Letter Sequence Other |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: ML070370281, ML073100027, ML073510180, ML080360067, ML080430700, ML080500171, ML080530256, ML081010450, ML081010451, ML081120502, ML081700294, ML081720078, ML081760295, ML082040065, ML082050462, ML082100425, ML082810470, ML083120308, ML083240224, ML083250083, ML090130718, ML090340528, ML090720951, ML090760630, ML091320366, ML092020345, ML092430520, ML092440518, ML092460495, ML092460496, ML092460497, ML092460498, ML092460500, ML092540483, ML092680057, ML12319A076, ML13044A498
|
MONTHYEARML0631104352006-11-0707 November 2006 Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes Project stage: Request 05000260/LER-2007-001, Re Automatic Turbine Trip and Reactor Scram Due to Equipment Failure During Performance of the Main Generator Rheostat Test2007-03-0202 March 2007 Re Automatic Turbine Trip and Reactor Scram Due to Equipment Failure During Performance of the Main Generator Rheostat Test Project stage: Request ML0711300782007-04-18018 April 2007 Units 1, 2, & 3 - Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Supplemental Response to Requests for Additional Information (RAI) Project stage: Supplement ML0711503662007-04-24024 April 2007 Units 1, 2, & 3 - Fire Protection Program - Post-Fire Operator Manual Actions Project stage: Request ML0711503712007-04-24024 April 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Steam Dryer Evaluations Project stage: Request ML0712905652007-05-16016 May 2007 Withholding Information from Public Disclosure, Response to Nuclear Regulatory Commission (NRC) Request for Additional Information - Round 12 for Browns Ferry EPU: Supplemental to SBWB-64 Project stage: RAI ML0716303492007-06-15015 June 2007 Meeting with the Tennessee Valley Authority Concerning the Status of Browns Ferry Nuclear Plant, Units 1, 2 and 3, Steam Dryer Review Project stage: Meeting ML0718700242007-07-0303 July 2007 Technical Specifications (TS) Change TS-461 - Modification of Restart Large Transient Testing License Condition 2. (G) 2 - Supplement 1 Project stage: Request ML0717801902007-07-0505 July 2007 Request for Additional Information for Extended Power Uprate - Round 13 (TS-431 and TS-418 Project stage: RAI ML0719004762007-07-10010 July 2007 Meeting with the Tennessee Valley Authority (TVA) Concerning the Pending ACRS Meeting on the Browns Ferry Extended Power Uprate Project stage: Meeting ML0721501562007-07-18018 July 2007 Slides from Meeting with Tennessee Valley Authority on the Browns Ferry Power Uprate ACRS Presentation Project stage: Meeting ML0721303712007-07-27027 July 2007 Technical Specifications Changes TS-431 and TS-418, Extended Power Uprate - Steam Dryer Evaluations Project stage: Request ML0721303752007-07-31031 July 2007 CDI Report No. 07-05NP, Revision 0, Finite Element Model for Stress Assessment of Browns Ferry, Unit 1, Steam Dryer to 250 Hz Project stage: Request ML0721400442007-08-0808 August 2007 Summary of Meeting with Tennessee Valley Authority on the Browns Ferry Power Uprate ACRS Presentation Project stage: Meeting 05000259/LER-2007-005, Regarding Automatic Reactor Scram Due to Turbine Trip as a Result of Invalid High Level in Moisture Separator Drain Tank2007-08-0808 August 2007 Regarding Automatic Reactor Scram Due to Turbine Trip as a Result of Invalid High Level in Moisture Separator Drain Tank Project stage: Request ML0723602572007-08-21021 August 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Steam Dryer Limit Curves Project stage: Request ML0724805472007-08-31031 August 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 13 Request for Additional Information (RAI) - Containment Overpressure Project stage: Request ML0727606602007-10-0909 October 2007 Request for Additional Information for Extended Power Uprate - Round 14 (TS-418) Project stage: RAI ML0728902372007-10-18018 October 