ML081370280

From kanterella
Jump to navigation Jump to search
Feb-Mar 05000259/2008301 Exam Draft SRO Written Exam (Part 2 of 2)
ML081370280
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 04/08/2008
From:
NRC/RGN-II
To:
Tennessee Valley Authority
References
50-259/08-301 50-259/08-301
Download: ML081370280 (107)


See also: IR 05000259/2008301

Text

REFERENCE PROVIDED: Unit-2 TRM Section 3.3.1

Plausibility Analysis:

(

In order to answer this question correctly, the candidate must determine the following:

1. Recognize that PIS 1-91A and 1-81A have failed in the conservative direction for the given plant

conditibns. (i.e; >30% power)

2. Based on Item 1 above, recognize that the TCVlSV Closure Scram capability is maintained as

long as power remains above 3QOk.

3. Recognize that an INFORMATION ONLY LCO is mandated to ensure these failures are addressed

when power is reduced below 30%.

4. Recognize that the Applicability NOTE for TRM 3.3.1 applies for the given plant conditions.

A is incorrect. The Applicability NOTE for TRM 3.3.1 applies for the given plant conditions, therefore

the requirement to place the channels in trip or restore them to OPERABLE status is NOT required. This

is plausible because the TCVlSV Closure Scram capability IS maintained and the actions in the

distractor closely resemble the required actions in the LCO.

B is correct.

C is incorrect. TCV/SV Closure Scram capability is maintained. This is plausible because the actions in

the distractor match the required actions in the LCO if the TCVlSV Closure Scram capability was NOT

maintained.

o is incorrect. TCVlSV Closure Scram capability is maintained. This is plausible because the actions in

the distractor match the required actions in the LCO if the TCVlSV Closure Scram capability was NOT

maintained.

(

Reactor Protection System Instrumentation

TR 3.3.1

TR 3.3

INSTRUMENTATION

(

TR 3.3.1

LCO 3.3.1

Reactor Protection System (RPS) Instrumentation

There shall be two OPERABLE or tripped trip systems with a

minimum of two OPERABLE instrument channels per trip system

for the Turbine First Stage Pressure Permissive. The pressure

switch allowable values shall be <154 psig.

APPLICABILITY:

~ 30% RTP (Turbine First Stage Pressure ~ 154 psig)


NOTE---------------------------

Required Actions shall be taken only if the permissive fails in such a manner to prevent

the affected RPS logic from performing its intended function. Otherwise, no action is

required.

ACTIONS

A.

CONDITION

One or more required

channels are

inoperable.

REQUIRED ACTION


NOTE----

Inoperable Turbine First Stage

Pressure Permissive channel(s)

or subsystem(s) may also affect

Technical Specifications LCO

3.3.1.1 and LCO 3.3.4.1.

COMPLETION TIME

A.1

Trip the inoperable

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />

channel(s) or entire trip

system(s).

OR

A.2.1

Initiate insertion of

OPERABLE rods.

AND

Immediately

A.2.2

Complete insertion of all

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

OPERABLE rods.

OR

(continued)

l

BFN-UNIT 2

3.3-1

TRM Revision 0, 12

August 17, 1999

Reactor Protection System Instrumentation

TR 3.3.1

(

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION TIME

A.

(continued)

A.3

Reduce power to less

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

than 30 percent of rated.


NOTE,----------------

A channel may be placed in an INOPERABLE status for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> for required

surveillance without placing the trip system in the tripped condition provided at least one

OPERABLE channel in the same trip system is monitoring that parameter.

TECHNICAL SURVEILLANCE REQUIREMENTS

TSR 3.3.1.1

TSR 3.3.1.2

BFN-UNIT 2

SURVEILLANCE

Perform CHANNEL FUNCTIONAL TEST.

Perform CHANNEL CALIBRATION.

3.3-2

FREQUENCY

92 days

24 months

TRM Revision 3, 12

August 17, 1999

TR 3.3

INSTRUMENTATION

(

TR 3.3.1

BASES

RPS Instrumentation

B 3.3.1

Reactor Protection System (RPS) Instrumentation

BACKGROUND

Fast closure of the TCVs results in the loss of a heat sink that

produces reactor pressure, neutron flux, and heat flux transients

that must be limited. Therefore, a reactor scram is initiated on TCV

fast closure in anticipation of the transients that would result from

the closure of these valves. The Turbine Control Valve Fast

Closure, Trip Oil Pressure -

Low Function is the primary scram

signal for the generator load rejection event without bypass valve

capability analyzed in the FSAR section 14.5. For this event, the

reactor scram reduces the amount of energy required to be

absorbed and, along with the ACTIONS of the EOC-RPT System,

ensures that the MCPR SL is not exceeded.

Turbine Control Valve Fast Closure, Trip Oil Pressure-Low

signals are initiated by the electrohydraulic control (EHC) fluid

pressure at each control valve. One pressure switch is associated

with each control valve, and the signal from each switch is

assigned to a separate RPS logic channel. This Function must be

enabled at THERMAL POWER ~ 30% RTP. This is normally

accomplished automatically by pressure transmitters sensing

turbine first stage pressure; therefore, opening the turbine bypass

valves may affect this function.

The Turbine Control Valve Fast Closure, Trip Oil Pressure-Low

Allowable Value is selected high enough to detect imminent TCV

fast closure.

Four channels of Turbine Control Valve Fast Closure, Trip Oil

Pressure -

Low Function with two channels in each trip system

arranged in a one-out-of-two logic are required to be OPERABLE

to ensure that no single instrument failure will preclude a scram

from this Function on a valid signal. This Function is required,

consistent with the analysis assumptions, whenever THERMAL

POWER is ~ 30% RTP. This Function is not required when

THERMAL POWER is < 30% RTP, since the Reactor Vessel

Steam Dome Pressure-High and the Average Power Range

Monitor Fixed Neutron Flux-High Functions are adequate to

maintain the necessary safety margins.

BFN-UNIT 2

B 3.3-1

~viSion o

(

BASES

BACKGROUND

(continued)

RPS Instrumentation

B3.3.1

Closure of the TSVs results in the loss of a heat sink that produces

reactor pressure, neutron flux, and heat flux transients that must be

limited. Therefore, a reactor scram is initiated at the start of TSV

closure in anticipation of the transients that would result from the

closure of these valves. The Turbine Stop Valve -

Closure

Function is the primary scram signal for the turbine trip event

analyzed in the FSAR section 14.5. For this event, the reactor

scram reduces the amount of energy required to be absorbed and,

along with the ACTIONS of the End of Cycle Recirculation Pump

Trip (EOC-RPT) System, ensures that the MCPR SL is not

exceeded.

Turbine Stop Valve-Closure signals are initiated from position

switches located on each of the four TSVs. Two independent

position switches are associated with each stop valve. One of the

two switches provides input to RPS trip system A; the other, to RPS

trip system B. Thus, each RPS trip system receives an input from

four Turbine Stop Valve-Closure channels, each consisting of

one position switch. The logic for the Turbine Stop Valve-

Closure Function is such that three or more TSVs must be closed

to produce a scram. This Function must be enabled at THERMAL

POWER ~ 30% ~TP. 1: .

's normally accomplished automati~

by.J~ressureJ!!nsmitters sensing turbine I

"Stage press~

f

t~.e-m

ct~fQre ,_oJ?enilliDtLe-tOrbln~ bypa~~!~ may a~~

un

Ion.

The Turbine Stop Valve-Closure Allowable Value is selected to

be high enough to detect imminent TSV closure, thereby reducing

the severity of the SUbsequent pressure transient.

Eight channels of Turbine Stop Valve-Closure Function, with four

channels in each trip system, are required to be OPERABLE to

ensure that no single instrument failure will preclude a scram from

this Function if any three TSVs should close. This Function is

required, consistent with analysis assumptions, whenever

THERMAL POWER is ~ 30% RTP. This Function is not required

when THERMAL POWER is < 30% RTP since the Reactor Vessel

Steam Dome Pressure-High and the Average Power Range

Monitor Fixed Neutron Flux- High Functions are adequate to

maintain the necessary safety margins.

BFN-UNIT 2

B 3.3-2

TRM Revision 0

(

RPS Instrumentation

B 3.3.1

BASES

APPLICABLE

This function must inhibit the automatic bypassing of turbine

SAFETY ANALYSIS

control valve fast closure or turbine trip scram and turbine stop

valve closure scram whenever turbine first stage pressure is

greater than or equal to 154 psig.

This in combination with the TSV's 10% closure limit switches and

the TCVs low trip oil pressure are required to prevent exceeding

the MCPR SL.

LCO 3.3.1

APPLICABI L1TY

TRM LCO 3.3.1 requires that the 30% RTP sensed by the turbine

first stage pressure either be OPERABLE or tripped. These

pressure switches function to bypass the Scram for the TSVs and

TCVs. The switches sense greater than 30% RTP when in the

conservative condition (Le., will function to cause a Scram on

closure of the TCV's and TSVs). For the Turbine First Stage

Pressure Permission, an instrument channel consists of the

pressure switch assigned to that channel. Pressure switches

PI5-1-81A and PIS-1-91A are assigned to trip system Band

pressur~)witchesPIS-1-81Band PIS-1-91 B are assigned to trip

system A.

If these switches are tripped, the failure is in the conservative

direction.

'--...

~

r----

This Scram is only needed above 30% RTP as indicated by

~ 154 psig Turbine First Stage Pressure since adequate margin to

MCPR SL is assured for any type of turbine trip, with or without

bypass valves.

BFN-UNIT2

B 3.3-3

vision 0

BASES

ACTIONS

TECHNICAL

SURVEILLANCE

REQUIREMENTS

RPS Instrumentation

B 3.3.1

A note is provided to indicate that Required Actions are to be taken

only if the permissive fails in such a manner to prevent the affected

RPS logic from performing its intended function. Otherwise, no

action is required since the RPS function is maintained.

One hour to trip the inoperable channel(s) or trip system(s) is

reasonable and consistent with conservative operation with

degraded safety functions. Since these pressure switches do not

cause a Scram by themselves, but rather in combination with the

TSV's or TCVs, the switches may be tripped without causing a half

Scram.

A.2.1 and A.2.2

Four hours to insert all OPERABLE control rods provides the same

end function as a Scram and is within conservative operating

considerations given the degraded safety function to maintain

MCPR SL.

Dropping below 30% RTP also provides for conservative operation

since any turbine trip below that power does not cause the MCPR

SL to be exceeded

TSR 3.3.1.1 and TSR 3.3.1.2

Functional test consists of the injection of a simulated signal into

the electronic trip circuitry in place of the sensor signal to verify

OPERABILITY of the trip and alarm functions.

Calibration consists of the adjustment of the primary sensor and

associated components so that they correspond within acceptable

range and accuracy to known values of the parameter which the

channel monitors, including adjustment of the electronic trip

circuitry, so that its output relay changes state at or more

conservatively than the analog equivalent of the trip level setting.

Surveillance requirement times are based on equipment reliability

and engineering judgment and conservatively set to provide

adequate assurance of safety function performance.

BFN-UNIT2

B 3.3-4

TRM Revision 0

BASES

REFERENCES

RPS Instrumentation

B 3.3.1

1.

BFN Technical Specifications (version prior to standardized

version)

2.

Section 14.5 of BFN FSAR

BFN-UNIT2

B 3.3-5

TRM Revision 0

}

E

MINATION

REFERENCE

( PROVIDED TO

CANDIDATE

Reactor Protection System Instrumentation

TR 3.3.1

TR 3.3

INSTRUMENTATION

(

TR 3.3.1

LCO 3.3.1

Reactor Protection System (RPS) Instrumentation

There shall be two OPERABLE or tripped trip systems with a

minimum of two OPERABLE instrument channels per trip system

for the Turbine First Stage Pressure Permissive. The pressure

switch allowable values shall be <154 psig.

APPLICABILITY:

~ 30% RTP (Turbine First Stage Pressure ~ 154 psig)


NOTE-------------------------------------------------------

Required Actions shall be taken only if the permissive fails in such a manner to prevent

the affected RPS logic from performing its intended function. Otherwise, no action is

required.

ACTIONS

A.

CONDITION

One or more required

channels are

inoperable.

REQUIRED ACTION


NOTE----

Inoperable Turbine First Stage

Pressure Permissive channel(s)

or subsystem(s) may also affect

Technical Specifications LCO

3.3.1.1 and LCO 3.3.4.1.

COMPLETION TIME

A.1

Trip the inoperable

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />

channel(s) or entire trip

system(s).

A.2.1

Initiate insertion of

OPERABLE rods.

Immediately

A.2.2

Complete insertion of all

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

OPERABLE rods.

(continued)

BFN-UNIT 2

3.3-1

TRM Revision Q, 12

August 17, 1999

Reactor Protection System Instrumentation

TR 3.3.1

(

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION TIME

A.

(continued)

A.3

Reduce power to less

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

than 30 percent of rated.

  • ---NOTE---

A channel may be placed in an INOPERABLE status for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> for required

surveillance without placing the trip system in the tripped condition provided at least one

OPERABLE channel in the same trip system is monitoring that parameter.


._- -

TECHNICAL SURVEILLANCE REQUIREMENTS

TSR 3.3.1.1

TSR 3.3.1.2

BFN-UNIT2

SURVEILLANCE

Perform CHANNEL FUNCTIONAL TEST.

Perform CHANNEL CALIBRATION.

3.3-2

FREQUENCY

92 days

24 months

TRM Revision 8, 12

August 17, 1999

(

(

16. SRO 268000A2 .01 00 lIe/A/TIG2/0PL171.084//268000A2.0l//SRO ONLY/12/18/2007 RMS

Given the following plant conditions:

BFN is in the process of discharging the Waste Sample Tank to the river in accordance with an

approved Discharge Permit.

With the discharge in progress, the Radwaste operator calls the control room and reports that

0-RR-90-130 (Radwaste Effluent Radiation Monitor) is now reading below the initial background

radiation level prior to commencing the discharge.

Which ONE of the following describes the required action(s), if any, and the potential cause of this

indication?

A.

The discharge may continue. This is an expected indication during a discharge of low activity water

processed by the Thermex System.

B. The discharge may continue.

Discharging water surrounding the detector is acting to shield it from

background radiation .

C. Have Radwaste terminate the discharge. Suspect 0-RR-90-130 has not been properly calibrated

prior to commencing the discharge.

D~ Have Radwaste terminate the discharge. Suspect 0-RR-90-130 was not suspended in water when

background radiation levels were initially recorded.

KIA Statement:

268000 Radwaste

A2.01 - Ability to (a) predict the impacts of the following on the RADWASTE ; and (b) based on those predictions,

use procedures to correct, control, or mitigate the consequences of those abnormal conditions or operations :

System rupture

KIA Justification: This question satisfies the KIA statement by requiring the candidate to demonstrate

knowledge of the consequences of a rupture or leak involving a Radwaste system or component. This

question is based on Operating Experience at BFN when a leaking drain valve caused 0-RR-90-130 to be

exposed to higher than normal background radiation levels prior to commencing a discharge.

