Handouts - Meeting Summary with Omaha Public Power District on Dry Fuel Storage at the Fort Calhoun Station
ML080720004
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 03/20/2008
From:
Omaha Public Power District
To:
Office of Nuclear Reactor Regulation
Markley, M T, NRR/DORL/LP4, 301-415-5723
Shared Package
ML080720002 List:
References
Download: ML080720004 (9)


Text

000 Dry Fuel Storage at Fort Calhoun Station Omaha Public Power District (OPPD)

Presentation to NRC February 19th, 2008 000

.2

.3 Agenda

  • Background Crane Uprate Equipment Delivery Status 100-Ton Transfer Cask and Transfer Trailer Availability, Key Remaining Open Issues OPPD Schedule 0 4 5

OPPD Febwary 19, 2008

ooo Background

  • March 2006 - NRC questions 72.48 for Transnuclear (TN) design change to reduce the weight of the transfer cask
  • June 2006 - NRC grants exemption for loading 4 canisters
  • October 2006 - NRC finds TN 72.48 evaluation for the OS 1 97L to be invalid
  • Parallel success paths developed for Phase 2 loading campaign 3

OPPO Febftwy 19, 2W8 o o o Background (Cont.)

Parallel Paths o TN to amend the C of C Tech. Spec. to license the light weight transfer cask

- Amendment 11 o OPPD to uprate the auxiliary building crane to use the standard weight transfer cask

19. 20 4

OPPO Febni~y lB. 2000

ooo Status Licensing Activities

" TN submitted the license amendment request for the 75-ton cask design in April 2007

" OPPD met with NRC Division of Spent Fuel Storage and Transportation in September 2007

  • NRC issued a letter to OPPD on TN's amendment in October 2007
  • NRC issued RAIs on the TN amendment request in October 2007 5

OPPO FebMr 19, 208 ooo Status Licensing Activities (cont.)

" TN met with NRC to discuss RAIs in November 2007

" TN submitted RAI responses in December 2007 OPPO Fe*ar 19, 2008 a

OPPO Fetxua*y

19. 2008

000 Crane Uprate Equipment Delivery Status

" Contract issued to PAR on February 6, 2008

" Delivery date is November 21, 2008

" Installation contract to be issued late August 2008

" Estimated installation and test completion is January 30, 2009 7

OPPD Fe1uarY 19,2008 00 0 Changes to Previous Information e OPPD will procure a new hook and lower block

  • Reduces trolley lifted load by 1.5 tons
  • Increases lift height by -2 feet
  • Eliminates the 60 degrees restriction on sling angle
  • Allows use of standard cask yokes 8

OPPD FeNUar 19. 2008

o o o Crane Modification Scope e Hoist gears

  • Wire rope
  • Hoist drum pillow block and drum safety support

" Drum pinion pillow block

" Transfer sheave pivot pin Lower block and hook OPPD Februm 19, 2008 0 0 Engineering Change Package

  • Analysis of crane and auxiliary building for crane uprate is complete
  • Crane parts contract issued
  • 60 % ECP package complete
  • Testing procedure
  • New load test @ 125% rated load 10 OPPD Februay 19. 2008

000 100-Ton Transfer Cask and Transfer Trailer Availability

  • TN has a transfer cask/transfer trailer (TC/TT) available 1st quarter 2009

" USA plant has a TC/TT available starting May 2009

  • Working through USA and TN 11 OPPO February 19, 2008 0 0 0 Key Remaining Open Issues
  • Finalize agreements on use of TC/TT
  • Establish final cask move weights
  • Finalize structural analyses 125-ton cask letdown analysis
  • Issue installation contract 12 OPPD Febnuary 19, 2008

0 0 0 Key Remaining Open Issues (cont.)

  • Issue modification package
  • Install modification
  • Test crane @ 125% rated load
  • Revise 72.212 Report and loading procedures
  • Procurement of a compatible yoke 13 OPPD Febmary 19, 2008 000 Schedule
  • FCS must transfer fuel prior to new fuel receipt for Fall 2009 refueling outage

" Crane uprate schedule

  • Cask availability
  • Amendment 11 issue
  • Kewaunee bridge welds 14 OPPD Febnmay 19. 2008

000 Schedule 41 I* lefla(2nd u

71 28Iu 10Qftm Iidsmats !2~fý3Qf Iloom*

1tw '

Ii2jýter 3dMddmftu aIQmfti listQW1r uaI 0-t 14oto 41 7'

121 12 HI

  • IflhSAGWIRLAfl Stb"LARIMMC OUC low, urwtndmoti weeoImic lefl SI U3,U-1 ZSAdWttAA*---

-- ) dU~dm*;

S.aAebO.og Deds~oA4l Apipfavi of arm upqde Proemg C,." EC la¢kain WCC USA PlhM OSItB W kA H*Ca fnr 1 E LFOBW 420 guaww tef.

Drop gmdDfte #&I l

lebe Owaue W

21,"*,, o,,,,,V mL 000 Summary

" OPPD is on track to uprate the auxiliary building/crane to 106-ton capacity

" Loading window has opened up

  • Approval of TN Amendment 11 by January 2009 will support OPPD contingency needs for fuel loading 16 OPPD Februar 19. 2008 16 oppo Febuary 19. 2008

000 QUESTIONS/COMMENTS 17 OPP6 Fe~xuay 19, 2008