2007 Request for Withholding Information from Public Disclosure Concerning Round 13 Request for Additional Information for Browns Ferry Nuclear Plant (Tac Nos. MD5262, MD5263 and MD5264) Project stage: RAI ML0729603112007-10-22022 October 2007 Technical Specification (TS) Changes TS-431 & TS-418, Extended Power Uprate - EPU Large Transient Testing Project stage: Request ML0731000272007-11-0909 November 2007 Request for Schedule Regarding Analysis for Steam Dryers on Extended Power Uprate Amendment Requests (TAC Nos. MD5262, MD5263, and MD5264) (TS-431 and TS-418-S) Project stage: Other ML0732303482007-11-15015 November 2007 Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 13 Request for Additional Information (RAI) - Containment Overpressure APLA-35/37 Project stage: Request ML0733304832007-11-21021 November 2007 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Preliminary Findings on Steam Dryer Stress Analysis Project stage: Request 05000296/LER-2007-003, Leak in an ASME Class I Code Reactor Pressure Boundary Pipe2007-11-21021 November 2007 Leak in an ASME Class I Code Reactor Pressure Boundary Pipe Project stage: Request ML0735101802007-12-14014 December 2007 Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Schedule Regarding Analysis for Steam Dryers Project stage: Other ML0734607572007-12-19019 December 2007 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant (Tac No. MD5262, MD5263 and MD5264) Project stage: Withholding Request Acceptance ML0735400102008-01-25025 January 2008 Summary of Meeting with Tennessee Valley Authority on Steam Dryer Portion of the Extended Power Uprate Review (TAC Nos. MD5262, MD5263, and MD5264), Browns Ferry Units 1, 2, and 3 Project stage: Meeting ML0801504182008-01-25025 January 2008 (Public Version) - Summary of December 10, 2007 Meeting with TVA on Steam Dryer Portion of the Extended Power Uprate Review Project stage: Meeting ML0803205212008-01-25025 January 2008 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) Response to Round 15 Request for Additional Information (RAI) - APLA-38/40, SRXB-71, and SRXB-72 Project stage: Request ML0803600672008-01-25025 January 2008 Steam Dryer RAI 15 Status, Slides Project stage: Other ML0802501652008-01-30030 January 2008 Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear Plant (Tac Nos. MD5262, MD5263, and MD5264) Project stage: Withholding Request Acceptance ML0803805602008-01-31031 January 2008 Technical Specifications (TS) Change TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 15 Request for Additional Information (RAI) Regarding Steam Dryer Analyses Project stage: Request ML0804307002008-02-11011 February 2008 Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Schedule Regarding EPU Project stage: Other ML0804304462008-02-11011 February 2008 Notification of Potential Part 21 Report Power Supply Unit Is Limited at Elevated Temperatures Project stage: Request ML0803503812008-02-14014 February 2008 Summary of Meeting with Tennessee Valley Authority - on Extended Power Uprate Review Project stage: Meeting ML0806501012008-02-21021 February 2008 Response to Round 16 Request for Additional Information SRXB-73 Project stage: Request ML0805302562008-02-21021 February 2008 Unit 1 - Technical Specifications (TS) Change TS-431 - Extended Power Uprate (EPU) - Fuels Methods Commitments Project stage: Other ML0804506472008-02-27027 February 2008 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0803506982008-02-29029 February 2008 Request for Additional Information for Extended Power Uprate - Round 16 (TS-431 and TS-418) (TACs MD5262, MD5263, MD5264) Project stage: RAI ML0807104982008-03-0606 March 2008 (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Change TS-418 and TS-431 - Extended Power Uprate (EPU) - Response to Round 16 Request for Additional Information (RAI) - SRXB-74/86 and SRXB-87 Through SRXB-90 