment-

alignment problems were being identified and appropriately resolved. Specific

documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of two (2) complete system walkdown samples as

defined in Inspection Procedure 71111.04-05.

b.

Findings

No findings were identified.

3

System Walkdown associated with Temporary Instruction (TI) 2515/177, Managing Gas

Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment

Spray Systems.

a.

Inspection Scope

During the month of April 2010 (during Refueling Outage 1R22) and week of

September 26, 2010, the inspectors conducted a walkdown of the Unit 1 trains A and B

low pressure injection/decay heat removal systems in sufficient detail to reasonably

assure the acceptability of the licensees walkdowns (TI 2515/177, Section 04.02.d).

In addition, the inspectors verified that the licensee had isometric drawings that describe

the Unit 1, trains A and B, low pressure/decay heat removal system configurations and

had acceptably confirmed the accuracy of the drawings (TI 2515/177, Section 04.02.a).

The inspectors verified the following related to the isometric drawings:

High point vents were identified. High points that do not have vents were acceptably

recognizable. Other areas where gas can accumulate and potentially impact subject

system operability, such as at orifices in horizontal pipes, isolated branch lines, heat

exchangers, improperly sloped piping, and under closed valves, were acceptably

described in the drawings or in referenced documentation. Horizontal pipe centerline

elevation deviations and pipe slopes in nominally horizontal lines that exceed specified

criteria were identified. All pipes and fittings were clearly shown. The drawings were up-

to-date with respect to recent hardware changes and that any discrepancies between

as-built configurations and the drawings were documented and entered into the

corrective action program for resolution.

The inspectors verified that piping and instrumentation diagrams accurately described

the subject systems, that they were up-to-date with respect to recent hardware changes,

and any discrepancies between as-built configurations, the isometric drawings, and the

piping and instrumentation diagrams were documented and entered into the corrective

action program for resolution (TI 2515/177, Section 04.02.b).

Documents reviewed are listed in the attachment to this report.

- 11 -

Enclosure 2

This inspection effort counts towards the completion of TI 2515/177 which will be closed

in a later inspection report.

b.

Findings

No findings were identified.

1R05 Fire Protection (71111.05)

.1

Quarterly Fire Inspection Tours

a.

Inspection Scope

The inspectors conducted fire protection walkdowns that were focused on availability,

accessibility, and the condition of firefighting equipment in the following risk-significant

plant areas:

September 9, 2010, Unit 2, Fire Zone 2137-I, Upper south electrical penetration

room

September 9, 2010, Unit 2, Fire Zone 2098-L, Cable spreading room

September 30, 2010, Unit 1, Fire Zone 86-G, North emergency diesel generator

room

September 30, 2010, Unit 1, Fire Zone 87-H, South emergency diesel generator

room

The inspectors reviewed areas to assess if licensee personnel had implemented a fire

protection program that adequately controlled combustibles and ignition sources within

the plant; effectively maintained fire detection and suppression capability; maintained

passive fire protection features in good material condition; and had implemented

adequate compensatory measures for out of service, degraded or inoperable fire

protection equipment, systems, or features, in accordance with the licensees fire plan.

The inspectors selected fire areas based on their overall contribution to internal fire risk

as documented in the plants Individual Plant Examination of External Events with later

additional insights, their potential to affect equipment that could initiate or mitigate a

plant transient, or their impact on the plants ability to respond to a security event. Using

the documents listed in the attachment, the inspectors verified that fire hoses and

extinguishers were in their designated locations and available for immediate use; that

fire detectors and sprinklers were unobstructed; that transient material loading was

within the analyzed limits; and fire doors, dampers, and penetration seals appeared to

be in satisfactory condition. The inspectors also verified that minor issues identified

during the inspection were entered into the licensees corrective action program.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four (4) quarterly fire-protection inspection

samples as defined in Inspection Procedure 71111.05-05.

- 12 -

Enclosure 2

b.

Findings

No findings were identified.

1R06 Flood Protection Measures (71111.06)

a.

Inspection Scope

The inspectors reviewed the Safety Analysis Report, the flooding analysis, and plant

procedures to assess susceptibilities involving internal flooding; reviewed the corrective

action program to determine if licensee personnel identified and corrected flooding

problems; inspected underground bunkers/manholes to verify the adequacy of sump

pumps, level alarm circuits, cable splices subject to submergence, and drainage for

bunkers/manholes; and verified that operator actions for coping with flooding can

reasonably achieve the desired outcomes. The inspectors also inspected the one area

listed below to verify the adequacy of equipment seals located below the flood line, floor

and wall penetration seals, watertight door seals, common drain lines and sumps, sump

pumps, level alarms, and control circuits, and temporary or removable flood barriers.

Specific documents reviewed during this inspection are listed in the attachment.

September 30, 2010, Unit 1, Area 38-Y, Emergency feedwater pump room

These activities constitute completion of one (1) flood protection measures inspection

sample as defined in Inspection Procedure 71111.06-05.

b.

Findings

No findings were identified.

1R11 Licensed Operator Requalification Program (71111.11)

.1

Quarterly Review

a.

Inspection Scope

On September 15, 2010, the inspectors observed a crew of licensed operators in the

plants simulator to verify that operator performance was adequate, evaluators were

identifying and documenting crew performance problems, and training was being

conducted in accordance with licensee procedures. The inspectors evaluated the

following areas:

Licensed operator performance

Crews clarity and formality of communications

Crews ability to take timely actions in the conservative direction

- 13 -

Enclosure 2

Crews prioritization, interpretation, and verification of annunciator alarms

Crews correct use and implementation of abnormal and emergency procedures

Control board manipulations

Oversight and direction from supervisors

Crews ability to identify and implement appropriate technical specification

actions and emergency plan actions and notifications

The inspectors compared the crews performance in these areas to pre-established

operator action expectations and successful critical task completion requirements.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one (1) quarterly licensed-operator

requalification program sample as defined in Inspection Procedure 71111.11.

b.

Findings

No findings were identified.

.2

Biennial Inspection (Units 1 and 2)

The licensed operator requalification program involves two training cycles that are

conducted over a 2-year period. In the first cycle, the annual cycle, the operators are

administered an operating test consisting of job performance measures and simulator

scenarios. In the second part of the training cycle, the biennial cycle, operators are

administered an operating test and a comprehensive written examination. Unit 1 was in

the first part of the training cycle while Unit 2 was in the second part of the training cycle.

The examiners observed the associated training cycles for both units during this period.

a.

Inspection Scope

To assess the performance effectiveness of the licensed operator requalification

program, the inspectors conducted personnel interviews, reviewed both the operating

tests and written examinations, and observed ongoing operating test activities.

The inspectors interviewed 12 licensee personnel, consisting of 8 operators,

2 instructors, and 2 training supervisors, to determine their understanding of the policies

and practices for administering requalification examinations. The inspectors also

reviewed operator performance on the written exams and operating tests. These

reviews included observations of portions of the operating tests by the inspectors. The

operating tests observed included six job performance measures and five scenarios that

were used in the current biennial requalification cycle. These observations allowed the

inspectors to assess the licensee's effectiveness in conducting the operating test to

ensure operator mastery of the training program content. The inspectors also reviewed

medical records of 10 licensed operators for conformance to license conditions and the

- 14 -

Enclosure 2

licensees system for tracking qualifications and records of license reactivation for

8 operators.

The results of these examinations were reviewed to determine the effectiveness of the

licensees appraisal of operator performance and to determine if feedback of

performance analyses into the requalification training program was being accomplished.

The inspectors interviewed members of the training department and reviewed minutes of

training review group meetings to assess the responsiveness of the licensed operator

requalification program to incorporate the lessons learned from both plant and industry

events. Examination results were also assessed to determine if they were consistent

with the guidance contained in NUREG 1021, "Operator Licensing Examination

Standards for Power Reactors," Revision 9, Supplement 1, and NRC Inspection Manual

Chapter 0609, Appendix I, Operator Requalification Human Performance Significance

Determination Process.

In addition to the above, the inspectors reviewed examination security measures,

simulator fidelity and existing logs of simulator deficiencies.

On August 10, 2010, the licensee informed the lead inspector of the following Unit 1

results:

Of the 59 total licensed operators, 2 operators have not been tested (1 RO and

1 SRO have yet to be tested due to illness)

9 of 10 crews passed the simulator portion of the operating test

56 of 57 licensed operators passed the simulator portion of the operating test

57 of 57 licensed operators passed the job performance measure portion of the

examination

The individuals that failed the simulator scenario portions of the operating test were

remediated, retested, and passed their retake operating tests.

On August 10, 2010, the licensee informed the lead inspector of the following Unit 2

results:

10 of 11 crews passed the simulator portion of the operating test

54 of 55 licensed operators passed the simulator portion of the operating test

55 of 55 licensed operators passed the job performance measure portion of the

examination

54 of 55 licensed operators passed the biennial written exam

The individuals that failed the applicable portions of the operating test were remediated,

retested, and passed their retake operating tests. The individual that failed the written

exam has been remediated and passed the retake written exam.

- 15 -

Enclosure 2

The inspectors completed (1) one inspection sample of the biennial licensed operator

requalification program as defined in Inspection Procedure 71111.11.

b.

Findings

Introduction. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, Drawings, at Unit 2 for failure to

follow procedures required by the requalification program in order to develop written

examinations for the biennial cycle. Specifically, the licensee exceeded the 50 percent

maximum overlap for written questions on the biennial written exams defined in their

requalification program procedures for weeks four, five, and six written examinations.

These examinations were administered by the facility during the weeks of July 5-9, 2010,

July 12-16, 2010, and July 19-23, 2010. This finding was documented in licensee-

initiated Condition Report CR-ANO-2-2010-01460, which resulted in the licensee

removing five questions from the week four exam, writing new exams for weeks five and

six and administering them prior to the cycle end date of July 31, 2010.

Description. The inspectors identified that the written exams for weeks four, five, and six

exceeded the 50 percent threshold for overlap between and among the biennial

examinations. The issue was identified while conducting the Unit 2 biennial Licensed

Operator Requalification Training Program inspection during the week of July 19, 2010.

The week four exam contained 20 repeat questions out of 35 questions, or a 57 percent

overlap. The week five and week six exams each contained 100 percent overlap.

These practices did not comply with Entergys procedural guidance, EN-TQ-114,

Section 5.7[1](g) which states that, Written examinations will contain at least 50 percent

new material. This procedure is a quality procedure and, therefore, is required to meet

10 CFR Part 50, Appendix B, criteria.

The inspectors communicated these issues to the licensee staff on July 20, 2010, and

representatives of the licensees management agreed with the NRC inspection teams

assessment of the issues. The licensee determined that the 2010 Unit 2 written exams

already administered for weeks four and five were invalid due to the excessive written

exam question overlap for weeks four, five, and six. Exam administration was

suspended for Unit 2 pending development of new exams. The licensee initiated

Condition Report CR-ANO-2-2010-01460, dated July 21, 2010, to document this issue.

The inspectors also found that many of the written exam questions which were

considered new questions were almost identical to previous exam questions. The stem

of several questions had very minor changes (i.e., a change in pressure) which changed

the correct response. The same concept was being asked with a new correct answer.

The inspectors also found that there appeared to be a goal of repeating 15 of the

35 questions on weeks three, four, five and six. The 50 percent repeat of questions is a

limit, not a goal, and minimizing the amount of overlap could have prevented this

violation.

Following the onsite visit, the NRC inspection team conducted an in-office review of the

modified week four exam and the newly written and administered week five and six

examinations and found no issues with them.

- 16 -

Enclosure 2

Analysis. The excessive overlap of the written exam portion of the Unit 2 2010 biennial

written exams was a performance deficiency in that the licensee failed to follow their

established requalification procedures. Specifically, in 2010 some operators were tested

using requalification written exams that repeated greater that 50 percent of the questions

that had already been used in the earlier exam weeks. This finding was more than

minor because if left uncorrected it could lead to a more significant safety concern, in

that, licensed operations personnel could be returned to licensed duties without

receiving a procedurally valid examination. The inspectors applied Manual Chapter 0609

Significant Determination Process, Appendix I, Licensed Operator Requalification

Significance Determination Process, and determined that the finding should be

dispositioned as a Green noncited violation. The finding was assessed as having very

low safety significance (Green) because: (1) the overlap issues were found during the

biennial examinations of the operators, (2) there were no actual consequences due to

the inadequate examinations, (3) the applicable crews were re-evaluated once the

issues were found, (4) this issue did not exist on the last biennial written exams in 2008

and did not occur on any of the Unit 1 biennial written examinations, and (5) the

performance on the newly written examinations was satisfactory.

This written exam overlap finding should have been discovered and corrected by the

licensee prior to NRC identification. The licensee should have discovered the problem

prior to the NRCs identification because: (1) similar issues were described in 2002 and

2007 industry operating experience involving exam compromises; (2) the licensee

completed a Pre-71111.11 Inspection in May 2010 that failed to identify this issue; and

(3) the practices clearly violated NRC guidance and requirements, as well as the fleet-

wide Entergy procedural guidance aimed at preventing exam compromise. Following

identification of this issue by the NRC, the licensee took immediate and substantive

corrective actions to remedy the 2010 biennial written exam overlap issues by

developing new exams and retesting the affected Unit 2 licensed operators within the

required biennial exam cycle. This finding has a crosscutting aspect in the area of work

practices because the licensee did not ensure that supervisory and management

oversight of work activities supported nuclear safety because the 2010 Unit 2 written

exam overlap issues were not caught during the supervisory review and approval prior to

administration of the examinations or prior to the start of this inspection H.4(c).