References:

BFPER 971713 (level B) 10/28/97 on Radwaste effluent Radiation Monitor

Level of Knowledge Justification: This question is rated as MEM due to the requirement to recall

or recognize discrete bits of information.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (4) Radiation

hazards that may arise during normal and abnormal situations, including maintenance activities and

various contamination conditions.

0610 NRC SRO Exam

(

REFERENCE PROVIDED: None

Plausibility Analysis:

In order to answer this question correctly, the candidate must determine the following :

1. Recall the event which occurred at BFN and the causal factors.

2. Determine the appropriate action if a similar event were to occur while they were performing the

function of Unit Supervisor.

A is incorrect. A discharge of low activity water will typically not provide any change in radiation levels

detected by O-RR-90-130. A reduction in radiation levels is not expected. This becomes plausible if the

candidate is not aware that O-RR-90-130 is immersed in water prior to and after a discharge.

B is incorrect. This becomes plausible if the candidate is not aware that O-RR-90-130 is immersed in

water prior to and after a discharge.

C is incorrect. Detector O-RR-90-130 is required to be calibrated prior to each discharge but verification

that the detector is properly immersed in water prior to taking background readings is NOT required. Even

so, improper calibration would not manifest itself by a reduction in radiation levels after the discharge was

begun. This is plausible because the appropriate action was taken to secure the discharge and this was,

in fact, the suspected cause during the actual event.

D is correct.

(

(c)

BFPER 971713 (level B) 10/28/97 on Radwaste effluent

Radiation Monitor.

i.

0-RR-90-130 indicated lower than background during

discharge release on 10/27/97 where fluctuations from

-1500 cps to 900 cps occurred.

ii.

Subsequent discharge releases on 10/27/97 did not

repeat the same phenomenon. However, RWoperators

reported similar activity during release on 10/21/97.

OPL 171.084

Revision 5

Page 37 of 1

(d)

Action taken

i.

Instrument Mechanics verified calibration of both O-RM-

90-130 and 0-RR-90-130. As found was correct.

ii.

Subsequent troubleshooting revealed a leaking drain

valve (0-DRV-077-0879) due to crud buildup on the valve

seat allowing the detector chamber to drain down.

(i)

Water normally contained inside the chamber provides

shielding to the detector from the background radiation

levels.

(ii)

During the period the chamber was empty, the detector

saw a higher than usual background level. When a

relatively "low" activity release occurred, the newly

provided shielding from the water being released was

actually lower in activity than the background level

previously seen by the detector.

iii.

0-DRV-077-0879 was changed out.

Which ONE of the following describes the required operator action?

17. SRO 271000G2.4.36 00 lIelA/TIG2IEPIP- l//271000G2.4.361ISRO ONLY/12/3107 RMS

I

I

A transient has occurred on Unit-1 resulting in the following annunciators in alarm

STACK GAS RADIATION HI (1-RA-90-147B)

-

STACK GAS RADIATION HIGH-HIGH (1-RA-90-147A)

OG PRETREATMENT RADIATION HIGH (1-RA-90-157A)

-

RX BLDG,TURB BLDG, RF ZONE EXH RADIATION HIGH (1-RA-90-250A)

I

Given the following plant conditions:

I

(

Notify Radcon and

_

REFERENCE PROVIDED

C~ have Chemistry take a coolant sample to verify fuel damage. EPIP entry is required due to EAL

1.4-U.

B. a coolant sample is NOT required to verify fuel damage . No EPIP entry is required until radcon

surveys are completed at the site boundry.

A.

have Chemistry take a coolant sample to verify fuel damage. No EPIP entry is required until sample

results are completed.

i

I

I

I

I

II

D. a coolant sample is NOT required to verify fuel damage. EPIP entry is required due to EAL 1.4-U.

L

_

KIA Statement:

271000 Off-gas

2.4.36 - Emergency Procedures 1Plan Knowledge of chemistry 1health physics tasks during emergency

operations

KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

plant conditions to determine that Chemistry and Radcon support is required.

References:

ARPs for listed annunciators

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble,

sort, and integrate the parts of the question to predict an outcome . This requires mentally using this

knowledge and its meaning to predict the correct outcome.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (4) Radiation

hazards that may arise during normal and abnormal situations, including maintenance activities and

various contamination conditions.

0610 NRC SRO Exam

(

(

(

REFERENCE PROVIDED: EPIP-1

Plausibility Analysis:

In order to answer this question correctly, the candidate must determine the following:

1. The commmon denominator in all the ARPs for the given alarms is to have Radcon and Chemistry

personnel respond to the event.

2. Recognize that EPIP-1 requires a radiochemical analysis to verify fuel damage PRIOR to making

any classification based on fuel failure.

3. Recognize that a valid Off-Gas pretreatment radiation high alarm requires an Unusual Event

declaration in accordance with EAL 1.4U.

A is incorrect. EPIP entry is required based on multiple radiation alarms eliminating the potential for a

single failed annunciator. Therefore, the OG Pretreatment Radiation High alarm is valid and EAL 1.4U is

required. This is plausible because a radiochemical analysis is required to verify fuel damage.

8 is incorrect. EPIP entry is required based on multiple radiation alarms eliminating the potential for a

single failed annunciator. Therefore, the OG Pretreatment Radiation High alarm is valid and EAL 1.4U is

required. In addition, a radiochemical analysis IS required to verify fuel damage. This is plausible because

several EALs within EPIP-1 require site boundry surveys to verify EAL entry cond itions.

C is correct.

D is incorrect. A radiochemical analys is IS required to verify fuel damage. This is plausible because the

OG Pretreatment Radiation High alarm is valid and EAL 1.4U is required .

BROWNS FERRY

EMERGENCY CLASSIFICATION PROCEDURE

EVENT CLASSIFICATION MATRIX

EPIP-1

MSL I OFFGAS

LOSS OF DECAY HEAT

RADIATION

REMOVAL

Description

1.4-U I

I

I

I

Valid MAIN STEAM LINE RADIATION HIGH-HIGH

alarm, RA-90-135C

OR

Valid OG PRETREATMENT RADIATION HIGH

alarm, RA-90-157A.

OPERATING CONDITION:

Mode 1 or 2 or 3

I

Description

I

I

I

c:zc:

C/)c:>>r-

m<mz-I

I

I

I

I

1.5-A I

I

I

I

Reactor moderator temperature can NOT be

maintained below 2120 F whenever Technical

Specifications require Mode 4 conditions or during

operations in Mode 5.

>>r-m

U

-I

OPERATING CONDITION:

Mode 4 or 5

I

I

I

I

1.5-S I CURVE I

I

I US

Suppression Pool temperature, level and RPV

C/)

pressure can NOT be maintained in the safe area

=i

of Curve 1.5-S.

m

,

m

~m

U

G)

m

OPERATING CONDITION:

Zo

Mode 1 or 2 or 3

-<

I

I

I

I

I

I

I

I

G)

mzm

~r-

ms::m

0

G)

mzo-<

PAGE 22 OF 201

REVISION 42

BROWNS FERRY

EMERGENCY CLASSIFICATION PROCEDURE

TECHNICAL BASIS

EPlp*1

(

EAL:

MSL/OFFGAS RADIATION

1.4-U

UNUSUAL EVENT

Valid MAIN STEAM LINE RADIATION HIGH-HIGH alarm, RA-90-135C

OR

Valid OG PRETREATMENT RADIATION HIGH alarm, RA-90-157A.

OPERATING CONDITION: Mode 1 or 2 or 3

BASIS:

REFERENCES:

NOTES:

CURVESITABLES:

Main Steam Line radiation high high or offgas radiation high is indicative of fuel

cladding leakage.

The Main Steam Line radiation high high alarm setpoint is normally set at 3 times

normal full power background. 3 times normal full power background is in excess of

any spikes expected from operational transients that do not result in cladding failure.

This alarm setpoint is substantially above that which would be indicative of fuel

cladding damage above Technical Specification allowable limits; however, the

presence

of

a

valid

alarm warrants

declaration

of

an

Unusual

Event and

consideration of other symptoms and event classifications for possible upgrade of the

event based on fission product barrier loss.

The offgas pretreatment radiation high alarm setpoint is set at a value that is

indicative of the ODCM allowable limits for radiation release.

Either of these conditions is considered a potential degradation in the level of safety

of the plant and a potential precursor of a more serious problem.

Escalation to the Alert is based on either Reactor coolant samples exceeding

300 IJCi/gm or Drywell radiation levels indicative of loss of the fuel cladding barrier.

Reg Guide 1.101 Rev. 3, (NUMARC-SU4 example-1)

(

PAGE 102 OF 201

REVISION 42

BROWNS FERRY

EMERGENCY CLASSIFICATION PROCEDURE

TECHNICAL BASIS

EPIP-1

(

EAL:

OTHER

8.4-A

ALERT

Events are in process or have occurred which involve an actual or potential

substantial degradation in the level of safety of the plant or a security event that

involves probable life threatening risk to site personnel or damage to site equipment

because of HOSTILE ACTION.

Any releases are expected to be limited to small

fractions of the EPA ProtectiveAction Guideline exposure levels.

OR

Any loss or potential loss of fuel cladding or RCS pressure boundary.

OPERATING CONDITION: ALL

BASIS:

REFERENCES:

This event classification is intended to address conditions not explicitly addressed

elsewhere but that warrant declaration of an emergency because conditions exist

which are believed by the Site Emergency Director to fall under the Alert

classification.

BFN EALs were developed primarily utilizing the symptom based

grouping methodology. This approach is consistent with the BFN EOI methodology.

It is important to note here that the consideration of fission product barriers has been

incorporated within this symptom based approach. Barrier-based EALs refer to the

level of challenge to principal barriers used to assure containment of radioactive

material. For radioactive materials that are contained within the reactor core, these

barriers

are: fuel

cladding,

reactor

coolant

system

pressure

boundary, and

containment.

The level of challenge to these barriers encompasses the extent of

damage (loss or potential loss) and the number of barriers currently under challenge.

Site Emergency Directors should be continuously aware of all challenges to these

barriers and the number of barriers loss or potentially loss.

Also Site Emergency

Directors should consider that when the loss or potential loss thresholds is imminent

(Le., 1 to 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />) use judgment and classify as if the thresholds are exceeded.

The threshold for fission product barrier loss is considered to be consistent with the

following:

Fuel clad - A Reactor coolant sample that yields a result of 300 j../Cilgm lodine-131

equivalent is indicative of cladding failure (Refer to 1.3-A).

RCS barrier - Reactor coolant leakage of at least 50 GPM from the primary system

(Refer to 2.4-A).

Reg Guide 1.101 Rev. 3, (NUMARC HA6, FA)

NRC Bulletin 2005-02, July 18, 2005 - Attachment 2 (Emergency Classification Level

changes)

NEI White Paper, "Enhancements to Emergency Preparedness Programs for Hostile

Action", May 2005 (Revised November 18, 2005)

PAGE 196 OF 201

REVISION42

OTHER

8.4-5

(

BROWNS FERRY

EMERGENCY CLASSIFICATION PROCEDURE

TECHNICAL BASIS

EPIP-1

EAL:

SITE AREA EMERGENCY

Events are in process or have occurred which involve actual or likely major failures of

plant functions needed for protection of the public or HOSTILE ACTION that results

in intentional damage or malicious acts (1) toward site personnel or equipment that

could lead to the likely failure thereof or, (2) prevent effective access to equipment

needed for protection of the public.

Any releases are not expected to result in

exposure levels which exceed EPA Protective Action Guideline exposure levels

beyond the site boundary.

OR

Any loss or potential loss of both fuel cladding and RCS pressure boundary.

OR

Potential loss of either fuel cladding or RCS pressure boundary and loss of any

additional barrier.

OPERATING CONDITION: ALL

BASIS:

This event classification is intended to address unanticipated conditions not explicitly

addressed elsewhere but that warrant declaration of an emergency because

conditions exist which are believed by the Site Emergency Director to warrant Site

Area Emergency classification.

BFN EALs were developed primarily utilizing the

symptom based grouping methodology.

This approach is consistent with the BFN

EOI methodology.

It is important to note here that the consideration of fission

product barriers has been incorporated within this symptom based approach.

Barrier-based EALs refer to the level of challenge to principal barriers used to assure

containment of radioactive material.

For radioactive materials that are contained

within the reactor core, these barriers are: fuel cladding, reactor coolant system

pressure boundary, and containment.

The level of challenge to these barriers

encompasses the extent of damage (loss or potential loss) and the number of

barriers currently under challenge. Site Emergency Directors should be continuously

aware of all challenges to these barriers and the number of barriers loss or potentially

loss. Also Site Emergency Directors should consider that when the loss or potential

loss thresholds is imminent (l.e., 1 to 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />) use judgment and classify as if the

thresholds are exceeded.

Loss or potential loss of any two fission product barriers must be considered along

with inability to monitor fission product barriers during extreme conditions.

The

threshold for fission product barrier loss is considered to be consistent with the

following:

Fuel clad - A Reactor coolant sample that yields a result of 300 IJCi/gm lodine-131

equivalent is indicative of cladding failure (Refer to 1.3-A).

RCS barrier - Reactor coolant leakage of at least 50 GPM from the primary system

(Refer to 2.4-A).

Primary Containment barrier - Refer to 2.5-U.

(

PAGE 198 OF 201

REVISION 42

(

BFN

Unit 1

STACK GAS

RADIATION

HIGH

1-RA-90-147B

MA

~

(Page 1 of 1)

Panel 9-3

XA-55-3A

SensorlTrip Point:

0-RM-90-147B

0-RM-90-148B

0-RM-90-306

1-ARP-9-3A

Rev. 0036

Page 20 of 50

ill

11 ,948 CPS

11,948 CPS

5.57 X 10-2 mCi/cc

Sensor

Location:

O-RE-090-0147 and

O-RE-090-0148

EI 599'6", Pnl 25-39

inside stack

Probable

Cause:

Automatic

Action:

A. Source check.

B. Resin trap failure (RWCU or Cond Demin).

C. Possible fuel element failure.

D. Sensor malfunction.

None

Operator

Action:

A. CHECK alarm condition on the following:

1. WIDE RANGE GASEOUS EFFLUENT RADIATION MONITOR,

0-RM-90-306 on Panel 2-9-2.

2.

STACK GAS RADIATION, 0-RR-90-147 on Panel 1-9-2.

o

o

B. CHECK following radiation recorders on Panel 1-9-2 and associated

radiation monitors on Panel 1-9-10:

1. OFFGAS RADIATION, 1-RR-90-266

0

2.

OG POST-TREATMENT CH BRAD MaN RTMR,

1-RM-90-265A.

0

3.

OG POST-TREATMENT CH A RAD MaN RTMR,

1-RM-90-266A.

0

C. VERIFY dilution fan running and damper open by checking red light

illuminated above STACK DILUTION AIR FAN A (B), 1-HS-66-29A

(31A) on Panel 1-9-8.

