ML102990265

From kanterella
Jump to navigation Jump to search
IR 05000293-10-004; Entergy Nuclear Operations, Inc.; 07/01/2010-09/30/2010; Pilgrim Nuclear Power Station, NRC Integrated Inspection Report
ML102990265
Person / Time
Site: Pilgrim
Issue date: 10/26/2010
From: Diane Jackson
NRC/RGN-I/DRP/PB5
To: Bronson K
Entergy Nuclear Operations
Jackson, D E RI/DRP/PB5/610-337-5306
References
IR-10-004
Download: ML102990265 (35)


See also: IR 05000293/2010004

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

475 ALLENDALE ROAD

KING OF PRUSSIA, PA 19406-1415

October 26, 2010

..

Mr. Kevin Bronson

Site Vice President

Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station

600 Rocky Hill Road

Plymouth. MA 02360-5508

SUBJECT:

PILGRIM NUCLEAR POWER STATION - NRC INTEGRATED INSPECTION

REPORT 05000293/2010004

Dear Mr. Bronson:

On September 30, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Pilgrim Nuclear Power Station (PNPS). The enclosed inspection report

documents the results, whit:h were discussed on October 13, 2010, yvith you and members of

your staff.

The inspection examined activities performed under your license as they relate to safety and

compliance with the Commission's rules and regulations, and with the conditions of your

license. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel.

This report documents one NRC identified finding of very low safety significance (Green). The

finding was determined to involve a violation of NRC requirements. However, because of its

very low safety significance and because it was entered into your corrective action program, the

NRC is treating this finding as a non-cited violation (NCV), consistent with Section 2.3.2.a of the

NRC's Enforcement Policy. If you contest any NCV, you should provide a response within 30

days of the date of this inspection report, with the basis for your denial, to the Nuclear

Regulatory CommiSSion, A TIN.: Document Control Desk, Washington DC 20555-0001; with

copies to the Regional Administrator, Region I; the Director, Office of Enforcement, United

States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Senior

Resident Inspector at PNPS. In addition, if you disagree with the cross-cutting aspect assigned

to the finding in this report, you should provide a response within 30 days of the date of this

inspection report, with the basis for your disagreement, to the Regional Administrator, Region I,

and the NRC Senior Resident Inspector at PNPS.

K. Bronson

2

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of the

NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at

..

http://www.nrc.gov/reading-rm/adams.html(the Public Electr<1nic Reading Room).

Sincerely,

~t:""""'CAl--

Donald E. Jac on. Chief

Projects Branch 5

Division of Reactor Projects

Docket No.

50-293

License No.

DPR-35

Enclosure:

Inspection Report 05000293/2010004

w/Attachment: Supplemental Information

cc; w/encl:

Distribution via ListServ

\\

\\

K. Bronson

2

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available RElcords (PARS) component of the

NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).

..

Sincere~y,

IRA!

Donald E. Jackson, Chief

Projects Branch 5

Division of Reactor Projects

Docket No.

50-293

License No.

DPR-35

Enclosure:

Inspection Report 05000293/2010004

w/Attachment: Supplemental Information

Distribution w/encl:

W. Dean, RA

(R10RAMAIL RESOURCE)

T. Setzer, DRP

M. Dapas, DRA (R10RAMAIL RESOURCE)

M. Schneider, DRP, SRI

\\

D. Lew, DRP

(R10RAMAIL RESOURCE)

B, Smith, DRP, RI

J, Clifford, DRP (R1DRPMAIL RESOURCE)

S. Campbell, DRP, Resident OA

D. Collins, DRP (R1DRPMAIL RESOURCE)

A. Ford, DRP, Resident OA

D. Roberts, DRS(R1DRSMAIL RESOURCE)

D. Bearde, DRS

P. Wilson, DRS (R1DRSMAIL RESOURCE)

RidsNrrPMPilgrim Resource

L. Trocine, RI OEDO

RidsNrrDorlLPL1-1 Resource

D, Jackson, DRP

ROPreports Resource@nrc,gov

SUNSI Review Complete: _--!..TC::::,lS"--__ (Revlewer's Initials)

DOCUMENT NAME: G:\\DRP\\BRANCH5\\Reports\\Drafts\\pil2010004.docx

ML102990265

After declaring this document "An Official Agency Record" it will be released to the Public,

To receive a copy of this document, indicate in the box: "e" =Copy without attachment/enclosure "E" =Copy with

attachment/enclosure UN" = No copy

OFFICE

RIIDRP

Ilhp RIIDRP

l IRIIDRP

I

NAME

MSchneiderlTCS for

TSetzerlTS

  • DJackson/DJ

DATE

10/19/10

10/19110

110/25/10

OFFICIAL RECORD COpy

U.S. NUCLEAR REGULATORY COMMISSION

"

REGION I

Docket No:

50-293

License No:

DPR-35

Report No:

05000293/2010004

Licensee:

Entergy Nuclear Operations. Inc.

Facility:

Pilgrim Nuclear Power Station (PNPS)

Location:

600 Reeky Hill Road

Plymouth. MA 02360

Inspection Period:

July 1. 2010 through September 30, 2010

Inspectors:

Approved By:

M. Schneider, Senior Resident Inspector, Division of Reactor Projects (DRP)

B. Smith, Resident Inspector, DRP

R. Rolph, Health Physicist. Division of Reactor Safety (DRS)

J. Trapp, Plant Support Branch 1 , Branch Chief, DRS

B. Yip. Physical Security Inspector, DRS

Donald E. Jackson, Chief

Projects Branch 5

Division of Reactor Projects

Enclosure

2

TABLE OF CONTENTS

SUMMARY OF FINDINGS ...............................................................................................................3

REPORT DETAILS ..........................................................................................................................4

i.REACTOR SAFETy .....................................................................................................................4

1ROi

Adverse Weather Protection ................................................................................4

1R04

Equipment Alignment ...........................................................................................5

1R05

Fire Protection ......................................................................................................6

1R06

Flood Protection Measures ..................................................................................7

1R07

Heat Sink Performance ........................................................................................7

1R11

Licensed Operator Requalification Program .........................................................8

1R12

Maintenance Effectiveness ..................................................................................8

1R13

Maintenance Risk Assessments and Emergent Work Control} .............................8

1R 15

Operability Evaluations ...................................................................................... 1 0

1 R 18

Plant Modifications .............................................................................................11

1R 19

Post-Maintenance Testing .................................................................................12

1R22

Surveillance Testing ...........................................................................................12

1EP6

Drill Evaluation ...................................................................................................13

2.RADIATION SAFETY ...\\ ........................................................... \\' ............................................... 13

2RS06

Gaseous and Liquid Effluent Treatment.. ........................................................... 13

4.0THER ACTIViTIES ...................................................................................................................15

40A1

Performance Indicator (PI) Verification ................................................................15

40A2

Identification and Resolution of Problems ........................................................... 16

40A3

Event Follow-up .................................................................................................17

40A5

Other Activities ...................................................................................................18

40A6

Meetings, Including Exit ......................................................................................22

SUPPLEMENTAL INFORMATION ............................................................................................. A-1

KEY POINTS OF CONTACT ...................................................................................................... A-1

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED ............................................................ A-1

LIST OF DOCUMENTS REViEWED .......................................................................................... A-2

LIST OF ACRONyMS ................................................................................................................. A-9

Enclosure

3

SUMMARY OF FINDINGS

IR 05000293/2010004; 07101/2010-09/30/2010; Pilgrim Nuclear Power Station; Maintenance Risk

Assessments and Emergent Work Control.

The report covered a three-month period of inspection by the resident and region based inspectors ...

One Green non-cited violation (NCV) was identified. The significance of most findings is indicated

by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (lMC) 0609,

"Significance Determination Process." The cross-cutting aspect for the finding was determined

using IMC 0310, "Components Within The Cross-Cutting Areas." Findings for which the significance

determination process does not apply may be Green or be assigned a severity level after NRC

management review. The NRC's program for overseeing the safe operation of commercial nuclear

power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 4, dated

December 2006.

Cornerstone: Initiating Events

Green. The inspectors identified a Green non-cited violation (NCV) of 10 CFR 50.65

paragraph (a)(4) for Entergy's failure to manage a Yellow risk condition for an unplanned

half-scram. Specifically, Entergy performed an incorrect risk assessment and thereby did not

recognize an increase in risk to a Yellow condition had occurred, and as a result Entergy did

not specify any risk management actions. Entergy entered this issue into their corrective

action program, specified corrective actions to upgradr this risk to Yellow, and implemented

appropriate risk management actions.