Enforcement. Title 10 of the Code of Federal Regulations Part 50, Appendix B,

Criterion V, Instructions, Procedures, Drawings, requires, in part, that, Activities

affecting quality shall be described by procedures including appropriate acceptance

criteria and those procedures shall be followed. Contrary to this requirement, Entergy

fleet-wide Procedure EN-TQ-114, Revision 3, step 5.7[1](g) was not followed in that the

Unit 2 written exams for 2010 had several exams that exceeded the 50 percent overlap

requirement. Because this finding is of very low safety significance and was entered into

the licensees corrective action program as Condition Report CR-ANO-2-2010-01460,

this violation is being treated as a noncited violation, consistent with Section VI.A.1 of

the NRC Enforcement Policy: NCV 050000368/2010004-01, Excessive Overlap of

Unit 2 Written Examinations.

- 17 -

Enclosure 2

1R12 Maintenance Effectiveness (71111.12)

a.

Inspection Scope

The inspectors evaluated degraded performance issues involving the following risk

significant systems:

August 3, 2010, Unit 2, Emergency feedwater

September 15, 2010, Unit 1, High pressure injection system

The inspectors reviewed events such as where ineffective equipment maintenance has

resulted in valid or invalid automatic actuations of engineered safeguards systems and

independently verified the licensee's actions to address system performance or condition

problems in terms of the following:

Implementing appropriate work practices

Identifying and addressing common cause failures

Scoping of systems in accordance with 10 CFR 50.65(b)

Characterizing system reliability issues for performance

Charging unavailability for performance

Trending key parameters for condition monitoring

Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or -(a)(2)

Verifying appropriate performance criteria for structures, systems, and

components classified as having an adequate demonstration of performance

through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as

requiring the establishment of appropriate and adequate goals and corrective

actions for systems classified as not having adequate performance, as described

in 10 CFR 50.65(a)(1)

The inspectors assessed performance issues with respect to the reliability, availability,

and condition monitoring of the system. In addition, the inspectors verified maintenance

effectiveness issues were entered into the corrective action program with the appropriate

significance characterization. Specific documents reviewed during this inspection are

listed in the attachment.

These activities constitute completion of two (2) quarterly maintenance effectiveness

samples as defined in Inspection Procedure 71111.12-05.

- 18 -

Enclosure 2

b.

Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

a.

Inspection Scope

The inspectors reviewed licensee personnel's evaluation and management of plant risk

for the maintenance and emergent work activities affecting risk-significant and safety-

related equipment listed below to verify that the appropriate risk assessments were

performed prior to removing equipment for work:

July 6, 2010, Unit 2, Elevated risk for 2P-7B, motor driven emergency feedwater

pump unavailable for maintenance

July 26, 2010, Unit 2, Elevated risk for alternated AC diesel generator planned

maintenance activity

August 11, 2010, Unit 2, Emergency diesel generator 2K-4B planned 14-day

extended maintenance outage

August 12-13, 2010, Unit 1, Train B high pressure injection inoperable due to

planned maintenance

Week of August 23, 2010, Unit 2, Emergency diesel generator 2K-4B crankcase

vacuum issues that resulted in a technical specification required shutdown

September 17, 2010, Units 1 and 2, Evaluation of risk associated with crane

activities in the switchyard for lightning arrestor mast foundation excavation

September 23, 2010, Unit 1, Risk assessment evaluation for heavy load crane

activities in the vicinity of Unit 1 reactor building and condensate storage tank

The inspectors selected these activities based on potential risk significance relative to

the reactor safety cornerstones. As applicable for each activity, the inspectors verified

that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)

and that the assessments were accurate and complete. When licensee personnel

performed emergent work, the inspectors verified that the licensee personnel promptly

assessed and managed plant risk. The inspectors reviewed the scope of maintenance

work, discussed the results of the assessment with the licensee's probabilistic risk

analyst or shift technical advisor, and verified plant conditions were consistent with the

risk assessment. The inspectors also reviewed the technical specification requirements

and inspected portions of redundant safety systems, when applicable, to verify risk

analysis assumptions were valid and applicable requirements were met. Specific

documents reviewed during this inspection are listed in the attachment.

- 19 -

Enclosure 2

These activities constitute completion of seven (7) maintenance risk assessments and

emergent work control inspection samples as defined in Inspection

Procedure 71111.13-05.

b.

Findings

No findings were identified.

1R15 Operability Evaluations (71111.15)

a.

Inspection Scope

The inspectors reviewed the following issues:

April 10 and May 26, 2010, Unit 1, Core flood tank T-2A for gas space leakage

during the Unit 1 refueling outage

May 28, 2010, Unit 1, Emergency diesel generator 1 failure to secure from the

control room and required local operator action to secure

June 21, 2010, Unit 1, P-36C high pressure injection suction relief

valve PSV-1234 missed inservice test greater than technical specification

surveillance requirement and entry into technical specification Surveillance

Requirement 3.0.3

July 2, 2010, Unit 1, P-7A turbine driven emergency feedwater pump speed

increase

July 22, 2010, Unit 2, Emergency feedwater pump 2P-7A during erratic operation

of flow transmitter.

July 31, 2010, Unit 1, Degrading trend in reactor building pressure, actually

achieving a negative pressure

August 3, 2010, Unit 2, Excore detector channel C operability

August 9, 2010, Unit 1, Train B high pressure injection for leakage through

borated water storage tank stop check valve BW-3

August 19, 2010, Unit 1, VCH-4A emergency switchgear room chiller

September 25, 2010, Unit 1, Diesel generator ventilation systems susceptibility to

the depressurization effects of a tornado

The inspectors selected these potential operability issues based on the risk-significance

of the associated components and systems. The inspectors evaluated the technical

adequacy of the evaluations to ensure that technical specification operability was

properly justified and the subject component or system remained available such that no

- 20 -

Enclosure 2

unrecognized increase in risk occurred. The inspectors compared the operability and

design criteria in the appropriate sections of the technical specifications and Safety

Analysis Report to the licensee personnels evaluations to determine whether the

components or systems were operable. Where compensatory measures were required

to maintain operability, the inspectors determined whether the measures in place would

function as intended and were properly controlled. The inspectors determined, where

appropriate, compliance with bounding limitations associated with the evaluations.

Additionally, the inspectors also reviewed a sampling of corrective action documents to

verify that the licensee was identifying and correcting any deficiencies associated with

operability evaluations. Specific documents reviewed during this inspection are listed in

the attachment.

These activities constitute completion of ten (10) operability evaluations inspection

samples as defined in Inspection Procedure 71111.15-04

b.

Findings

Introduction. The inspectors identified a Green noncited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Action, for the failure of the licensee to promptly

identify and correct a known condition adverse to quality associated with the

susceptibility of the emergency diesel generators heating, ventilating and air

conditioning ducting to loading effects caused by natural phenomena, such as tornados.

Specifically, while performing a review in response to an NRC generic communication,

the licensee determined that they could not demonstrate the ability of the stations

emergency diesel generators heating, ventilating and air conditioning ducting to

withstand a tornado depressurization event. However no actions were taken to correct

or mitigate this issue at the time of discovery.

Description. On December 6, 2006, the NRC issued Regulatory Issue

Summary 2006-23, Post-Tornado Operability of Ventilating and Air-conditioning

Systems Housed in Emergency Diesel Generator Rooms. The purpose of this

Regulatory Information Summary was to notify licensees of the NRCs regulatory

position regarding loading effects caused by natural phenomena on safety related

systems and components housed inside a structure partially exposed to the outside

environment. Specifically, ventilating and air conditioning systems housed in the

emergency diesel generator rooms. The NRC expects licensees to consider natural

hazards during the design of systems and components housed inside safety-related

structures if these systems and components may be exposed to the outside environment

and if their malfunction or loss may prevent or impact the operability of safety-related

systems and components.

Of particular concern was that vented ventilating and air conditioning ducts, and other

internal safety-related systems and components, may be subject to the effects of rapid

room depressurization and re-pressurization and other effects associated with a tornado

event. In some cases the loss of structural integrity of ventilating and air conditioning

systems may pose a challenge to the safe operation of the facility. In such cases,

- 21 -

Enclosure 2

licensees should take necessary measures to ensure the operability of ventilating and air

conditioning duct systems located in emergency diesel generator rooms.

On December 6, 2006, Entergy corporate initiated Condition Report LO-LAR-2006-0171

to have all sites perform a review of Regulatory Information Summary 2006-023.

Specifically, each site was to determine if the site's design had adequately considered

tornado wind and pressure drop effects on safety-related systems and components

inside building structures open to the outside environment.

On April 12, 2007, the licensee completed their review and concluded that the plant's

design criteria to comply with General Design Criteria GDC-2 requires that the structure

remain fully functional before, during, and after a tornado event without exceeding ASME

Code allowables. The original designers accomplished this by: (1) designing the

external structure (walls, ceilings, floors) to resist tornado winds, missiles, and

depressurization; and (2) providing missile barriers near openings into the building

where a missile trajectory could potentially directly strike a safety-related

system/component. The temporary effects associated with a rapid external

depressurization of systems and components were not considered in the original

analyses. The safety-related components of Arkansas Nuclear Ones heating,

ventilation, and air conditioning system are protected from tornados and other natural

events by being located within the protection of reinforced concrete structures.

Arkansas Nuclear Ones reinforced concrete structures that house safety-related

equipment are designed to resist the effects of tornado conditions. For these structures,

the ventilation system intakes and exhausts are designed to resist tornado generated

missiles. However, neither the design basis nor the licensing basis required ventilation

systems to be designed for the differential pressures associated with a tornado. Units 1

and 2 were licensed before the issuance of Regulatory Guide 1.76 and are not

committed to it.

Based on interactions with the Entergy fleet, the licensee subsequently determined that

it would be prudent to further evaluate the tornado depressurization event and its

potential impact on the diesel generator rooms ventilation systems. The licensee

initiated Condition Report CR-ANO-C-2007-1308 to facilitate this. The licensee

performed subsequent calculations, based upon sound engineering principles using the

reduced differential pressures noted in Regulatory Guide 1.76, Revision 1, to evaluate

the emergency diesel generator ductwork and emergency diesel generator inlet dampers

in both units for effects of a tornado depressurization event. These calculations

concluded that; for Unit 2, initially closed emergency diesel generator inlet dampers

would be rendered inoperable by the event and resulting deformations would prevent

subsequent automatic opening; and for Unit 1, the emergency diesel generator inlet

ductwork to the combustion air filters would collapse and cut off air flow to the engines.

They also indicated that the suction ductwork to the exhaust fans in both units would

collapse and cut off air flow to the exhaust fans. Based on these results, station design

engineering could not ensure with a high level of confidence that the emergency diesel

generator combustion air and ventilation systems would remain functional after a

tornado event.

- 22 -

Enclosure 2

The inspectors reviewed this position and associated calculations and determined that

this was contrary to the regulatory position taken by the NRC in Regulatory Issue

Summary 2006-023. The inspectors also noted; that the licensee had evaluated piping

systems not located in Class 1 structures for tornado induced pressure differentials in

their Final Safety Analysis Report, and that the licensee had used differential pressures

which were less than those specified in their licensing basis to perform their evaluations.

As such, the inspectors questioned the diesel generator rooms ventilation system

capabilities to withstanding the rapid depressurization effects that can occur coincident

with a tornado. Specifically, the inspectors concluded that the evaluations that had been

performed to date did not provide a reasonable expectation of operability for the diesel

generator rooms ventilation systems in a tornado event, and the licensee had taken no

actions to provide compensatory measures to ensure continued operability.

The inspectors presented their concerns to the licensee and the licensee determined

that further review was necessary to determine the acceptability of the identified issues.

The licensee initiated Condition Report CR-ANO-C-2009-2296 to address these

concerns. Subsequent evaluations determined that the Unit 2 emergency diesel

generator ventilating and air conditioning systems would be able to withstand a tornado

event; but Unit 1 required compensatory measures to demonstrate operability for a

design basis tornado event.

Analysis. The failure to promptly identify and correct a know condition adverse to quality

associated with the susceptibility of the Unit 1 emergency diesel generators' heating,

ventilating and air conditioning ducting to loading effects caused by natural phenomena,

tornados, was a performance deficiency. The performance deficiency was determined

to be more than minor because it was associated with the protection against external

events attribute of the Mitigating Systems Cornerstone, and affected the associated

cornerstone objective to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences, and is therefore a

finding. Using Manual Chapter 0609.04, Phase 1 - Initial Screening and

Characterization of Findings, the finding was determined to have very low safety

significance because the finding: (1) was not a design or qualification issue confirmed

not to result in a loss of operability or functionality; (2) did not represent an actual loss of

safety function of the system or train; (3) did not result in the loss of one or more trains of

nontechnical specification equipment; and (4) did not screen as potentially risk

significant due to a seismic, flooding, or severe weather initiating event. The finding was

determined to have a crosscutting aspect in the area of human performance, associated

with decision making, H.1(b), in that the licensee failed to use conservative assumptions

in decision making and adopt a requirement to demonstrate that the proposed action is

safe in order to proceed rather than a requirement to determine it is unsafe in order to

disapprove the action.