0

D. VERIFY Charcoal Adsorbers in service.

0

E. NOTIFY RADCON and Shift Manager.

0

F. REQUEST Chemistry perform radiochemical analysis to determine

wu~e.

0

References:

1-47E620-3

0-SIMI-90B

0-47E610-90-4 & 20

c

BFN

Unit 1

STACK GAS

RADIATION

HIGH-HIGH

1-RA-90-147A

Panel 9-3

XA-55-3A

SensorlTrip Point:

0-RM-90-147B

0-RM-90-148B

Hi-Hi alarm from drawer

1-ARP-9-3A

Rev. 0036

Page 11 of 50

HI-HI

23,896 CPS

23,896 CPS

MA

~

0-RM-90-306

(Page 1 of 1)

As listed in 2-AOI-90-2

Sensor

Location:

Probable

Cause:

Automatic

Action:

EI 599'6", Panel 25-39. Inside stack.

A. Source check.

B. Resin trap failure (RWCU or Cond Demin).

C. Possible fuel element failure.

D. Sensor malfunction.

E. Off-gas flow abnormal.

None

Operator

Action:

A. CHECK alarm condition on the following:

1. WIDE RANGE GASEOUS EFFLUENT RADIATION MONITOR,

0-RM-90-306 on Panel 2-9-2.

2. STACK GAS RADIATION, 0-RR-90-147 on Panel 1-9-2.

o

o

B. CHECK following radiation recorders on Panel 1-9-2 and associated

radiation monitors on Panel 1-9-10:

1. OFFGAS RADIATION, 1-RR-90-266.

0

2.

OG POST-TREATMENT, CH BRAD MON RTMR,

1-RM-90-265A.

0

3. OG POST-TREATMENT CH A RAD MON RTMR,

1-RM-90-266A.

0

C. VERIFY dilution fan running and damper open by checking red light

illuminated above STACK DILUTION AIR FAN A (B), 1-HS-66-29A

(31A) on Panel 1-9-8.

0

D. VERIFY Charcoal Adsorbers in service.

0

E. NOTIFY Shift Manager and RADCON.

0

F. REQUEST Chemistry perform radiochemical analysis to determine

wu~e.

0

G. REFER TO ODCM.

0

H. REFER TO EPIP-1.

0

(

References:

1-45E620-3

0-47E610-90-4 & 20

1-729E814-2

0-SIMI-90B

(

BFN

Unit 1

OG PRETREATMENT

RADIATION

HIGH

1-RA-90-157A

MA

1'5

(Page 1 of 1)

Panel 9-3

XA-55-3A

Sensorffrip Point:

1-RM-090-0157

Hi alarm from drawer.

1-ARP-9-3A

Rev. 0036

Page 10 of 50

HI

5000 MR/HR

Sensor

Location:

Probable

Cause:

Automatic

Action:

Turb. Bldg, EI. 565', B-T3, 1-RE-090-0157, OG Pretreatment Sample Chamber.

A. High radiation in the pretreatment Off-Gas System .

B. Resin trap failure (RWCU or Condo Demin)

C. Possible fuel element failure.

None

Operator

Action:

A. VERIFY high radiation by checking recorder 1-RR-90-266

(Panel 1-9-2) and ratemeters 1-RM-90-157 (Panel 1-9-10).

B. NOTIFY RADCON.

C. CHECK off-gas flow normal.

D. CHECK Main Steam Line Radiation Recorder 1-RR-90-135

(Panel 1-9-2).

E. CHECK STACK GAS RADIATION, 0-RR-90-147.

F. REQUEST Chemistry perform radiochemical analysis to determine

source.

G. MONITOR off-gas release rate for ODCM compliance. Power

reduction may be required.

H. IF ODCM Limits are exceeded, THEN

REFER TO EPIP-1.

o

o

o

o

o

o

o

o

References:

0-47W600-77

729E814 Series

1-47E610-90-1

1-45E620-3

BFN

Unit 1

RX BLDG,TURB BLDG,

RF ZONE EXH

RADIATION HIGH

1-RA-90-250A

MA

~

(Page 1 of 1)

Panel 9-3

XA-55-3A

SensorlTrip Point:

1-RM-90-250

Gas

1-ARP-9-3A

Rev. 0036

Page 9 of 50

HIGH ALARM - 6594 CPM

ALERT - 3297 CPM

Sensor

Location:

Probable

Cause:

Automatic

Action:

Operator

Action:

EI 664' Refuel Floor R-4 P-Line

A. Daily source check .

B. High radiation in the Reactor Building, Turbine Building, Refuel Zone exhaust

ventilation ducts.

C. Dry Cask storage activities in progress.

None

A. CHECK 1-RM-90-250 on Panel 1-9-2 (O-MON-90-361) and

MONITOR activity levels on recorder AIR PARTICULATE MONITOR

CONTROLLER 1-MON-90-50 on Panel 1-9-2.

D

B. IF high activity is conformed, THEN

NOTIFY RADCON.

D

C. REQUEST Chemistry perform analysis to determine source.

D

D. IF Dry Cask storage activities are in progress, THEN

NOTIFY CASK Supervisor.

D

E. IF the TSC is NOT manned, THEN

EVACUATE personnel from affected areas .

D

F. IF the TSC is manned, THEN

REQUEST the TSC to evacuate unnecessary personnel from

affected areas.

D

G. MONITOR release rate for ODCM compliance.

D

H. IF ODCM Limits are exceeded, THEN

REFER TO EPIP-1.

D

I.

IF Eberline is operable, THEN

REFER TO 1-01-90, to reset alarms.

D

References:

0-47W600-80

1-SIMI-90B

1-47E610-90-1

45E620-3

TVA Calc NDQ00902005008/EDC63693

r

TENNESSEE VALLEY AUTHORITY

BROWNS FERRY NUCLEAR PLANT

EMERGENCY PLAN IMPLEMENTING PROCEDURE

EPIP-1

EMERGENCY CLASSIFICATION PROCEDURE

REVISION 42

PREPARED BY: RANDY WALDREP

PHONE: 2038

RESPONSIBLE ORGANIZATION: EMERGENCY PREPAREDNESS

APPROVED BY:

TONY ELMS

EFFECTIVE DATE: 04/06/2007

LEVEL OF USE: REFERENCE USE

QUALITY-RELATED

DATE: 04/06/2007

I

II(

18. SRO 288000A2.03 OO l/C/A/T2G2/0I-30//288000A2.03//SRO ONLY11211S/2007 RMS

Given the following Unit 3 conditions:

Unit-3 was at 100% rated power

A Loss of Coolant Accident occurred resulting in the following plant indications:

Reactor water level is +30 inches and steady with RCIC injecting.

Reactor pressure is 750 psig and lowering slowly .

Drywell pressure is 5.0 psig and rising slowly.

Reactor Zone exhaust radiation is 65 mR/hr.

Refuel Zone exhaust radiation is 4 mR/hr.

SGT trains A, 8 and C are running.

Which ONE of the following describes the status of Reactor Zone and Refuel Zone ventilation and any

corrective actions required for these conditions?

A.

Reactor and Refuel Zone ventilation systems are isolated. Perform 3-EOI Appendix 8E and restart

ventilation per 3-01-30A and 3-01-308.

B~ Reactor and Refuel Zone ventilation systems are isolated. Perform 3-EOI Append ix 8E and restart

ventilation per 3-EOI Appendix 8F.

C. Reactor Zone ventilation system is isolated. Refuel Zone ventilation is unaffected. Perform 3-EOI

Appendix 8E and restart ventilation per 3-01-308.

D. Reactor Zone ventilation system is isolated. Refuel Zone ventilation is unaffected. Perform 3-EOI

Appendix 8E and restart ventilation per 3-EOI Appendix 8F

KJA Statement:

288000 Plant Ventilation

A2.03 - Ability to (a) predict the impacts of the following on the PLANT VENTILATION SYSTEMS ; and (b)

based on those predictions, use procedures to correct, control, or mitigate the consequences of those

abnormal conditions or operations: Loss of coolant accident: Plant-Specific

KJA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

plant conditions to determ ine ventilation system status and take the appropriate corrective actions.

References: 3-01-30A and 8. 3-EOI Append ix 8E & F

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,

sort, and integrate the parts of the question to predict an outcome. This requires mentally using this

knowledge and its meaning to predict the correct outcome.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (5) Assessment

of facility conditions and selection of appropriate procedures during normal, abnormal, and emergency

situations.

0610 NRC SRO Exam

(

REFERENCE PROVIDED: None

Plausibility Analysis:

In order to answer this question correctly, the candidate must determine the following :

1. High drywell pressure causes an isolation of BOTH Reactor Zone and Refuel Zone ventilation .

2. 3-EOI Appendix BE is required to bypass a PCIS Group 6 isolation to allow restarting ventilation .

3. 3-EOI Appendix BF is required to restart ventilation following implementation of 3-EOI Appendix BE.

4. It is not appropriate to use 3-01-30A or 30B to restart ventilation once 3-EOI Appendix BE has been

implemented.

A is incorrect. 3-EOI Appendix BF is required to restart ventilation following implementation of 3-EOI

Appendix BE. It is not appropriate to use 3-01-30A or 30B. This is plausible because 3-01-30A and 30B

are functionally correct, but fail to address SGT trains in operation .

B is correct.

C is incorrect. High drywell pressure causes an isolation of BOTH Reactor Zone and Refuel Zone

ventilation. This is plausible due to confusion between differing isolation signals for each zone. For

example, refuel zone high radiation does not impact the reactor zone ventlation system. In addition, it is

not appropriate to use 3-01-30B to restart ventilation once 3-EOI Appendix BE has been implemented.

D is incorrect. High drywell pressure causes an isolation of BOTH Reactor Zone and Refuel Zone

ventilation. This is plausible due to confusion between differing isolation signals for each zone. For

example, refuel zone high radiation does not impact the reactor zone ventlation system.

BFN

Reactor Zone Ventilation System

3-01-30B

Unit 3

Rev. 0018

Page 7 of 34

(

3.0

PRECAUTIONS AND LIMITATIONS

A.

The Reactor Zone Ventilation System should be operated in a manner such that

no area will exceed 0.5 inches negative water pressure.

B.

A Work Order (WO) should be submitted to have Reactor Zone inlet filters

replaced when the differential pressure across the filters rises to 0.6 inch water.

C.

Refueling Zone supply and exhaust fans should be operating prior to startup of

Reactor Zone supply and exhaust fans to establish negative refuel zone

pressure prior to start of reactor zone fans.

D.

During cold weather operation, the Air Wash and Air Wash Pump B (Air Wash

Pump) and associated valves should be lined up in accordance with

0-GOI-200-1.

E.

Whenever primary containment is required , the Reactor Zone Ventilation

System should be restored to service as soon as possible following a Reactor

Building isolation to prevent a possible main steam line tunnel high temperature

Group I isolation.

F.

When the Reactor Zone Ventilation System is out of service and primary

containment is required, reference should be made to Technical Specification,

3.3.6.1 and 3-AOI-30B-1, Reactor Zone Ventilation Failure. Shift Manager

should be notified immediately.

G.

The Reactor Zone Supply and Exhaust Fans will auto trip due to any of the

following :

1.

Reactor Zone exhaust duct high radiation.

2.

Drywell high pressure.

3.

Reactor low water level.

4.

Reactor Zone high or low pressure.

H.

Reactor Zone supply and exhaust fans are alternated every six weeks.

BFN

Refuel Zone Ventilation System

3-01-30A

Unit 3

Rev. 0025

Page 7 of 33

3.0

PRECAUTIONS AND LIMITATIONS

A.

The Refueling Zone Ventilation System is required to be operated in a manner

such that the area pressure does not exceed 0.5 inches negative water

pressure.

B.

A WO should be submitted to have Refueling Zone inlet filters replaced when

the inlet DP rises to 0.6 inches H20.

C.

Refueling Zone supply and exhaust fans should be operating prior to startup of

Reactor Zone supply and exhaust fans.

D.

During cold weather operation, the air wash associated valves should be lined

up for freeze protection. REFER TO 0-GOI-200-1 .

E.

The Refueling Zone supply and exhaust fans automatically shut down due to

anyone of the following:

1.

Refueling Zone high radiation

2.

Drywell high pressure

3.

Reactor low water level

4.

Refueling Zone high or low pressure

5.

Reactor Zone high radiation

F.

The Refueling Ventilation System is required to be in the refuel mode prior to

refueling operations. REFER TO the following:

1.

Mechanical Maintenance should be requested to manually adjust the

normally closed dampers, REACTOR CAVITY EXH DAMPER,

3-DMP-064-0501, and DRYER AND SEP STORAGE POOL EXH

DAMPER , 3-DMP-064-0504, to obtain to obtain desired flow rate

REFER TO Section 8.3 and 3-TI-218, or

2.

With permission from the Shift Manager (or his designated alternate)

continuous operation of the Standby Gas Treatment System (SGT) taking

suction from the Refueling Floor will satisfy the requirement for the

ventilation system being in the Refuel Mode.

G.

Whenever a ventilation fan is placed in operation, the fan and motor should be

checked. REFER TO 0-GOI-300-1.

H.

Dual speed fans should be run in SLOW speed during the heating season and

FAST speed during the cooling season. SLOW speed reduces heating load

during cold weather and FAST speed maximizes cooling effect during hot

weather.

19. SRO GENERIC 2.1.12 00l/C/A/T3/RPS/2/212000G2.1.12/2.9/4.0/SRO ONLY/

Given the following plant conditions:

Unit 1 is operating at 1000h power.

Unit 2 is operating at 100

% power.

Unit 3 is refueling (MODE 5), fuel movement is in progress.

Recirc pump 3A suction line work is in progress and has the potential to drain the RPV.

The 3ED DIG is out of service for an inspection.

During performance of the monthly SGT Surveillance, B SGT fails to start.

Which ONE of the following describes the required actions per Technical Specifications?

REFERENCE PROVIDED

A.

Enter LCO 3.0.3 on Unit 1 and 2 immediately. Suspend Unit 3 fuel movement immediately.

B. ttl

Enter LCO 3.0.3 on Unit 1 and 2 in 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Initiate actions to suspend OPDRVs immediately.

C.

Be in Mode 3 on Unit 1 and 2 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and Mode 4 in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Start A and C SGT trains in 4

hours.

D.

Be in Mode 3 on Unit 1 and 2 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and Mode 4 in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Initiate actions to suspend

OPDRVs immediately.

KIA Statement:

Conduct of Operations

2.1.12 Ability to apply technical specifications for a system

KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

plant conditions and times to correctly determine the required actions per Technical Specifications.

References: Unit-3 Tech Specs

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble,

sort, and integrate the parts of the question to predict an outcome. This requires mentally using this

knowledge and its meaning to predict the correct outcome.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (2) Facility

operating limitations in the technical specifications and their bases.