This finding was determined to be more than minor because Entergy did not consider the

increase in Initiating Event likelihood where the outcome of the overall elevated plant risk put

the plant into a higher risk management category, and thereby required additional risk

management actions. In addition, the finding affected the Human Performance attribute of

the Initiating Events cornerstone's objective to limit the likelihood of those events that upset

plant stability and challenge critical safety functions. The inspectors performed an evaluation

in accordance with IMC 0609, "Significance Determination Process," Appendix K,

"Maintenance Risk Assessment and Risk Management Significance Determination Process,"

because the finding related to Entergy's assessment anci management of risk. The finding

was determined to be of very low safety significance (Gmen) because the Incremental Core

Damage Probability Deficit for the medium trip risk for the durati.On of the activity was less

than 1.0 E-6 per year (approximately 1.0 E-9 per year). The inspectors determined that this

finding had a cross-cutting aspect in the Human Performance cross-cutting area, Decision

Making component, because when faced with an unexpected plant condition, Entergy did not

correctly implement its systematic process to make a risk-significant decision. [H.1 (a)]

(Section 1 R13)

Enclosure

i

.1

4

REPORT DETAILS

Summary of Plant Status

..

Pilgrim Nuclear Power Station (PNPS) began the inspection period operating at 100 percent power.

On July 15, 2010, operators reduced power to 50 percent to p13rform a thermal backwash of the

main condenser. Pilgrim returned to 100 percent power on July 16, 2010. On July 19, 2010,

operators reduced power to 88 percent for a control rod pattern adjustment and returned to 100

percent power later the same day. On August 1, 2010, operators reduced power to 48 percent for

an unplanned backwash of the main condenser due to a large deposition of mussels in the main

condenser. Pilgrim returned to 100 percent power on August 2, 2010. On August 3, 2010,

operators reduced power to 89 percent for a control rod pattern adjustment and returned to 100

percent power later the same day. On August 17, 2010, operators reduced power to 48 percent to

perform a thermal backwash. Pilgrim returned to 100 percent power on August 18, 2010. On

August 20, 2010, operators reduced power to 87 percent for a control rod pattern adjustment and

returned to 100 percent power later the same day. Operators maintained the reactor at or near 100

percent power for the remainder of the inspection period.

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R01

Adverse Weather Protection (71111.01)

Seasonal Susceptibility

a.

Inspection Scope (1 sample)

The inspectors performed a review of seasonal weather preparations during the week of

July 4, 2010, to evaluate the site's readiness for the onset of hot weather. The inspectors

reviewed the readiness of three risk-significant plant areas, which included the Reactor

Building, the Turbine Building, and the Control Room. The inspection examined selected

equipment and supporting structures to determine if they were configured in accordance with

Entergy procedures, and if adequate controls were in place to ensure functionality of the

systems. The inspectors performed partial walkdowns of the Reactor Building, Turbine

Building, associated fan rooms, and the Control Room to determine the adequacy of

equipment protection from the effects of hot outside temperatures. The documents reviewed

during the inspection are listed in the Attachment.

b.

Findings

No findings were identified.

Enclosure

5

.2

External Flooding

a.

Inspection Scope (1 sample)

The inspectors reviewed the Pilgrim plant design and procedures for coping with the design

basis probable maximum flood during the week of August 23, 2010. The inspectors

reviewed the "Storm Flooding Protection" section of the Updated Final Safety Analysis

Report (UFSAR) and operating procedures for mitigating external flooding conditions during

severe weather. The inspectors also performed a walkdown of the site to determine if all

susceptible flooding conditions had been considered in the plant design, and whether

operating procedures could be reasonably carried out to mitigate flooding concerns. The

documents reviewed during this inspection are listed in the Attachment.

b.

Findings

No findings were identified .

. 3

Imminent Adverse Weather

a.

Inspection Scope (1 sample)

During the week of August 30. 2010, Hurricane Earl was tracking to impact the Pilgrim plant

late in the week. {he inspectors reviewed Entergy's preparations for the hurricane and the

high winds expected to accompany the storm. The inspectors reviewed Entergy's severe

weather procedures including operations during SeVerE! weather, coastal storm preparation,

and high winds (hurricane) procedures. The inspectors also conducted a walkdown of the

outside areas including the switchyard to determine if loose debris or other material could

become airborne in the presence of high winds and thereby potentially impact safety related

equipment. The documents reviewed during this inspection are listed in the Attachment.

b.

Findings

No findings were identified.

1 R04 Equipment Alignment (71111.04)

.1

Partial System Walkdowns (71111.040)

a.

Inspection Scope (3 samples)

The inspectors performed three partial system walkdowns during this inspection period. The

inspectors reviewed the documents listed in the Attachment to determine the correct system

alignment. The inspectors performed a partial walkdown of each system to determine if the

critical portions of the selected systems were correctly aligned in accordance with

procedures, and to identify any discrepancies that may have had an effect on operability.

The walkdowns included selected control switch position verifications, valve pOSition checks,

and verification of electrical power to critical components. In addition, the inspectors

evaluated other elements, such as material condition, housekeeping, and component

Enclosure

6

labeling. The following systems were reviewed based on their risk significance for the given

plant configuration:

High Pressure Coolant Injection (HPCI) System with Reactor Core Isolation Cooling

(RCIC) Systj?m Out of Service for Maintenance;

..

  • RCIC System Following Maintenance on the HPCI System; and
  • "A" Core Spray System Following Maintenance and Testing.

b.

Findings

No findings were identified .

. 2

Complete System Walkdowns (71111.04S)

a.

Inspection Scope (1 sample)

The inspectors completed a detailed review of the Station Blackout (SBO) Emergency Diesel

Generator(EDG) system to assess the functional capability of the system. The inspectors

performed a walkdown of the system to determine whether the critical components, such as

valves and breakers. were aligned in accordance with operating procedures, and to assess

the material condition of valves, piping, and other supporting equipment. The inspectors

discussed system health with the system engineer, reviewed the system's Maintenance Rule

status, and performed a review of outstanding mainten'lnce work orders to determine

whether the deficiencies significantly affected the SBO EDG system fUnction. The inspectors

also reviewed condition reports from the past year to determine whether SBO EDG

eqUipment problems were being identified and appropriately resolved. The documents

reviewed during this inspection are listed in the Attachment.

b.

Findings

No findings were identified.

1 R05 Fire Protection (71111.05)

Fire Protection - Tours (71111.050)

a.

Inspection Scope (5 samples)

The inspectors performed walkdowns of five fire protection areas during the inspection

period. The inspectors reviewed Entergy's fire protection program to determine the fire

protection design features, fire area boundaries, and combustible loading requirements for

the selected areas. The inspectors walked down these areas to assess Entergy's control of

transient combustible material and ignition sources. In addition, the inspectors evaluated the

material condition and operational status of fire detection and suppression capabilities and

fire barriers. The inspectors then compared the existing condition of the areas to the fire

protection program requirements to determine whether all program requirements were met.

The documents reviewed during this inspection are listed in the Attachment. The fire

protection areas reviewed were:

Enclosure

7

Fire Area 1.21, Fire Zone 1.21, "A" Reactor Building Closed Cooling Water (RBCCW)

Pumps/Heat Exchanger Room;

Fire Area 1.10, Fire Zone 1.22, "B" RBCCW Pumps/Heat Exchanger Room;

Fire Area 1.9, Fire Zone 1.1, "A" Residual Heat Removal and Core Spray Pumps

Quadrant;

..

Fire Area 1.10, Fire Zone 1.10A, Traversing In~Core Probe Room; and

Fire Area 1.10, Fire Zone 1.4, High Pressure Coolant I njection Control Panel Room.

b.

Findings

No findings were identified.

1 R06 Flood Protection Measures (71111.06)

Internal Flooding Inspection

Inspection Scope (1 sample)

The inspectors walked down the "A" R8CCW pump room and associated flood propagation

pathways to assess the effectiveness of Entergy's internal flood control measures. The

inspectors assessed the condition of the RBCCW floor drain to the torus room, curbing,

selected flood pathways, and the flood door separating the "A" and "8" RBCCW rooms. The

inspectors also evaluated whether potential source~ o'f internal flooding were analyzed. The \\

documents reviewed during this inspection are listea in the Attachment.

b.

Findings

No findings were identified.

1 R07 Heat Sink Performance (71111.07)

a.