Enforcement. Title 10 of the Code of Federal Regulations Part 50, Appendix B,

Criterion XVI, Corrective Action, requires, in part, that Measures shall be established

to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies,

deviations, defective material and equipment, and nonconformances are promptly

identified and corrected. Contrary to the above, from December 2006 through

- 23 -

Enclosure 2

November 2009, the licensee failed to ensure that a known condition adverse to quality

associated with the susceptibility of the Unit 1 emergency diesel generators' heating,

ventilating and air conditioning ducting to loading effects caused by natural phenomena,

tornados, was corrected in a timely manner. Because this finding is of very low safety

significance and has been entered into the corrective action program as Condition

Report CR-ANO-C-2009-2296, this violation is being treated as a noncited violation

consistent with Section 2.3.2.a of the NRC Enforcement Policy: NCV 05000313/2010004-02, Failure to Promptly Identify and Correct a Condition Adverse to

Quality Associated with Emergency Diesel Generator Heating, Ventilation and Air

Conditioning Ducting Susceptibility to Tornado Loading.

1R18 Plant Modifications (71111.18)

Permanent Plant Modifications

a.

Inspection Scope

The inspectors reviewed key affected parameters associated with energy needs,

materials/replacement components, timing, heat removal, control signals, equipment

protection from hazards, operations, flow paths, pressure boundary, ventilation

boundary, structural, process medium properties, licensing basis, and failure modes for

the modification listed below.

Unit 1, modifications performed to emergency switchgear chillers VCH-4A/B

The inspectors verified that modification preparation, staging, and implementation did

not impair emergency/abnormal operating procedure actions, key safety functions, or

operator response to loss of key safety functions; postmodification testing will maintain

the plant in a safe configuration during testing by verifying that unintended system

interactions will not occur, systems, structures and components performance

characteristics still meet the design basis, the appropriateness of modification design

assumptions, and the modification test acceptance criteria will be met; and licensee

personnel identified and implemented appropriate corrective actions associated with

permanent plant modifications. Specific documents reviewed during this inspection are

listed in the attachment.

These activities constitute completion of one (1) sample for permanent plant

modifications as defined in Inspection Procedure 71111.18-05

a.

Findings

Introduction. The inspectors documented a Green self-revealing noncited violation of

10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for the failure of the

licensee to promptly identify and correct a known condition adverse to quality associated

with the improper setup of the dead band of service water flow control valve CV-6034 for

cold weather operation. This resulted in the pressure control valve not properly

modulating in response to pressure control inputs and the chiller tripping on high

discharge pressure.

- 24 -

Enclosure 2

Description. On December 1, 2009, the licensee was conducting a normal surveillance

run of emergency switchgear chiller VCH-4A in accordance with station

Procedure OP-1104.027, Battery and Switchgear Emergency Cooling System,

Revision 5. During this run, operators noted the discharge pressure for the chiller was

cycling excessively, followed by the chiller tripping on high discharge pressure. This

issue was entered into the stations corrective action program as Condition

Report CR-ANO-1-2009-2212.

The licensee performed an apparent cause evaluation of this issue as documented in

Condition Report CR-ANO-1-2009-2212. During their review, the licensee noted that a

similar issue had occurred previously on chiller VCH-4B in January 2008, and was

documented in Condition Report CR-ANO-1-2008-0098. The apparent cause of that

issue had been determined to be degraded and/or inappropriate set-up of the dead band

of the Modutronic circuit board for service water flow control valve CV-6036. This was

corrected by adjusting the gain so that the dead band was more appropriate, resulting in

less movement and no motor thermal overload concerns for cold weather operation.

The licensee also noted that the extent of condition review had identified CV-6034, the

service water flow control for VCH-4A, as being susceptible to this issue. However,

because a degraded piece/part had been discovered on CV-6036 (gain potentiometer

disengaged) and no previous issues had been identified with CV-6034, no corrective

actions were pursued to troubleshoot and repair CV-6034. Instead, the model work

order for these valves was revised to incorporate some lessons learned for future

maintenance.

The licensee determined that the apparent cause of the improper operation of the valves

was an increase in stroke times of the valves. Specifically, CV-6034 and CV-6036 valve

bodies were replaced in December 2006 with stainless steel bodies, where they formerly

utilized carbon steel bodies, and the subsequent testing performed indicated that the

opening stroke times had increased by as much as 20 percent with no changes to the

motor-operated valve dead band adjustment. The licensee determined that these motor

operated valves had very little margin regarding current draw and overload relay

settings, and this change introduced enough additional drag or load on the motor

operated valve that the overload relay settings trip during certain modes of operation.

This was corrected by adjusting the gain so that the dead band was more appropriate,

resulting in less movement and no motor thermal overload concerns for cold weather

operation.

Analysis. Failure to promptly identify and correct a known condition adverse to quality

associated with the improper setup of the dead band of service water flow control

valve CV-6034 for cold weather operation was a performance deficiency. The

performance deficiency was determined to be more than minor because it was

associated with the equipment performance attribute of the Mitigating Systems

Cornerstone, and affected the associated cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences, and is therefore a finding. Using Manual

Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings, the

- 25 -

Enclosure 2

finding was determined to have very low safety significance because: (1) the finding

was not a qualification deficiency that resulted in a loss functionality of chiller VCH-4A;

(2) it did not lead to an actual loss of safety function of the system or train; (3) it did not

result in an actual loss of safety function of a single train for greater than its technical

specification allowed outage time; (4) it did not represent an actual loss of safety function

of one or more nontechnical specification trains of equipment designated as risk-

significant per 10 CFR 50.65, for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; (5) it did not screen as

potentially risk-significant due to a seismic, flooding, or severe weather initiating event.

The finding was determined to have a crosscutting aspect in the area of human

performance, associated with decision making in that, although the licensee had

identified the vulnerability of the VCH-4A chiller, decided not to pursue the corrective

actions to adjust the dead band for valve CV-6034 and resulted in the subsequent

improper operation of the valve H.1(b).

Enforcement. Title 10 of the Code of Federal Regulations Part 50, Appendix B,

Criterion XVI, Corrective Action, requires, in part, that Measures shall be established

to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies,

deviations, defective material and equipment, and nonconformances are promptly

identified and corrected. Contrary to the above, from December 2006 through

December 2009 the licensee failed to ensure that a known condition adverse to quality

associated with the setup of the dead band for service water flow control valve CV-6034,

which affected the operation of the valve during cold weather operations, was corrected

in a timely manner. Because this finding is of very low safety significance and has been

entered into the corrective action program as Condition Report CR-ANO-1-2009-2212,

this violation is being treated as a noncited violation consistent with Section 2.3.2.a of

the NRC Enforcement Policy: NCV 05000313/2010004-03, Failure to Promptly Identify

and Correct a Condition Adverse to Quality Associated with Emergency Switchgear

Chiller VCH-4A.

1R19 Postmaintenance Testing (71111.19)

a.

Inspection Scope

The inspectors reviewed the following postmaintenance activities to verify that

procedures and test activities were adequate to ensure system operability and functional

capability:

July 7, 2010, Unit 1, P-7A turbine driven emergency feedwater pump speed

circuit calibration after electronic governor module replacement

July 14, 2010, Unit 1, VCH-4B TS-6060 lockout on high temperature emergency

temporary modification and corrective maintenance

July 30, 2010, Unit 2, Alternate AC diesel generator after maintenance period

August 4-5, 2010, Unit 2, Containment spray transmitter 2FT-5610 following

replacement activities

- 26 -

Enclosure 2

August 22, 2010, Unit 2, Emergency diesel generator 2K-4B following repair

activities for a crank case vacuum issue

Week of Sept 6, 2010, Unit 2, Emergency diesel generator 2 following extensive

maintenance to resolve crankcase vacuum issue

The inspectors selected these activities based upon the structure, system, or

component's ability to affect risk. The inspectors evaluated these activities for the

following:

The effect of testing on the plant had been adequately addressed; testing was

adequate for the maintenance performed

Acceptance criteria were clear and demonstrated operational readiness; test

instrumentation was appropriate

The inspectors evaluated the activities against the technical specifications, the Safety

Analysis Report, 10 CFR Part 50 requirements, licensee procedures, and various NRC

generic communications to ensure that the test results adequately ensured that the

equipment met the licensing basis and design requirements. In addition, the inspectors

reviewed corrective action documents associated with postmaintenance tests to

determine whether the licensee was identifying problems and entering them in the

corrective action program and that the problems were being corrected commensurate

with their importance to safety. Specific documents reviewed during this inspection are

listed in the attachment.

These activities constitute completion six (6) postmaintenance testing inspection

samples as defined in Inspection Procedure 71111.19-05.

b.

Findings

Introduction. The inspectors documented a self-revealing finding for station electrical

maintenance personnel's failure to adequately implement station Procedure EN-WM-

102, Work Implementation and Closeout, Revision 4. Specifically, station personnel

performing Work Order 00182908-01, removal/reinstallation of isophase fan motor C-8A,

did not stop work when a condition that was not identified in the work order was

discovered.

Description. On March 24, 2010, during Refueling Outage 1R22, maintenance

personnel performed work on the Unit 1 isophase blower fan motor C-8A using station

Work Order 00182908-01. The purpose of the work order was to remove the fan motor

for rewinding off site and reinstallation. During de-termination of the fan motor power

leads, two additional leads were removed from two of the three phases and documented

on the lifted lead log sheet. After the motors return to the site, on April 7-8, 2010, the

original lifted lead log was used to re-terminate the motor heater leads, vibration probes,

and grounds. A new lifted lead log was prepared to re-terminate the motor leads since

they had been relabeled. Two wires that were not labeled or lugged were identified and

the maintenance personnel assumed that they were spares and were left as found.

- 27 -

Enclosure 2

Motor rotation was checked and the work was completed. Following completion of the

refueling outage, on April 27, 2010, while operators were attempting to swap isophase

fans, it was discovered that the damper for isophase blower C-8A failed to open. This

was documented in Condition Report CR-ANO-1-2010-2105. Subsequently, station

Work Order 00235005 was generated to troubleshoot why the damper did not open.

Work was completed on May 11, 2010. Subsequently, maintenance initiated Condition

Report CR-ANO-1-2010-2260 which identified that, following the troubleshooting, the

power supply leads for the damper motors were not terminated in the fan motor

termination box.

The licensee performed an apparent cause evaluation of the issue, documented in

Condition Report CR-ANO-1-2010-2260, and during the inspectors' review, they noted

the maintenance personnel did not question the removal of two power leads from two of

the motor phases and only one power lead for the other motor phase and continued the

work and did not communicate the discrepancy for a potential scope change to the work

order. The inspectors determined this to be contrary to Station Procedure EN-WM-102,

Work Implementation and Closeout, Revision 4, which states, in part, in Section 5.3

that a scope change has occurred if any of the following are identified during

performance of the work: The activity is not covered by the postmaintenance test; the

work instructions require a revision other than an editorial change, detail classification,

enhancement, or remedy of omissions; or additional components or systems are

affected. As such, the inspectors determined that maintenance personnel had failed to

follow station procedure and generate a scope change to the work package.

Analysis. Failure of station maintenance personnel to follow the requirements of station

Procedure EN-WM-102 and process a scope change due to unexpected conditions for

this reference level work package was a performance deficiency. The finding was more

than minor because it affected the human performance attribute of the Initiating Events

Cornerstone, and it directly affected the cornerstone objective to limit the likelihood of

those events that upset plant stability during power operations. Using Manual

Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings, the

finding was determined to have very low safety significance because it did not contribute

to both the likelihood of a reactor trip and the likelihood that mitigation equipment or

functions would not be available. The finding had a crosscutting aspect in the area of

Human Performance associated with work practices H.4(a), in that the licensee failed

to communicate human error prevention techniques, such as holding pre-job briefings,

self- and peer-checking, and proper documentation of activities. Specifically, station

maintenance personnel failed to follow Procedure EN-WM-102 when discovering a

condition that was unexpected for this work package and did not stop work to resolve the

issue prior to continuing with the work which resulted in inadequate completion and

testing in the work package for the planned activities for the isophase blower motor and

damper.

Enforcement. This finding does not involve enforcement action because no regulatory

requirement violation was identified, since the affected isophase blower damper is not

safety-related. Because this finding does not involve a violation, has very low safety

significance, and has been entered into the corrective action program as

- 28 -

Enclosure 2

Condition Report CR-ANO-1-2010-2260, it is identified as FIN 05000313/2010004-04,

Failure to Follow Station Work Control Procedure Results in Unavailable Equipment.

1R20 Refueling and Other Outage Activities (71111.20)

a.

Inspection Scope

The inspectors reviewed the outage plan and contingency plans for the Unit 2 Forced

Outage 2FO1 conducted August 23 through September 4, 2010, to confirm that licensee

personnel had appropriately considered risk, industry experience, and previous site-

specific problems in developing and implementing a plan that assured maintenance of

defense in depth. During the forced outage, the inspectors observed portions of the

shutdown and cooldown processes and monitored licensee controls over the outage

activities listed below.

Configuration management, including maintenance of defense in depth, is

commensurate with the outage safety plan for key safety functions and

compliance with the applicable technical specifications when taking equipment

out of service

Installation and configuration of reactor coolant pressure, level, and temperature

instruments to provide accurate indication, accounting for instrument error

Status and configuration of electrical systems to ensure that technical

specifications and outage safety plan requirements were met and controls over

switchyard activities

Monitoring of decay heat removal processes, systems, and components

Controls over activities that could affect reactivity

Startup and ascension to full power operation, tracking of startup prerequisites,

walkdown of the primary containment to verify that debris had not been left which

could block emergency core cooling system suction strainers, and reactor

physics testing

Licensee identification and resolution of problems related to forced outage

activities

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one (1) forced outage inspection sample as

defined in Inspection Procedure 71111.20-05.

b.

