March 20, 2008 Tennessee Valley Authority ATTN:
Mr. William R. Campbell, Jr.
Chief Nuclear Officer and Executive Vice President 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
MEETING ANNOUNCEMENT - PUBLIC MEETING BROWNS FERRY NUCLEAR PLANT, DOCKET NOS. 50-259, 50-260 AND 50-296
Dear Mr. Campbell:
This letter confirms the conversation between Mr. Tony Langley of your staff and Ms. Rebecca Nease on March 18, 2008, concerning a Category 1 meeting which has been scheduled for April 16, 2008, at 2:00 p.m. (EDT). The meeting notice, which provides additional details, is enclosed.
The purpose of the meeting, scheduled at our request, is to discuss the NRC=s Reactor Oversight Process Annual Assessment of your Browns Ferry facility.
The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or other information from the meeting in another format (e.g., braille, large print), please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room).
Should you have any questions concerning this meeting, please contact me at (404) 562-4530.
Sincerely,
/RA/
Rebecca L. Nease, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos. 50-259, 50-260, 50-296 License No. DPR-33, DPR-52, DPR-68
Enclosure:
As stated cc w/encl.: (See page 2)
OFFICE RII:DRP RII:DRP SIGNATURE JBB5 RLN1 NAME JBaptist RNease DATE 3/20/2008 03/26/2008 E-MAIL COPY?
YESNO YESNO YESNO YESNO YESNO YESNO YESNO
2 cc w/encls:
Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority Electronic Mail Distribution James R. Douet Vice President, Nuclear Support Tennessee Valley Authority Electronic Mail Distribution H. Rick Rogers, Vice President Nuclear Engineering & Technical Services Tennessee Valley Authority Electronic Mail Distribution Rusty G. West Site Vice President Browns Ferry Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution General Counsel Tennessee Valley Authority Electronic Mail Distribution Steven M. Douglas, General Manager Browns Ferry Site Operations Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Beth A. Wetzel, Manager Corporate Nuclear Licensing and Industry Affairs Tennessee Valley Authority Electronic Mail Distribution James E. Emens, Jr., Interim Manager Licensing and Industry Affairs Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 John C. Fornicola, General Manager Nuclear Assurance Tennessee Valley Authority Electronic Mail Distribution Larry E. Nicholson, General Manager Performance Improvement Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801 State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, AL 36130-3017 Chairman Limestone County Commission 310 West Washington Street Athens, AL 35611
3 Letter to W. R. Campbell from Rebecca L. Nease dated March 20, 2008
SUBJECT:
MEETING ANNOUNCEMENT - PUBLIC MEETING BROWNS FERRY NUCLEAR PLANT, DOCKET NOS. 50-259, 50-260 AND 50-296 Distribution w/encl:
Region II Administrator=s Secretary Region II DRP Division Secretary Region II Division Directors and Deputies Regional Counsel Region II State Liaison Officer Region II Public Affairs Officers Region II Resource Management Branch Chief Region II Receptionist PMNS Headquarters Operations Officer RIDSNRRDIRS RIDSNRRDIRSIPAB OEMAIL PUBLIC E. Brown, NRR L. Raghavan, NRR L. Slack, RII
SUBJECT:
PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY FACILITY:
Browns Ferry Nuclear Power Plant DOCKETS:
50-259, 50-260, and 50-296 DATE & TIME:
Wednesday, April 16, 2008 2:00 PM to 4:00 PM (EDT)
LOCATION:
Browns Ferry Training Center Auditorium at the plant site in Athens, AL.
PURPOSE:
Discuss the NRC Reactor Oversight Process Annual Assessment for the Browns Ferry facility. The Annual Assessment Letter is accessible from the Publicly Available Records (PARS) component of NRC's document system (ADAMSML080630640) or from the NRC Web site at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/bf_2007q4.pdf The NRC's Policy Statement, "Enhancing Public Participation in NRC Meetings," effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Web site, www.nrc.gov and contains information regarding conduct of NRC meetings.
CATEGORY:
This is a Category 1 meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
NRC OFFICE(S)
PARTICIPATING:
Region II (RII)
OTHER ORGANIZATIONS PARTICIPATING:
None PARTICIPANTS:
NRC (partial list)
C. Casto, Acting Deputy Regional Administrator, Region II (RII)
R. Nease, Chief, Reactor Projects Branch 6, Division of Reactor Projects (DRP), RII T. Ross, Senior Resident Inspector, DRP, RII C. Stancil, Resident Inspector, DRP, RII K. Korth, Resident Inspector, DRP, RII LICENSEE (partial list)
R.G. West, Site Vice President, Browns Ferry Nuclear Plant S.M. Douglas, Manager Site Operations, Browns Ferry Nuclear Plant D.T. Langley, Licensing and Industry Affairs Manager, Browns Ferry Nuclear Plant MEETING CONTACT:
Rebecca L. Nease, NRC, RII 404-562-4530 RLN1@nrc.gov
Enclosure AUDIO TELE-CONFERENCE:
Not available VIDEO TELE -
CONFERENCE:
Not available