0610 NRC SRO Exam

REFERENCE PROVIDED: U3 Tech Spec Sections 3.6 and 3.8

Plausibility Analysis:

In order to answer this question correctly, the candidate must determine the following:

1. Recognize that "C" SGT is only OPERABLE with 3ED DIG INOP as long as "A" and "B" SGT remain

OPERABLE. (supported system)

2. Recognize that "B" SGT becoming INOP also impact Units 1 & 2.

3. Recognize that Tech Specs allows 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> from discovery to declare supported systems INOP.

A is incorrect.

The supported system LCO is not applied for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Fuel movement on Unit-3 is only

suspended when 2 or more U3 DIGs are INOP.

B is correct.

C is incorrect. These actions are required for failure to meet the LCO for 1 SGT train inop. Starting "A"

and "C" SGT trains is only required if "B" SGT has been INOP for longer than 7 days with no other

supported system issues.

D is incorrect. These actions are required for failure to meet the LCO for 1 SGT train inop.

SGT System

3.6.4.3

3.6

CONTAINMENT SYSTEMS

3.6.4.3 Standby Gas Treatment (SGT) System

LCO 3.6.4.3

Three SGT subsystems shall be OPERABLE.

APPLICABILITY:

MODES 1, 2, and 3,

During operations with a potential for draining the reactor vessel

(OPDRVs).

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. One SGT subsystem

A.1

Restore SGT subsystem

7 days

inoperable.

to OPERABLE status.

B. Required Action and

B.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

associated Completion

Time of Condition A not

AND

met in MODE 1, 2, or 3.

B.2

Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

(continued)

BFN-UNIT 3

3.6-51

Amendment No. 24-2, 249

September 27, 2004

ACTIONS (continued)

SGT System

3.6.4.3

CONDITION

REQUIRED ACTION

COMPLETION

TIME

C. Required Action and

C.1

Place two OPERABLE

Immediately

associated Completion

SGT subsystems in

Time of Condition A not

operation.

met during OPDRVs.

OR

C.2

Initiate action to suspend

Immediately

OPDRVs.

D. Two or three SGT

D.1

Enter LCO 3.0.3.

Immediately

subsystems inoperable in

MODE 1, 2, or 3.

(continued)

BFN-UNIT 3

3.6-52

Amendment No. 2-+2-, 249

September 27, 2004

ACTIONS (continued)

CONDITION

REQUIRED ACTION

SGT System

3.6.4.3

COMPLETION

TIME

E. Two or three SGT

subsystems inoperable

during OPDRVs.

E.1

Initiate action to suspend

Immediately

OPDRVs.

BFN-UNIT 3

3.6-53

Amendment No. ~, 249

September 27, 2004

AC Sources - Shutdown

3.8.2

3.8

ELECTRICAL POWER SYSTEMS

3.8.2

AC Sources - Shutdown

LCO 3.8.2

The following AC electrical power sources shall be OPERABLE:

a. One qualified circuit connected between the offsite transmission

network and the onsite Class 1E AC electrical power

distribution subsystem(s) required by LCO 3.8.8, "Distribution

Systems - Shutdown";

b. Two of the four Unit 3 diesel generators (DGs) each capable of

supplying one 4.16 kV shutdown board of the onsite Class 1E

AC electrical power distribution subsystem(s) required by

LCO 3.8.8, "Distribution Systems - Shutdown"; and

c.

Unit 1 and 2 DGs capable of supplying the Unit 1 and 2 4.16 kV

shutdown boards required by LCO 3.8.8.

APPLICABILITY:

MODES 4 and 5,

During movement of irradiated fuel assemblies in the secondary

containment.

BFN-UNIT 3

3.8-14

Amendment No. 212

ACTIONS

AC Sources - Shutdown

3.8.2

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. (continued)

A.2.3

Initiate action to suspend

Immediately

operations with a

potential for draining the

reactor vessel (OPDRVs).

AND

A.2.4

Initiate action to restore

Immediately

required offsite power

circuit to OPERABLE

status.

B. One or more required

B.1.1

Suspend CORE

Immediately

Unit 3 DGs inoperable.

ALTERATIONS.

AND

B.1.2

Suspend movement of

Immediately

irradiated fuel assemblies

in secondary

containment.

AND

B.1.3

Initiate action to suspend

Immediately

OPDRVs.

AND

B.1.4

Initiate action to restore

Immediately

required Unit 3 DGs to

OPERABLE status.

(continued)

BFN-UNIT 3

3.8-16

Amendment No. 212

ACTIONS (continued)

CONDITION

REQUIRED ACTION

AC Sources - Shutdown

3.8.2

COMPLETION

TIME

C. One or more required

Unit 1 and 2 DGs

inoperable.

C.1

Declare affected SGT and

30 days

CREV subsystem(s)

inoperable.

AND

Immediately from

discovery of

Condition C

concurrent with

inoperability of

redundant

required

feature(s)

BFN-UNIT 3

3.8-17

Amendment No. 212

(

SGT System

3.6.4.3

3.6

CONTAINMENT SYSTEMS

3.6.4.3

Standby Gas Treatment (SGT) System

LCO 3.6.4.3

Three SGT subsystems shall be OPERABLE.

APPLICABI LITY:

MODES 1, 2, and 3,

During operations with a potential for draining the reactor vessel

(OPDRVs).

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. One SGT subsystem

A.1

Restore SGT subsystem

7 days

inoperable.

to OPERABLE status.

B. Required Action and

B.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

associated Completion

Time of Condition A not

AND

met in MODE 1, 2, or 3.

B.2

Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

(continued)

BFN-UNIT 3

3.6-51

Amendment No. ~, 249

September 27, 2004

SGT System

3.6.4.3

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

C. Required Action and

C.1

Place two OPERABLE

Immediately

associated Completion

SGT subsystems in

Time of Condition A not

operation.

met during OPDRVs.

OR

C.2

Initiate action to suspend

Immediately

OPDRVs.

D. Two or three SGT

D.1

Enter LCO 3.0.3.

Immediately

subsystems inoperable in

MODE 1, 2, or 3.

(continued)

BFN-UNIT 3

3.6-52

Amendment No. ~, 249

September 27, 2004

ACTIONS (continued)

CONDITION

REQUIRED ACTION

SGT System

3.6.4.3

COMPLETION

TIME

E. Two or three SGT

subsystems inoperable

during OPDRVs.

E.1

Initiate action to suspend

Immediately

OPDRVs.

BFN-UNIT 3

3.6-53

Amendment No. ~, 249

September 27, 2004

AC Sources - Shutdown

3.8.2

3.8

ELECTRICAL POWER SYSTEMS

3.8.2

AC Sources - Shutdown

LCO 3.8.2

The following AC electrical power sources shall be OPERABLE:

a. One qualified circuit connected between the offsite transmission

network and the onsite Class 1E AC electrical power

distribution subsystem(s) required by LCO 3.8.8, "Distribution

Systems - Shutdown";

b. Two of the four Unit 3 diesel generators (DGs) each capable of

supplying one 4.16 kV shutdown board of the onsite Class 1E

AC electrical power distribution subsystem(s) required by

LCO 3.8.8, "Distribution Systems - Shutdown"; and

c.

Unit 1 and 2 DGs capable of supplying the Unit 1 and 2 4.16 kV

shutdown boards required by LCO 3.8.8.

APPLICABILITY:

MODES 4 and 5,

During movement of irradiated fuel assemblies in the secondary

containment.

BFN-UNIT 3

3.8-14

Amendment No. 212

ACTIONS

CONDITION

REQUIRED ACTION

AC Sources - Shutdown

3.8.2

COMPLETION

TIME

A. One required offsite

circuit inoperable.


NOTE----------------

Enter applicable Condition and

Required Actions of LCO 3.8.8,

with any required 4.16 kV

shutdown board not energized

from a qualified source as a

result of Condition A.

A.1

Declare affected required

Immediately

feature(s) with no

qualified offsite power

available inoperable.

OR

A.2.1

Suspend CORE

ALTERATIONS.

Immediately

A.2.2

Suspend movement of

Immediately

irradiated fuel assemblies

in secondary

containment.

(continued)

BFN-UNIT 3

3.8-15

Amendment No. 212

ACTIONS

AC Sources - Shutdown

3.8.2

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. (continued)

A.2.3

Initiate action to suspend

Immediately

operations with a

potential for draining the

reactor vessel (OPDRVs).

AND

A.2.4

Initiate action to restore

Immediately

required offsite power

circuit to OPERABLE

status.

B. One or more required

B.1.1

Suspend CORE

Immediately

Unit 3 DGs inoperable.

ALTERATIONS.

AND

B.1.2

Suspend movement of

Immediately

irradiated fuel assemblies

in secondary

containment.

AND

B.1.3

Initiate action to suspend

Immediately

OPDRVs.

AND

B.1.4

Initiate action to restore

Immediately

required Unit 3 DGs to

OPERABLE status.

(continued)

BFN-UNIT 3

3.8-16

Amendment No. 212

ACTIONS (continued)

CONDITION

REQUIRED ACTION

AC Sources - Shutdown

3.8.2

COMPLETION

TIME

C. One or more required

Unit 1 and 2 DGs

inoperable.

C.1-

Declare affected SGT and

30 days

CREV subsystem(s)

inoperable.

AND

Immediately from

discovery of

Condition C

concurrent with

inoperability of

redundant

required

feature(s)

BFN-UNIT 3

3.8-17

Amendment No. 212

(

20. SRO GENERIC 2.2.22 OOl/CIA/TECH SPECS/HPCVlG2.2.22/4.l/SRO/lO/27/2007

Given the following plant conditions:

Unit 2 is operating at 100% power with HPCI tagged out at 0730 hours0.00845 days <br />0.203 hours <br />0.00121 weeks <br />2.77765e-4 months <br />.

It is determ ined that a control power fuse had blown on MSRV 1-23, after noticing a loss of

position indication on Panel 9-3 vertical section, also at 0730 hours0.00845 days <br />0.203 hours <br />0.00121 weeks <br />2.77765e-4 months <br />.

Which ONE of the following describes the minimum required actions imposed by Tech Specs?

REEFERENCE PROVIDED

A.

Restore both the MSRV and HPCI to operable within 14 days or be in MODE 3 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and

MODE 4 in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

B. Restore either the MSRV Q! HPCI to operable within 14 days or be in MODE 3 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and

MODE 4 in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

(

C.

Enter LCO 3.0.3 immediately.

D~ Restore HPCI in 14 days or be in MODE 3 in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and reduce reactor pressure to less than or

equal to 150 psig in 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

KIA Statement:

Equipment Control

2.2.22 Knowledge of limiting conditions for operations and safety limits.

KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

equipment conditions and times to correctly determine operability issues and Limiting Conditions for

Operation.

References: Unit-2 Tech Specs

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,

sort, and integrate the parts of the question to predict an outcome. This requires mentally using this

knowledge and its meaning to predict the correct outcome.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (2) Facility

operating limitations in the technical specifications and their bases.

0610 NRC SRO Exam

(

(

REFERENCE PROVIDED: Unit-2 Tech Spec section 3.4 & 3.5

Plausibility Analysis:

In order to answer this question correctly, the candidate must:

1- recall from memory that MSRV 1-23 is NOT an ADS valve on Unit-2. (ref. pg 1)

2- correctly apply the applicability of TS 3.5.1 excepting HPCI from operability ~ 150 psig. (ref. pg 2)

3- recognize that only 12 of 13 MSRVs are required to be operable for other than ADS function . (ref. pg 6)

Answer A is incorrect because MSRV 1-23 is not a LCO per TS 3.4.3 and HPCI is excepted from MODE

4 requirements. It is plausible if the candidate fails to apply #2 and #3 above.

Answer B is incorrect because MSRV 1-23 is not a LCO per TS 3.4.3 and HPCI is excepted from MODE

4 requirements. It is plausible if the candidate fails to apply #1, #2 and #3 above.

Answer C is incorrect because MSRV 1-23 is NOT an ADS valve, therefore TS 3.5.1.H does not apply.

This is plausible if the candidate fails to apply #1 above.

Answer D is the correct answer.

(

S/RVs

3.4.3

3.4

REACTOR COOLANT SYSTEM (RCS)

3.4.3 Safety/Relief Valves (S/RVs)

LCO 3.4.3

The safety function of 12 S/RVs shall be OPERABLE.

APPLICABILITY:

MODES 1,2, and 3.

ACTIONS

(

CONDITION

A. One or more required

S/RVs inoperable.

BFN-UNIT 2

REQUIRED ACTION

A.1

Be in MODE 3.

A.2

Be in MODE 4.

3.4-7

COMPLETION

TIME

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

36 hours

Amendment 253

(

ECCS - Operating

3.5.1

3.5

EMERGENCY CORE COOLING SYSTEMS (ECCS) AND REACTOR CORE

ISOLATION COOLING (RCIC) SYSTEM

3.5.1

ECCS - Operating

LCO 3.5.1

Each ECCS injection/spray subsystem and the Automatic

Depressurization System (ADS) function of six safety/relief valves

shall be OPERABLE.

APPLICABILITY:

MODE 1,

MODES 2 and 3, except high pressure coolant injection (HPCI) and

ADS valves are not required to be OPERABLE with reactor

steam dome pressu re s 150 psig.

ACTIONS


NOTE--------------------------------------------------

LCO 3.0.4.b is not applicable to HPCI.

CONDITION

A. One low pressure ECCS

A.1

injection/spray subsystem

inoperable.

One low pressure coolant

injection (LPCI) pump in

both LPCI subsystems

inoperable.

REQUIRED ACTION

Restore low pressure

ECCS injection/spray

subsystemts) to

OPERABLE status.

COMPLETION

TIME

7 days'?

(continued)

(1) _ This Completion Time may be extended to 14 days on a one-time basis. This temporary approval

expires June 1, 2005.

(

BFN-UNIT 2

3.5-1

Amendment No. 253, 269, 286, 294

May 9,2005

ACTIONS (continued)

CONDITION

REQUIRED ACTION

ECCS - Operating

3.5.1

COMPLETION

TIME

B. Required Action and

B.1

Be in MODE 3.

associated Completion

Time of Condition A not

AND

met.

B.2

Be in MODE 4.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

36 hours

(continued)

BFN-UNIT 2

3.5-1a

Amendment No. 286

December 1, 2003

(

ECCS - Operating

3.5.1

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

C. HPCI System inoperable.

C.1

Verify by administrative

Immediately

means RCIC System is

OPERABLE.

AND

C.2

Restore HPCI System to

14 days

OPERABLE status.

D. HPCI System inoperable.

D.1

Restore HPCI System to

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

OPERABLE status.

AND

OR

Condition A entered.

D.2

Restore low pressure

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

ECCS injection/spray

subsystem to OPERABLE

status.

E. One ADS valve

E.1

Restore ADS valve to

14 days

inoperable.

OPERABLE status.

F. One ADS valve

F.1

Restore ADS valve to

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

inoperable.

OPERABLE status.

AND

OR

Condition A entered.

F.2

Restore low pressure

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

ECCS injection/spray

subsystem to OPERABLE

status.

(continued)

BFN-UNIT 2

3.5-2

Amendment No. ass, 269

March 12, 2001

(

ECCS - Operating

3.5.1

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

G. Two or more ADS valves

G.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

inoperable.