Project stage: Request ML0811205102008-03-20020 March 2008 Summary of March 20, 2008, Meeting with Tennessee Valley Authority Regarding Steam Dryer Portion of the Extended Power Uprate Review (TAC Nos. MD5262, MD5263, and MD5264) - Slides Project stage: Meeting ML0810104502008-04-0404 April 2008 (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 15 and Round 16 Requests for Additional Information (RAI) Regarding Steam Dryer Analyses Project stage: Other ML0810104512008-04-0404 April 2008 Technical Specifications (TS) Changes TS-431 and TS-418 Extended Power Uprate (EPU) BFN Steam Monitoring Plan Project stage: Other ML0817602952008-04-0909 April 2008 Units 1, 2, & 3 - Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Confirmation of Commitment Completions Project stage: Other ML0811205022008-04-16016 April 2008 CDI Incoming Letter Dated April 16, 2008 Regarding NRC Presentation Entitled, Tennessee Valley Authority Browns Ferry Nuclear Plant - Extended Power Uprate Steam Dryers Project stage: Other ML0811302312008-04-17017 April 2008 Public Slides - Summary of April 17, 2008, Meeting Regarding Steam Dryer Portion of the Extended Power Uprate Review, Project stage: Meeting ML0811200332008-04-30030 April 2008 Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Withholding Information from Public Disclosure for Round 15 Fuels Responses Project stage: Withholding Request Acceptance ML0812806272008-05-0101 May 2008 Technical Specifications Change TS-418, Extended Power Uprate Supplemental Response to Round 16 Request for Additional Information - SRXB-87 & SRXB-89 Project stage: Supplement ML0812804712008-05-0202 May 2008 Request for Additional Information for Extended Power Uprate - Round 17 Project stage: RAI ML0805001712008-05-0202 May 2008 Schedule Regarding Analysis for Steam Dryers on Extended Power Uprate Amendment Requests (TAC Nos. MD5262, MD5263, and MD5264) (TS-431 and TS-418) Project stage: Other 2007-07-05
[Table View] |
Text
April 9, 2008 TVA-BFN-TS-418 TVA-BFN-TS-431 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Mail Stop OWFN, P1-35 Washington, D.
C.
20555-0001 Gentlemen:
In the Matter of
)
Docket Nos.
50-259 Tennessee Valley Authority
)
50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN)
UNITS 1, 2, AND 3
TECHNICAL SPECIFICATIONS (TS)
CHANGES TS-431 AND TS-418 -
EXTENDED POWER UPRATE (EPU)
CONFIRMATION OF COMMITMENT COMPLETIONS (TAC NOS.
- MD5262, MD5263 AND MD5264)
By letters dated June 28, 2004 and June 25, 2004 (ADAMS Accession Nos.
ML041840109 and ML041840301),
TVA submitted license amendment applications for EPU operation at 3952 Megawatts Thermal (MWt) for BFN Unit 1, and BFN Units 2 and 3,
respectively.
On September 22,
- 2006, TVA submitted a supplemental TS-431 change request (ML062680459),
which revised the original June 28,
- 2004, Unit 1 EPU application to request approval of a 5 percent increase in thermal power over the original licensed thermal power (i.e.,
an increase from 3293 MWt to 3458 MWt).
The September 22,
- 2006, supplemental TS-431 request was approved by NRC on March 6, 2007 (ML063350404).
With this
- change, all three BFN units are currently licensed for power operation at 3458 MWt.
U.S. Nuclear Regulatory Commission Page 2 April 9, 2008 Section 4.0, Regulatory Commitments, of NRC's March 6,
- 2007, Safety Evaluation (SE) for the Unit 1 TS-431 supplement listed several commitments that were shown as open at the time the SE was issued.
NRC recently requested that TVA provide the status of these commitments to assist in the staff review of the pending full EPU license applications.
The completion status of these commitments is provided below.
Commitment As discussed in Section 2.2.4 <of this SE>,
the licensee stated that the MOV switch settings at Unit 1would be set prior to restart, but that some dynamic testing would be conducted during power ascension.
