February4, 2008 Mr. Tom E. Tynan Vice President - Vogtle Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, EVALUATION OF EMERGENCY ACTION LEVELS REVISED TO SUPPORT MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE (TAC NOS. MD6872 AND MD6873)
Dear Mr. Tynan:
By letter dated September 27, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML072740102), as supplemented by letter dated December 20, 2007 (ADAMS Accession No. ML073580622), Southern Nuclear Operating Company, Inc. (the licensee), requested prior Nuclear Regulatory Commission (NRC) approval for changes to several of the emergency action levels (EALs) for Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle 1 and 2).
The requested changes to the licensees EALs are to support a Measurement Uncertainty Recapture (MUR) power uprate of 1.7% for which the licensee submitted a Licensee Amendment Request (LAR) to the NRC by letter dated August 28, 2007 (ADAMS Accession No. ML072470688). The proposed changes to the EALs are consistent with the proposed changes in the licensed power level for Vogtle 1 and 2.
As a result of the proposed 1.7% power uprate, the licensee has identified 7 EALs that would require a corresponding setpoint change consistent with the increase in power. Enclosed please find the list of EALs that the licensee has proposed to revise for Vogtle 1 and 2.
The licensee provided calculation X6CNA14 to facilitate the technical review of these proposed changes to the stated EALs. The NRC staff has reviewed this calculation and has determined that the overall basis for the stated setpoints has not been changed, just the corresponding power level, reactor fuel source term, or decay heat value. Therefore, pending approval of the MUR power uprate LAR, the corresponding changes to the EALs listed in the enclosure for Vogtle 1 and 2 do not decrease the effectiveness of the applicable EALs, and the revised EALs continue to meet the standards of Section 50.47(b) and the requirements of Appendix E to Title 10 of the Code of Federal Regulations, Part 50.
Sincerely,
/RA/
Siva P. Lingam, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-424 and 50-425
Enclosure:
EALs to be Revised to Support MUR Power Uprate cc w/encl: See next page
- transmitted by memo dated OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NSIR/DPR/DDRP/BC NRR/LPL2-1/BC (A)
NAME SLingam MO=Brien KWilliams MWong DATE 02/04/08 02/04/08 1/10/08*
02/04/08
Enclosure EMERGENCY ACTION LEVELS TO BE REVISED TO SUPPORT MEASUREMENT UNCERTAINTY RECAPTURE POWER UPRATE VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 DOCKET NOS. 50-424 AND 50-425 EAL From To RU1.1 1.2 x 10-3 µCi/cc 1.3 x 10-3 µCi/cc RU1.2 8.6 x 10-3 µCi/cc 2.5 x 10-2 µCi/cc RA1.1 1.2 x 10-1 µCi/cc 1.3 x 10-1 µCi/cc RA1.2 8.6 x 10-1 µCi/cc 2.5 µCi/cc RS1.1 RE-12839: 1.4 x 104 µCi/cc RE-12444: 6.9 x 101 µCi/cc RE-13119 thru 13122: 3.0 x 104 µCi/cc RE-12839: 1.5 x 104 µCi/cc RE-12444: 7.0 x 101 µCi/cc RE-13119 thru 13122: 3.1 x 104 µCi/cc RG1.1 RE-12839: 1.4 x 105 µCi/cc RE-12444: 6.9 x 102 µCi/cc RE-13119 thru 13122: 3.0 x 105 µCi/cc RE-12839: 1.5 x 105 µCi/cc RE-12444: 7.0 x 102 µCi/cc RE-13119 thru 13122: 3.1 x 105 µCi/cc SU4.1 RE-48000: 5.45 µCi/gm RE-48000: 5.55 µCi/gm
Vogtle Electric Generating Plant, Units 1 & 2 cc:
Mr. Tom E. Tynan Vice President - Vogtle Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830 Mr. N. J. Stringfellow Manager, Licensing Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 Mr. Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 Mr. Steven M. Jackson Senior Engineer - Power Supply Municipal Electric Authority of Georgia 1470 Riveredge Parkway, NW Atlanta, GA 30328-4684 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission 244 Washington St., SW Atlanta, GA 30334 Mr. Harold Reheis, Director Department of Natural Resources 205 Butler Street, SE, Suite 1252 Atlanta, GA 30334 Attorney General Law Department 132 Judicial Building Atlanta, GA 30334 Mr. Laurence Bergen Oglethorpe Power Corporation 2100 East Exchange Place P.O. Box 1349 Tucker, GA 30085-1349 Arthur H. Domby, Esquire Troutman Sanders Nations Bank Plaza 600 Peachtree Street, NE Suite 5200 Atlanta, GA 30308-2216 Resident Inspector Vogtle Plant 8805 River Road Waynesboro, GA 30830 Office of the County Commissioner Burke County Commission Waynesboro, GA 30830 Mr. Bob Masse Resident Manager Oglethorpe Power Corporation Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830