February 14, 2008 Dr. Jill Lipoti, Director Division of Environmental Safety and Health P.O. Box 424 Trenton, NJ 08625-0424
Dear Dr. Lipoti:
In your letter dated October 12, 2007, on behalf of the New Jersey Department of Environmental Protection, you provided the Nuclear Regulatory Commission (NRC) staff your recommendations with regard to AmerGens new structural analysis and suggested real-time drywell thickness measurements. I provided an interim reply to your letter, dated November 15, 2007, advising you that the NRC staff was awaiting the decision of the Atomic Safety and Licensing Board (ASLB) regarding the hearing conducted for Oyster Creek, and therefore could not comment on potential decisions of the ASLB. It would have been premature for the staff to comment on issues that were being considered by the ASLB. Based on the decision issued by the ASLB on December 18, 2007, I am providing a response to the recommendations in your letter of October 12, 2007 and your subsequent letter of February 6, 2008.
Let me first state that the NRC agrees with you that any sound regulatory relationship should be transparent. Being open to public scrutiny and discourse is one of the guiding principals of this agency and we strive, whenever possible, to conduct our business in the light of public scrutiny.
However there are legal limits to the information that we can make available, and the actions we take must be balanced between the competing need of transparency and burden on the licensee.
You expressed your expectation that the calculations performed by AmerGen for the 3-D finite-element analysis of the drywell shell be released as non-proprietary. The NRC staff has made clear its expectation that AmerGen provide a summary report of their findings, rather than providing the actual calculations. Because the calculations contain design information that is considered proprietary, and owned by General Electric and other entities outside of AmerGen, a non-proprietary summary report is our customary practice for making the findings of this type of analysis available to the public. As discussed in our regulations, 10 CFR 2.390, the staff is required to protect from public disclosure information that has been legitimately found to be proprietary, and a summary report balances the need to protect proprietary data with the necessity to make the findings of the analysis public. If the staff has any concerns or questions about the findings in the report, the staff will perform an on-site audit of the analysis including all the proprietary information.
Moreover, as we have discussed with you, the NRC Regional Office, using inspection procedure (IP) 71003, has begun a sequence of inspections to confirm that the licensees commitments and license conditions, tied to license renewal, have been met prior to entering the period of extended operation. The commitment to perform the 3-D analysis is only one of many commitments that AmerGen will be required to complete prior to the period of extended operation. If the license is renewed, the NRC staff will be inspecting these commitments and license conditions using IP 71003, sending an inspection team to the site. Headquarters staff will provide additional technical expertise, as needed. As is consistent with our memorandum of agreement with the State of New Jersey Department of Environmental Protection, your staff is welcome to participate in the aforementioned audit or inspections, as they have been for the other inspections that have been performed on site at Oyster Creek.
With regard to your October 12, 2007, recommendation that real-time drywell thickness measurements be performed, the Atomic Safety and Licensing Boards initial decision found:
that AmerGen has demonstrated that the frequency of its planned UT measurements, in combination with the other elements of its aging management program, provides reasonable assurance that the sand bed region of the drywell shell will maintain the necessary safety margin during the period of extended operations.
An appeal of the Licensing Board decision is now before the Commission.
Thank you for your comments and recommendations regarding the license renewal process.
Sincerely,
/RA/
Pao-Tsin Kuo, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-219 cc: See next page
ML080170420 OFFICE:
PM:RLRA:DLR LA:DLR OGC NLO BC:RPB1:DLR D:DLR NAME:
DAshley YEdmonds MBaty LLund PTKuo DATE:
02/08/08 02/11/08 02/12/08 02/12/08 02/14/08
Letter to J. Lipoti, from P.T. Kuo, dated February 14, 2008 DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSrxb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter CHolden RLaufer GMiller RBellamy, RI RCureton, RI JLilliendahl, RI MModes, RI MSykes, RI TMensah MYoung RidsOpaMail
Oyster Creek Nuclear Generating Station cc Site Vice President - Oyster Creek Nuclear Generating Station AmerGen Energy Company, LLC P.O. Box 388 Forked River, NJ 08731 Senior Vice President of Operations AmerGen Energy Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Kathryn M. Sutton, Esq.
Morgan, Lewis, & Bockius LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004 Kent Tosch, Chief New Jersey Department of Environmental Protection Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625 Vice President - Licensing and Regulatory Affairs AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Mayor of Lacey Township 818 West Lacey Road Forked River, NJ 08731 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 445 Forked River, NJ 08731 Director - Licensing and Regulatory Affairs AmerGen Energy Company, LLC Correspondence Control P.O. Box 160 Kennett Square, PA 19348 Manager Licensing - Oyster Creek Exelon Generation Company, LLC Correspondence Control P.O. Box 160 Kennett Square, PA 19348 Regulatory Assurance Manager Oyster Creek AmerGen Energy Company, LLC P.O. Box 388 Forked River, NJ 08731 Assistant General Counsel AmerGen Energy Company, LLC 200 Exelon Way Kennett Square, PA 19348 Ron Bellamy, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Correspondence Control Desk AmerGen Energy Company, LLC 200 Exelon Way, KSA 1-1 Kennett Square, PA 19348 Oyster Creek Nuclear Generating Station Plant Manager AmerGen Energy Company, LLC P.O. Box 388 Forked River, NJ 08731 License Renewal Manager Exelon Generation Company, LLC 200 Exelon Way, Suite 230 Kennett Square, PA 19348
Oyster Creek Nuclear Generating Station cc:
Mr. Michael P. Gallagher Vice President License Renewal Exelon Generation Company, LLC 200 Exelon Way, Suite 230 Kennett Square, PA 19348 Mr. Christopher M. Crane President and Chief Nuclear Officer AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555