TVA also indicated its commitment to implement the Joint-Owners' Group Program on MOV periodic verification as part of its response to GL 96-05.
Status TVA's May 12,
- 2007, submittal (ML071340090) documented the completion of the NRC Bulletins, Generic Letters (GL),
Nuclear Performance Plan Special Programs, and TMI Action Items required for Unit 1 restart as defined in the TVA and NRC regulatory framework letters.
In the May 12,
- 2007, TVA submittal, GL 96-05, "Generic Letter 96-05: Periodic Verification of Design-Basis Capability Of Safety-Related Motor-Operated Valves" and GL 89-10, "Safety-Related Motor-Operated Valve Testing and Surveillance" were documented as complete except for the testing of several valves that required nuclear steam/pressure for the completion of testing.
This commitment completion included implementation of the GL 96-05 Joint Owners' Group Program on MOV periodic verification.
NRC closed GL 96-05 in Unit 1 Recovery Inspection Report 2005-009, dated February 13, 2006 (ML060440586) and closed GL 89-10 in Unit i Recovery Inspection Report 2006-009, dated March 5, 2007 (ML070640353).
The testing activity (for the several valves that required nuclear steam/pressure) was documented in of the May 12,
- 2007, TVA submittal as a commitment, was
U.S. Nuclear Regulatory Commission Page 3 April 9, 2008 tracked by TVA's commitment management program, and was completed during Unit 1 restart testing.
Commitment As discussed in Section 2.5.3.1 <of this SE>,
the licensee has established a regulatory commitment to implement procedure changes that will:
(1) define and control the generation of cycle-specific fuel pool heat load calculations, and (2) control the installation of the fuel pool gates based on the calculated fuel pool heat load.
Status This commitment is open and being tracked in TVA's commitment management program as required for completion prior to EPU operation.
Commitment As discussed in Section 2.6.5 <of this SE>,
the licensee has committed to terminate drywell cooling within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of entry into the safe shutdown procedure which would be used for a shutdown due to fire.
Status The BFN safe shutdown instructions (SSIs) were revised to include provisions to terminate drywell cooling within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of entry.
These SSIs are applicable to all three BFN units.
This commitment activity was tracked in accordance with TVA's commitment management program and was completed following revision of the SSIs.
Commitment As part of the two-step approach to EPU, TVA will perform two Large Transient Tests (LTTs):
- A large transient test that simulates the rejection of generator load will be completed within 30 days of reaching 105-percent Original Licensed Thermal Power (OLTP).
U.S. Nuclear Regulatory Commission Page 4 April 9, 2008 An MSIV Closure with valve position scram large transient test will be performed within 30 days of reaching 115 percent to 120-percent OLTP.
As discussed in Section 2.12 <of this SE>,
the NRC staff reviewed this commitment and did not agree with the power level proposed for the second LTT, therefore, a License Condition was established mandating performance at 105 percent.
Status As noted above, the original TVA commitment was modified by a Unit 1 License Condition 2.G(2),
which required performance of a Main Steam Isolation Valve (MSIV) closure test and a turbine generator load reject test during the power uprate power ascension test program and prior to exceeding 30 days of plant
- operation above a nominal 3293 MWt power level.
The full power MSIV closure transient test was performed on June 23, 2007, 'in accordance with License Condition 2.G(2).
The integrated plant.
response to the trip was as expected and the transient was uneventful.
TVA subsequently requested the deletion of the turbine generator load.reject test License Condition.
The License Condition deletion was approved by NRC on August 14, 2007 (ML072250619),
in the NRC letter
- titled, "Browns Ferry Nuclear Plant, Unit 1 Issuance of Amendment Regarding Deletion of License Condition 2.G. (2)
(TAC No.
MD5871)
(TS-461)."
Additionally, in a TVA submittal dated October 22, 2007 (ML072960311) regarding the BFN EPU test program, TVA made an NRC commitment to perform a turbine generator l6ad reject transient test from full EPU conditions within 60 days of operating at EPU power on Unit 1. The October 22,
- 2007, submittal also justified not performing additional MSIV LTTs on any BFN units.