Inspection Scope (1 sample)

The inspectors reviewed one sample of Entergy's program for maintenance, testing, and

monitoring of risk significant heat exchangers (HXs) to assess the capability of the HXs to

perform their design functions. The inspectors assessed whether the HX program

conformed to Entergy's commitments at Pilgrim related to NRC Generic Letter 89-13,

"Service Water System Problems Affecting Safety~Related Equipment." In addition, the

inspectors evaluated whether potential common cause heat sink performance problems

could affect multiple HXs in mitigating systems or result in an initiating event. Based on risk

significance and prior inspection history, the "A" RBCCW Heat Exchanger was selected for

detailed review by the inspectors.

b.

Findings

No findings were identified.

Enclosure

8

1R11

Licensed Operator Requalification Program (71111.11)

Resident Inspector Quarterly Review (71111.11 Q)

a.

Inspection Scope (1 sample)

..

The inspectors observed licensed operator performance during a simulator as-found

Licensed Operator Requalification training evaluated scenario on July 26. 2010. The

inspectors observed crew response to a scenario which included a steam release into the

secondary containment. The inspectors assessed the licensed operators' performance to

determine if the training evaluators adequately addressed observed deficiencies. The

inspectors reviewed the applicable training objectives from the scenario to determine if they

had been achieved. In addition. the inspectors performed a simulator fidelity review to

determine if the arrangement of the simulator instrumentation. controls. and tagging closely

paralleled that of the control room. The documents reviewed during this inspection are listed

in the Attachment.

b.

Findings

No findings were identified.

1 R 12 Maintenance Effectiveness (71111.12Q)

Inspection Scope (2 samples)

The inspectors reviewed the two samples listed below for items such as: (1) appropriate

work practices; (2) identifying and addressing common cause failures; (3) scoping in

accordance with 10 CFR 50.65 paragraph (b) of the Maintenance Rule; (4) characterizing

reliability issues for performance; (5) trending key parameters for condition monitoring; (6)

charging unavailability for performance; (7) classification and reclassification in accordance

with 10 CFR 50.65 paragraph (a)(1) or (a)(2); and (8) appropriateness of performance criteria

for structures, systems. and components (SSCs)/functions classified as paragraph (a)(2)

and/or appropriateness and adequacy of goals and corrective actions for SSCs/functions

classified as paragraph (a)( 1). The documents reviewed during this inspection are listed in

the Attachment. Items reviewed included the following:

"C" Salt Service Water Pump Experiencing High Vibrations; and

Station Blackout Emergency Diesel Generator System.

b.

Findings

No findings were identified.

1 R13 Maintenance Risk Assessments and_Emergent Work Control (71111.13)

a.

Inspection Scope (5 samples)

The inspectors evaluated five maintenance risk assessments for planned and emergent

maintenance activities. The inspectors reviewed maint,enance risk evaluations, work

Enclosure

1

9

schedules, and control room logs to determine if concurrent maintenance or surveillance

activities adversely affected the plant risk already incurred with out-of-service components.

The inspectors evaluated whether Entergy took the necessary steps to control work

activities, minimized the probability of initiating events, and maintained the functional

capability of mitigating systems. The inspectors assessed Entergy's risk management

actions during plant walkdowns. The documents reviewed during this inspection are listed in

the Attachment. The inspectors reviewed the conduct and adequacy of maintenance risk

assessments for the following maintenance and testing activities:

Green Risk for Emergent Half Scram and Diesel Fire Pump Out of Service;

Switch;

  • Yellow Risk during Reactor Building Closed Cooling Water Support Bolt Replacement;

and

  • Yellow Risk during the week of August 30, 2010, due to the Shutdown Transformer and

Station Blackout Emergency Diesel Generator Out of Service and the onset of Hurricane

Earl.

b.

Findings

Introduction: The inspectors identified a Green non-cited violation (NCV) of 10 CFR 50.65

paragraph (a)(4lfor Entergy's failure to identify and manage a Yellow risk condition for an

unplanned half-scram. Specifically, an incorrect risk assessment resulted in Entergy not

recognizing an increase in risk to a Yellow condition, and therefore no risk management

actions were taken.

Description: On July 26, 2010, operators received an unplanned half-scram on the "8"

channel of their Reactor Protection System (RPS) and determined the cause was a failure of

the power supply to that channel. During the event, Entergy's Diesel Fire. Pump was out of

service for scheduled maintenance. In addition, Entergy had input into their Equipment Out

of Service (EOOS) risk assessment model an increase in Loss of Offsite Power risk (LOOP

risk low) for an ongoing upgrade project to their 345 kilovolt (kV) relay protection scheme.

Following the half-scram, Entergy performed a risk assessment and concluded that they

remained green for their equipment configuration and initiating event inputs.

The inspectors inquired with operations about the adequacy of the emergent risk

assessment. Specifically, the inspectors noted that the likelihood for a reactor scram had

increased due to one half ("B" channel) of the scram channels being placed in the trip

condition. Following the discussion, operations performed a second risk assessment and

input an increase in the trip likelihood (Trip risk medium in EOOS) into their model.

Operations concluded that their risk characterization was now Yellow for their equipment

configuration and the additional initiating event input. Entergy then implemented risk

management actions for the Yellow condition, which included protecting the Vital Motor

Generator Set Room.

Analysis: The performance deficiency associated with this finding is that Entergy performed

an incorrect risk assessment for an emergent half scram and, as a result. did not take risk

management actions as specified by 10 CFR 50.65(a)(4). Traditional Enforcement did not

Enclosure

10

apply as the issue did not have actual or potential safety consequence, had no willful

aspects, nor did it impact the NRC's ability to perform its regulatory function.

A review of NRC Inspection Manual Chapter (IMC) 0612, Appendix E, "Minor Examples,"

identified that Section 7, Maintenance Rule, Example e, reflected a similar more than minor

example. This finding was determined to be more than minor because Entergy did not

consider the increase in Initiating Event likelihood, where the outcome of the overall elevated

plant risk put the plant into a higher risk management category and thereby required

additional risk management actions. In addition, the finding affected the Human

Performance attribute of the Initiating Events cornerstone's objective to limit the likelihood of

those events that upset plant stability and challenge critical safety functions. The inspectors

performed an evaluation in accordance with IMC 0609, "Significance Determination

Process," Appendix K, "Maintenance Risk Assessment and Risk Management Significance

Determination Process," because the finding related to Entergy's assessment and

management of risk. The finding was determined to be of very low safety significance

(Green) because the Incremental Core Damage Probability Deficit for the medium trip risk for

the duration of the activity was less than 1.0 E-6 per year (approximately 1.0 E-9 per year).

The inspectors determined that this finding had a cross-cutting aspect in the Human

Performance cross-cutting area, Decision Making component, because when faced with an

unexpected plant condition, Entergy did not correctly implement its systematic process to

make an appropriate risk-significant decision. [H .1 (a)]

Enforcement: 10 CFR 50.65 paragraph (a)(4), "ReqJirements for Monitoring the

Effectiveness of Maintenance at Nuclear Power Plants," states, in part, that " ... the licensee

shall manage the increase in risk that may result from the proposed maintenance activities."

Contrary to the above, on July, 26, 2010, Entergy incorrectly assessed the increased risk that

resulted from an emergent condition. As a result. Entergy did not recognize the Yellow risk

condition and thus did not take any risk management actions. Corrective actions included

Entergy upgrading their risk characterization to Yellow and taking risk management actions

which included protecting the Vital Motor-Generator Set Room. Because of the very low

safety-significance and because it has been entered into the corrective action program (CR

PNP-2010-3440), the NRC is treating this as a non-cited violation (NCV), consistent with

Section 2.3.2 a of the NRC's Enforcement Policy. (NCV 05000293/2010004-01, Failure to

Manage a Yellow Risk Condition for an Unplanned Half Scram)

1 R15 Operability Evaluations (71111.15)

a.

Inspection Scope (5 samples)

The inspectors reviewed five operability determinations associated with degraded or

non-conforming conditions to determine if the operability determination was justified and if

the mitigating systems or barriers remained available such that no unrecognized increase in

risk had occurred. The inspectors also reviewed compensatory measures to determine if the

compensatory measures were in place and were appropriately controlled. The inspectors

reviewed Entergy's performance against related Technical Specifications and Updated Final

Safety Analysis Report requirements. The documents reviewed during this inspection are

listed in the Attachment. The inspectors reviewed the following degraded or non-conforming

conditions:

Enclosure

.1

11

Leak;

~

.

~

Loops Show Signs of Degradation; and

CR-PNP-2010-2645, Buried Condensate Storage Tank Transfer Piping Indications.

b.

