ML090480471
Letter Sequence Meeting | |
|---|---|
TAC:MD6311, Clarify Application of Setpoint Methodology for LSSS Functions, Control Room Habitability, Steam Generator Tube Integrity (Approved, Closed) | |
Initiation
Questions Answers Results Other: CNL-14-154, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 12 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 12, CNL-15-137, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 13 (TAC No. MD6311) and Status of Generic Communications for Unit 2 - Revision 13, ML080860026, ML080860040, ML081700293, ML082410088, ML083460177, ML090480486, ML101200204, ML101260469, ML101600477, ML101680561, ML102170077, ML103010299, ML11213A130, ML11362A056, ML12234A688, ML13023A315, ML13213A194 | |
MONTHYEARML0728203072007-10-11011 October 2007
[Table View]Electronic Distribtion Initiative Letter, Licensee List, Electronic Distribution Input Information, Division Plant Mailing Lists Project stage: Request ML0732401242007-11-26026 November 2007 Summary of Meeting with Tennessee Valley Authority on Use of Eagle 21 at Watts Bar Unit 2 Project stage: Meeting ML0734400222007-12-0505 December 2007 Westinghouse Eagle - 21 Process Protection System Project stage: Request ML0735209712008-01-0303 January 2008 Summary of Meeting with Tennessee Valley Authority on Reconstitution of the Licensing Basis for Watts Bar, Unit 2 Project stage: Meeting ML0801705432008-01-0303 January 2008 Summary of December 12, 2007, Meeting with Tennessee Valley Authority on Reconstruction of the Licensing Basis for Watts Bar Unit 2 Project stage: Meeting ML0733300822008-02-15015 February 2008 IMC 2517, Watts Bar Unit 2 Construction Inspection Program Project stage: Request ML0807702372008-03-13013 March 2008 Regulatory Framework for the Completion of Construction and Licensing Activities for Unit 2 - Restructured Tables Project stage: Request ML0812105062008-05-0707 May 2008 Request for Additional Information Regarding Eagle-21 Process Protection System (Tac No. MD6311) Project stage: RAI ML0808600262008-05-0808 May 2008 Assessment of Remaining Operating License Application Review Scope Project stage: Other ML0808600402008-05-0808 May 2008 Enclosure 1- Watts Bar Nuclear Plant, Unit 2 - Assessment of Remaining Operating License Application Review Scope Project stage: Other ML0810101162008-05-0808 May 2008 Review Topics for Safety Evaluation, Attachment 1 Project stage: Approval ML0814300282008-05-14014 May 2008 Transmittal of Annual Radiological Environmental Operating Report of 2007 Project stage: Request ML0817002932008-06-16016 June 2008 Response to Additional Information Request on Regulatory Framework for the Completion of Construction and Licensing, Revision 1 Project stage: Other ML0818504602008-07-0202 July 2008 Final Supplemental Environmental Impact Statement - Request for Additional Information Project stage: Supplement ML0824100882008-08-25025 August 2008 Westinghouse Eagle-21 Process Protection System Project stage: Other ML0834601772008-12-0909 December 2008 Unit 2 - Licensing Basis Preservation and Construction Refurbishment Program for Structures, Systems and Components (Sscs) Project stage: Other ML0904804862009-02-23023 February 2009 TVA December 11, 2008 - Public MtgR1 Project stage: Other ML0904804712009-02-23023 February 2009 Region II - December 2008 Public Meeting with Notes Project stage: Meeting ML0904804662009-02-23023 February 2009 NRR - Public Meeting WBN2 Status 12-11-08 Project stage: Meeting ML0904804362009-02-23023 February 2009 Summary of December 11, 2008, Meeting with Tennessee Valley Authority on Status of Construction and Licensing Activities Project stage: Meeting ML1012002042010-04-20020 April 2010 Preservice Inspection Program Plan and Additional Information Project stage: Other ML1012604692010-04-29029 April 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 2, and Status of Generic Communications for Unit 2 - Revision 2 Project stage: Other ML1016004772010-06-0303 June 2010 Final Safety Analysis Report (FSAR) - Response to Preliminary Requests for Additional Information Project stage: Other ML1015903722010-06-0303 June 2010 Information Regarding Buried Piping/Cable Project stage: Request ML1016805612010-06-17017 June 2010 Preservice Inspection Program Plan and Additional Information Project stage: Other ML1020404842010-06-30030 June 2010 Enclosure 5, WNA-DS-01617-WBT-NP, Rev. 1, Rras Watts Bar 2 NSSS Completion Program I&C Projects, Post Accident Monitoring System - System Requirements Specification Project stage: Request ML1020404822010-06-30030 June 2010 WNA-DS-01667-WBT-NP, Rev. 1, Rras Watts Bar 2 NSSS Completion Program I&C Projects, Post Accident Monitoring System - Design Specification