AND

OR

G.2

Reduce reactor steam

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

Required Action and

dome pressure to

associated Completion

~ 150 psig.

Time of Condition C, D,

E, or F not met.

H. Two or more low pressure

H.1

Enter LCO 3.0.3.

Immediately

ECCS injection/spray

subsystems inoperable

for reasons other than

Condition A.

OR

HPCI System and one or

more ADS valves

inoperable.

BFN-UNIT 2

3.5-3

Amendment No. ~ 269

March 12, 2001

E

MINATION

REFERENCE

(,PROVIDED TO

CANDIDATE

(

S/RVs

3.4.3

3.4

REACTOR COOLANT SYSTEM (RCS)

3.4.3 Safety/Relief Valves (S/RVs)

LCO 3.4.3

The safety function of 12 S/RVs shall be OPERABLE.

APPLICABILITY:

MODES 1,2, and 3.

ACTIONS

(

CONDITION

A. One or more required

S/RVs inoperable.

BFN-UNIT 2

REQUIRED ACTION

A.1

Be in MODE 3.

A.2

Be in MODE 4.

3.4-7

COMPLETION

TIME

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

36 hours

Amendment 253

(

ECCS - Operating

3.5.1

3.5

EMERGENCY CORE COOLING SYSTEMS (ECCS) AND REACTOR CORE

ISOLATION COOLING (RCIC) SYSTEM

3.5.1

ECCS - Operating

LCO 3.5.1

Each ECCS injection/spray subsystem and the Automatic

Depressurization System (ADS) function of six safety/relief valves

shall be OPERABLE.

APPLICABILITY:

MODE 1,

MODES 2 and 3, except high pressure coolant injection (HPCI) and

ADS valves are not required to be OPERABLE with reactor

steam dome pressure s 150 psig.

ACTIONS


NOTE--------------------------------------------------

LCO 3.0.4.b is not applicable to HPCI.

CONDITION

A. One low pressure ECCS

A.1

injection/spray subsystem

inoperable.

OR

One low pressure coolant

injection (LPCI) pump in

both LPCI subsystems

inoperable.

REQUIRED ACTION

Restore low pressure

ECCS injection/spray

subsystem(s) to

OPERABLE status.

COMPLETION

TIME

7 days'"

(continued)

(1) _ This Completion Time may be extended to 14 days on a one-time basis. This temporary approval

expires June 1, 2005.

BFN-UNIT 2

3.5-1

Amendment No. 253, 269, 286, 294

May 9,2005

c

ACTIONS (continued)

CONDITION

REQUIRED ACTION

ECCS - Operating

3.5.1

COMPLETION

TIME

B. Required Action and

8.1

Be in MODE 3.

associated Completion

Time of Condition A not

AND

met.

8.2

Be in MODE 4.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

36 hours

(continued)

(

BFN-UNIT 2

3.5-1 a

Amendment No. 286

December 1, 2003

(

ECCS - Operating

3.5.1

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

C. HPCI System inoperable.

C.1

Verify by administrative

Immediately

means RCIC System is

OPERABLE.

AND

C.2

Restore HPCI System to

14 days

OPERABLE status .

D. HPCI System inoperable.

D.1

Restore HPCI System to

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

OPERABLE status.

AND

OR

Condition A entered.

D.2

Restore low pressure

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

ECCS injection/spray

subsystem to OPERABLE

status .

E. One ADS valve

E.1

Restore ADS valve to

14 days

inoperable.

OPERABLE status.

F. One ADS valve

F.1

Restore ADS valve to

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

inoperable.

OPERABLE status .

AND

OR

Condition A entered.

F.2

Restore low pressure

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

ECCS injection/spray

subsystem to OPERABLE

status.

(continued)

(

BFN-UNIT 2

3.5-2

Amendment No. 2-&d, 269

March 12, 2001

(

ECCS - Operating

3.5.1

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

G. Two or more ADS valves

G.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

inoperable.

AND

OR

G.2

Reduce reactor steam

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

Required Action and

dome pressure to

associated Completion

s; 150 psig.

Time of Condition C, D,

E, or F not met.

H. Two or more low pressure

H.1

Enter LCO 3.0.3.

Immediately

ECCS injection/spray

subsystems inoperable

for reasons other than

Condition A.

OR

HPCI System and one or

more ADS valves

inoperable.

BFN-UNIT 2

3.5-3

Amendment No. ~ 269

March 12, 2001

r

(

21. SRO GENERIC 2.2.24 OOl/CIA/T3/23112/GEN2.2.24/2.5/3.7/SRO/lO/27/07

Given the following plant conditions:

Unit 1 in Mode 5, initial fuel load in progress .

Unit 2 is 100% RTP.

Unit 3 is in Mode 5, CRD drive replacement in progress after 1st portion of fuel moves.

81 RHRSW pump is tagged for impeller replacement.

2C RHR Heat Exchanger tagged for eddy current testing.

The Outside AUO reports that both D RHRSW pump room sump pumps have failed to start

and water level is above the grate of the room sump.

Which ONE of the following describes the required actions for Unit 2?

REFERENCE PROVIDED

A.,;

7 day LCO for Suppression Pool cooling, Suppression Chamber sprays and Drywell sprays

30 day LCO for RHRSW system and Ultimate Heat Sink

B.

30 day LCO for Suppression Pool cooling, Suppression Chamber sprays and Drywell sprays

8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> LCO for RHRSW system and Ultimate Heat Sink

C.

7 day LCO for Suppression Pool cooling, Suppression Chamber sprays and Drywell sprays

8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> LCO for RHRSW system and Ultimate Heat Sink

D.

30 day LCO for Suppression Pool cooling, Suppression Chamber sprays and Drywell sprays

30 day LCO for RHRSW system and Ultimate Heat Sink

KIA Statement:

Equipment Control

2.2.24

Ability to analyze the affect of maintenance activities on LCO status.

KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

plant conditions to correctly determ ine the LCO status resulting from maintenance activities .

References: U2 TSR Section 3.6 and 3.7

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble ,

sort, and integrate the parts of the question to predict an outcome. This requires mentally using this

knowledge and its meaning to predict the correct outcome.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (2) Facility

operating limitations in the technical specifications and their bases.

0610 NRC SRO Exam

REFERENCE PROVIDED: U2 Tech Spec Section 3.6 and 3.7

Plausibility Analysis:

In order to answer this question correctly the candidate must know the following :

-

The 0 RHRSW Pump Room sumps result in 01 , 02 and 03 RHRSW Pumps being inoperable per

Tech Spec Bases.

-

RHRSW flow through the RHR HX is required for SP Cooling, Spray and OW Spray to be operable per

Tech Spec Bases. This leads to 2 RHRSW subsystems INOP for Unit 2.

-

Which RHRSW pumps provide flow to each RHRHX. (system knowledge)

-

Determine the LCO for RHRSW pumps, RHRSW subsystem, SP Cooling, SP Spray, and OW Spray.

A is correct.

B is incorrect. A 30 day LCO is required if only one RHRSW subsystem is INOP. In addition, the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

LCO for RHRSW system applies if 2 units are fueled. (six pumps required) Initial conditions state that only

one unit is fueled.

C is incorrect. The 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> LCO for RHRSW system applies if 2 units are fueled . (six pumps required)

Initial conditions state that only one unit is fueled.

D is incorrect. A 30 day LCO is required if only one RHRSW subsystem is INOP.

(

RHR Suppression Pool Cooling

3.6.2.3

3.6

CONTAINMENT SYSTEMS

3.6.2.3 Residual Heat Removal (RHR) Suppression Pool Cooling

LCO 3.6.2.3

Four RHR suppression pool cooling subsystems shall be

OPERABLE.

APPLICABILITY:

MODES 1, 2, and 3.

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. One RHR suppression

A.1

Restore the RHR

30 days

pool cooling subsystem

suppression pool cooling

inoperable.

subsystem to OPERABLE

status.

B. Two RHR suppression

B.1

Restore one RHR

7 days

pool cooling subsystems

suppression pool cooling

inoperable.

subsystem to OPERABLE

status.

C. Three or more RHR

C.1

Restore required RHR

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

suppression pool cooling

suppression pool cooling

subsystems inoperable.

subsystems to

OPERABLE status.

(continued)

(

BFN-UNIT 2

3.6-31

Amendment No. ~272

June 8,2001

(

RHR Suppression Pool Cooling

3.6.2.3

ACTIONS (continued)

CONDITION

D. Required Action and

associated Completion

Time not met.

REQUIRED ACTION

D.1

Be in MODE 3.

AND

D.2

Be in MODE 4.

COMPLETION

TIME

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

36 hours

BFN-UNIT 2

3.6-32

Amendment No. ~272

June 8,2001

(

RHR Suppression Pool Cooling

3.6.2.3

SURVEILLANCE REQUIREMENTS

SR 3.6.2.3.1

SR 3.6.2.3.2

SURVEILLANCE

Verify each RHR suppression pool cooling

subsystem manual, power operated , and

automatic valve in the flow path that is not

locked, sealed, or otherwise secured in

position is in the correct position or can be

aligned to the correct position.

Verify each RHR pump develops a flow rate

2 9000 gpm through the associated heat

exchanger while operating in the suppression

pool cooling mode.

FREQUENCY

31 days

In accordance

with the Inservice

Testing Program

(

BFN-UNIT 2

3.6-33

Amendment No. 253

(

RHR Suppression Pool Spray

3.6.2.4

3.6

CONTAINMENT SYSTEMS

3.6.2.4 Residual Heat Removal (RHR) Suppression Pool Spray

LCO 3.6.2.4

Four RHR suppression pool spray subsystems shall be

OPERABLE.

APPLICABILITY:

MODES 1, 2, and 3.

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A, One RHR suppression

A,1

Restore the RHR

30 days

pool spray subsystem

suppression pool spray

inoperable.

subsystem to OPERABLE

status.

B. Two RHR suppression

B.1

Restore one RHR

7 days

pool spray subsystems

suppression pool spray

inoperable.

subsystem to OPERABLE

status.

C. Three or more RHR

C.1

Restore required RHR

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

suppression pool spray

suppression pool spray

subsystems inoperable.

subsystems to

OPERABLE status.

D. Required Action and

D.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

associated Completion

Time not met.

AND

D.2

Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

BFN-UNIT 2

3.6-34

Amendment No. 253

(

RHR Suppression Pool Spray

3.6.2.4

SURVEILLANCE REQUIREMENTS

SURVEILLANCE

FREQUENCY

SR 3.6.2.4.1

SR 3.6.2.4.2

Verify each RHR suppression pool spray

31 days

subsystem manual, power operated, and

automatic valve in the flow path that is not

locked, sealed, or otherwise secured in

position is in the correct position or can be

aligned to the correct position.

Verify each suppression pool spray nozzle is

5 years

unobstructed.

(

BFN-UNIT 2

3.6-35

Amendment No. 253

(

RHR Drywell Spray

3.6.2.5

3.6

CONTAINMENT SYSTEMS

3.6.2.5 Residual Heat Removal (RHR) Drywell Spray

LCO 3.6.2.5

Four RHR drywell spray subsystems shall be OPERABLE.

APPLICABI L1TY:

MODES 1, 2, and 3.

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. One RHR drywell spray

A.1

Restore the RHR drywell

30 days

subsystem inoperable.

spray subsystem to

OPERABLE status.

B. Two RHR drywell spray

B.1

Restore one RHR drywell

7 days

subsystems inoperable.

spray subsystem to

OPERABLE status.

C. Three or more RHR

C.1

Restore required RHR

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

drywell spray subsystems

drywell spray subsystems

inoperable.

to OPERABLE status.

D. Required Action and

D.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

associated Completion

Time not met.

AND

D.2

Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

BFN-UNIT 2

3.6-36

Amendment No. 253

(

RHR Drywell Spray

3.6.2.5

SURVEILLANCE REQUIREMENTS

SURVEILLANCE

FREQUENCY

SR 3.6.2.5.1

SR 3.6.2.5.2

Verify each RHR drywell spray subsystem

31 days

manual, power operated, and automatic valve

in the flow path that is not locked, sealed , or

otherwise secured in position is in the correct

position or can be aligned to the correct

position.

Verify each drywell spray nozzle is

5 years

unobstructed.

BFN-UNIT 2

3.6-37

Amendment No. 253

(

RHRSW System and UHS

3.7.1

3.7

PLANT SYSTEMS

3.7.1

Residual Heat Removal Service Water (RHRSW) System and Ultimate Heat

Sink (UHS)

LCO 3.7.1


NOTE----------------------------------------

The number of required RHRSW pumps may be reduced by one

for each fueled unit that has been in MODE 4 or 5 for ~ 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Four RHRSW subsystems and UHS shall be OPERABLE with the

number of OPERABLE pumps as listed below:

1. 1 unit fueled - four OPERABLE RHRSW pumps.

2. 2 units fueled - six OPERABLE RHRSW pumps.

3. 3 units fueled - eight OPERABLE RHRSW pumps.

(

APPLICABILITY:

MODES 1, 2, and 3.

BFN-UNIT 2

3.7-1

Amendment No. 254

September 08, 1998

(

ACTIONS

CONDITION

REQUIRED ACTION

RHRSW System and UHS

3.7.1

COMPLETION

TIME

A. One required RHRSW

pump inoperable.

A.1


NOTES-----------

1.

Only applicable for the

2 units fueled

condition.

2.

Only four RHRSW

pumps powered from

a separate 4 kV

shutdown board are

required to be

OPERABLE if the

other fueled unit has

been in MODE 4 or 5

for ~ 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Verify five RHRSW

pumps powered from

separate 4 kV shutdown

boards are OPERABLE.

Immediately

A.2

Restore required RHRSW

30 days

pump to OPERABLE

status.

(continued)

(

BFN-UNIT 2

3.7-2

Amendment No. 254

September 08, 1998

(

RHRSW System and UHS

3.7.1

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

B. One RHRSW subsystem

8.1


NOTE-------------

inoperable.

Enter applicable

Conditions and Required

Actions of LCO 3.4.7,

"Residual Heat Removal

(RHR) Shutdown Cooling

- Hot Shutdown," for RHR

shutdown cooling made

inoperable by the

RHRSW system.


Restore RHRSW

30 days

subsystem to OPERABLE

status.

C. Two required RHRSW

C.1

Restore one inoperable

7 days

pumps inoperable.

RHRSW pump to

OPERABLE status.

D. Two RHRSW subsystems

D.1


NOTE-------------

inoperable..

Enter applicable

Conditions and Required

Actions of LCO 3.4.7, for

RHR shutdown cooling

made inoperable by the

RHRSW System.


Restore one RHRSW

7 days

subsystem to OPERABLE

status.

(continued)

BFN-UNIT 2

3.7-3

Amendment No. 254

September 08, 1998

c.

RHRSW System and UHS

3.7.1

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

E. Three or more required

E.1

Restore one RHRSW

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

RHRSW pumps

pump to OPERABLE

inoperable.

status.