Findings

No findings were identified.

1R18 Plant Modifications (71111,18)

Temporary Modification to Modify Drain Piping to Facilitate Validating the Integrity of the

Main Stack Drain Line

a.

Inspection Scope (1 sample)

The inspectors reviewed Temporary Modification EC 23807, "Modify Drain Piping to

Facilitate Validating the Integrity of the Main Stack Drain Line," to determine whether the

integrity of Secondary Containment had been de9[aded through the modification. The

\\

inspectors reviewed Control Room drawings, calculations. work orders, and limiting condition

of operation logs to ensure the temporary modification did not adversely affect the integrity of

secondary containment. The inspectors reviewed the annotated drawings to determine

whether they properly reflected the temporary modification. The inspectors also walked

down the High Pressure Coolant Injection Control Panel Room to review the installed

modification. The documents reviewed during this inspection are listed in the Attachment.

b.

Findings

No findings were identified .

. 2

Temporarv Modification to Gag AO-N-98 in the Open Position

a.

Inspection Scope (1 sample)

The inspectors reviewed Temporary Modification EC 23892, "Gag AO-N-98 in the Open

Position,>> to determine whether the performance capability of the Standby Gas Treatment

(SBGT) System had been degraded through the modification. The inspectors reviewed

Control Room and procedural drawings, relevant condition reports, and work orders to

ensure the temporary modification did not adversely affect the SBGT system. The inspectors

reviewed the annotated drawings to determine whether they properly reflected the temporary

modification. The inspectors also walked down the Traversing In-Core Probe room to review

the installed modification. The documents reviewed during this inspection are listed in the

Attachment.

Enclosure

12

b.

Findings

No findings were identified.

1R19 Post-Maintenance Testing (71111.19)

..

a.

Inspection Scope (6 samples)

The inspectors reviewed six samples of post-maintenance tests during this inspection period.

The inspectors reviewed these activities to determine whether the post-maintenance test

adequately demonstrated that the safety-related function of the equipment was satisfied

given the scope of the work performed. and that operability of the system was restored. In

addition, the inspectors evaluated the applicable test acceptance criteria to verify consistency

with the associated design and licensing bases, as well as Technical Specification

requirements. The inspectors also evaluated whether conditions adverse to quality were

entered into the corrective action program for resolution. The documents reviewed during

this inspection are listed in the Attachment. The following maintenance activities and their

post-maintenance tests were evaluated:

  • Voltage Balance Relay Replacement for Relay 160-609 on the "B" Emergency Diesel

Generator;

\\

  • Replace Reactor Building Closed Cooling Water Temperature Control Valve Linkage;
  • Electric Fire Pump Replacement;

Maintenance.

b.

Findings

No findings were identified.

1 R22 Surveillance Testing (71111.22)

a.

Inspection Scope (5 samples)

The inspectors witnessed five surveillance activities and/or reviewed test data to determine

whether the testing adequately demonstrated equipment operational readiness and the

ability to perform the intended safety-related functions. The inspectors reviewed selected

prerequisites and precautions to determine if they were met, and if the tests were performed

in accordance with the procedural steps. Additionally, the inspectors evaluated the

applicable test acceptance criteria for consistency with associated design bases, licensing

bases, and Technical Specification requirements. The inspectors also evaluated whether

conditions adverse to quality were entered into the corrective action program for resolution.

The documents reviewed during this inspection are listed in the Attachment. The following

surveillance tests were evaluated:

Enclosure

13

Control Rod Weekly Exercise;

High Pressure Coolant Injection Quarterly In-Service Test (1ST);

Station Blackout Emergency Diesel Generator Test;

Core Spray Keepfill Check; and

Reactor Coolant System (RCS) Leakage Detection.

b.

Findings

No findings were identified.

1 EP6 Drill Evaluation (71114.06)

Cornerstone: Emergency Preparedness

a.

Inspection Scope (1 sample)

The inspectors observed licensed operator "as-found", simulator training on July 26,2010.

The inspectors evaluated the operating crew activities related to an accurate and timely

classification and notification of a site area emergency. Additionally, the inspectors assessed

the ability of training evaluators to adequately address operator performance deficiencies

identified during the exercise. The documents reviewed during this inspection are listed in

the Attachment.

1

b.

Findings

No findings were identified.

2.

RADIATION SAFETY (RS)

Cornerstone: Occupational/Public Radiation Safety

2RS06 Gaseous and liquid Effluent Treatment (71124.06)

a.

Inspection Scope

During the period July 12,2010 through July 15,2010, the inspectors performed the

following activities to verify the gaseous and liquid effluent systems are maintained, and

discharges and conditions are control/ed in accordance with applicable regulatory

requirements and Pilgrim procedures.

Inspection Planning

The inspectors reviewed the Effluent and Waste Disposal 2008 Annual Report. The

inspectors noted no anomalous results and reviewed the effluent monitor operability issues

reported. The inspectors reviewed the Updated Final Safety Analysis Report (UFSAR) and

descriptions of the radioactive effluent monitoring systems, treatment systems, and effluent

flow paths. The inspectors reviewed the changes made to revision 10 of Pilgrim's Offsite

Dose Calculation Manual (ODeM). The inspectors verified there were no systems

Enclosure

14

contaminated with licensed material that were previously uncontaminated. The inspectors

reviewed reported groundwater monitoring results, and changes to the Pilgrim written

program for identifying and controlling contaminated spillslleaks to groundwater. The

inspectors reviewed reports and procedures for the effluent program .

Walk-downs and Observations

The inspectors walked down accessible components of the gaseous and liquid discharge

systems. The inspectors verified the equipment configuration and flow paths aligned with the

UFSAR. The inspectors observed the equipment physical condition. The inspectors

determined no condition surveillance records exist for areas that are not readily accessible.

The inspectors walked-down the filtered ventilation systems and verified there were no

degraded High Efficiency Particulate Assemblies or charcoal banks, improper alignment, or

system installation issues that would impact performance, or the effluent monitoring

capability, of the effluent system. The inspectors observed sampling and analysis of the

main stack ventilation. The inspectors verified that no changes have been made to effluent

release points. The inspectors observed the simulated sampling and analysis of a Treated

Water Tank (TWT) for release.

Sampling and Analysis

The inspectors verified liquid effluent sampling includes provisions for sample line flushing,

vessel recirc'!lation. and composite sampling durin~ a release. The inspectors reviewed two

release packages for releases made with monitoring equipment out of service. The

inspectors verified that compensatory sampling was performed consistent with the ODCM.

The inspectors verified Pilgrim is not routinely relying on the use of compensatory sampling

in lieu of adequate system maintenance. Liquid releases are performed on an infrequent

basis. The inspectors reviewed the inter-laboratory comparison program to verify the quality

of the radioactive effluent sample analyses. and that the program included hard-to-detect

isotopes.

Instrumentation and Eguipment

The inspectors reviewed the methodology Pilgrim uses to determine the main stack and

reactor building vent flow rates. The inspectors verified the flow rates used are consistent

with the ODCM values. The inspectors reviewed surveillance test results for the standby gas

treatment and the control room environmental filters system to verify they met Technical

Specification acceptance criteria.

Dose Calculations

The inspectors verified there were no Significant changes in the reported dose values

compared to the previous Radiological Effluent Release Report. The inspectors reviewed

two (2) liquid release permits to verify that projected doses to members of the public are

accurate and based on representative samples. There were no gaseous release packages

to review. The inspectors reviewed the analysis used to determine hard-to-detect

radionuclides. The inspectors verified these radioisotopes were included in the source term.

The inspectors reviewed the changes made for Revision 10 of the ODCM since the last

inspection. The inspectors reviewed the latest Land Use Census and verified that no

Enclosure

.1

15

changes were needed to the dose calculations. The inspectors verified for the release

packages review, the calculated doses were within the 10 CFR Part 50, Appendix I and

Technical Specification dose criteria. The inspectors verified there were no abnormal

releases during this inspection period.

  • Groundwater Protection Implementation (GPI) *

The inspectors reviewed the monitoring results of the GPI Initiative to verify Pilgrim has

implemented their program as intended and to identify any anomalous results. The

inspectors verified that no entries were made into the 10 CFR 50.75 (g) file during this

inspection period. The inspectors verified there were no leaks or spills during this inspection

period. The inspectors could not evaluate discharges from onsite surface water bodies

because Pilgrim has no onsite surface water bodies. The inspectors verified that the results

of groundwater monitoring are included in the Annual Radiological Effluent Release Report.

