ML101180320
| ML101180320 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 01/26/2010 |
| From: | Robert Carrion NRC/RGN-II/DRS/EB3 |
| To: | Lake L NRC/RGN-II/DRS/EB3 |
| References | |
| FOIA/PA-2010-0116 | |
| Download: ML101180320 (1) | |
Text
Carrion, Robert From:
Sent:
To:
Subject:
Carrion, Robert C0 Tuesday, January 26, 2010 10:12 AM Lake, Louis RE: Recent High Level Schedule Info Thanks, Lou.
Bob From: Lake, Louis Sent: Tuesday, January 26, 2010 10:06 AM To: Dan naus; Masters, Anthony; Carrion, Robert; Thomas, George Cc: Franke, Mark
Subject:
Recent High Level Schedule Info FYI As you may know, recent schedule info was presented to the FL PSC indicates that CR3 is scheduled to be on line in mid 2010. I will be getting additional schedule info when on site tomorrow and will keep you informed, however, I have been given the following which is unofficial and distribution is non-public.
0 S
0 0
0 0
Relief Cut(I Cut) Complete -
Tension Detensioning Complete -
Delamination Removal Complete Concrete Repair Complete -
Tendon Retensioning Complete -
Post Repair Testing Complete -
Plant Restart -
January 20 (Complete)
March 8 March 23 May 9 June 9 June 17 June 22 Lou