F. Three or more RHRSW

F.1


NOTE-------------

subsystems inoperable.

Enter applicable

Conditions and Required

Actions of LCO 3.4.7 for

RHR shutdown cooling

made inoperable by the

RHRSW System.


Restore one RHRSW

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

subsystem to OPERABLE

status.

G. Required Action and

G.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

associated Completion

Time not met.

AND

G.2

Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

OR

UHS inoperable

BFN-UNIT 2

3.7-4

Amendment No. 254

September 08, 1998

)

E

MINATION

REFERENCE

.(;PROVIDED TO

CANDIDATE

(

RHR Suppression Pool Cooling

3.6.2.3

3.6

CONTAINMENT SYSTEMS

3.6.2.3 Residual Heat Removal (RHR) Suppression Pool Cooling

LCO 3.6.2.3

Four RHR suppression pool cooling subsystems shall be

OPERABLE.

APPLICABILITY:

MODES 1, 2, and 3.

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. One RHR suppression

A.1

Restore the RHR

30 days

pool cooling subsystem

suppression pool cooling

inoperable.

subsystem to OPERABLE

status.

B. Two RHR suppression

B.1

Restore one RHR

7 days

pool cooling subsystems

suppression pool cooling

inoperable.

subsystem to OPERABLE

status.

C. Three or more RHR

C.1

Restore required RHR

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

suppression pool cooling

suppression pool cooling

subsystems inoperable.

subsystems to

OPERABLE status.

(continued)

(

BFN-UNIT 2

3.6-31

Amendment No. ~272

June 8,2001

(

RHR Suppression Pool Cooling

3.6.2.3

ACTIONS (continued)

CONDITION

D. Required Action and

associated Completion

Time not met.

REQUIRED ACTION

0 .1

Be in MODE 3.

AND

0 .2

Be in MODE 4.

COMPLETION

TIME

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

36 hours

BFN-UNIT 2

3.6-32

Amendment No. ~272

June 8,2001

(

RHR Suppression Pool Cooling

3.6.2.3

SURVEILLANCE REQUIREMENTS

SR 3.6.2.3 .1

SR 3.6.2.3.2

BFN-UNIT 2

SURVEILLANCE

Verify each RHR suppression pool cooling

subsystem manual, power operated, and

automatic valve in the flow path that is not

locked, sealed, or otherwise secured in

position is in the correct position or can be

aligned to the correct position.

Verify each RHR pump develops a flow rate

~ 9000 gpm through the associated heat

exchanger while operating in the suppression

pool cooling mode.

3.6-33

FREQUENCY

31 days

In accordance

with the Inservice

Testing Program

Amendment No. 253

(

RHR Suppression Pool Spray

3.6.2.4

3.6

CONTAINMENT SYSTEMS

3.6.2.4 Residual Heat Removal (RHR) Suppression Pool Spray

LCO 3.6.2.4

Four RHR suppression pool spray subsystems shall be

OPERABLE.

APPLICABILITY:

MODES 1, 2, and 3.

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. One RHR suppression

A.1

Restore the RHR

30 days

pool spray subsystem

suppression pool spray

inoperable.

subsystem to OPERABLE

status.

B. Two RHR suppression

B.1

Restore one RHR

7 days

pool spray subsystems

suppression pool spray

inoperable.

subsystem to OPERABLE

status.

C. Three or more RHR

C.1

Restore required RHR

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

suppression pool spray

suppression pool spray

subsystems inoperable.

subsystems to

OPERABLE status.

D. Required Action and

D.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

associated Completion

Time not met.

AND

D.2

Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

(

BFN-UNIT 2

3.6-34

Amendment No. 253

RHR Suppression Pool Spray

3.6.2.4

SURVEILLANCE REQUIREMENTS

SURVEILLANCE

FREQUENCY

SR 3.6.2.4.1

SR 3.6.2.4.2

BFN-UNIT 2

Verify each RHR suppression pool spray

31 days

subsystem manual, power operated, and

automatic valve in the flow path that is not

locked, sealed, or otherwise secured in

position is in the correct position or can be

aligned to the correct position.

Verify each suppression pool spray nozzle is

5 years

unobstructed.

3.6-35

Amendment No. 253

(

RHR Drywell Spray

3.6.2.5

3.6

CONTAINMENT SYSTEMS

3.6.2.5 Residual Heat Removal (RHR) Drywell Spray

LCO 3.6.2.5

Four RHR drywell spray subsystems shall be OPERABLE.

APPLICABILITY:

MODES 1,2, and 3.

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. One RHR drywell spray

A.1

Restore the RHR drywell

30 days

subsystem inoperable.

spray subsystem to

OPERABLE status.

B. Two RHR drywell spray

B.1

Restore one RHR drywell

7 days

subsystems inoperable.

spray subsystem to

OPERABLE status.

C. Three or more RHR

C.1

Restore required RHR

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

drywell spray subsystems

drywell spray subsystems

inoperable.

to OPERABLE status.

D. Required Action and

D.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

associated Completion

Time not met.

AND

D.2

Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

(

BFN-UNIT 2

3.6-36

Amendment No. 253

(

RHR Drywell Spray

3.6.2.5

SURVEILLANCE REQUIREMENTS

SURVEILLANCE

FREQUENCY

SR 3.6.2.5.1

SR 3.6.2.5.2

Verify each RHR drywell spray subsystem

31 days

manual, power operated, and automatic valve

in the flow path that is not locked, sealed, or

otherwise secured in position is in the correct

position or can be aligned to the correct

position.

Verify each drywell spray nozzle is

5 years

unobstructed.

(

BFN-UNIT 2

3.6-37

Amendment No. 253

(

RHRSW System and UHS

3.7.1

3.7

PLANT SYSTEMS

3.7.1

Residual Heat Removal Service Water (RHRSW) System and Ultimate Heat

Sink (UHS)

LCO 3.7.1


NOTE----------------------------------------

The number of required RHRSW pumps may be reduced by one

for each fueled unit that has been in MODE 4 or 5 for ~ 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Four RHRSW subsystems and UHS shall be OPERABLE with the

number of OPERABLE pumps as listed below:

1. 1 unit fueled - four OPERABLE RHRSW pumps.

2. 2 units fueled - six OPERABLE RHRSW pumps.

3. 3 units fueled - eight OPERABLE RHRSW pumps.

APPLICABILITY:

MODES 1, 2, and 3.

BFN-UNIT 2

3.7-1

Amendment No. 254

September 08, 1998

(

ACTIONS

CONDITION

REQUIRED ACTION

RHRSW System and UHS

3.7.1

COMPLETION

TIME

A. One required RHRSW

pump inoperable.

A.1


NOTES-----------

1.

Only applicable for the

2 units fueled

condition.

2.

Only four RHRSW

pumps powered from

a separate 4 kV

shutdown board are

required to be

OPERABLE if the

other fueled unit has

been in MODE 4 or 5

for ~ 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Verify five RHRSW

pumps powered from

separate 4 kV shutdown

boards are OPERABLE.

Immediately

A.2

Restore required RHRSW

30 days

pump to OPERABLE

status .

(continued)

(

BFN-UNIT 2

3.7-2

Amendment No. 254

September 08, 1998

(

RHRSW System and UHS

3.7.1

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

B. One RHRSW subsystem

B.1


NOTE-------------

inoperable.

Enter applicable

Conditions and Required

Actions of LCO 3.4.7,

"Residual Heat Removal

(RHR) Shutdown Cooling

- Hot Shutdown," for RHR

shutdown cooling made

inoperable by the

RHRSW system.


Restore RHRSW

30 days

subsystem to OPERABLE

status.

C. Two required RHRSW

C.1

Restore one inoperable

7 days

pumps inoperable.

RHRSW pump to

OPERABLE status.

D. Two RHRSW subsystems

D.1


NOTE-------------

inoperable..

Enter applicable

Conditions and Required

Actions of LCO 3.4.7, for

RHR shutdown cooling

made inoperable by the

RHRSW System.


Restore one RHRSW

7 days

subsystem to OPERABLE

status.

(continued)

(

BFN-UNIT 2

3.7-3

Amendment No. 254

September 08, 1998

RHRSW System and UHS

3.7.1

ACTIONS (continued)

CONDITION

REQUIRED ACTION

COMPLETION

TIME

E. Three or more required

E.1

Restore one RHRSW

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

RHRSWpumps

pump to OPERABLE

inoperable.

status.

F. Three or more RHRSW

F.1


NOTE-------------

subsystems inoperable.

Enter applicable

Conditions and Required

Actions of LCO 3.4.7 for

RHR shutdown cooling

made inoperable by the

RHRSW System.


Restore one RHRSW

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

subsystem to OPERABLE

status.

G. Required Action and

G.1

Be in MODE 3.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

associated Completion

Time not met.

AND

G.2

Be in MODE 4.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />

OR

UHS inoperable

BFN-UNIT 2

3.7-4

Amendment No. 254

September 08, 1998

22. SRO GENERIC 2.3.3 OOl IMEMlT3111GENERIC 2.3.3IISRO ONLY/ll/27/07 RMS

During performance of 0-SR-DCS3.1 .2.1, Spent Fuel Storage Inspection, you receive a report that a pile l

of leaves and other debris has been found at the base of Overpack BFN-0-CASK-079-01 00/8 .

(

Wh ich ONE of the following describes the required action(s)?

I

I;

A.

Notify Maintenance and Modifications Management within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. No further action is required.

B.

Notify the Maintenance Shift Manager to remove the debris and clear the blockage. Note that the

blockage was found in the Post Test Remarks.

C. Contact Facilities Management to remove the debris and clear the blockage.

No notations are

required since the blockage was cleared .

D~ Coordinate with Radiation Protection to remove the debris and clear the blockage. Note that the

blockage was found and cleared in the Post Test Remarks.

KIA Statement:

Radiation Control

2.3.3 Knowledge of SRO responsibilities for auxiliary systems that are outside the control room (e.g.,

waste disposal and handling systems).

KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

plant conditions to determine the required actions following discovery of a loss of radioactive material

control.

References: O-SR-DCS 3.1.2.1

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble,

sort, and integrate the parts of the question to predict an outcome. This requires mentally using this

knowledge and its mean ing to predict the correct outcome.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (4) Radiation

hazards that may arise during normal and abnormal situations, including maintenance activities and

various contam ination conditions.

0610 NRC SRO Exam

REFERENCE PROVIDED: None

Plausibility Analysis:

(

In order to answer this question correctly, the candidate must:

1. Determine the appropriate action to take regarding the blockage.

2. Determine the documentation required based on Item 1.

A is incorrect. Maintenance and Modifications Management is only notified if the debris cannot be

cleared. This is plausible becuase the notification time required is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

B is incorrect. The Maintenance Shift Manager is only contacted if the blockage CANNOT be removed.

This is plausible because the documentation requirements are correct.

C is incorrect. The Facilities Department is not responsible for HI-STORM debris removal. This is

plausible since Facilities is responsible for general cleanliness inside the protected area EXCEPT the

ISFSI Pad area.

D is correct.

(

BFN

Spent Fuel Storage Inspection

0-SR-DCS3.1.2.1

Unit 0

Rev. 0004

Page 7 of 10

Date

7.2

Single HI-STORM Inspection Prior to Placement on the ISFSI

PAD: (continued)

[4]

IF the HI-STORM(s) located on the ISFI Pad will not be

inspected during the performance of this surveillance, THEN

MARK the HI-STORM(s) listed on Attachment 2 as N/A.

(Otherwise N/A this step.)

7.3

Inspection of HI-STORM(s) Located on the ISFSI Pad

[1]

PERFORM Attachment 2, HI-STORM Inspection Log.

[2]

IF any Inlet or Outlet Vents are found to have blockage, THEN

PERFORM the following: (Otherwise N/A this section.)

[2.1]

NOTIFY the Unit Supervisor which HI-STORM

ventilation ducts have blockage.

[2.2]

IF the blockage can be readily removed, THEN

PERFORM the following: (Otherwise N/A)

A..ffiIIF

nd COORDINATE wit~R-a"':"d-ia-ti-o--n'

Protectio

for debris removal.

.~

B.

REMOVE the blockage and debris from associated

HI-STORM(s).

C.

RECORD the HI-STORM UNID and specific vent(s)

that were blocked and cleared in the Narrative Log

for all HI-STORM(s) with blockage.

(

BFN

Spent Fuel Storage Inspection

0-SR-DCS3.1.2.1

UnitO

Rev. 0004

Page 8 of 10

Date

7.3

Inspection of HI-STORM(s) Located on the ISFSI Pad (continued)

[2.3]

IF the blockage cannot be readily removed, THEN

PERFORM the following: (Otherwise N/A)

A.

NOTIFY the Shift Maintenance Manager to

PERFORM applicable section of

MSI-O-079-DCS036 ISFSI Abnormal Conditions

Procedure.

B.

IF acceptance criteria are not met within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />,

THEN

c.

NOTIFY Maintenance and Modifications

Management to start preparation for MPC up load

to HI-TRAC. (Otherwise N/A)

7.4

Completion and Notification

[1]

VERIFY the Inlet and Outlet Vents on all HI-STORM(s)

inspected on Attachment 2 are free of blockage.

[2]

COMPLETE Attachment 1, Surveillance Procedure Review

Form, up to Unit Supervisor review.

[3]

NOTIFY the Unit One, Two, and Three Unit Operators (UOs)

this Surveillance Procedure is complete.

[4]

NOTIFY the Unit Supervisor this Surveillance Procedure is

complete and PROVIDE status of any required Corrective

Action per SPP-8.1 or unsatisfactory performances.

8.0

ATTACHMENTS

Attachment 1: Surveillance Procedure Review Form

Attachment 2: HI-STORM Inspection Log

US

__(AC) I

(

23. SRO GENERIC 2.3.9 OOl/C/A/T3/CONTAINMENT//G2.3.9/2.5/3.4/R1TCK

Given the following plant conditions:

Unit 2 is commencing a scheduled reactor shutdown due to a leak in the Drywell.

The Operations Manager has directed that the Drywell and Torus be de-inerted so that an

entry team can inspect the Drywell prior to cold shutdown.

Containment entry is scheduled in 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br />.

The unit is currently at 25% power.

Which ONE of the following describes the earliest time and method for purging the containment to allow

for Drywell entry?

A~ Immediately begin purging the Drywell. The Torus cannot be purged concurrently.

B.

Drywell purging cannot be commenced until the unit is <15% power. The Torus cannot be purged

concurrently.

C.

Immediately begin purging the Drywell and the Torus concurrently.

D. Drywell purging cannot be commenced until the unit is <15% power. The Torus can be purged

concurrently.

KIA Statement:

Radiation Control

2.3.9 Knowledge of the process for performing a containment purge.

KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

plant conditions and times to correctly determine the process for performing a containment purge.

References: 2-01-64, Rev.1 06, section 8.1

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble,

sort, and integrate the parts of the question to predict an outcome. This requires mentally using this

knowledge and its meaning to predict the correct outcome .