Findings

Introduction. The inspectors identified a Green cited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, associated with the

- 29 -

Enclosure 2

licensees failure to adequately implement Procedure EN-MA-118, Foreign Material

Exclusion, Revision 5/6. Specifically, between October 31, 2008, and September 2,

2010, inspectors identified multiple occasions where licensee personnel failed to

implement appropriate foreign material exclusion controls in Zone 1 areas around safety-

related equipment (e.g. failure to appropriately log material in to and out of the zone) as

required by station procedure. Each identified instance was a repeat occurrence of

previously identified issues that were documented as NRC identified violations in

previous inspection reports in 2008, 2009, and early 2010. Measures established by

Arkansas Nuclear One to address these previously identified noncited violations failed to

restore compliance within a reasonable time after these violations were identified.

Finally, these failures had the potential of having a negative impact on safety related

components such as fuel failure, safety system reliability and safety related equipment

availability. This issue was entered into the licensee's corrective action program as

Condition Reports CR-ANO-2-2010-1839, CR-ANO-C-2010-2192, and

CR-ANO-X-2010-3155.

Description. Inspectors issued NCVs05000313/2008005-03, 05000368/2009004-04,

and 05000313/2010003-02 to the licensee for the failure of licensee personnel to

appropriately implement the requirements of station procedure EN-MA-118, for foreign

material exclusion controls in areas designated as Zone 1 foreign material exclusion

areas.

05000313/2008005-03: The resident staff identified multiple issues with the

licensees implementation of their foreign material control program during

refueling outage 1R21. Specifically, the resident staff determined that the issue

was associated with the failure of station personnel to follow the procedural

requirements including failure to adequately log materials in to and out of a Zone

1 area. (Note: while there were multiple examples identified of station

personnels failure to follow procedure, there were no actual introductions of

material into critical systems).

The licensee performed an apparent cause evaluation and determined the

apparent cause was poor worker and supervisory work practices. Specifically,

supervision and management were lacking in oversight performance, which was

due to the significant procedure changes not being recognized as a potential trap

for those implementing the procedure from a worker / FME Monitor / supervisor

standpoint. Change management was inadequate from an oversight

perspective. The licensee also identified as a contributing cause inadequate

training / procedure knowledge for supervisor and craft.

05000368/2009004-04: The resident staff identified multiple issues with the

licensees implementation of their foreign material control program during

refueling outage 2R20. The resident staff determined that the issue was

associated with the failure of station personnel to follow the procedural

requirements including failure to adequately log material in to and out of a Zone 1

area. (Note: this was after the completion of all corrective actions for NCV 05000313/2008005-03). Additionally, some of these examples included actual

- 30 -

Enclosure 2

introductions of material into critical systems that had not been logged when

taken into the Zone 1 area.

The licensee performed an apparent cause evaluation and determined there to

be two apparent causes; proper worker practices have not been reinforced

through supervisor feedback (AC1) and in training (AC2). (The residents noted

that these were essentially the same causes that had been identified previously;

apparent cause was poor worker and supervisory work practices, and the

contributing cause inadequate training / procedure knowledge for supervisor and

craft.)

05000313/2010003-02: The resident staff identified multiple issues with the

licensees implementation of their foreign material control program during

refueling outage 1R22. The resident staff determined that the issue was

associated with the failure of station personnel to follow the procedural

requirements. (Note: this was after the completion of all corrective actions for the

previous NCVs05000313/2008005-03 and 05000368/2009004-04, and some of

these examples were actual introductions of material into critical systems)

The licensee did not perform an apparent cause evaluation for this issue.

Instead, each issue was addressed in the condition report that identified it, and a

rollup condition report was written to capture lessons learned for future refueling

outages.

The inspectors noted that the condition reports that captured the individual issues

actually failed to appropriately call out the failure to follow procedure. Instead,

most were closed to actions taken for material recovery, and/or coaching.

On August 24, 2010, while conducting a tour of the facility the inspectors noted work in

progress in the area of the safety related emergency diesel generator 2K-4B, which had

been designated a Zone 1 foreign material exclusion area, was not in accordance with

station procedures. Specifically, the inspectors noted that individuals working in the area

were not appropriately implementing the requirements of station Procedure EN-MA-118,

Foreign Material Exclusion, Revision 5. The inspectors identified that some personnel

in the zone 1 foreign material exclusion area failed to have their hard hats, eye

protection, pens or tools properly secured. The inspectors informed the licensee of this

issue and it was entered into the corrective action program as Condition Report

CR-ANO-2-2010-1839.

On August 25, 2010, while touring emergency diesel generator 2K-4B room again, the

inspectors again identified issues with station personnels implementation of the

requirements of station procedure EN-MA-118 for a Zone 1 foreign material exclusion

area. Specifically, the inspectors identified that a clear plastic bag had been introduced

into the Zone 1 foreign material exclusion area (procedurally clear plastic is not allowed

in foreign material exclusion zone 1 areas without distinguishing markings) and this bag

had not been logged into the foreign material exclusion area log. The inspectors also

observed station personnel placing a spiral wound notebook and pen in the Zone 1

foreign material exclusion area without logging them in and verifying they were failsafe

- 31 -

Enclosure 2

as required by procedure. The inspectors informed the licensee of this issue and it was

entered into the corrective action program as Condition Report CR-ANO-C-2010-2192.

On September 2, 2010, while touring the spent fuel floor, the inspectors again identified

issues with station personnels implementation of the requirements of station procedure

EN-MA-118 for a Zone 1 foreign material exclusion area. Specifically, the inspectors

observed an individual enter the Zone 1 area around the spent fuel pool for Unit 1,

without their hard hat being properly secured. The inspectors determined that this

represented an instance where foreign material, the hard hat, could be introduced into a

safety related system containing spent fuel assemblies. The inspectors informed the

licensee of this issue and it was entered into the corrective action program as Condition

Report CR-ANO-1-2010-3155.

Through their review the inspectors determined that the licensee had failed to ensure

that Procedure EN-MA-118 requirements were followed. Specifically, the station

personnel failed to appropriately secure material entering a Zone 1 foreign material

exclusion area and failed to properly log material entering a Zone 1 foreign material

exclusion area to ensure accountability was maintained. The inspectors also determined

that there has been sufficient time for previous corrective actions identified by the

licensee to take effect, and as such, the previous corrective actions that had been taken

were inadequate.

The inspectors concluded that while the identified examples of station personnels failure

to follow Procedure EN-MA-118 was indicative of a continued programmatic issue

associated with the station personnels implementation of the foreign material exclusion

program which could directly impact safety related equipment as well as critical systems.

While there was no actual damage to station critical systems, there has been at least

one example of introduction of foreign material into a critical system, which was

discovered before damage occurred.

Analysis. The failure of station personnel to follow Procedure EN-MA-118, Foreign

Material Exclusion, when working in Zone 1 foreign material exclusion areas around

safety related equipment/areas, was a performance deficiency. The performance

deficiency was determined to be more than minor because it was associated with the

human performance attribute of the Mitigating Systems Cornerstone, and affected the

associated cornerstone objective to ensure the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences, and is

therefore a finding. Using the Manual Chapter 0609, Significance Determination

Process, Phase 1 Worksheets, the finding was determined to have very low safety

significance because the finding: (1) was not a design or qualification issue confirmed

not to result in a loss of operability or functionality; (2) did not represent an actual loss of

safety function of the system or train; (3) did not result in the loss of one or more trains of

nontechnical specification equipment; and (4) did not screen as potentially risk

significant due to a seismic, flooding, or severe weather initiating event. The finding was

determined to have a crosscutting aspect in the area of problem identification and

resolution, associated with the corrective action program, P.1(d), in that the licensee

takes appropriate corrective actions to address safety issues and adverse trends in a

timely manner, commensurate with their safety significance and complexity.

- 32 -

Enclosure 2

Enforcement. Title 10 of the Code of Federal Regulations Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities

affecting quality shall be prescribed by documented instructions, procedures or

drawings, of a type appropriate to the circumstances and shall be accomplished in

accordance with these instructions, procedures, or drawings.

Arkansas Nuclear One Procedure EN-MA-118, Foreign Material Exclusion, Revision 6

requires the establishment of a Foreign Material Exclusion Zone 1 when loss of foreign

material exclusion integrity could result in fuel failure, reduced system safety, station

availability or significant cost for recovery. Section 5.11, FME Zone 1 Requirements, of

the same procedure, states in part that for Foreign Material Exclusion Zone 1, the

Foreign Material Exclusion Monitor shall control personnel and material access to the

Foreign Material Exclusion zone.

Contrary to the above, between October 31, 2008, and September 2, 2010, Arkansas

Nuclear One failed to ensure Foreign Material was controlled in accordance with the

requirements of Procedure EN-MA-118. Specifically, the inspectors identified multiple

occasions where the licensee personnel failed to implement appropriate foreign material

exclusion controls (e.g., failure to appropriately log material in to and out of the area) in

Foreign Material Exclusion Zone 1 areas around safety-related equipment as required by

station procedure. Additionally, these failures had the potential of having a negative

impact on safety-related components.

This finding was of very low safety significance and was entered into the licensees

corrective action program as condition reports CR-ANO-2-2010-1839,

CR-ANO-C-2010-2192, and CR-ANO-1-2010-3155. Due to the described programmatic

nature, this violation is being cited in a Notice of Violation consistent with Section 2.3.2.a

of the NRC Enforcement Policy: VIO 05000313;05000368/2010004-05, Failure to

Adequately Implement Foreign Material Exclusion Controls.

1R22 Surveillance Testing (71111.22)

a.

Inspection Scope

The inspectors reviewed the Safety Analysis Report, procedure requirements, and

technical specifications to ensure that the surveillance activities listed below

demonstrated that the systems, structures, and/or components tested were capable of

performing their intended safety functions. The inspectors either witnessed or reviewed

test data to verify that the significant surveillance test attributes were adequate to

address the following:

Preconditioning

Evaluation of testing impact on the plant

Acceptance criteria

- 33 -

Enclosure 2

Test equipment

Procedures

Test data

Testing frequency and method demonstrated technical specification operability

Test equipment removal

Restoration of plant systems

Fulfillment of ASME Code requirements

Updating of performance indicator data

Engineering evaluations, root causes, and bases for returning tested systems,

structures, and components not meeting the test acceptance criteria were correct

Reference setting data

Annunciators and alarms setpoints

The inspectors also verified that licensee personnel identified and implemented any

needed corrective actions associated with the surveillance testing.

July 7, 2010, Unit 2, Emergency diesel generator 1 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> endurance run

July 9, 2010, Unit 2, Emergency diesel generator 2 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> endurance run

July 14, 2010, Unit 1 , VCH-4B, Emergency switchgear chiller quarterly

surveillance test

August 4-5, 2010, Unit 2, Containment spray pump train A

August 22, 2010, Unit 2, Emergency feedwater pump 2P-7A

August 23, 2010, Unit 1, P-7A, Turbine-driven emergency feedwater pump

quarterly surveillance test

September 2, 2010, Unit 2, Emergency diesel generator 2 after forced

maintenance outage activities

September 28-30, 2010, Unit 1 and Unit 2, Reactor coolant system leakage

calculations

September 30, 2010, Unit 1, Containment isolation valve SV-1818, pressurizer

sampling and reactor coolant system sampling isolation valve

- 34 -

Enclosure 2

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of nine (9) surveillance testing inspection samples

as defined in Inspection Procedure 71111.22-05.

b.

Findings

Introduction. The inspectors documented a Green self-revealing noncited violation of

10 CFR Part 50, Appendix B, Criterion III, Design Control, associated with the

licensees failure to assure that the applicable design basis for applicable structures,

systems, and components were correctly translated into specifications, procedures, and

instructions. Specifically, during initial plant installation the licensee failed to correctly

identify the effect redundant protective equipment interlocks could have on maintaining

operability of VCH-4B design requirements upon a loss of normal non-safety cooling.

This resulted in emergency switchgear chiller VCH 4B, not being able to start and

perform its design function due to a combination of high room temperature due to loss of

normal non-safety related cooling and normally energized compressor oil heaters which

led to a high compressor oil temperature switch actuation that caused a lockout of the

chiller that would have prevented a chiller start.

Description. At 2:10 p.m. on July 14, 2010, the Unit 1 control room received a

VCH-4A/B trouble alarm. Local investigation found the high oil temperature/high

discharge pressure alarm/lockout was active on south emergency switchgear

chiller VCH-4B. Chiller VCH-4B was and had been idle prior to the receipt of the control

room alarm. Subsequent investigation determined that high oil temperature

switch TS-6060 for chiller VCH-4B, had actuated on a valid high oil temperature

condition in compressor C-52, for chiller VCH-4B.

Normal nonsafety-related room cooler VUC-2A, for room 100 where chiller VCH-4B is

located, had failed some time during the day and had caused the temperature in

room 100 to rise. Chiller VCH-4B compressor C-52 is designed with a compressor sump

oil heater element that is energized when the unit is offline to avoid refrigerant emulsion

into the oil. The combined effect of the loss of normal room cooling, the energized oil

heaters, and the high ambient temperature led to oil sump temperatures reaching the

actuation set point of 157 degrees Fahrenheit for TS-6060, causing a lockout of

chiller VCH-4B.

The licensee declared chiller VCH-4B inoperable at 2:38 p.m. and commenced

performing contingency actions contained in Procedure OP-1104.027, Battery and

Switchgear Emergency Cooling System, to exit the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> allowed outage time of

Technical Specifications 3.8.4, 3.8.9, and the 12 shutdown action statements for

Technical Specification 3.8.7, and to then enter a 30 day administrative time clock.