Project stage: Request ML1021700772010-07-30030 July 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 3, and Status of Generic Communications for Unit 2 - Revision 3 Project stage: Other ML1022403822010-08-11011 August 2010 NRC August 3-4, 2010 Instrumentation and Controls Meeting - Request for Additional Information Project stage: Meeting ML1022900752010-08-16016 August 2010 Unit 2 - Change to Developmental TS Section 4.2.2, Control Rod Assemblies Project stage: Request ML1022801282010-08-16016 August 2010 OL - FW: 7-30-10_GL 95-07 RAI Response to NRC Project stage: Request ML1027404372010-10-12012 October 2010 Notice of Forthcoming Meeting with Tennessee Valley Authority (TVA) to Discuss Responses to the NRC Requests for Additional Information (Rais) for General Letter 2004-02 Project stage: RAI ML1030102992010-10-28028 October 2010 – Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 4, and Status of Generic Communications for Unit 2 - Revision 4 Project stage: Other ML1032100192010-10-31031 October 2010 Nuclear Automation Watts Bar 2 NSSS Completion Program I&C Projects, Failure Modes and Effects Analysis (FMEA) for the Post Accident Monitoring System (Nonproprietary), WNA-AR-001 80-WBT-NP, Revision 0, Dated October 2010. Attachment 2 Project stage: Request ML1031403142010-11-0101 November 2010 OL - TVA Letter to NRC_10-29-10_WBN U2 FSAR 101 Project stage: Request ML1032001462010-11-0909 November 2010 Final Safety Analysis Report (FSAR) - Response to Requests for Additional Information Project stage: Response to RAI ML1032106442010-11-17017 November 2010 Revision of Commitment for Implementation of the Maintenance Rule Project stage: Request ML1106910592010-12-16016 December 2010 Request for Comments Project stage: Request ML1035405602010-12-17017 December 2010 Safety Evaluation Report Supplement 22 (SSER22) - Response to Requests for Additional Information Project stage: Supplement ML1106806302011-01-12012 January 2011 OL - FW: RAI 15.5-1 Response Needed to Complete Draft SE Project stage: Request ML1104504952011-02-10010 February 2011 Submittal of Pre-op Test Instructions Project stage: Request ML1106806242011-02-11011 February 2011 OL - FW: Updated OI List Project stage: Request ML1106806252011-02-11011 February 2011 OL - NRC I&C RAI Metrics Project stage: Request ML1104702722011-02-11011 February 2011 Final Safety Analysis Report (FSAR) - Response to Requests for Additional Information Project stage: Response to RAI ML1104202282011-02-11011 February 2011 Notice of Meeting with Tennessee Valley Authority to Discuss Watts Bar Nuclear Plant, Unit 2, Final Safety Analysis Report Related to Section 7 Instrumentation and Control Project stage: Request ML1106806262011-02-15015 February 2011 OL - FW: 20110211 Open Item List Master TVA Update 02-14-11.docx Project stage: Request ML1104904372011-02-16016 February 2011 Submittal of Pre-op Test Instructions Project stage: Request ML1104905702011-02-16016 February 2011 Supplemental Information for Review of Developmental Revision a of the Unit 2 Technical Specifications (TS) and Technical Specifications Bases (TS Bases) Project stage: Request ML1106806532011-02-16016 February 2011 OL - TVA Letter to NRC_02-16-11_TS-TS Bases Supplemental Info Project stage: Request ML1106806522011-02-16016 February 2011 OL - 02-16-11_2-PTI-063-05-A & 2-PTI-063-05-B Transmittal to NRC Project stage: Request 2010-11-01 |
| ML090480471 | |
| Person / Time | |
|---|---|
| Site: | Watts Bar |
| Issue date: | 02/23/2009 |
| From: | Watts Bar Special Projects Branch |
| To: | |
| Milano P, NRR/DORL, 415-1457 | |
| Shared Package | |
| ML090480388 | List: |
| References | |
| TAC MD6311 | |
| Download: ML090480471 (6) | |
Similar Documents at Watts Bar | |
|---|---|
Text
1 Watts Bar 2 Inspection Program December 11, 2008
2 Region II Construction Inspection Program Division of Construction Inspection Division Of Construction Projects Construction Inspection Branches Construction Projects Branch 3 Senior Project Inspector Project Inspector Senior Resident Inspector Resident Inspectors Specialist Inspectors Construction Inspection Organization
Construction Phase IMC 2512 Startup Testing IMC 2514 NRC Construction Inspection Program Preop Testing
& Operational Prep IMC 2513
4 Inspection Program Elements Inspection Program Generic Communications Previously Completed inspections New Or re-work CAPs/SPs Licensing issues Allegations Historical Open items (VIO,NCV,IFI..)
5 Inspection and Assessment Assessments (Quarterly, Mid Cycle,
End Of Cycle)
Assessments (Quarterly, Mid Cycle,
End Of Cycle)
Inspection Program Results Annual Public Meeting Quarterly Integrated Reports Construction Readiness Inspection
6 3/4 Backup Slides