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (5) Assessment

of facility conditions and selection of appropriate procedures during normal , abnormal, and emergency

situations.

0610 NRC SRO Exam

(

REFERENCE PROVIDED: None

Plausibility Analysis:

In order to answer this question correctly, the candidate must:

Plausibility Analysis:

The primary decisions that must be made to correctly answer this question are:

1. Can the purge be started immediately or must it commence after power is reduced below 15%?

2. Can the Drywell and Torus be purged simultaneously, or only one at a time?

Although the TS bases for 3.6.3.2 is clear in describing the ability to commence purging 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> prior to

going less than 15% RTP, the wording in Applicability (b) ofTS 3.6.3.2 has been known to cause

confusion. This makes Answer Band C plausible.

The ability to simultaneously purge the Drywell and Torus is well within the capability of the system,

however this is prohibited due to an analysis of the potential for containment over-pressurization if a

LOCA occurred during the evolution . This makes Answer C and D plausible because the purge lineup is

available.

Answer A is the correct answer.

Answer B is incorrect since you don't have to wait until 15% power to start de-inerting. The shutdown is

scheduled, therefore you can begin de-inerting 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> prior to reducing power < 15%.

Answer C is incorrect since you cannot purge the Drywell and Torus concurrently when in Mode 1,2 or 3.

Answer D is incorrect since you don't have to wait until 15% power to start de-inerting and you cannot

purge the Drywell and Torus concurrently when in mode 1,2 or 3.

(

(

BFN

Containment Inerting System

2-01-76

Unit 2

Rev. 0062

Page 8 of 82

3.0

PRECAUTIONS AND LIMITATIONS

A.

During normal operation, Primary Containment oxygen concentration is

required to be maintained less than 4% (by volume) by dilution with pure

nitrogen. This will minimize the potential for combustion with the hydrogen that

could result from fuel damage following a Loss Of Cooling Accident (LOCA).

B.

During startup, the Drywell and Suppression Chamber is required to be inerted

within 24-hours of reaching 15% Thermal Power. De-inerting may commence

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> prior to reducing Thermal Power to <15% prior to a Reactor

Shutdown .

C.

H2/02 Analyzers are normally maintained in a standby configuration. Analyzers

may be placed in service to monitor the Drywell or the Suppression Chamber at

Operations discretion. If one of the analyzers is inoperable, then the other

analyzer should be utilized to satisfy TRM requirements. Operable analyzer

may be transferred to Suppression Chamber for a reading, then placed back to

Drywell as often as necessary. H2/02Analyzers flow rate outside 12.75

and 17.25 scth renders monitor inoperable.

D.

Containment Inerting System supplies makeup gas to accommodate

temperature changes and leakage during normal power generation.

E.

After Drywelll Suppression Chamber differential pressure has been established,

any subsequent makeup or venting of Primary Containment is required to be

logged in 2-SI-4.7.A.2.a, Primary Containment Nitrogen Consumption and

Leakage.

F.

Drywell to Suppression Chamber differential pressure should NOT exceed

1.3 psid.

G.

Minimum storage tank level for tank A is 140 inches H20 on level indicator,

0-L1-076-0003, which corresponds to 3,500 gallons of liquid nitrogen. Additional

supply is necessary when level drops to 3,500 gallons or prior to inerting.

H.

The 6320-gallon Liquid Nitrogen Storage Tank (tank A) is designed to store

6,000 gallons of liquid. This is equivalent to 550,000 standard cubic feet of gas

(one gallon of liquid nitrogen =93.11 SCF). Due to purging during inerting

operation, over one million SCF of nitrogen gas (two full tanks or one tank and

one supply transport) will be required to fully inert containment.

I.

Use of keylock bypass switch, 2-HS-76-69(79), on Panel 2-9-54(55) is only

permitted after a valid Group 6 Isolation with permission from Shift Manager.

J.

Drywell entry when a corrected value of oxygen content is <19.5% is permitted

only with use of a self-contained breathing apparatus (SCBA).

K.

Prior to admitting nitrogen for inerting, a "NO ENTRY" sign is required to be

posted at Drywell entrance.

(

BFN

Containment Inerting System

2-01-76

Unit 2

Rev. 0062

Page 9 of 82

3.0

PRECAUTIONS AND LIMITATIONS (continued)

L.

Liquid nitrogen freezes skin on contact. Injury can also result from handling

bare piping filled with liquid nitrogen. Caution should be used to prevent

exposure from leaks and spills of liquid and insulated gloves should be worn to

avoid direct contact with cold piping.

M.

BFN FSAR stipulates that 2-FCV-84-19 will be maintained closed except during

surveillance testing or when directed by EOls.

N.

The following valves are interlocked closed with Mode Switch in RUN unless

Division I and II RUN MODE BYPASS Switches, 2-HS-64-24 and 2-HS-64-25,

are in BYPASS position:

Div I (BYPASS SW 2-HS-64-24)

Div II (BYPASS SW 2-HS-64-25)

2-64-18

2-64-17

2-64-19

2-64-30

2-64-29

2-64-33

2-64-32

2-76-24

O.

TOE 0-97-064-0823 evaluated the impact of inerting or purging Suppression

Chamber and Drywell concurrently (Both FCV 64-19 and FCV 64-18 open at

the same time). This evaluation concluded there is a slight potential to over

pressurize primary containment in the event of a large break LOCA with both

FCV 64-19 and FCV 64-18 open at the same time with Reactor NOT in Cold

Shutdown. This situation could create a large bypass flow path between the

Drywell and the Suppression Chamber. Therefore, Suppression Chamber and

the Drywell are NOT allowed be inerted or purged at the same time when

Reactor is NOT in Cold Shutdown.

P.

Unless authorized by Shift Manager, applicable CAD TANK, level indicator's in

the main control rooms (Unit 1 or 3) is required to be indicating 100% prior to

filling/topping off Nitrogen tanks A or B (Refer to 2(3)-01-84 for filling CAD

TANKS)

Q.

Drywell O2 CONCENTRATION indicators on Panels 2-9-54 and 2-9-55 are no

longer calibrated in the high range. PIP-97-189 should be used to correct O2

CONCENTRATION value as a reference until a grab sample is taken. Grab

sample values of O2 concentration are expected to vary from high-range O2

analyzer values.

(

Primary Containment Oxygen Concentration

3.6.3.2

3.6

CONTAINMENT SYSTEMS

3.6.3.2 Primary Containment Oxygen Concentration

LCO 3.6.3.2

The primary containment oxygen concentration shall be < 4.0

volume percent.

APPLICABILITY:

MODE 1 during the time period:

a. From 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after THERMAL POWER is > 15% RTP

following startup, to

b. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> prior to reducing THERMAL POWER to < 15% RTP

prior to the next scheduled reactor shutdown .

ACTIONS

CONDITION

REQUIRED ACTION

COMPLETION

TIME

A. Primary containment

A.1

Restore oxygen

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />

oxygen concentration not

concentration to within

within limit.

limit.

B. Required Action and

8.1

Reduce THERMAL

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

associated Completion

POWER to s 15% RTP.

Time not met.

BFN-UNIT 2

3.6-42

Amendment No. 253

(

24. SRO GENERIC 2.4.21 00lIC/A/T3/RHRIB15/GENERIC 2.4.21//SRO ONLY/l1l27/07 RMS

Given the following plant conditions:

During normal full power operation of Unit-3, a loss of 250VDC power causes the RHR

System I (Div I) Logic Power Failure alarm to occur.

I&C investigates and reports a blow fuse in the logic circuit.

Prior to any corrective action being taken, a Loss of Coolant Accident results in the followinq

plant conditions:

RPV Level

RPV Pressure

Drywell Pressure

8elowTAF

100 psig

21 psig

Which ONE of the following describes the response of Loop I RHR pumps and what subsequent actions

must be taken to address these plant conditions?

A.

RHR Pumps 3A and 3C should be manually started in DW Spray mode. 38 and 3D auto start in

LPCI mode and should remain there until RPV level is above TAF ..

B.

RHR Pump 3A only will auto start in LPCI mode. 3C can be manually started in LPCI mode and

should remain there until RPV level is above TAF. 38 and 3D should be manually started in DW

Spray mode.

C.

RHR Pump 3C only will auto start in LPCI mode. 3A can be manually started in LPCI mode and

should remain there until RPV level is above TAF. 38 and 3D should be manually started in LPCI

mode.

0 .01 All four (4) RHR pumps auto start in the LPCI mode and should remain there until RPV level is

above TAF.

KIA Statement:

Emergency Procedures IPlan

2.4.21 Knowledge of the parameters and logic used to assess the status of safety functions including:1

Reactivity control 2. Core cooling and heat removal 3. Reactor coolant system integrity 4. Containment

conditions 5. Radioactivity release control

KIA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

plant conditions to determine the response of RHR system components during an emergency based on a

logic failure.

References:

OPL171.044, 3-ARP-9-3D (5), 1-ARP-9-3D (5), 2-ARP-9-3D (5)

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble,

sort, and integrate the parts of the question to predict an outcome. This requires mentally using this

knowledge and its meaning to predict the correct outcome.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (5) Assessment

of facility conditions and selection of appropriate procedures during normal, abnormal, and emergency

situations.

0610 NRC SRO Exam

REFERENCE PROVIDED: None

Plausibility Analysis:

In order to answer this question correctly, the candidate must determine the following :

1. Recognize how a 1055 of Div 1 logic power affects the RHR pump initiation logic.

2. Recognize the difference between Unit-3 logic and Unit 1/2 logic.

3. Determine the correct application of EOI requirements with RPV level below TAF.

A is incorrect. 3A and 3C RHR pumps auto start in LPCI mode. It is not appropriate to divert LPCI

injection for containment control until RPV level has been restored above TAF. This is plausible because

the Div 1 pumps on Unit 1/2 will not start automatically.

B is incorrect. 3C RHR pump will start in LPCI mode. It is not appropriate to divert LPCI injection for

containment control until RPV level has been restored above TAF. This is plausible because the CAS

logic for Unit 1/2 are divided into "preferred" and "non-preferred" pumps as well as Divisionalized initiation

logic.

C is incorrect. 3A RHR pump will auto start in LPCI mode. 3C and 3D RHR pumps were not affected by

the logic power failure and would start in LPCI mode. This is plausible because the CAS logic for Unit 1/2

are divided into "preferred" and "non-preferred" pumps as well as Divisionalized initiation logic.

D is correct.

OPL171.044

Revision 15

Page 49 of 159

INSTRUCTOR NOTES

4.

Pumps Trip/interlocks

a.

Electrical Faults

Obj. V.D.8.

b.

Loss of suction path

Obj. V.C.7.

c.

Each RHR pump has a NORMAUEMERGENCY

Obj. V.C.7.

switch at the breaker.

(1)

With the switch in the EMERGENCY position,

the pump can only be started from the breaker

(Le. automatic, local, and control room starts

are removed) and then only if the associated

pump drain valve is closed.

(2)

With switch in the EMERGENCY position, the

pump will trip only from operation of breaker

control switch, Shutdown board load shed, and

electrical faults.

d.

With an LPCI initiation signal present, the local

Obj. V.C.7.

station cannot be used to stop the pump.

(1)

The "white" light above the control switch in the

control room indicate one of the following:

(a)

The breaker is tripped with the control

switch in the Normal-Atter-Start or Start

position

(b)

Atter an automatic start, the white light

Red target on

would not come on if the pump tripped

control switch

unless the control switch was place to the

Start position.

(c)

The pump is running at "overload amp

condition".

e.

Since Unit 1 and Unit 2 share the U1/2 diesel as an

Obj. V.C.8.

onsite power supply, the possibility existed that the

TP-45, 46, 47,

diesels could be lost due to an overload conditions if

and 48

Unit 1 and Unit 2 equipment were to start on the

TP-61, 62, 63, 64

board at the same time.

To prevent this, each Unit was assigned

"Preferred and Non-preferred" pumps and logic

controls the pumps that are automatically started

based upon which unit(s) is/are experiencing an

accident.

(

OPL171.044

Revision 15

Page 50 of 159

INSTRUCTOR NOTES

Note:

Presently Unit 1 Accident signal will not affect Unit 2 due to DCN H2?35A that lifted wires

from relays. Unit 2 will still affect Unit 1.

However, the following represents modifications

to the inter-tie logic as it will be upon Unit 1 recovery.

f.

(1)

Unit 1 Preferred RHR pumps are 1A and 1C

(2)

Unit 2 Preferred RHR pumps are 28 and 2D

(3)

Unit 2 initiation logic is as follows: Div 1 RHR

logic initiates Div 1 pumps ( A and C), and

Div 2 logic initiates Div 2 pumps (B and D)

Accident Signal

(1)

LOCA signals are divided into two separate

signals, one referred to as a Pre Accident

Signal (PAS) and the other referred to as a

Common Accident Signal (CAS).

  • PAS

-122" Rxwater level (Level 1)

OR

2.45 psig OW pressure

-122" Rx water level (Level 1)

OR

2.45 psig OW pressure AND <450

psig Rxpressure

(2)

If a unit receives an accident signal, then all

its respective RHR and Core Spray pumps

will sequence on based upon power source

to the SO Boards.

(3)

All RHR and Core Spray pumps on the non-

affected unit will trip (if running) and will be

blocked from manual starting for 60 seconds.

Obj. V.B.13.

Obj. V.C.3

Obj. V.C.?

Obj. V.D.6

Obj. V.E.II

Obj. V.B.13.

Obj. V.C.3

Obj. V.C.?

Obj. V.D.6

Obj. V.E.II

Note:

It should be clear

that the only

difference

between the two

signals is the

inclusion of Rx

pressure in the

CAS signal. The

PAS signal is an

anticipatory signal

that allows the

DG's to start on

rising OW

pressure and be

ready should a

CAS be received.

OPL171.044

Revision 15

Page 51 of 159

(

INSTRUCTOR NOTES

(4)

After 60 seconds all RHR pumps on the non-

Operator diligence

affected unit may be manually started.

required to

(5)

The non-preferred pumps on the non-

prevent

overloading SD

affected unit are also prevented from

boards/DG's

automatically starting until the affected unit's

accident signal is clear.

(6)

The preferred pumps on the non-affected

unit are locked out from automatically starting

until the affected unit accident signal is clear

OR the non-affected unit receives an

accident signal.

g.

4KV Shutdown Board Load Shed

Obj. V.C.8.

(1)

A stripping of motor loads on the 4KV boards

occurs when the board experiences an

undervoltage condition. This is referred to as a

4KV Load Shed. This shed prepares the board

for the DG ensuring the DG will tie on to the

bus unloaded and without faults.

(2)

The Load Shed occurs when an undervoltage

is experienced on the board i.e. or if the Diesel

were tied to the board (only source) and one

of the units experienced an accident signal

which trips the Diesel output breaker.