However, one of the required nonsafety-related coolers, VUC-13B, north battery charger

normal cooling, was out of service for maintenance. This prevented the completion of

the contingency actions of Procedure OP-1104.027 and kept the station in a limiting

12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> shutdown action statement of Technical Specification 3.8.7. At 9:58 p.m., Unit 1

exited all technical specification limiting condition for operations when VCH-4B was

declared operable after implementation of an emergency temporary modification, an

- 35 -

Enclosure 2

engineering evaluation to permanently disable hi compressor oil temperature

lockout TS-6060 and performing the monthly surveillance test to demonstrate equipment

operability. The licensee initiated Condition Report CR-ANO-1-2010-2815 to document

the issue in the stations corrective action program. The licensee documented the

operability of north emergency switchgear chiller VCH-4A, in Condition

Report CR-ANO-1-2010-3075. The licensee performed an apparent cause evaluation

and developed a corrective action plan to permanently disable the compressor sump

high oil temperature lockout feature for both chillers VCH-4B and VCH-4A.

Analysis. The inspectors determined that the licensees failure to ensure that design

requirements were correctly translated into installed plant equipment was a performance

deficiency. The performance deficiency was determined to be more than minor because

it was associated with the equipment performance attribute of the Mitigating Systems

Cornerstone and affected the associated cornerstone objective to ensure availability,

reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences, and is therefore a finding. Specifically, the licensee failed to

correctly analyze and identify that chiller VCH-4B could receive a high oil temperature

lockout with a loss of normal room cooling prior to receiving a valid start signal due to the

compressor sump oil heaters and a high ambient room temperature and prevent

fulfillment of its required design function. Using Manual Chapter 0609.04, Phase 1 -

Initial Screening and Characterization of Findings, the finding was determined to have

very low safety significance because: (1) the finding was not a qualification deficiency

that resulted in a loss of functionality of chiller VCH-4B; (2) it did not lead to an actual

loss of safety function of the system or train; (3) it did not result in an actual loss of

safety function of a single train for greater than its technical specification allowed outage

time; (4) it did not represent an actual loss of safety function of one or more non-

technical specification trains of equipment designated as risk-significant per

10 CFR 50.65, for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; (5) it did not screen as potentially risk-

significant due to a seismic, flooding, or severe weather initiating event. The inspectors

determined that since the licensee had not recently re-evaluated the design of the

emergency switchgear room chillers high oil temperature lockout; this finding did not

represent current plant performance, and therefore did not have a crosscutting aspect

associated with it

Enforcement. Title 10 of the Code of Federal Regulations Part 50, Appendix B,

Criterion III, Design Control, requires, in part, measures be established to assure that

applicable regulatory requirements and the design basis, as defined in 10 CFR 50.2 and

as specified in the license application, for those components to which this appendix

applies are correctly translated into specifications, drawings, procedures, and

instructions. Contrary to the above, from initial installation through July 2010, the

licensee failed to ensure that that design requirements for the Unit 1 emergency

switchgear chillers were correctly translated into installed plant equipment. Because this

finding is of very low safety significance and has been entered into the corrective action

program as Condition Report CR-ANO-1-2010-2815, this violation is being treated as a

noncited violation consistent with Section 2.3.2.a of the NRC Enforcement Policy:

NCV 05000313/2010004-06, Failure to Correctly Translate VCH-4B Design

Requirements into Installed Plant Configuration.

- 36 -

Enclosure 2

2.

RADIATION SAFETY

Cornerstone: Occupational and Public Radiation Safety

2RS06 Radioactive Gaseous and Liquid Effluent Treatment (71124.06)

a.

Inspection Scope

This area was inspected to: (1) ensure the gaseous and liquid effluent processing

systems are maintained so radiological discharges are properly mitigated, monitored,

and evaluated with respect to public exposure; (2) ensure abnormal radioactive gaseous

or liquid discharges and conditions, when effluent radiation monitors are out of service,

are controlled in accordance with the applicable regulatory requirements and licensee

procedures; (3) verify the licensee=s quality control program ensures the radioactive

effluent sampling and analysis requirements are satisfied so discharges of radioactive

materials are adequately quantified and evaluated; and (4) verify the adequacy of public

dose projections resulting from radioactive effluent discharges. The inspectors used the

requirements in 10 CFR Part 20; 10 CFR Part 50, Appendices A and I; 40 CFR Part 190,

the offsite dose calculation manual, and licensee procedures required by the technical

specifications as criteria for determining compliance. The inspectors interviewed

licensee personnel and reviewed and/or observed the following items:

Radiological effluent release reports since the previous inspection and reports

related to the effluent program issued since the previous inspection, if any

Effluent program implementing procedures, including sampling, monitor setpoint

determinations and dose calculations

Equipment configuration and flow paths of selected gaseous and liquid

discharge system components, filtered ventilation system material condition,

and significant changes to their effluent release points, if any, and associated

10 CFR 50.59 reviews

Selected portions of the routine processing and discharge of radioactive gaseous

and liquid effluents (including sample collection and analysis)

Controls used to ensure representative sampling and appropriate compensatory

sampling

Results of the inter-laboratory comparison program

Effluent stack flow rates

Surveillance test results of technical specification-required ventilation effluent

discharge systems since the previous inspection

Significant changes in reported dose values, if any

- 37 -

Enclosure 2

A selection of radioactive liquid and gaseous waste discharge permits

Part 61 analyses and methods used to determine which isotopes are included in

the source term

Offsite dose calculation manual changes, if any

Meteorological dispersion and deposition factors

Latest land use census

Records of abnormal gaseous or liquid tank discharges, if any

Groundwater monitoring results

Changes to the licensees written program for indentifying and controlling

contaminated spills/leaks to groundwater, if any

Identified leakage or spill events and entries made into 10 CFR 50.75 (g)

records, if any, and associated evaluations of the extent of the contamination and

the radiological source term

Offsite notifications and reports of events associated with spills, leaks, or

groundwater monitoring results, if any

Audits, self-assessments, reports, and corrective action documents related to

radioactive gaseous and liquid effluent treatment since the last inspection

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of the one required sample, as defined in

Inspection Procedure 71124.06-05.

b.

Findings

No findings were identified.

2RS07 Radiological Environmental Monitoring Program (71124.07)

a.

Inspection Scope

This area was inspected to: (1) ensure that the radiological environmental monitoring

program verifies the impact of radioactive effluent releases to the environment and

sufficiently validates the integrity of the radioactive gaseous and liquid effluent release

program; (2) verify that the radiological environmental monitoring program is

implemented consistent with the licensees technical specifications and/or offsite dose

calculation manual, and to validate that the radioactive effluent release program meets

the design objective contained in Appendix I to 10 CFR Part 50; and (3) ensure that the

radiological environmental monitoring program monitors non-effluent exposure

- 38 -

Enclosure 2

pathways, is based on sound principles and assumptions, and validates that doses to

members of the public are within the dose limits of 10 CFR Part 20 and 40 CFR

Part 190, as applicable. The inspectors reviewed and/or observed the following items:

$

Annual environmental monitoring reports and offsite dose calculation manual

$

Selected air sampling and thermoluminescence dosimeter monitoring stations

$

Collection and preparation of environmental samples

$

Operability, calibration, and maintenance of meteorological instruments

$

Selected events documented in the annual environmental monitoring report

which involved a missed sample, inoperable sampler, lost thermoluminescence

dosimeter, or anomalous measurement

$

Selected structures, systems, or components that may contain licensed material

and has a credible mechanism for licensed material to reach groundwater

$

Records required by 10 CFR 50.75(g)

$

Significant changes made by the licensee to the offsite dose calculation manual

as the result of changes to the land census or sampler station modifications since

the last inspection

$

Calibration and maintenance records for selected air samplers, composite water

samplers, and environmental sample radiation measurement instrumentation

$

Inter-laboratory comparison program results

$

Audits, self-assessments, reports, and corrective action documents related to the

radiological environmental monitoring program since the last inspection

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of the one required sample as defined in

Inspection Procedure 71124.07-05.

b.

Findings

No findings were identified.

2RS08 Radioactive Solid Waste Processing, and Radioactive Material Handling, Storage,

and Transportation (71124.08)

a.

Inspection Scope

This area was inspected to verify the effectiveness of the licensee=s programs for

processing, handling, storage, and transportation of radioactive material. The inspectors

used the requirements of 10 CFR Parts 20, 61, and 71 and Department of

- 39 -

Enclosure 2

Transportation regulations contained in 49 CFR Parts 171-180 for determining

compliance. The inspectors interviewed licensee personnel and reviewed the following

items:

$

The solid radioactive waste system description, process control program, and the

scope of the licensee=s audit program

$

Control of radioactive waste storage areas including container labeling/marking

and monitoring containers for deformation or signs of waste decomposition

$

Changes to the liquid and solid waste processing system configuration including

a review of waste processing equipment that is not operational or abandoned in

place

$

Radio-chemical sample analysis results for radioactive waste streams and use of

scaling factors and calculations to account for difficult-to-measure radionuclides

$

Processes for waste classification including use of scaling factors and

10 CFR Part 61 analysis

$

Shipment packaging, surveying, labeling, marking, placarding, vehicle checking,

driver instructing, and preparation of the disposal manifest

Audits, self assessments, reports, and corrective action reports radioactive solid

waste processing, and radioactive material handling, storage, and transportation

performed since the last inspection

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of the one required sample as defined in

Inspection Procedure 71124.08-05.

b.

Findings

Introduction. The inspectors identified a Green noncited violation of 10 CFR 20.2006(b)

for failure to ship radioactive waste with an accurate manifest.

Description. On May 19, 2009, the licensee shipped 20 Unit 2 spent fuel pool filters to a

waste processor for segregation. The waste manifest (NRC Forms 540 and 541)

accompanying the shipment indicated a total activity of 1650 millicuries based on dose

rate measurements of the filters. The recipient of the shipment performed dose

measurements of the filters to determine which filters could be kept for processing. The

licensee was notified on June 1, 2009, that dose rate on one filter was almost twice the

licensee reported dose rate (38 rem/hr vice 20 rem/hr) which equated to a total activity of

5000 millicuries. This event was documented in the corrective action program as

Condition Report CR-ANO-C-2009-1008. The licensee determined that the waste

classification of the shipment was unchanged by the higher curie content.

- 40 -

Enclosure 2

The total activity of the shipment based on the higher dose rate was approximately three

times more than reported on the shipping manifest. Until questioned by the inspectors,

the licensee failed to issue a corrected manifest or review how this event may have

affected other areas of the radiation protection program, such as reports made detailing

the amount of radioactive waste shipped annually. This was documented in the

corrective action program as Condition Report CR-ANO-C-2010-1866.

Analysis. The failure to include the correct total radioactivity on a waste manifest is a

performance deficiency. The finding is greater than minor because it was associated

with the Public Radiation Safety Cornerstone attribute of program and process

(transportation program), and affected the cornerstone objective, in that, it provided

incorrect information as part of hazard communication which could increase public dose.

Using the public radiation safety significance determination process, the inspectors

determined the finding had very low safety significance because (1) radiation limits were

not exceeded, (2) there was no breach of a package during transit, (3) it did not involve a

certificate of compliance issue, (4) it was not a low level burial ground nonconformance,

and (5) it did not involve a failure to make notifications or provide emergency

information. This finding had a crosscutting aspect in the area of corrective action

program, low threshold, because the licensee did not set a low threshold for identifying

issues completely and accurately P.1(a).

Enforcement. Title 10 of the Code of Federal Regulations 20.2006(b) requires, Any

licensee shipping radioactive waste intended for ultimate disposal at a licensed land

disposal facility must document the information required on NRCs uniform low-level

radioactive waste manifest and transfer this recorded manifest information to the

intended consignee in accordance with Appendix G to 10 CFR Part 20. Appendix G,

Section I. B, requires, in part, that, The shipper of the radioactive waste shall provide

the following information regarding the waste shipment on the uniform manifest: The

total radionuclide activity in the shipment. Contrary to the above, on May 19, 2009, the

licensee failed to provide an accurate total radionuclide activity on the manifest with

Radioactive Waste Shipment 09-051. Specifically, the manifest incorrectly listed the

total amount of radioactivity in the shipment as 1650 millicuries instead of approximately

5000 millicuries. This violation was entered into the licensees corrective action program

as Condition Report CR-ANO-C-2010-1866. This issue is being treated as a noncited

violation, consistent with Section 2.3.2.a of the NRC Enforcement Policy:

NCV 05000368/2010004-07, Failure to Provide an Accurate Shipping Manifest.

- 41 -

Enclosure 2

4.

OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency

Preparedness, Public Radiation Safety, Occupational Radiation Safety, and

Physical Protection

4OA2 Identification and Resolution of Problems (71152)

.1

Routine Review of Identification and Resolution of Problems

a.

Inspection Scope

As part of the various baseline inspection procedures discussed in previous sections of

this report, the inspectors routinely reviewed issues during baseline inspection activities

and plant status reviews to verify that they were being entered into the licensees

corrective action program at an appropriate threshold, that adequate attention was being

given to timely corrective actions, and that adverse trends were identified and

addressed. The inspectors reviewed attributes that included the complete and accurate

identification of the problem; the timely correction, commensurate with the safety

significance; the evaluation and disposition of performance issues, generic implications,

common causes, contributing factors, root causes, extent of condition reviews, and

previous occurrences reviews; and the classification, prioritization, focus, and timeliness

of corrective actions. Minor issues entered into the licensees corrective action program

because of the inspectors observations are included in the attached list of documents

reviewed.

These routine reviews for the identification and resolution of problems did not constitute

any additional inspection samples. Instead, by procedure, they were considered an

integral part of the inspections performed during the quarter and documented in

Section 1 of this report.

b.

Findings

No findings were identified.

.2

Daily Corrective Action Program Reviews

a.

