Tennessee Valley Authority, Post Office Box 2000, Spring City, TN 37381-2000 September 8, 2009 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop: OWFN P1-35 Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ON PROGRAMS FOR LICENSING BASIS PRESERVATION AND CONSTRUCTION REFURBISHMENT (TAC NO. MD6581)
- 1. NRC Letter dated April 28, 2009, "Watts Bar Nuclear Plant, Unit 2 - Request for Additional Information on Programs for Licensing Basis Preservation and Construction Refurbishment (TAC NO. MD6581)
Reference:
This responds to a request for additional information (RAI) (Reference 1) regarding details of the process steps used in the Unit 2 Licensing Basis Preservation Program. Enclosure 1 provides excerpts from Procedure 25402-3DP-GO4G-00081, Revision 002, "Engineering Document Construction Release," which address how each Unit 2 design change is evaluated for licensing basis impact.
In Reference 1, NRC also requested information regarding equipment refurbishment. This information was provided in TVA's letter to NRC dated July 8, 2009, 'Watts Bar Nuclear Plant (WBN) Unit 2 - Response to Request for Additional Information on Program for Construction Refurbishment (TAC NO. MD6581)."
Printed on recycled paper Tennessee Valley Authority, Post Office Box 2000, Spring City, TN 37381-2000 September 8, 2009 u.S. Nuclear Regulatory Commission AnN: Document Control Desk Mail Stop: OWFN P1-35 Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ON PROGRAMS FOR LICENSING BASIS PRESERVATION AND CONSTRUCTION REFURBISHMENT (TAC NO. MD6581)
Reference:
- 1. NRC Letter dated April 28, 2009, "Watts Bar Nuclear Plant, Unit 2 - Request for Additional Information on Programs for Licensing Basis Preservation and Construction Refurbishment(TAC NO. MD6581)
This responds to a request for additional information (RAI) (Reference 1) regarding details of the process steps used in the Unit 2 Licensing Basis Preservation Program. Enclosure 1 provides excerpts from Procedure 25402-3DP-G04G-00081, Revision 002, "Engineering Document Construction Release," which address how each Unit 2 design change is evaluated for licensing basis impact.
In Reference 1, NRC also requested information regarding equipment refurbishment. This information was provided in TVA's letter to NRC dated July 8,2009, 'Watts Bar Nuclear Plant (WBN) Unit 2 - Response to Request for Additional Information on Program for Construction Refurbishment (TAC NO. MD6581)."
Printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 September 8, 2009 In addition, NRC suggested that a public meeting be held to discuss topics raised in Reference 1. Accordingly, a public meeting was held on August 6, 2009.
If you have any questions, please contact me at (423) 365-2351.
Sincerely, Masoud Br)eani Watts Bar U it 2 Vice President
Enclosure:
- 1. Procedure 25402-3DP-GO4G-00081, Revision 002, "Engineering Document Construction Release" cc (Enclosure):
U. S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381 u.s. Nuclear Regulatory Commission Page 2 September 8, 2009 In addition, NRC suggested that a public meeting be held to discuss topics raised in Reference 1. Accordingly, a public meeting was held on August 6, 2009.
If you have any questions, please contact me at (423) 365-2351.
Sincerely, f1. 73~
.. ".wr-~
. Masoud B ~ani Watts Bar; U it 2 Vice President
Enclosure:
cc (Enclosure):
- 1. Procedure 25402-3DP-G04G-00081, Revision 002, "Engineering Document Construction Release" U. S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
ENCLOSURE I Procedure 25402-3DP-GO4G-00081, Revision 002, "Engineering Document Construction Release" to ENCLOSURE 1 Procedure 25402-3DP-G04G-00081, Revision 002, "Engineering Document Construction Release"