The inspectors noted that Pilgrim has no new discharge paints.

Problem Identification and Resolution

The inspectors reviewed Pilgrim self-assessments, audits, and special reports related to the

radiological effluent treatment system to determine if identified problems were entered into

the corrective action program. The inspectors verified that problems identified were put into

the corrective action program and corrective actions were appropriate.

b.

~indings

\\

No findings were identified.

4.

OTHER ACTIVITIES [OA]

40A1 Performance Indicator (PI) Verification (71151)

Cornerstone: Mitigating Systems

a.

Inspection Scope (3 samples)

The inspectors reviewed PI data to determine the accuracy and completeness of the

reported data. The review was accomplished by comparing reported PI data to confirmatory

plant records and data available in plant logs, eRs, Licensee Event Reports (LERs), and

NRC inspection reports. The acceptance criteria used for the review was Nuclear Energy

Institute (NEI) 99-02, Revision 6, "Regulatory Assessment Performance Indicator

Guidelines." The documents reviewed during the inspection are listed in the Attachment.

The following performance indicators were reviewed:

High Pressure Injection System from the third quarter of 2009 through the second quarter

of 2010 [MS07];

Heat Removal System from the third quarter of 2009 through the second quarter of 2010

[MS08J; and

quarter of 2010 [MS09].

Enclosure

16

b.

Findings

No findings were identified.

..

.2

Cornerstone: Occupational/Public ~adiation Safety

Radiological Effluent Technical Specification (RETS) /Offsite Dose Calculation Manual

(aDeM) Radiological Effluent Occurrences [PR01]

a.

Inspection Scope (1 sample)

The inspectors reviewed relevant effluent release reports for the period January 1, 2009

through December 31, 2009, for issues related to the pubHc radiation safety performance

indicator, which measures radiological effluent release occurrences that exceed 1.5 milli

rem/quarter whole body or 5.0 milli-rem/quarter organ dose for liquid effluents; 5 milli

rads/quarter gamma air dose; 10 milli-rads/quarter beta air dose; and 7.5 milli-rads/quarter

for organ dose for gaseous effluents. This inspection activity represents the completion of

one sample relative to this inspection area; completing the annual inspection requirement.

b.

Findings

No findings were identified.

\\

\\

40A2 Identification and Resolution of Problems (71152)

.1

Review of Items Entered into the Corrective Action Program {CAP}

a.

Inspection Scope

The inspectors performed a screening of each item entered into Entergy's corrective action

program. This review was accomplished by reviewing printouts of each Condition Report

(CR), attending daily screening meetings and/or accessing Entergy's database. The purpose

of this review was to identify conditions such as repetitive equipment failures or human

performance issues that might warrant additional follow-up.

b.

Findings

No findings were identified .

. 2

Annual Sample: Operator Workarounds

a.

Inspection Scope (1 sample)

The inspectors performed the annual review of operator workarounds to verify Entergy was

identifying operator workaround problems at an appropriate threshold and entering them into

the corrective action program. The inspectors reviewed identified workarounds to determine

whether the mitigating system function was affected, whether the operator's ability to

implement abnormal and emergency operating procedures was affected, and whether

Enclosure

.1

17

appropriate procedures had been updated to reflect actual plant conditions. The inspection

was accomplished through personnel interviews, plant tours, and review of station

documents. The documents reviewed during the inspection are listed in the Attachment.

b.

Findings and Observations

No findings were identified. Operator workarounds have been identified and entered into the

corrective action program for resolution. No unrecognized impacts to operator or system

performance were identified, and corrective actions have been implemented to restore the

affected systems.

40A3 Event Foliow-uR (71153)

Release of Hydrogen Gas to the Environment

a.

Inspection Scope (1 sample)

On August 25,2010, Entergy identified an increase in generator hydrogen gas usage

following the return to service of a hydrogen seal oil system vacuum pump. Operators

isolated the vacuum pump and generator hydrogen makeup returned to normal. Operations

reviewed reporting requirements and notified the State of Massachusetts due to the release

of hydrogen gas greater than the reportable quantity of 10 Ibs. (approximately 20 Ibs. was

released). Operations also notified the Nuclear Regulatory Commission Headquarters

Operations Officer. The inspectors reviewed Entergy's actions, procedures, notification

requirements, and applicability of emergency action level guidance.

b.

Findings

No findings were identified .

. 2

o.perator Performance During Main Condenser Backwash

a.

Inspection Scope (1 sample)

The inspectors observed operators perform a backwash on August 1, 2010. Specifically, the

inspectors observed an unplanned plant downpower to 48 percent reactor power to support

the backwash of the main condenser due to fouling. The inspectors reviewed procedural

guidance for station power changes and the power maneuver plan, and observed control

room conduct and control of the evolution. The documents reviewed during this inspection

are listed in the Attachment.

b.

Findings

No findings were identified.

Enclosure

.1

18

40A5 Other Activities

(Closed) Temporary Instruction 2515/173, Review of the Implementation of the Voluntary

Industry Groundwater Protection Initiative (GPI}

..

.

a.

Inspection Scope

During the period July 12,2010, through July 15, 2010, an NRC assessment was performed

of Pilgrim's GPI program to determine whether Pilgrim implemented the voluntary Industry

Groundwater Protection Initiative, dated August 2007 (Nuclear Energy Institute (NEI) 07-07,

ADAMS Accession Numbers ML07261 0036 and ML072600292). The inspectors interviewed

personnel, performed walkdowns of selected areas as needed and reviewed documentation.

GPI Objective 1.1 - Site Hydrology and Geology

The inspectors verified that a hydrology and geologic study was performed by an outside

contractor to determine the predominant groundwater flow characteristics and gradients.

The inspectors verified the study was reviewed by a knowledgeable utility employee. The

inspectors verified that potential pathways have been identified for groundwater migration

from on-site locations to off-site locations through groundwater. The inspectors verified that

a five (5) year frequency has been established in Pilgrim procedures for periodic review of

the hydrogeologie studies. The inspectors verified that no changes were required to the

Updated Firal Safety Analysis ~eport.

GPI Objective 1.2 - Site Risk Assessment

The inspectors verified that Pilgrim has identified structures, systems, and components

(SSCs) that involve or could reasonably be expected to involve licensed material and for

which there is a credible mechanism for licensed material to reach groundwater. The

inspectors verified that the Pilgrim corrective action program will be used to identify and track

corrective actions.

GPI Objective 1.3 - On-Site Groundwater Monitoring

The inspectors verified Pilgrim has considered the placement of monitoring wells down

gradient from the plant but within the site boundary. The inspectors verified that Pilgrim

considered placing sentinel wells closer to structures, systems or components (SSCs) that

have the highest potential for inadvertent releases that could reach groundwater. The

inspectors verified that Pilgrim has established sampling and analysiS protocols, including

analytical sensitivity in site procedures. The inspectors verified that a formal written program

has been established for long term groundwater monitoring. The inspectors verified that the

Offsite Dose Calculation Manual has not been revised to include groundwater monitoring as

the monitoring locations are not included in the Radiological Environmental Monitoring

Program (REMP). The inspectors verified that the analytical capabilities are periodically

reviewed as part of the analytical cross check program. The inspectors verified that a long

term program has been established in Pilgrim procedures for the groundwater monitoring

wells. The inspectors verified a frequency has been established in Pilgrim procedures for the

periodiC review of the groundwater monitoring program.

Enclosure

..

\\

19

GPI Objective 1.4 - Remediation Process

The inspectors verified that written procedures have been established outlining the decision

making process for the remediation of leaks and spills or other instances of inadvertent

releases. The inspectors verified that an evaluation was performed of the potential for

detectible levels of licensed material from plarlhed releases of liquids and/or airborne

materials.

GPI Objective 1.5 - Record Keeping

The inspectors verified that a record keeping program has been established to meet the

requirements of 10 CFR 50.75 (g).

GPI Objective 2.1 - Stakeholder Briefings

The inspectors verified by discussion with Pi/grim staff and review of documentation that

initial briefings have been conducted with designated State and Local officials of the site

specific GPI program. The inspectors verified Pilgrim has considered including additional

information or updates on groundwater protection in the annual reports for the State and

Local officials.

9PI Objective 2.2 - Voluntary Communications

The inspectors verified that Pilgrim procedures ~stablish communication protocols for

communicating leaks and spills to State and Local officials. The inspectors verified that the

ODCM establishes communication protocols for groundwater samples exceeding REMP

reporting criteria.