Inspection Scope

In order to assist with the identification of repetitive equipment failures and specific

human performance issues for follow-up, the inspectors performed a daily screening of

items entered into the licensees corrective action program. The inspectors

accomplished this through review of the stations daily corrective action documents.

The inspectors performed these daily reviews as part of their daily plant status

monitoring activities and, as such, did not constitute any separate inspection samples.

- 42 -

Enclosure 2

b.

Findings

No findings were identified.

.3

Semi-Annual Trend Review

a.

Inspection Scope

The inspectors performed a review of the licensees corrective action program and

associated documents to identify trends that could indicate the existence of a more

significant safety issue. The inspectors focused their review on repetitive equipment

issues, but also considered the results of daily corrective action item screening

discussed in Section 4OA2.2, above, licensee trending efforts, and licensee human

performance results. The inspectors nominally considered the 6-month period of

January 2010 through August 2010, although some examples expanded beyond those

dates where the scope of the trend warranted.

The inspectors also included issues documented outside the normal corrective action

program in major equipment problem lists, repetitive and/or rework maintenance lists,

departmental problem/challenges lists, system health reports, quality assurance

audit/surveillance reports, self-assessment reports, and Maintenance Rule assessments.

The inspectors compared and contrasted their results with the results contained in the

licensees corrective action program trending reports. Corrective actions associated with

a sample of the issues identified in the licensees trending reports were reviewed for

adequacy.

These activities constitute completion of one (1) single semi-annual trend inspection

sample as defined in Inspection Procedure 71152-05.

b.

Findings

No findings were identified.

.4

Selected Issue Follow-up Inspections

a.

Inspection Scope

Based on previous observations and identified issues, the inspectors selected, for a

more in-depth review, the stations work order generation process as it related to

maintenance activities planned on safety-related equipment. The inspectors selected

this issue for review because of the past history of inadequate work orders for planned

maintenance activities associated with plant equipment. Furthermore, the inspectors

determined that the failure to appropriately plan, provide appropriate guidance or

conduct appropriate postmaintenance testing because of inadequate work orders could

significantly impact on station equipment and result in these systems not being able to

perform their design functions. The inspectors considered the following, as applicable,

during the review of the licensee's actions: (1) complete and accurate identification of

- 43 -

Enclosure 2

the problem in a timely manner; (2) evaluation and disposition of operability/reportability

issues; (3) consideration of extent of condition, generic implications, common cause, and

previous occurrences; (4) classification and prioritization of the resolution of the problem;

(5) identification of root and contributing causes of the problem; (6) identification of

corrective actions; and (7) completion of corrective actions in a timely manner.

These activities constitute completion of one (1) in-depth problem identification and

resolution sample as defined in Inspection Procedure 71152-05.

b.

Findings

Introduction. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, for station planning

personnels failure to adequately implement station Procedures EN-FAP-WM-011, Work

Planning Standard, Revision 0, and EN-WM-102, Planning, Revision 6.

Description. On August 3, 2010, while conducting a review of station work orders for

scheduled maintenance activities on safety related equipment, the inspectors noted

instances where these work orders were not written in accordance with the requirements

of Procedure EN-FAP-WM-011. Specifically, the inspectors noted that, contrary to the

requirements of Section 3.2.2 of this procedure, multiple reference level work orders

generated by the fix-it-now team contained blanket references to other procedures

without providing specific guidance to which sections were to be used, and specific

starting and stopping points. The inspectors informed the licensee of this issue and it

was entered into the corrective action program Condition Report CR-ANO-C-2010-1962.

Based on this observation, and the inspectors knowledge of past programmatic issues

with work order generation, the inspectors performed increased monitoring of station

work orders being generated for activities on safety related equipment. From August 17

through August 19, 2010, the inspectors noted additional instances where planning

personnel failed to appropriately implement procedural requirements associated with

work order generation requirements for emergent work performed on emergency diesel

generator 2K-4B.

Work Order 52026722, task 12, was generated to allow craft personnel to investigate

and repair issues associated with the loss of crank case vacuum of emergency diesel

generator 2K-4B, using the applicable steps of station procedures and system

engineering direction. This work order task had been designated as a reference level

task and provided the following work plan details:

4.2

INVESTIGATE/REPAIR using applicable steps of OP 2306.005 and

System engineering direction to determine the cause of the loss of vacuum and

over pressurization of the engine crankcase

4.3

ENSURE that any Temporary Services and Equipment used during the

performance of this task were removed, along with their applicable tag(s)

- 44 -

Enclosure 2

On August 18, 2010, during their review, the inspectors determined that the licensee

planned to install temporary equipment on the emergency diesel generator, for testing

activities, using the above guidance. However, there were no references available in

station procedures to provide direction for the proposed activities, and the work was

being done at the direction of the vendor. The inspectors determined that this was

contrary to the requirements of Procedure EN-WM-105, section 3[19], which defines a

reference package as, The level of detail is above skill of the craft but reference

material is available to provide all of the necessary guidance. This includes procedures,

work standards, vendor manuals and/or excerpts of these references, and

section 5.2[4].e, which states, For Reference packages the planner will identify what

needs to be done, and refer to approved references for work instructions. The

inspectors informed the licensee of this issue and it was entered into the corrective

action program as Condition Report CR-ANO-2-2010-1736.

On August 19, 2010, the inspectors again reviewed this task because a scope addition

had been performed to support installation of other temporary equipment on the

emergency diesel generator and the changing of the air ejector orifice using the above

guidance. The inspectors again questioned the lack of instructions for the temporary

equipment installation and the referencing of the vendor technical manual for the orifice

replacement without referencing the specific manual sections. The inspectors informed

the licensee of this issue and it was entered into the corrective action program as

Condition Report CR-ANO-C-2010-2114. In response to the inspectors questions, the

licensee reviewed the procedural requirements and the vendor technical manual and

determined that the vendor manual did not contain guidance on changing the orifice and

specific work instructions had to be generated for this task.

Analysis. The inspectors determined that the failure of station planning personnel to

follow Procedures EN-FAP-WM-011 and EN-WM-105 and to ensure that adequate

procedures were generated for maintenance conducted on safety-related equipment

was a performance deficiency. The performance deficiency was determined to be more

than minor because if left uncorrected it would become a more significant safety

concern. Specifically, the continued practice of generating inadequate work orders for

maintenance activities on safety-related equipment would have the potential to leave risk

significant equipment in a degraded condition without the knowledge and approval of site

management and operations personnel, and is therefore a finding. The finding was

associated with the Mitigating Systems Cornerstone. Using Manual Chapter 0609.04,

Phase 1 - Initial Screening and Characterization of Findings, the finding was

determined to have very low safety significance because the finding: (1) was not a

design or qualification issue confirmed not to result in a loss of operability or

functionality; (2) did not represent an actual loss of safety function of the system or train;

(3) did not result in the loss of one or more trains of nontechnical specification

equipment; and (4) did not screen as potentially risk significant due to a seismic,

flooding, or severe weather initiating event. The finding was determined to have a

crosscutting aspect in the area of human performance, associated with work practices

H.4(b) in that the licensee defines and effectively communicates expectations regarding

procedural compliance and personnel follow procedures.

- 45 -

Enclosure 2

Enforcement. Title 10 of the Code of Federal Regulations Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities

affecting quality shall be prescribed by documented instructions, procedures or

drawings, of a type appropriate to the circumstances and shall be accomplished in

accordance with these instructions, procedures, or drawings. Contrary to the above,

between August 3 through 19, 2010, multiple occasions were identified where station

planning personnel failed to follow Procedures EN-FAP-WM-011 and EN WM 105 and to

ensure that adequate procedures were generated for maintenance conducted on safety

related equipment. Because this finding is of very low safety significance and has been

entered into the corrective action program as Condition Reports CR-ANO-C-2010-1962,

CR-ANO-C-2010-1964, CR-ANO-2-2010-1736, CR-ANO-C-2010-2114,

CR-ANO-C-2010-2119, and CR-ANO-C-2010-2140, this violation is being treated as a

noncited violation consistent with Section 2.3.2.a of the NRC Enforcement Policy:

NCV 05000368/2010004-08, Failure to Follow Procedures and Generate Adequate

Work Orders for Maintenance on Safety Related Equipment.

.5

Annual Sample: Review of Level 1 Tagging Errors During Unit 1 Refueling Outage 1R22

.a

Inspection Scope

The inspectors noticed an unusually high number of Level 1 tagging errors during the

most recent Unit 1 refueling outage. There were four tagging errors in a two week

period and one of the errors resulted in contaminated (reactor coolant system) water

inadvertently being drained to the containment basement. The inspectors reviewed

each issue and the roll up condition report and root cause associated with this issue.

.b

Findings

Introduction. The inspectors documented a green, self-revealing noncited violation of

Unit 1 Technical Specification 5.4.1.a for the failure to follow Procedure EN-OP-102,

Protective and Caution Tagging, Revision 12. Specifically, a maintenance tagout

holder signed off a tagout prior to all work being complete, which led to the removal of

the clearance. This resulted in draining the pressurizer to the containment basement

floor instead of to a drain tank.

Description. On March 31, 2010, while Unit 1 was in Mode 6, operations personnel

removed tags associated with the replacement of valve RBD-25 and performed a valve

lineup to drain the Unit 1 pressurizer during Refueling Outage 1R22. When operations

personnel began to drain the pressurizer through the pressurizer surge line drains, water

was identified running out from beneath the temporary shielding. Operations personnel

were promptly notified and the drain was secured. An investigation into the leakage

revealed that a spectacle flange had not been reassembled following completion of

welding activities in support of valve RBD-25 replacement.

This issue was entered into the corrective action program as Condition

Report CR-ANO-1-2010-1013. Mechanical maintenance personnel had removed the

flange on March 25, 2010. In accordance with Procedure EN-OP-102, the mechanical

maintenance lead should have remained on the tagout until the flange had been re-

- 46 -

Enclosure 2

installed. The mechanical maintenance war room coordinators (special team that

oversees mechanical maintenance during outages) incorrectly believed that as long as

another organization was on the tagout, as the tagout holder, all other work on the

tagout would be covered. The mechanical maintenance war room was also of the

mindset to minimize all personnel on the tagout to minimize the time it would take to

remove a tagout. As a result the mechanical war room supervision convinced the

mechanical maintenance lead to sign off on the tag-out before the flange had been

reassembled.

On March 30, 2010, the outage control center identified the work associated with the

RBD-25 valve replacement as being on critical path for draining the pressurizer. A

senior reactor operator was tasked to follow this work and ensure prompt removal of the

tagout as soon as possible. Welders, who were the only tagout holders on the tagout,

completed their work and signed off the tagout. The senior reactor operator failed to

recognize that all work had not been completed and removed the tagout. Operations

personnel were notified that the system was ready for use. Operations personnel

aligned the system for pressurizer drain and commenced draining. Soon after the

draining evolution had begun the pressurizer water was discovered draining onto the

containment building floor.

Analysis. The inspectors determined that the failure of station personnel to follow

Procedure EN-OP-102, Protective and Caution Tagging, Revision 12, was a

performance deficiency. The performance deficiency was determined to be more than

minor because if left uncorrected it could lead to a more significant safety issue.

Specifically, the continued failure to follow this procedure could lead to the inappropriate

release of systems and equipment to other organizations when these systems or

equipment are not capable of performing their function. This is therefore a finding.

Using NRC Manual Chapter 0609, Significance Determination Process, Appendix G,

"Shutdown Operations Significance Determination," Attachment 1, the finding was

determined to have very low safety significance because the finding did not affect core

heat removal, inventory control, power availability, and containment control or reactivity

guidelines. The finding was determined to have a crosscutting aspect in the area of

human performance, associated with work practices H.4(c), in that the licensee did not

ensure supervisory and management oversight of work activities such that nuclear

safety is supported. Specifically, instead of supplying appropriate guidance and

supervision for the workers in the field, the mechanical war room coordinators actions

resulted in the failure to follow procedure by convincing the mechanical lead to sign off

on the tagout before the work had been completed.

Enforcement. Technical Specification 5.4.1.a states, in part, that written procedures

shall be implemented in accordance with Regulatory Guide 1.33, Appendix A. Tagging

activities is one of the areas covered in Regulatory Guide 1.33, Appendix A. Contrary to

the above, the licensee failed to follow Procedure EN-OP-102, Protective and Caution

Tagging, Revision 12, and released a tagout that resulted in operations draining the

pressurizer to the Unit 1 reactor building basement floor. Because this finding is of very

low safety significance and has been entered into the corrective action program as

Condition Report CR-ANO-1-2010-1013, this violation is being treated as a noncited

- 47 -

Enclosure 2

violation consistent with Section 2.3.2.a of the NRC Enforcement Policy:

NCV 05000313/2010004-09, Failure to Follow Procedure Results in Draining Unit 1

Pressurizer to Reactor Building Floor.

.6

In-depth Review of Operator Workarounds

a.

Inspection Scope

The inspectors selected this issue for review to verify that licensee personnel were

identifying operator workaround problems at an appropriate threshold and entering them

in the corrective action program, and has proposed or implemented appropriate

corrective actions. The inspectors reviewed and evaluated the licensee's operator

workaround log, for both Units 1 and 2, operator logs and associated condition reports.

The inspectors considered the following, as applicable, during the review of the

licensee's actions: (1) complete and accurate identification of the problem in a timely

manner; (2) evaluation and disposition of operability/reportability issues;

(3) consideration of extent of condition, generic implications, common cause, and

previous occurrences; (4) classification and prioritization of the resolution of the problem;

(5) identification of root and contributing causes of the problem; (6) identification of

corrective actions; and (7) completion of corrective actions in a timely manner.

b.