(3)

Then, when the Diesel output breaker

interlocks are satisfied, the DG output

breaker would close and, if an initiation signal

is present (CAS) the RHR, CS, and RHRSW

pumps would sequence on

(4)

Following an initiation of a Common Accident

Signal (which trips the diesel breaker), if a

subsequent accident signal is received from

another unit, a second diesel breaker trip on

a "unit priority" basis is provided to ensure

that the Shutdown boards are stripped prior to

starting the RHR pumps and other ECCS

loads

(5)

When an accident signal trip of the diesel

Occurs due to

breakers is initiated from one unit (CASA or

actuation of the

(

CASB), subsequent CAS trips of all eight

diesel breaker

diesel breakers are blocked.

TSCRN relay

(

RHR

SYS I

LOGIC

POWER FAILURE

I

5

REV 0025

Panel 9-3

3-XA- 55-3 D

SENSOR/TRI P POINT:

10A- K14 Relay

UNIT 3

3-ARP-9-3D

Page 6

Loss of 250V DC power

SENSOR LOCATION:

Panel 3-9-32,

Aux Instr Rm,

El 593'

PROBABLE CAUSE :

1.

Failed fuse .

AUTOMATI C ACTION:

2.

Loss of 25 0V DC power

s upply at 250V DC RMOV Bd 3B.

Non e

OPERATOR ACTION:

1.

DISPATCH personnel

to 250V DC RMOV Bd 3B,

Breaker 1E2 ,

t o verify position .

NOTE :

2.

DISPATCH personnel to Panel 3-9-32 t o check 10-AMP

fuses

10A-F1A and 10A-F2A.

3 .

REFER TO Te ch Spec 3.3.5.1 ,

3.5 . 1 ,

3.5 .2 ,

3 .6 .2 .3 ,

3.6 .2 .4, 3.6 .2.5,

and

TRM 3.3.3 .4.

IF alarm is valid ,

THEN t he fo llowing will

occur:

3A and 3C RHR Pumps wi l l

not receive an auto start

signal from Div I Logic.

3A and 3C RHR Pump wi l l

receive an auto start signal from Div II Logic .

SYS I Inboard Injection Valve will not receive an auto op en signal from DIV

I Logic.

SYS I Inboard Injection Valve will not manually open from the control room

due to loss of 450 psig logic from DIV I.

The SYS I

I nboa r d Injection Valve will

receive an

auto open signal from DIV II Logic .

REFERENCES :

3-45N620-2;

3- 45E712- 2 ;

FSAR 8 . 6 . 4 .2 ;

Tech Spec 3 .3 . 5 . 1 ,

Emergency Core Coo l i ng System

(ECCS)

Instrumentation;

3.5 .1,

ECCS - Operating;

3 .5.2,

ECCS -

Shutdown;

3 .6 . 2 .3 ,

Residual

Heat Removal

(RHR) Suppression Pool Cooling ,

3.6 .2.4 ,

Re sidual

Heat Removal

(RHR) Suppression Pool

Spray;

3 .6 .2.5 , Residual Heat Removal

(RHR) Drywell Spray,

TRM 3 .3.3 .4 ECCS and RCIC Trip System Bus Power Monitors.

(

BFN

Unit 1

RHR

SYS I LOGIC

POWER FAILURE

(Page 1 of 1)

Panel 9-3

XA-55-3D

Sensorrrrip Point:

10A-K1A Relay

1-ARP-9-3D

Rev. 0021

Page 8 of 43

Loss of 250V DC power

Sensor

Location:

Probable

Cause:

Automatic

Action:

Operator

Action:

1-PNLA-009-0032

Aux Instr. Rm, EI 593'

A. Cleared fuse.

B. Loss of 250V DC power supply.

None

A.

DISPATCH personnel to 250V DC Rx MOV Bd 1B, breaker 1E2, to

verify position. (Rx Bldg, EI593', R-1 Q-L1NE)

B. DISPATCH personnel to 1-PNLA-009-0032 to check fuses 10A-F1A

and 10A-F2A (10 amp).

C. REFER TO Tech Spec Sections 3.3.5.1, 3.5.1, 3.5.2, 3.6.2.3,

3.6.2.4, 3.6.2.5, TRM Section 3.3.3.4.

NOTE

n

o

o

IF alarm is valid, THEN the following will occur:

1A RHR Pump will NOT auto start.

1C RHR Pump will NOT auto start.

SYS I Inboard Injection Valve will NOT receive an auto open signal.

SYS I Inboard Injection Valve will NOT manually open from the control room due to loss of

450 psig logic from DIV I.

References:

1-45E602-2

1-45E712-2

1-730E920-4 and -12

BFN

Unit 2

RHR SYS I

LOGIC POWER

FAILURE

(Page 1 of1)

Panel 2-9-3

2-XA-55-3D

SensorlTrip Point:

2-RLY-074-10A-K1A

2-ARP-9-3D

Rev. 0025

Page 8 of 42

Loss of 250V DC power

Sensor

Location:

Probable

Cause:

Automatic

Action:

Operator

Action:

Panel 2-9-32, Aux Instr Rm, EI 593'

A. Cleared fuse.

B. Loss of 250V DC power supply, at 250V DC RMOV Board 2B.

None

A. DISPATCH personnel to Panel 2-9-32 to check 10-amp fuses

10A-F1A and 10A-F2A.

B. DISPATCH personnel to 250V DC RMOV Bd 2B Breaker 1E2, to

verify position.

C. REFER TO Tech Specs 3.3.5.1, 3.5.1, 3.5.2, 3.6.2.3, 3.6.2.4,

3.6.2.5, TRM 3.3.3.4.

o

o

o

NOTE

1)

IF alarm is valid, THEN the following will occur:

2A RHR Pump will NOT auto start.

2C RHR Pump will NOT auto start.

SYS I Inboard Injection Valve will NOT receive an auto open signal.

SYS I Inboard Injection Valve will NOT manually open from the control room due to loss of

450 psig logic from DIV I.

References:

2-45E620-2

2-45E712-2

GE 730E937-5

2-45E765-4

Tech Specs 3.3.5.1, Emergency Core Cooling System (ECCS) Instrumentation

3.5.1, ECCS - Operating

3.5.2, ECCS - Shutdown

3.6.2.3, Residual Heat Removal (RHR) Suppression Pool Cooling

3.6.2.4, Residual Heat Removal (RHR) Suppression Pool Spray

3.6.2.5, Residual Heat Removal (RHR) Drywell Spray

TRM 3.3.3.4, ECCS and RCIC Trip System Bus Power Monitors

(

(

25. SRO GENERIC 2.4.30 001/CIA/REPIIIGENERIC 2.4.301ISRO ONLY/11/27/07 RMS

Given the following plant conditions:

You are the Shift Manager on dayshift attending the morning meeting.

During the meeting you are informed that both seals on 2A Recirc Pump have failed.

When you arrived in the Unit-2 control room, the following conditions were noted:

- Unit-2 reactor was manually scrammed.

- Actions were carried out in accordance with 2-AOI-68-1 to isolate the recirc pump

- Actions were carried out in accordance with 2-AOI-64-1 to vent the drywell.

- EOI-1 was entered, executed and exited.

- Reactor pressure is being controlled by bypass valves.

- Reactor water level is +32 inches being controlled by RFPT 2C in automatic.

- All four EDGs are running unloaded with an AUO monitoring their status locally.

- The drywell is being vented with pressure at 0.75 psig and lowering.

- 2A Recirc loop is isolated with CRD purge isolated.

Which ONE of the following describes the Emergency Classification Level and the appropriate action to

take?

REFERENCE PROVIDED

A.

An Alert (2.1-A) shall be declared to the ODS and the NRC, and then subsequently cancelled .

B.~

An Alert (2.1-A) shall be reported to the ODS and the NRC, but should not be declared.

C.

A NOUE (2.4-U) shall be reported to the ODS only and need not be reported to the NRC since the

emergency is resolved .

D.

An Alert (2.4-A) shall be reported to the NRC only and need not be reported to the ODS since the

emergency is resolved.

KJA Statement:

Emergency Procedures IPlan

2.4.30 Knowledge of which events related to system operations/status should be reported to outside

agencies

KJA Justification: This question satisfies the KIA statement by requiring the candidate to use specific

plant conditions to determine the emergency classification level and the associated reporting

requirements.

References:

EPIP-1

Level of Knowledge Justification: This question is rated as CIA due to the requirement to assemble,

sort, and integrate the parts of the question to predict an outcome. This requires mentally using this

knowledge and its meaning to predict the correct outcome.

SRO Level Justification: This question satisfies the requirements of 10 CFR 55.43(b) (5) Assessment

of facility conditions and selection of appropriate procedures during normal, abnormal, and emergency

situations .

0610 NRC SRO Exam

(

REFERENCE PROVIDED: EPIP-1

Plausibility Analysis:

In order to answer this question correctly , the candidate must determine the following :

1. Determine that current conditions do NOT indicate an EAL is being exceeded.

2. Determine that previous conditions, based on running DIGs, indicate that EAL 2.1-A or 2.4-A were

applicable at an earlier time but has been resolved before being declared .

3. Determine the correct notification requirement based on Item 2 above.

A is incorrect. The EAL should NOT be declared . This is plausible based on conservative decision

making, but is NOT in accordance with the directions in EPIP-1.

B is correct.

C is incorrect. The EAL is incorrect. A dual seal failure of a Recirc Pump will yield a significantly higher

leak rate than specified in EAL 2.4-U. In addition, the NRC should also be notified in accordance with

EPIP-1. This is plausible for a novice operator candidate.

D is incorrect. The ODS should also be notified in accordance with EPIP-1. This is plausible for a novice

operator candidate.

3.0

INSTRUCTION

(

BROWNS FERRY

EMERGENCY CLASSIFICATION PROCEDURE

EPIP-1

3.1

Following plant events or transients review EPIP-1 Section II, 1.0 through 8.0 and

determine if an event should be classified as an emergency.

NOTE

1. If an emergency action level for a higher classification was exceeded, but the present

situation indicates a lower classification, the fact that the higher classification occurred shall

be reported to the NRC and the CECC, if staffed, or ODS if the CECC is not staffed. The

higher classification should not be declared.

2. If an emergency action level was met but the emergency has been totally resolved, the

emergency class that was appropriate shall be reported to the ODS and the NRC but

should not be declared.

3.1.1

EPIP-1 Section 11,1 .0 through 8.0 captures events in eight major

categories as listed on the event classification index.

3.1.2

Each emergency action level (EAL) in a category is given an alpha-

numeric designator. The first numeric component of the EAL indicates the

section followed by a numeric designator for the specific EAL within the

section and an alpha numeric designator for the event class.

Example: 5.2-U

These designators provide for cross-reference between the specific EAL

and the basis document which provides technical supporting information

for the EAL and may aid the Shift Manager/SED in classifying events.

Curves, notes, or tables that support the EAL are located on the face

adjacent page within the matrix section of the procedure and are identified

within the event classification window on the information bar that precedes

the designator. The information bar contains the appropriate indication to

alert the user that a corresponding curve, note, or table applies to the

EAL.

Curves, notes, or tables that contain unit specific information will also be

identified within the event classification window by the letter "US" located

at the end of the EAL information bar. This information should alert the

user that the corresponding curve, note, or table contains unit specific

information.

Example

I

5.2-U I CURVE I NOTE I TABLE ~

PAGE 3 OF 201

REVISION 42

BROWNS FERRY

EMERGENCY CLASSIFICATION PROCEDURE

EVENT CLASSIFICATION MATRIX

EPlp*1

PRIMARY CONTAINMENT

PRIMARY CONTAINMENT

PRESSURE

HYDROGEN

Description

Description

I

I

I

I

I

I

I

I

c::zc::enc::>>r-m

c:::mz

-4

2.1-A I

I

I TABLE I

I

I

I

I

Drywell pressure at or above 2.45 psig

AND

>>r-

Indication of Primary System leakage into

m

Primary Containment. Refer to Table 2.1-A.

U

-4

OPERATING CONDITION:

Mode 1 or 2 or 3

2.1-S I CURVE I

I

I

2.2-S I

I

I

I

Suppression Chamber pressure can NOT be

Drywell or Suppression Chamber

en

maintained in the safe area of Curve 2.1-S.

hydrogen concentration at or above 4%

=im

AND

m

S

Drywell or Suppression Chamber

m

U

oxygen concentration at or above 5%.

G)m

OPERATING CONDITION:

OPERATING CONDITION:

Z

0

Mode 1 or 2 or 3

Mode 1 or 2 or 3

-<

2.1-G I

I

I

I

2.2-G I

I

I

I

Suppression Chamber pressure can NOT be

Drywell or Suppression Chamber

maintained below 55 psig.

hydrogen concentration at or above 6%

G)mz

AND

m

Drywell or Suppression Chamber

~r-

oxygen concentration at or above 5%.

ms:m

0

(j)m

OPERATING CONDITION:

OPERATING CONDITION:

Z

0

Mode 1 or 2 or 3

Mode 1 or 2 or 3

-<

PAGE 26 OF 201

REVISION 42

(

BROWNS FERRY

II NOTES

CURVESITABLES:

EMERGENCY CLASSIFICATION PROCEDURE

EVENT CLASSIFICATION MATRIX

EPIP-1

II

TABLE 2.1-A

INDICATIONS OF PRIMARY SYSTEM LEAKAGE

INTO PRIMARY CONTAINMENT

Primary Containment Pressure Hiqh Alarm

Drvwsll Floor Drain Sump Pump Excessive Operation

Drvwell CAM Activity lncreasino

Orvwell Temperature Hloh Alarm

Chemistry Sample Radionuclide Comparison To Reactor Water

CURVE 2.1-5

PRESS SUPPR PRESS

35 __--r----r----r---,-----,--.-,------,------,-----,

-

ACTION

__ -

REOUIRED

_I.---


SAFE

(

14

15

16

SUPPRPL LVL(FT)

PAGE 25 OF 201

17

18

19

20

REVISION 42

DRYWELL INTERNAL

LOSS OF PRIMARY

LEAKAGE

CONTAINMENT

Description

Description

2.4-U I

I

I

I

2.5-U I

I

I TABLE I

Drywell unidentified leakage exceeds 10 gpm

Inability to maintain Primary Containment

c:

pressure boundary. Refer to Table 2.3/2.5-U.

Z

OR

c:

C/)c:

Drywell identified leakage exceeds 40 gpm.

>>

rm

OPERATING CONDITION:

OPERATING CONDITION:

<:m

Mode 1 or 2 or 3

Mode 1 or 2 or 3

Z-t

2.4-A I

I

I

I

I

I

I

I

Drywell unidentified leakage exceeds 50 gpm.

>>

rm

iO

-t

OPERATING CONDITION:

Mode 1 or 2 or 3

I

I

I

I

I

I

I

I

C/)

=imms:m

iO

(j)mz

0-<

I

I

I

I

I

I

I

I

(j)mzm

~r-ms:m

0

(j)mzo-<

(

BROWNS FERRY

EMERGENCY CLASSIFICATION PROCEDURE

EVENT CLASSIFICATION MATRIX

PAGE 30 OF 201

EPIP-1

REVISION 42