GPI Objective 2.3 - Thirty Day Reports

The inspectors verified that groundwater samples are analyzed and compared to the

standards and limits contained in the ODeM. The inspectors verified that no thirty day

special reports for groundwater monitoring have been submitted to the Nuclear Regulatory

Commission (NRC).

GPI Objective 2.4 - Annual Reporting

The inspectors verified that appropriate changes have beEm made to appropriate Pilgrim

procedures to support the 2006 performance. The inspectors verified that aI/ groundwater

sample results are included in the Annual Radiological Effluent Release Report (ARERR).

The inspectors verified that no groundwater samples taken as part of the GPI are part of the

REMP program. The inspectors verified that, at the time of this inspection, no water sample

results exceeded REMP reporting thresholds since the implementation of the GPI.

Enclosure

20

GPI Objective 3.1 - Perform a Seff Assessment of the GPI Program

The inspectors verified that an independent individual performed the initial self assessment

of the groundwater program prior to the implementation of the GPI and another self

assessment performed in 2009. The inspectors verified that self assessments are s;>ecified

every five years per Pilgrim procedures. The inspectors verified that the self assessment

included an evaluation of all of the GPI objectives. The inspectors verified the self

assessments are documented in accordance with Pilgrim procedures.

GPI Objective 3.2 - Review the Program Under the Auspices of NEI

The inspectors verified an independent individual performed an initial review after the initial

assessment. The inspector verified that Pilgrim procedures require a periodic review of the

GPI program every five years.

b.

Findings and Assessments

No findings were identified. Implementation of the Industry GPI is VOluntary. Under the final

Initiative, each site was to have developed an effective, technically sound groundwater

protection program by August 2008. The inspectors identified that, at the time of this

inspection, Pilgrim had not taken action on all groundwater initiative objectives (as outlined in

the Temporary Instruction) as follows:

\\

1

GPI Objective 1.2

Pilgrim has identified SSGs that involve or could reasonably be expected to involve licensed

material and for which there is a credible mechanism for licensed material to reach

groundwater. However, Pilgrim has not identified work practices that involve or could

reasonably be expected to involve licensed material and for which there is a credible

mechanism for licensed material to reach groundwater. Pilgrim has not established a relative

risk for the SSGs identified. Pilgrim has not identified existing leak detection methods for

each sse and work practice that involve or could reasonably be expected to involve licensed

material and for which there is a credible mechanism for licensed material to reach

groundwater.

Pilgrim has not identified potential enhancements to leak detection systems or programs.

Pilgrim has not identified potential enhancements to prevent spills or leaks from reaching

groundwater. Pilgrim has a written long term program; however, it has not been formalized.

GPI Objective 1.4

Pilgrim has not documented an evaluation of the decommissioning impacts resulting from

remediation activities or the absence of remediation activities. However, a draft procedure

has been written about the subject.

In the 2007/2008 period, in accordance with the voluntary Groundwater Protection Initiative

(NEI-07-07), Pilgrim installed four monitoring wells (MW-201, 201,203, and 204) that were

located to detect potential radioactive material leakage from underground structures,

systems, and components (SSGs). These wells, and two other existing monitoring wells

(MW-3 and MW-4), were incorporated into Pilgrim's groundwater protection program, and

Enclosure

21

have been sampled on a quarterly basis, The samples are split with the Massachusetts

Department of Public Health (MDPH). These wells have not indicated any condition

perceived as an indicator of leakage from any SSC.

In May 2010, Pilgrim installed six additional groundwater monitoring wells in response to an

independent self-assessment that Entergy conducted relative to Pilgrim's implementation of

the NEI-07-07 objectives. These wells were identified as MW-202(1), 205, 206, 207, 208(S),

and 208(1}. [Note: S and I refer to Shallow and Intermediate depth). On May 16, 2010, the

first sample results for these six wells were reported. All indicated typically expected results,

with the exception of MW-205, which indicated 5,300 picocuries per liter (pCi/l), tritium (H-3).

Subsequent sampling on June 11 indicated 8,600 pCi!l; on June 21 indicated 11,000 pCi/l;

and on June 30 indicated 8,400 pCill. Since that time, sample results from MW-205 have

continued to vary; and the highest concentration measured to-date has been approximately

25,000 pCi/L

Entergy has been keeping the Massachusetts Emergency Management Agency (MEMA) and

the MDPH informed of these conditions, and has issued notifications to the NRC in

accordance with 10 CFR 50.72. The licensee has frequently met with representatives of

MEMA, MDPH, and NRC to discuss its plans and investigation process for determining the

source of the tritium contamination. Additionally, NRC resident inspectors and region-based

inspectors have been closely monitoring the licensee's plans, process, and progress in .

determining the cause and source of the contamination.

The NRC confirmed that Entergy established a technical team dedicated to the resolution of

this matter, and has implemented appropriate and reasonable actions to determine the

source and to resolve the condition. Frequent sampling of existing wells, development of

additional monitoring wells, application of ground penetrating radar surveillance.

implementation of leak detection techniques on suspected underground SSCs that are in the

vicinity of MW-205, and development of additional hydrological data are continuing. NRC

resident inspectors are closely following the licensee's onsite activities, and the licensee is

frequently communicating its plans and progress to NRC and to appropriate representatives

of the State of Massachusetts.

The NRC will continue to follow the licensee's performance closely to assure conformance

with regulatory requirements, and to assure that public health and safety is maintained.

Based on information reviewed to-date, the groundwater condition at Pilgrim has not, nor is

expect to, result in any public health and safety consequence .

. 2

Strike Contingency Plan (92709)

a.

Inspection Scope

Entergy developed a Security Staffing Contingency Plan to ensure a sufficient number of

qualified security officers were available to maintain Pilgrim's security plan in the event that

the United Government Security Officers of America, Local 25 security officers engaged in a

job action upon the expiration of their contract on October 1,2010. Using the guidance

contained in NRC Inspection Procedure 92709, "Licensee Strike Contingency Plans," the

inspectors reviewed Entergy's plans to address a potential job action at the site. The

inspection included an evaluation of the Security Staffing Contingency Plan content and the

Enclosure

22

actions needed to implement the plan, and a review to determine whether the number of

qualified security officers needed for the proper implementation of Pilgrim's Security Plan

would be available.

b.

Findings ..

..

No findings were identified.

40A6 Meetings, Including Exit

On July 15. 2010, the regional inspector conducted a Radiation Safety and closure of TI

2515/173 exit meeting. Bob Smith. Plant General Manager, attended the meeting. At the

exit meeting, the inspectors confirmed that no proprietary information was provided to the

inspectors for the inspection.

On October, 13,2010, the resident inspectors conducted an exit meeting and presented the

preliminary inspection results to Mr. Kevin Bronson, and other members of the Pilgrim staff.

The inspectors confirmed that proprietary information provided or eXamined during the

inspection was controlled and/or returned to Entergy, and the content of this report includes

no proprietary information.

\\

1

ATTACHMENT: SUPPLEMENTAL INFORMATION

Enclosure

A-1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Entergy personnel:

S. Bethay

Director, Nuclear Safety Assurance

R. Bowen

Chemistry Technician

K. Bronson

Site Vice President

G. Dechen

Engineer, Underground Pipes and Tanks

V. Fallacara

Engineering Director

W. Lobo

licensing Engineer

J. Lynch

Licensing Manager

J. Macdonald

Assistant Operations Manager-Shift

T. McElhinney

Chemistry Manager

D. Noyes

Operations Manager

B. Panzarella

Chemistry Technician

J. Priest

Radiation Protection Manager

J. Scheffer

Chemistry Supervisor

K. Sejkora

Staff Chemist

R. Smith

General Manager, Pilgrim Operations

\\

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened and Closed

NCV 05000293/2010004-01

Failure to Manage a Yellow Risk Condition for an Unplanned

Half Scram (Section 1R13)

Attachment

A-2

LIST OF DOCUMENTS REVIEWED

Section 1 R01

Procedure 2.2.40, Revision 31, Reactor Building Heating, Cooling, and Ventilation System

Procedure 2.1.42, Revision 10, Operation During Severe Weather

..