U.S. Nuclear Regulatory Commission Page 5 April 9, 2008 Commitment As discussed in Section 2.12 <of this SER>,
TVA committed to trip a condensate booster pump, a condensate pump, and a main feedwater pump on an individual basis (i.e.,
one at a time).
The NRC staff reviewed this commitment and issued a license condition-mandating performance at 105 percent.
Status Full power condensate, condensate booster pump, and main feedpump trip tests were performed on June 23,
- 2007, as part of the Unit 1 restart test program.
The integrated plant response to these pump transients was as expected.
Commitment As discussed in Section 2.1.3.1 <of this SER>,
the NRC staff was concerned that any new components or material/environment combinations to be installed to support the restart that were not included in the License Renewal Application (LRA) should be identified and evaluated for aging management as part of this review rather than waiting for the annual update.
To resolve this concern, the licensee agreed to submit an update on the status of the modifications.
This letter was submitted on December 1, 2006.
Status In November 2006 TVA performed a preliminary review of the planned EPU modifications on Units 1, 2, and 3 with regard to inclusion in the Aging Management Review (AMR) program.
No additional components, materials, or environments were identified that would affect the AMR that was contained in the LRA.
The results of this review were reflected in Table 3 of the TVA submittal referenced above dated December 1, 2006 (ML063380029).
EPU modifications have now been completed for Units 1 and 2 with the exception of the TS-418 and TS-431 instrument setpoint changes, high pressure turbine modifications on
U.S. Nuclear Regulatory Commission Page 6 April 9, 2008 Unit 2, and modifications associated with steam dryer structural integrity (addition of steam line suppression devices).
Unit 3 has implemented a limited number of EPU modifications with the bulk of the modifications scheduled for installation in the Spring 2010 refueling outage.
The scope of EPU modifications was reviewed using the guidance of Regulatory Issue Summary 2007-16 to determine the current impact on the AMR Program.
With the exception of the steam line suppression devices, the scope of EPU modifications remains the same for which the December 1, 2006 review was performed.
These involve installation of new components designed for the life of the plant and outside the scope of the AMR program.
Therefore, the conclusions of Table 3 in the above referenced letter will remain valid through EPU implementation.
TVA has determined that the additional information provided by this letter does not affect the no significant hazards considerations associated with the proposed TS changes.
The proposed TS changes still qualify for a categorical exclusion from environmental review pursuant to the provisions of 10 CFR 51.22(c) (9).
If you have any questions regarding this
- letter, please contact me at (256)729-2636.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on this 9th day of April, 2008.
Sincerely, Original signed by D.
T.
Langley Manager of Licensing and Industry Affairs
U.S. Nuclear Regulatory Commission Page 7 April 9, 2008 cc: State Health Officer Alabama State Department of Public Health RSA Tower Administration Suite 1552 P.O.
Box 303017 Montgomery, Alabama 36130-3017 NRC Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road
- Athens, AL 35611-6970 Branch Chief U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 Eva Brown, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739
U.S. Nuclear Regulatory Commission Page 8 April 9, 2008 JEE:BCM:BAB CC:
G.
P. Arent, EQB lB-WBN W. R.
Campbell, Jr. LP 3R-C S.
M. Douglas, POB 2C-BFN R.
F.
- Marks, Jr.,
PAB 1C-BFN D.
C. Matherly, BFT 2A-BFN L.
E. Nicholson, BR 4X-C R.
G.
- West, NAB 2A-BFN B.
A.
- Wetzel, BR 4X-C S.
A. Vance, WT 6A-K E.
J.
Vigluicci, ET llA-K NSRB Support, LP 5M-C EDMS (with enclosures)
WT CA-K s:lic/submit/subs/EPU/Unit 1 105% SER Section 4 0 commitment status submittal April 8r2.doc