Findings

No findings were identified.

4OA5 Other Activities

.1

(Closed) Temporary Instruction 2515/173, Review of the Implementation of the Industry

Groundwater Protection Voluntary Initiative, Revision 1

a.

Inspection Scope

An NRC assessment was performed of the licensees groundwater protection program to

determine whether the licensee implemented the voluntary Industry Groundwater

Protection Initiative, dated August 2007 (Nuclear Energy Institute 07-07, Industry

Groundwater Protection Initiative - Final Guidance Document, ADAMS Accession

Number ML072610036). The inspectors interviewed personnel, performed walkdowns

of selected areas, and reviewed the following items:

Records of the site characterization of geology and hydrology

Evaluations of systems, structures, and or components that contain or could

contain licensed material and evaluations of work practices that involve licensed

material for which there is a credible mechanism for the licensed material to

reach the groundwater

Implementation of an onsite groundwater monitoring program to monitor for

potential licensed radioactive leakage into groundwater

- 48 -

Enclosure 2

Procedures for the decision making process for potential remediation of leaks

and spills, including consideration of the long term decommissioning impacts

Records of leaks and spills recorded, if any, in the licensees decommissioning

files in accordance with 10 CFR 50.75(g)

Licensee briefings of local and state officials on the licensees groundwater

protection initiative

Protocols for notification to the local and state officials, and to the NRC regarding

detection of leaks and spills

Protocols and/or procedures for 30-day reports if an onsite groundwater sample

exceeds the criteria in the radiological environmental monitoring program

Groundwater monitoring results as reported in the annual effluent and/or

environmental monitoring report

Licensee and industry assessments of implementation of the groundwater

protection initiative

b.

Findings

No findings of significance were identified. Implementation of the Industry Groundwater

Protection Initiative is voluntary. Under the final initiative, each site was to have

developed an effective, technically sound groundwater protection program by

August 2008. At the time of the inspection, the inspectors determined that the licensee

had still not fully implemented the following objectives of Nuclear Energy Institute 07-07.

Additional monitoring wells are needed, according to the licensees consultants,

to adequately perform hydrogeologic and geologic studies to determine

groundwater flow characteristics and gradients, in accordance with

Objective 1.1a and to identify potential pathways for groundwater migration from

onsite locations to offsite locations, in accordance with Objective 1.1c.

No evaluation of work practices that involve or could reasonably be expected to

involve licensed material and for which there was a credible mechanism for the

licensed material to reach groundwater was conducted, in accordance with

Objective 1.2a.

Existing leak detection methods were not correlated to each system, structure,

and component and identified for each work practice that involves or could

involve licensed material for which there is a creditable potential for inadvertent

release to groundwater, in accordance with Objective 1.2b.

Potential enhancements were not identified to leak detection systems or

programs, in accordance with Objective 1.2c.

- 49 -

Enclosure 2

Potential enhancements to prevent spills or leaks from reaching the groundwater

were not identified, in accordance with Objective 1.2d.

Groundwater monitoring wells were not placed down gradient from the plant in

accordance with Objective 1.3a. Three wells were installed south to southwest of

the plant. However, data from these wells suggest the locations are not down

gradient of critical systems, structures, and components.

Sentinel wells were not placed near to systems, structures, and components that

have the highest potential for inadvertent releases that could reach groundwater,

in accordance with Objective 1.3b.

The procedure used for communicating actual release information to the

state/local officials, in accordance with Objective 2.2c, did not include all required

information.

The 2006 and 2007 groundwater sample results were not reported in the 2007

and 2008 annual radiological environmental operating report, respectively, in

accordance with Objective 2.4a.

Condition Report CR-HQN-2010-00207 was initiated to ensure implementation of

actions to address the items listed above.

.2

(Closed) Unresolved Item 05000313/2009005-07, Diesel Generator Ventilation Systems

Susceptibility to the Depressurization Effects of a Tornado

In NRC Inspection Report 05000313/2009005 inspectors opened an unresolved item

concerning the potential susceptibility of the Unit 1 emergency diesel generator heating,

ventilating and air conditioning ducting to loading effects caused by natural phenomena,

tornados. Inspectors reviewed this issue for closure and documented a noncited

violation (05000313/2010004-02) in Section 1R15 of this report.

.3

(Open) NRC Temporary Instruction 2515/177, Managing Gas Accumulation in

Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems (NRC

Generic Letter 2008-01)

As documented in Section 1R04, the inspectors confirmed the acceptability of the

described licensees actions. This inspection effort counts towards the completion of

TI 2515/177 which will be closed in a later Inspection Report.

- 50 -

Enclosure 2

- 51 -

Enclosure 2

.4

IP 92723, Follow Up Inspection for Three or More Severity Level IV Traditional

Enforcement Violations in the Same Area in a 12-Month Period

.a

Inspection Scope

The inspectors performed Inspection Procedure 92723 in accordance with the Arkansas

Nuclear One 2009 end of cycle assessment letter. Arkansas Nuclear One received four

traditional violations during the 2009 assessment period. The inspectors reviewed the

licensees condition reports for each violation and the roll up root cause analysis for the

following items:

Problem identification

Cause, extent of condition and extent of cause

Evaluation of corrective actions

.b

Findings

No findings were identified.

4OA6 Meetings

Exit Meeting Summaries

On, July 22, 2010, inspectors briefed Mr. B. Berryman, Acting Site Vice President, and other

members of the licensee's staff of the results of the licensed operator requalification program

inspection. The lead inspector obtained the final biennial examination results and telephonically

exited with Mr. R. Martin, Unit Operations Training Superintendent, on August 16, 2010. The

licensee representatives acknowledged the findings presented. The inspectors asked the

licensee whether any materials examined during the inspection should be considered

proprietary. No proprietary information was identified.

On July 23, 2010, inspectors presented the results of the radiation safety inspections to Mr. M.

Chisum, Acting General Manager, Plant Operations, and other members of the licensee staff.

The licensee acknowledged the issues presented. The inspectors asked the licensee whether

any materials examined during the inspection should be considered proprietary. No proprietary

information was identified.

On September 27, 2010, resident inspectors presented the inspection results to Mr. B.

Berryman, Acting Site Vice President and other members of the licensee staff. The licensee

acknowledged the issues presented. The inspectors asked the licensee whether any materials

examined during the inspection should be considered proprietary. No proprietary information

was identified.

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

J. Bacquet, ALARA Supervisor, Radiation Protection

R. Beard, EP&C

B. Berryman, Acting Site Vice President

D. Bice, Acting Manager, Licensing

D. Calloway, Effluent and Environmental Monitoring Specialist, Chemistry

M. Chisum, Acting General Manager, Plant Operations

A. Clinkingbeard, Operations Training, Assistant Operations Manager

S. Cotton, Training Manager

R. Crowe, Superintendent, Security

S. Cupp, Simulator Superintendent

R. Dodds, Manager, Maintenance

R. Gresham, Senior Emergency Planner

R. Henry, EP&C

D. Hicks, Support Supervisor, Radiation Protection

D. James, Director, Nuclear Safety Assurance

J. James, Laboratory Technician, Chemistry

K. Jones, Manager, Operations

R. Jones, EP&C

J. McCoy, Acting Director, Engineering

D. Meatheany, EP&C

R. Martin, U1 Operations Training Superintendent

D. Marvel, Supervisor, Radiation Protection Operations

T. Nickels, ALARA Coordinator, Radiation Protection

K. Panthen, EP&C

M. Paterak, EP&C

J. Priore, Ventilation Systems Engineer, Systems Engineering

J. Smith, Manager, Radiation Protection

R. Starkey, Radwaste Supervisor, Radiation Protection

G. Stephenson, Effluent and Environmental Monitoring Specialist, Chemistry

T. Rolniak, Specialist, Radiation Protection

B. Short, Licensing Specialist

C. Simpson, U2 Operations Training Superintendent

D. Stringer, EP&C

G. Thompson, Supervisor, Chemistry

F. VanBuskirk, Licensing Specialist

A-1

Attachment

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

2515/177

TI

Managing Gas Accumulation in Emergency Core Cooling, Decay

Heat Removal and Containment Spray Systems (NRC Generic

Letter 2008-01) (Section 4OA5)

05000313;05000368/

2010004-05

VIO

Failure to Adequately Implement Foreign Material Exclusion

Controls (Section 1R20)

Opened and Closed 05000368/2010004-01 NCV

Excessive Overlap of Unit 2 Written Examinations (Section 1R11)05000313/2010004-02 NCV

Failure to Promptly Identify and Correct a Condition Adverse to

Quality Associated with Emergency Diesel Generators Heating,

Ventilation, and Air Conditioning Ducting Susceptibility to Tornado

Loading (Section 1R15)05000313/2010004-03 NCV

Failure to Promptly Identify and Correct a Condition Adverse to

Quality Associated with Emergency Switchgear Chiller VCH-4A

(Section 1R18). 05000313/2010004-04 FIN

Failure to Follow Station Work Control Procedure Results in

Unavailable Equipment (Section 1R19)05000313/2010004-06 NCV

Failure to Correctly Translate VCH-4B Design Requirements into

Installed Plant Equipment (Section 1R22)05000368/2010004-07 NCV

Failure to Provide an Accurate Shipping Manifest

(Section 2RS08)05000368/2010004-08 NCV

Failure to Follow Procedures and Generate Adequate Work

Orders for Maintenance on Safety Related Equipment

(Section 4OA2.4)05000318/2010004-09 NCV

Failure to Follow Procedure Results in Draining Unit 1 Pressurizer

to Reactor Building Floor (Section 4OA2.5)

Closed

2515/173

TI

Review of the Implementation of the Industry Groundwater

Protection Voluntary Initiative, Revision 1 (Section 4OA5)05000313/2009005-07 URI

Diesel Generator Ventilation Systems Susceptibility to the

Depressurization Effects of a Tornado (Section 4OA5)

A-2

Attachment

LIST OF DOCUMENTS REVIEWED

Section 1R04: Equipment Alignment

PROCEDURES

NUMBER

TITLE

REVISION

OP-2106.006

Emergency Feedwater System Operations

76

OP-1106.006

Emergency Feedwater Pump Operation

79 & 80

OP-1104.005

Reactor Building Spray System Operation

59

OP-2104.037

Alternate AC Diesel Generator Operations

19

OP-2104.036

Emergency Diesel Generator Operations

75

OP-1104.004

Decay Heat Removal Operating Procedure

90

DRAWINGS

NUMBER

TITLE

REVISION

M-2217 sheets 1-3 Unit 2 Emergency Diesel Generator Auxiliary Systems

M-2236 sheet 4

Unit 2 Emergency Feedwater System

66

E-2005 sheet 2

Alternate AC Generator System and 4.16KV Generation

and Switchgear

1

M-2204 sheet 1

Unit 2 Emergency Feedwater System

150

7-DH-1

Large Pipe Isometric Decay Heat Removal To Reactors

20

7-DH-3

Large Pipe Isometric Decay Heat Removal From Reactor

19

7-DH-4

Large Pipe Isometric Decay Heat Removal From Reactor

23

7-DH-5

Large Pipe Isometric Decay Heat Removal Pump

Discharge

9

7-DH-1 1

Large Pipe Isometric Decay Heat Removal Pump

Discharge

21

A-3

Attachment

7-DH-1 2

Large Pipe Isometric Engineered Safeguards Pump

Suction Header

20

M-232-1

Decay Heat Removal System

103

Section 1R05: Fire Protection

PROCEDURES

NUMBER

TITLE

REVISION

FHA

Arkansas Nuclear One Fire Hazard Analysis

13

PFP-U1

ANO Prefire Plan (Unit 1)

12

PFP-U2

ANO Prefire Plan (Unit 2)

10

DRAWINGS

NUMBER

TITLE

REVISION

FZ-1032

Unit 1 fire zone detail - north and south Emergency

Diesel Generator rooms

2

FZ-2039

Unit 2 fire zone detail - upper south electrical penetration

room

2

FZ-2051

Unit 2 fire zone detail - Hot Instrument shop, Tool Room

and Auxiliary Building Corridor

2

FZ-2045

Unit 2 fire zone detail - Electrical Equipment and Cable

Spreading room

2

Section 1R06: Flooding

PROCEDURES

NUMBER

TITLE

REVISION

ULD-0-TOP-17

ANO Topical Flooding

0

CALCULATION

NUMBER

TITLE

REVISION

CALC-89-E-0042-35

ANO-1 Internal Flooding Analysis

0

A-4

Attachment

CALC-92-R-0024-01

Flooding Evaluation INPO SOER 85-5

0

CALC-92-R-0034-01

Flooding Evaluation INPO SOER 85-5-2nd Iteration

0

Section 1R11: Licensed Operator Requalification

PROCEDURES

NUMBER

TITLE

REVISION

EN-TQ-114

Licensed Operator Requalification Training Description

3

EN-TQ-210

Conduct of Simulator Training

3

EN-TQ-201

Systematic Approach to Training Process

13

EN-TQ-205

Training Exemptions

1

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

REVISION /

DATE

Written Exams U1 and U2 Weeks 1 through 6 Biennial Exams (RO and SRO)