Master/Local Control Center Procedure No.2 (M/L CC2) Abnormal Conditions Alert, Revision 14

Procedure 2.2.94, Revision 106, Seawater System

Procedure 2.4.149, Revision 10, Loss of Control Room Air Conditioning

Procedure 2.4.153, Revision 19, Loss of Turbine Building/Auxiliary Bay Area Ventilation

Procedure 8.C.40, Section 3, Revision 24, Warm Weather Surveillance

Procedure 2.1.37, Revision 26, Coastal Storm - Preparations and Actions

UFSAR, Section 2.4.4, Storm Flooding Protection

CR-PNP-2010-03006, NRC review of station response to the August 22-24 coast storm identified

that Procedure 2.1.37, Coastal Storm Preparations and Actions, does not direct a

preemptive walkdown of the site

NUREG-0654, Appendix 1, Basis for Emergency Action Levels for Nuclear Power Facilities

Procedure 5.2.2, Revision 31, High Winds (Hurricane)

Pilgrim Station Prep Checklist for Hurricane Earl

Section 1 R04

Procedure 2.2.21, Revision 77, High Pressure Coolant Injection System

Procedure 2.2.22, R}3vision 71, Reactor Core Isolation Cooling System

\\

Procedure .2.2.20, Revision 73, Core Spray

UFSAR Chapter 8.10, Blackout AC power Source

Procedure 2.2.146, Revision 40, Station Blackout Diesel Generator

Drawing M264, P&ID Station Blackout Diesel Generator Set

CR-PNP-2010-3320, SBO Valve has a position of "Factory Set" with no method to verify this

Position in Procedure 2.2.146

Section 1 R05

Procedure 8.B.17.1, Revision 18, Inspection of Fire Door Assemblies

Fire Hazards Analysis Section Fire Area 1.21, Fire Zone 1.21, "AU RBCCW Pumps/Heat

Exchanger Room

Engineering Evaluation No.3, Unprotected Structural Steel in part of wall barriers

Fire Hazards Analysis Section Fire Area 1.10, Fire Zone 1.22, "B" RBCCW Pumps/Heat

Exchanger Room

Exemption Request No. 12, Exemption for Redundant Trains of Equipment Separated by a Three-

Hour Barrier

Fire Hazards Analysis, Fire Zone Data Sheet for Fire Zone 1.1 OA

Procedure 8.B.17.2, Revision 12, Inspection of Fire Damper Assemblies

"Exemptions to Section III.G of Appendix R" Approval Letter dated December 18, 1984

"Correction to Exemption and Safety Evaluation Related to Section III.G of Appendix R" Approval

Letter dated June 1 0, 1985

Procedure 5.5.2, Revision 46, Special Fire Procedure

CR-2010-2945, TIP Room Discrepancies

Attachment

A-3

Fire Hazards Analysis Data Sheets for Fire Area 1.10, Fire Zone 1.4

EN-DC-161, Revision 4, Control of Combustibles

EC 23807, Modify Drain Piping to Facilitate Validating the Integrity of the Main Stack Drain Line

Section 1 R06

CR-PNP-2010-2594, Reactor Building Closed Cooling Water Suction header for both loops show

signs of degradation and associated operability evaluation

Calculation S&SA 60, Revision 0, Flooding due to Emergency Core Cooling System Leakage

Outside Containment

Calculation S&SA 61, Revision 1. Flood Level Calculations

Flood Propagation Pathway Charts

PNPS Probabilistic Safety Assessment IPE, Revision 1, Appendix E, Internal Flooding Analysis

Section 1R07

Generic Letter 89-13, Service Water System Problems Affecting Safety Related Equipment

Work Order (WO) 51674422, Tasks 1-3, "A" RBCCW HX Thermal Performance Test

Procedure 8.5.3.14.1, Revision 4, RBCCW Heat Exchanger Thermal Performance Test

Calculation M-710, Heat Exchanger Thermal Performance Testing

Section 1 R 11

As-Found Testing Scenario SES-171, Revision 1

Emergency Action Levels

Section 1R12

CR-PNP-2008-3736, P208C experienced high vibration and associated functional failure

determination

CR-PNP-2010-2291 , P208C experienced high vibration and was pulled to lock and associated

functional failure determination

Maintenance Rule Basis Document for Salt Service Water System

Procedure EN-DC-205, Revision 2, Maintenance Rule Monitoring

UFSAR Chapter 8.10, Blackout AC Power Source

Procedure 2.2.146, Revision 40, Station Blackout Diesel Generator

Drawing M264. P&ID Station Blackout Diesel Generator Set

Condition Report List for Station Blackout Diesel Generator Issues Documented September 2009

through September 2010

Maintenance Rule Basis Document for Station Blackout Diesel Generator

SBO Diesel Generator System Health Report

SBO CR listing from September 2009 through September 2010

Section 1 R 13

Equipment Out of Service (EOOS) Tool

Risk Profile for week of July 4 - July 11, 2010

Risk Sheet for Medium Trip Risk for July 26.2010

Attachment

A-4

Risk Sheet for High Trip Risk for July 26,2010

CR~PNP~2010-2584, Power Supply EIS 2229~BIL Blown Fuse 5-AF-30B

Work Week Schedules

Scheduler's Evaluation for Pilgrim the week of August 30, 2010

Compensatory"M.easures and Protected Area Sheet

Hurricane Earl Checklist

CR-PNP-2010-3440, Yellow Risk Condition Not Recognized

Section iRiS

CR-PNP-2010~2264. Scram Discharge Volume West Not Drained Alarm coming in the Control

Room and associated Operability Evaluation

CR-PNP-2009-3385, Scram Discharge Volume Level Instrumentation Drifting High

ODMllmplementation Action Plan for LT-302-83D, Drifting Causing False High Level Indication,

Revision 0

Alarm Response Procedure ARP-C905R-61, Revision 24

Procedure 8.M.1-32A.1, Revision 0, Analog Trip System':"" Trip Calibration with Gross Fail Check

Cabinet C2229-B2

CR-PNP-2010-2355, Lack of Board Certified Rated Capacities for Safety Relief Valves

CR-PNP~201 O~2935, HPCI Steam Admission Valve Packing Leak

EN-OP-104, Revision 4, Operability Determination Process

Technical Specification 3.5.C, HPCI System

CR-PNP-201 0-45~4, Reactor Building Closed Cooling Water Suction header for both loops show

Signs of degradation and associated operability evaluation

CR-PNP-2009~3338, RBCCW suction header piping show corrosion is in need of mitigation

CR-PNP-2001-9145, Degraded piping on RBCCW Loop A suction piping

Mechanical Calculations, Evaluation of RBCCW suction header piping calculation M*1036,

Revision 0

CR-PNP-2010-2645, Indications identified on Condensate Transfer Buried Piping

P&ID M209, Revision 67, Condensate and Demineralized Water Storage and Transfer Systems

CST System Safety Function Sheets

Section 1R18

EC 23892, Gag AO-N-98 in the Open Position

CR*PNP-2010-2716, Damper AO-N-98 found with blade not functioning properly

Procedure a.CA, Revision 22, Routine Running of SBGT System

Drawing M294, SBGT System

Technical SpeCification 3.7.B, SBGT System and Control Room High Efficiency Air Filtration

System

Drawing M294, Heating, Venting and Air Conditioning SBGT System Control Diagram

UFSAR, Section 5.3, Secondary Containment System

EN-DC-134, Attachment 9.1, DeSign Verification Checklist

EN*1I*100, Process Applicability Determination for Temporary Modification to Gag AO~N-98 in the

Open Position

UFSAR 5.3, Secondary Containment System

UFSAR 7.18. Reactor Building Isolation and Control System

Control Room Technical Specification Logs

Attachment

A-5

Temporary Modification EC 23807, Modify Drain Piping to Facilitate Validating the Integrity of the

Main Stack Drain Line

10 CFR Part 50.59, Screen for EC 23807

WO 244934, Installation of TMOD EC 23807

P&ID M210. Augmented Off Gas

Calculation C15.0.3381. Revision 3, Leakage Permitted for Secondary Containment

CR-PNP-2010-3285, Total known leakage for secondary containment was miscalculated

Section 1R19

WO 002122652, Task 4, Relay 160-609 Relay Replacement

Procedure 3.M.3-51, Revision 26, Electrical Termination Procedure

WO 00222652, Tasks Postwork Test for 160-609 Replacement

Procedure EN-WM-107, Revision 2, Post Maintenance Testing

Procedure 3.M.3-1, Revision 127, A5/A6 Buses 4kV Protective Relay Calibration/Functional Test

