Addendum to Supplement to the Environmental Assessment Related to Construction and Operation of the Diablo Canyon ISFSI
ML073040434
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 11/07/2007
From: Hall J
NRC/NMSS/SFST
To: Keenan J
Pacific Gas & Electric Co
Hall J, NMSS/SFST (301) 492-3319
References
Download: ML073040434 (6)


Text

November 7, 2007 Mr. John S. Keenan Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 770000 San Francisco, CA 94177-0001

SUBJECT:

ADDENDUM TO SUPPLEMENT TO THE ENVIRONMENTAL ASSESSMENT RELATED TO THE CONSTRUCTION AND OPERATION OF THE DIABLO CANYON INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Mr. Keenan:

On August 30, 2007, the U.S. Nuclear Regulatory Commission (NRC) issued the Supplement to the Environmental Assessment (EA) and final Finding of No Significant Impact (FONSI) related to the Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI).

NRC issued its initial EA and FONSI for this action on October 24, 2003, and subsequently issued a license for the Diablo Canyon ISFSI to the Pacific Gas and Electric Company on March 22, 2004. On May 29, 2007, the NRC staff issued a preliminary supplement to the EA and draft FONSI, which addressed the environmental impacts from potential terrorist acts against the Diablo Canyon ISFSI, as directed by the Commission in its Memorandum and Order of February 26, 2007. On May 31, 2007, the staff published a notice of availability in the Federal Register (72 FR 30398), providing opportunity for public comment on the preliminary supplement to the EA and draft FONSI. In the August 30, 2007, supplement to the EA and final FONSI, the NRC staff summarized the public comments received and provided its responses to those comments in an appendix to the document. As part of its response, the staff had revised the supplement to list additional reference documents. Subsequent to the issuance of the supplement, the staff determined that certain other documents concerning NRC=s generic security assessments should also be included in the list of references. These additional references are identified in the enclosed Addendum to the supplement (Enclosure 1).

J. Keenan Also enclosed, for your information, is the Federal Register notice announcing the issuance of the Addendum (Enclosure 2). The notice has been forwarded to the Office of the Federal Register for publication. If you have any questions about this action, please contact me at (301) 492-3319.

Sincerely,

/RA/

James R. Hall, Senior Project Manager Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards Docket No. 72-26 (50-275, -323)

Enclosures:

1. Addendum to References Listed in the NRC Staffs Final Supplement To the Environmental Assessment For the Diablo Canyon Independent Spent Fuel Storage Installation
2. Notice of Issuance of Addendum cc: Mailing List

J. Keenan Also enclosed, for your information, is the Federal Register notice announcing the issuance of the Addendum (Enclosure 2). The notice has been forwarded to the Office of the Federal Register for publication. If you have any questions about this action, please contact me at (301) 492-3319.

Sincerely,

/RA/

James R. Hall, Senior Project Manager Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards Docket No. 72-26 (50-275, -323)

Enclosures:

1. Addendum to References Listed in the NRC Staffs Final Supplement To the Environmental Assessment For the Diablo Canyon Independent Spent Fuel Storage Installation
2. Notice of Issuance of Addendum cc: Mailing List DISTRIBUTION:

SFPO r/f NMSS r/f OFC:

SFST E

SFST C

OGC SFST NAME:

JRHall WWheatley LClark RNelson DATE:

11/ 1 /07 11/ 1 /07 11/ 6 /07 11/ 7 /07 C = COVER E = COVER & ENCLOSURE N = NO COPY OFFICIAL RECORD COPY Addendum to References Listed in the NRC Staff=s Final Supplement To the Environmental Assessment For the Diablo Canyon Independent Spent Fuel Storage Installation

1. SECY-04-0222, Decision-Making Framework for Materials and Research and Test Reactor Vulnerability Assessments, November 24, 2004.
2. SRM-SECY-04-0222, Staff Requirements - SECY-04-0222 - Decision-Making Framework for Materials and Research and Test Reactor Vulnerability Assessments, January 19, 2005.
3. Memorandum from Daniel H. Dorman to Wayne Hodges, Results of NSIR Screening of Nuclear Facility Security Scenarios for Remote and Speculative Nature Prior To Use In Decision-Making Framework, March 9, 2005.
4. Memorandum from Luis A. Reyes to the Commission, "Completion of Security Assessment of Spent Fuel Storage Casks for Land-Based Terrorist Threats," September 15, 2005.
5. Memorandum from Luis A. Reyes to the Commission, "Completion of Security Assessments of the Crash of a Large Plane into Spent Fuel Storage Casks," September 15, 2005.
6. Memorandum from Jack R. Strosnider to Roy P. Zimmerman, Framework Assessments of Spent Fuel Storage Casks and Transportation Packages and Radioactive Material Transportation Packages, December 9, 2005.

Notice of Issuance of Addendum to Supplement to the Environmental Assessment for the Diablo Canyon Independent Spent Fuel Storage Installation (see ADAMS Accession Number ML073050104)

Diablo Canyon Power Plant, Units 1 and 2 cc:

NRC Resident Inspector Diablo Canyon Nuclear Power Plant c/o U.S. Nuclear Regulatory Commission P.O. Box 369 Avila Beach, CA 93424 Sierra Club San Lucia Chapter ATTN: Andrew Christie P.O. Box 15755 San Luis Obispo, CA 93406 Ms. Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164.

Pismo Beach, CA 93448 Chairman, San Luis Obispo County Board of Supervisors 1055 Monterey Street, Suite D430 San Luis Obispo, CA 93408 Mr. Truman Burns Mr. Robert Kinosian California Public Utilities Commission 505 Van Ness, Room 4102 San Francisco, CA 94102 Diablo Canyon Independent Safety Committee ATTN: Robert R. Wellington, Esq.

Legal Counsel 857 Cass Street, Suite D Monterey, CA 93940 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavilion 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Jennifer Post, Esq.

Pacific Gas & Electric Company Post Office Box 7442 San Francisco, CA 94120 City Editor The Tribune 3825 South Higuera Street P.O. Box 112 San Luis Obispo, CA 93406-0112 Director, Radiologic Health Branch State Department of Health Services P.O. Box 997414 (MS 7610)

Sacramento, CA 95899-7414 Mr. James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 31)

Sacramento, CA 95814 Mr. James R. Becker, Vice President Diablo Canyon Operations and Station Director Diablo Canyon Nuclear Power Plant P.O. Box 56 Avila Beach, CA 93424 Jennifer Tang Field Representative United States Senator Barbara Boxer 1700 Montgomery Street, Suite 240 San Francisco, CA 94111 Diane Curran Harmon, Curran, Spielberg, & Eisenberg, L.L.P 1726 M Street N.W., Suite 600 Washington, D.C. 20036