July 2010

JPMs

U1 and U2 Reviewed weeks 1 through 6 for overlap

July 2010

1063.008

License Reactivation Procedure

39

ANO LERs

All 16 LERs from 2008-2010 for both Units

N/A

QA-19-2010

QA Audit Report for Training

February 2010

Simulator Test Steady State 100% Power

January 2010

Simulator Test Transient Test LOCA with LOOP

January 2010

Simulator Test Transient Test Load Reject from 100% Power

March 2010

DR-2007-0029 Simulator Closed Work Package

April 2007

DR-2010-0118 Simulator Open Work Package

February 2010

CONDITION REPORTS

ANO-2-2008-0924

ANO-2-2009-0254

ANO-2-2010-0327

ANO-2-2008-1318

ANO-2-2009-2002

ANO-2-2010-0764

ANO-2-2008-1761

ANO-2-2009-2207

ANO-2-2010-1460

ANO-2-2008-2056

ANO-2-2009-2321

ANO-2-2010-1830

ANO-2-2008-2609

ANO-2-2009-2352

ANO-2-2010-2056

ANO-2-2009-0145

ANO-2-2009-2391

A-5

Attachment

Section 1R12: Maintenance Effectiveness

PROCEDURES

NUMBER

TITLE

REVISION

EN-DC-203

Maintenance Rule Program

1

EN-DC-204

Maintenance Rule Scope and Basis

1

EN-DC-205

Maintenance Rule Monitoring

2

EN-DC-206

Maintenance Rule (a)(1) Process

2

MISCELLANEOUS

TITLE

Unit 1 High Pressure Injection Maintenance Rule Database and Scoping Document

Unit 2 Emergency Feedwater Maintenance Rule Database and Scoping Document

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

PROCEDURES

NUMBER

TITLE

REVISION

COPD-024

Risk Assessment Guidelines

31

Section 1R15: Operability Evaluations

PROCEDURES

NUMBER

TITLE

REVISION

EN-OP-104

Operability Determinations

4

CONDITON REPORTS

ANO-2-2010-1158

ANO-2-2010-1229

ANO-2-2010-1402

ANO-2-2010-1009

ANO-C-2007-1308

ANO-C-2007-1469

A-6

Attachment

ANO-C-2009-2296

ANO-1-2010-2614

ANO-2-2010-1327

ANO-1-2010-2815

LO-LAR-2006-0171

MISCELLANEOUS

NUMBER

TITLE

REVISION

EC-23352

Operability Input for CR-ANO-2-2010-1158 and CR-ANO-2-

2010-1229

EC-18589

Determine Effects of Tornado Induced DP Effects on EDG

Room Ductwork and Dampers Using Reg Guide 1.76 Rev.

1 Non-Design Basis Study Calc

ULD-1-STR-01

ANO-1 Auxiliary Building

1

Evaluation of the Ultimate Pressure Capacity of

Rectangular HVAC Ducts for Nuclear Power Plants (Volume

2 of ASCE Structural Engineering in Nuclear Facilities.)

EC-23940

Tornado Differential Pressure Effects on ANO-1 EDG Room

Duct Work and Damper

0

CALCULATION

NUMBER

TITLE

REVISION

CALC-09-E-0020-01

Maximum DP Across Ducts Serving the ANO-1 EDG

Rooms During A Tornado

0

CALC-09-E-0020-02

Maximum DP Across Ducts Serving the ANO-2 EDG

Rooms During A Tornado

0

CALC-09-E-0020-03

Tornado Induced DP Effects on EDG Room Ductwork and

Dampers

0

Section 1R18: Plant Modifications

PROCEDURES

NUMBER

TITLE

REVISION

OP-1104.027

Battery and Switchgear Emergency Cooling System

35

A-7

Attachment

CONDITION REPORTS

ANO-1-2009-2122

ANO-1-2008-0098

Section 1R19: Postmaintenance Testing

PROCEDURES

NUMBER

TITLE

REVISION

OP-2104.036

Emergency Diesel Generator Operations

75

OP-2402.147

Unit 2, 2K-4 Diesel Engine Maintenance

5

CONDITION REPORTS

ANO-1-2010-2260

ANO-1-2010-2105

ANO-1-2010-1347

ANO-2-2010-1694

ANO-2-2010-1765

ANO-2-2010-1867

ANO-2-2010-1699

ANO-2-2010-1778

ANO-2-2010-1870

ANO-2-2010-1710

ANO-2-2010-1787

ANO-2-2010-1885

ANO-2-2010-1717

ANO-2-2010-1794

ANO-2-2010-1889

ANO-2-2010-1718

ANO-2-2010-1796

ANO-2-2010-1897

ANO-2-2010-1719

ANO-2-2010-1826

ANO-2-2010-1911

ANO-2-2010-1725

ANO-2-2010-1844

ANO-2-2010-1914

ANO-2-2010-1729

ANO-2-2010-1857

ANO-2-2010-1920

ANO-2-2010-1741

ANO-2-2010-1858

ANO-2-2010-1939

ANO-2-2010-1744

ANO-2-2010-1861

ANO-2-2010-1958

ANO-2-2010-1965

ANO-2-2010-1349

ANO-2-2010-1350

ANO-2-2010-1981

ANO-2-2010-1343

ANO-C-2010-2084

MISCELLANEOUS

NUMBER

TITLE

EC-23515

Evaluate VCH-4B Operability for temporary modification to remove lockout

feature for TS-6060

A-8

Attachment

EC-8569

Replace Containment Spray Flow Transmitter 2FT-5610

ULD-2-SYS-01

Emergency Diesel Generator System

WORK ORDERS

241315

52207054

242042

52026722

51667640

Section 1R20: Refueling and Other Outage Activities

PROCEDURES

NUMBER

TITLE

REVISION

OP-2102.001

Plant Pre-Heatup and Pre-Critical Checklist

68

EN-MA-118

Foreign Material Exclusion

5

WORK ORDERS

216672

162137

52236360

225146

224527

205511

158163

52032679

51670771

165587

214644

51695579

52024097

52218289

52195142

51683823

51697557

219285

51694251

51694250

51696279

52031347

247292

51697564

52242656

52215030

51696280

52215029

52201736

52224471

156861

52027898

51662172

241691

216670

51699369

201963

214536

52024097

162884

51699371

51699370

160017

216672

A-9

Attachment

216667

52026721

162884

225146

MISCELLANEOUS

NUMBER

TITLE

EC-24293

Evaluate Seismic Scaffold Erected in Unit 2 Containment for all Plant

Conditions

CONDITION REPORTS

ANO-1-2008-2491

ANO-2-2009-2843

ANO-2-2010-1839

ANO-2-2010-1868

ANO-C-2009-0720

ANO-C-2010-0688

ANO-C-2010-1570

ANO-C-2010-2192

ANO-C-2010-2684

LO-ALO-2009-0153

LO-ALO-2010-0040

LO-ALO-2009-0018

Section 1R22: Surveillance Testing

PROCEDURES

NUMBER

TITLE

REVISION

OP-1106.006

Unit 1 Emergency Feedwater Pump Operation

80

OP-1104.027

Unit 1 Battery and Switchgear Cooling System

35

OP-2304.236

Unit 2 Emergency Feedwater Flow and Pressure Green

Channel Calibration

12

OP-1104.029

Service Water and Auxiliary Cooling System

77

OP-1305.018

Local Leak Rate Testing-Type C

20

OP-2104.005

Containment Spray

59

OP-2104.036

Emergency Diesel Generator Operations

68

OP-1103.013

RCS Leak Detection

34

OP-2305.002

Reactor Coolant System Leak Detection

21

WORK ORDER 243163

52205155

A-10

Attachment

MISCELLANEOUS

TITLE

Equipment Qualification Data Record Sheets 2B010, 2B007, and 2A247

CONDITION REPORTS

ANO-1-2010-0653

ANO-1-2010-0754

Section 2RS06: Radioactive Gaseous and Liquid Effluent Treatment

AUDITS, SELF-ASSESSMENTS, AND SURVEILLANCES

NUMBER

TITLE

DATE

QA-216-2009-ANO-1 Combined Chemistry, Effluents, and Environmental

Monitoring

August 7, 2009

COMPENSATORY SAMPLING

UNIT

MONITOR

DATE

2

SPING 7

October 13, 2009

2

SPING 7

October 31, 2009

CORRECTIVE ACTION DOCUMENTS

C-2008-01583

2-2009-00360

C-2008-01778

1-2010-01657

1-2010-02067

2-2009-01917

2-2009-00386

1-2009-01300

1-2009-02288

1-2010-00089

C-2010-01373

1-2010-00101

2-2009-00350

C-2008-01612

IN-PLACE FILTER TESTING RECORDS

SYSTEM

WORK ORDER

DATE

Penetration Room Ventilation (VEF-38A) 51561623

May 7, 2009

Penetration Room Ventilation (VEF-38B) 51547088

February 3, 2009

VSF-9 Emergency Air Recirculation

51547584

February 3, 2009

2VSF-9

51557857

May 6, 2009

MISCELLANEOUS DOCUMENTS

TITLE

Annual Radioactive Effluent Release Report for 2008

Annual Radioactive Effluent Release Report for 2009

A-11

Attachment

PROCEDURES

NUMBER

TITLE

REVISION

1052.003

Nuclear Chemistry Quality Control Program

26

1604.015

Analysis of Unit Vent

17

2607.010

Sampling the Unit 2 Vents

16

RELEASE PERMITS

2GR 2009-0136

2 GR 2009-0150

2GR 2009-0153

1LR 2009-0059

Section 2RS07: Radiological Environmental Monitoring Program

AUDITS, SELF-ASSESSMENTS, AND SURVEILLANCES

NUMBER

TITLE

DATE

QA-2/6-2009-ANO-1 Quality Assurance Audit Report; Combined

Chemistry, Effluents and Environmental Monitoring

August 7,2009

CONDITION REPORTS

C-2008-01067

C-2008-02584

C-2009-00016

C-2009-00714

C-2009-00605

C-2009-00621

C-2009-00926

1-2009-01046

2-2009-01635

C-2010-00077

C-2010-00323

C-2010-00551

C-2010-01074

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

DATE

W/O 52037947

Perform the Semi-Annual Meterological Monitoring

Calibration

April 2, 2010

PROCEDURES

NUMBER

TITLE

REVISION/DATE

1608.005

Radiological Environmental Monitoring Program

35

1042.003

RadioChemistry Routine Surveillance Schedule and

Tech. Spec. Reporting

27

1012.018

Administration of Radiological Surveys

12

Annual Radiological Environment Operating Report

for 2009

May 11, 2010

Annual Radiological Environment Operating Report

for 2008

May 13, 2009

A-12

Attachment

Section 2RS08: Radioactive Solid Waste Processing and Radioactive Material Handling,

Storage, and Transportation

CONDITION REPORTS

ANO-C-2009-1008

ANO-C-2009-1039

ANO-C-2009-2051

MISCELLANEOUS

NUMBER

TITLE

DATE

199825001

10 CFR Part 61 Analysis for DAW Smears

April 11, 2008

199825007-1 10 CFR Part 61 Analysis for Oil

October 2, 2008

199825003

10 CFR Part 61 Analysis for Unit 1 RCS

October 2, 2008

224919001

10 CFR Part 61 Analysis for DAW Smears

March 31, 2009

218075001

10 CFR Part 61 Analysis for Unit 2 RCS

October 7, 2009

Annual Radioactive Effluent Release Report for 2008

PROCEDURES

NUMBER

TITLE

REVISION

EN-RW-101 Radioactive Waste Management

2

EN-RW-102 Radioactive Shipping Procedure

7

EN-RW-104 Scaling Factors

6

EN-RW-105 Process Control Program

1

1601.506

Radioactive Waste Management Program Surveillances

2

RADIOACTIVE MATERIAL SHIPMENTS

NUMBER

TITLE

DATE

RSR-09-051

20 Unit 2 SFP Filters

May 19, 2009

RSR-09-110

5 Gallon Drum with Alpha Smears

October 12, 2009

RSR-10-053

Unit 1 Primary Resin Samples

April 28, 2010

RSR-10-059

P-32C RCP Motor Impeller

May 3, 2010

Section 40A2: Identification and Resolution of Problems

PROCEDURES

NUMBER

TITLE

REVISION

OP-2304.134

Unit 2 EDG 2K-4A Instrument Calibration

19

A-13

Attachment

EN-WM-105

Planning

7

OP-2304.126

Unit 2 Containment Temperature and Dewpoint Instrument

Calibration

15

EN-FAP-WM-11

Work Planning Standard

0

CONDITION REPORTS

ANO-2-2010-1736

ANO-2-2010-1350

ANO-2-2010-1865

ANO-C-2010-1575

ANO-C-2010-1962

ANO-C-2010-1964

ANO-C-2010-2114

ANO-C-2010-2119

ANO-C-2010-2140

ANO-2-2010-1751

ANO-C-2010-2132

WORK ORDERS

83251

205016

51801189

209815

243722

244246

52026722

Section 4OA5: Other Activities

MISCELLANEOUS

TITLE

REVISION/DATE

Annual Radiological Environment Operating Report for 2009

May 11, 2010

Annual Radiological Environment Operating Report for 2008

May 13, 2009

NEI Groundwater Protection Initiative, NEI Peer Assessment Report

December 10, 2009

Tritium in Groundwater Evaluation Arkansas Nuclear One

July 26, 2006

GPI Data Review Arkansas Nuclear One

April 2009

Groundwater Monitoring Plan

2

PROCEDURES

NUMBER

TITLE

REVISION

EN-CY-108

Monitoring of Nonradioactive Systems

3

EN-CY-111

Radiological Groundwater Monitoring Program

0

EN-DC-343

Buried Piping and Tanks Inspection and Monitoring Program

2

EN-RP-113

Response to Contaminated Spills/Leaks

4

A-14

Attachment

A-15

Attachment

CONDITION REPORTS

ANO-C-2010-01373 ANO-C-2010-0493

ANO-C-2009-2590

ANO-C-2009-0445

ANO-1-2009-0281

ANO-C-2009-1415