And Annunciator Verification

UFSAR, Section 8.5, Standby AC Power Source

Procedure 3.MA-14.2, Revision 56, Salt Service Water Pumps Routine Maintenance

WO 00242322-01, Rebuild "C" SSW Pump

Equivalent Change EC 0000012107, SSW Pump "C" Bolted Connections

Design Engineering Evaluation Form for WO 242322

WO 002422322-14, Compliance Package

EC 23446, Revision 0, Attachment 1, Recommended Epoxy Injection Procedure

WO 00242332-03, SSW Pump "C" Post Work Testi~g

Procedure 8.5.3.2.1, Revision 22, Salt Service Water Pump Quarterly and Biennial

(Comprehensive) Operability and Valve Operability Tests

WO 00245886-01, TV-3835 Failed Open

EN-MA-125, Revision 6, Troubleshooting Control of Maintenance Activities

CR-2010-2812, EN-MA-125 does not discuss Post Maintenance testing requirements

WO 00235076, Tasks 1 and 3, Replace Electric Fire Pump

Procedure 8.B.15, Revision 44, Functional Tests of Fire Pumps P-135, P-140, and P-181

Procedure 3.MA-14, Revision 37, Rotating Equipment Inspection Assembly and Disassembly

Procedure EN-WM-107, Revision 2, Post Maintenance Testing

Vendor Manual V-0251, Revision 95, Lubrication Manual

EC 23892, Gag AO-N-98 in the Open Position

Procedure 8.C.4, Revision 22, Routine Running of Standby Gas Treatment System

CR-PNP-2010-2716, Damper AO-N-98 found with blade not functioning properly

Technical Specification 3.7.B, Standby Gas Treatment System and Control Room High Efficiency

Air Filtration System

Final Safety Analysis Report, Section 5.3, Secondary Containment System

Final Safety Analysis Report, 7.18, Reactor Building Isolation and Control System

Procedure 8.7.6.2, 34, SGTS Single Train Operability Test

CR-PNP-2010-2789, Post Maintenance not in accordance with Temporary Modification

Requirements

CR-PNP-2010-3073, Coil Mechanism for lockout relay 186 failed to unlatch with a trip Signal

Present

LCO Maintenance Planning Checklist

WO 52219838, Task 1, F15 Switchyard Ground Grid Visual Inspection

Attachment

A-6

WO 52202875, Tasks 1 & 2, Cal & Functional of Breaker 152-801

Procedure 3.M.3-29.1, Revision 7, A8 Bus 4kV Protective Relay Calibration and Functional

Testing

WO 52202876, Task 1, Cal & Functional Test of Breaker 152-802

WO 52220914, Task 1, Shutdown Transformer to A5 & A6 Tie Relays

WO 00~09609, Task 1, Repair Pull Box 1A

..

WO 00164156. Task 1, Replace the SOT Hot Spot Indicator Heater

Section 1 R22

Procedure 8.3.2, Revision 54, Control Rod Exercise

CR-PNP-2010-2389, Procedure is unclear in indication for verifying a coupling check

Procedure 8.5.4.1, Revision 105, HPCI System Pump and

Biennial Comprehensive Operability

WO 52261114, Task 1, Perform 8.5.4.1, P-205 HPCI Operability and Flow Rate Test at 100 psig

WO 52263889 01, Manually start and load Blackout Diesel Generator

Procedures 8.9.16.1, Revision 41, Manually start and load Blackout Diesel via the Shutdown

transformer

CR-PNP-2010-3073, Station Blackout Lockout Relay did not unlatch with a trip signal present

CR-PNP-2010-2253, Hot Water that flashed to a steamy-water mix present when keepfill check

was performed

Procedure 8.5.2.15, Attachment 3, Revision 17, LPCI System and Core Spray System keepfill

c'1ecks

Operabi/it~ Evaluations for CR-PNP-2009-3312 and CR-PNP-2009-3348

\\

Drywell Leakage 7-day Rolling Average Chart

Drywell Leakage Data Sheets

Procedure 2.1.5, Revision 204, Daily Surveillance Log

Daily Log Test #48, Log the Drywell Leakage (flow integrators) on Panel C20

Section 1EP6

NEI 99-02, Revision 6, Regulatory Assessment Performance Indicator Guideline

EN-EP-201, Revision 10, Performance Indicators

EP Performance Indicator Reporting and Information Form dated July 26,2010

Section 2RS06

Procedures:

7.1.132

Obtaining Liquid Samples, Revision 13

7.3.25

Particulate and Iodine Monitoring at the Main Stack and Reactor Building,

Revision 42

7.3.31

Tritium Sampling, Revision 22

7.3.37

Noble Gas Effluent Sampling, Revision 35

7.3.48

Airborne Effluent Monitoring of the Turbine Deck and Reactor Feed Pump Bay,

Revision 17

7.9.12

Liquid Effluent Releases with RETDAS, Revision 5

Attachment

A-7

Condition Reports:

CR-PNP-2008-01858

CR-PNP-2008-04014

CR*PNP-2009-03662

CR-PNP-2008-03074

CR-PNP-2009-01388

CR-PNP*2009-04660

CR-PNP-2008-03636

CR-PNP-2009*02951

CR-PNP-2010-00321

CR-PNP-2008-03991

CR-PNP-2009-03353

Audits and Assessments:

QA-02/06-2009-PNP-01,

Combined Chemistry, Effluents, and Environmental Monitoring,

September 16, 2009

Ventilation Surveillances

WO 51656607'A' CREFS

August 6, 2008

WO 51677838'8' CREFS

September 24, 2008

WO 51677839'8' S8GT

September 23, 2008

Release Permits

Liquid

2010001

'A'TWT

April 2. 2010

2010005

'8'TWT

April 6, 2010

Section 40A1

MSPI Data Sheets from 3mQuarter 2009 to 2nd Quarter 2010 for HPCIIRCIC

Control Room Logs

HPCIIRCIC Unavailability Data Spread Sheets

NEI 99-02. Revision 6. Regulatory Assessment Performance Indicator Guideline

Licensee Event Reports

NRC Inspection Reports

RHR System Health Report

NRC Performance Indicator Technique/Data Sheets for 3rd Quarter 2009 through 2nd quarter 2010

Section 40A2

Compensatory Actions and Disabled Annunciator Logs

Pilgrim Operator Workarounds Aggregate Impact Report

Pilgrim Operator Compensatory Measures Report

Section 40A3

Reactor Plant Event Notification 46206, Release of Hydrogen Gas to Environment and

Notification to the State of Massachusetts

Procedure 1.3.22, Revision 19, Oil Spill Prevention, Control and CounterMeasure Plan

EP-AD-600, Revision 15, Emergency Action Level Basis Document

NUREG 0654, Appendix 1, Emergency Action Level Guidelines for Nuclear Power Plants

Generator Auxiliaries Reference Text

Power Maneuver Plan

Attachment

A-8

Procedure 2.1.14, Revision 102, Station Power Changes

Procedure 2.2.94,5, Revision 5, Main Condenser Backwash

Section 40A5

Procedures

.

..

EN-CY-109

Sampling and Analysis of Groundwater Monitoring Wells, Revision 2

EN-CY-111

Radiological Groundwater Monitoring Program, Revision 0

Condition Reports

CR-HQN-2008-01055

CR-PNP-2009-00879

CR-PNP-2010-02075

CR-PNP-2007 -04048

CR-PNP-2009-03635

CR-PNP-2010-02316

CR-PNP-2008-00911

CR-PNP-2010-00256

CR-PNP-2008-02276

CR-PNP-20 10-00825

\\

\\

Attachment

A-9

LIST OF ACRONYMS

ARERR

Annual Radiological Effluent Release Report

ALARA

As Low As Reasonably Achievable

ADAMS

Agencywide Documents Access and Management System

CFR

CR

Code of Federal Regulations

Condition Report

..

..

DRP

Division of Reactor Projects

DRS

Division of Reactor Safety

EDG

Emergency Diesel Generator

GPI

Groundwater Protection Initiative

HPCI

High Pressure Coolant Injection

HX

Heat Exchanger

IMC

Inspection Manual Chapter

NCV

Non-Cited Violation

NEI

Nuclear Energy Institute

NRC

Nuclear Regulatory Commission

ODCM

Offsite Dose Calculation Manual

PARS

Publicly Available Records

PI

Performance Indicator

PNPS

Pilgrim Nuclear Power Station

RBCCW

Reactor Building Closed Cooling Water

RCIC

Reactor Core Isolation Cooling

RPS

REMP

Reactor Protection System

Radiological Environmental Monitoring Program

t

SBGT

Standby Gas Treatment

SBO

Station Blackout

SSC

Structure, System or Component

SSW

Salt Service Water

TWT

Treated Water Tank

UFSAR

Updated Final Safety Analysis Report

WO

Work Order

Attachment