Text
January 8, 2007 MEMORANDUM TO: Rani L. Franovich, Branch Chief Environmental Branch B Division of License Renewal Office of Nuclear Reactor Regulation FROM:
Alicia Williamson
/RA/
Environmental Branch B Division of License Renewal Office of Nuclear Reactor Regulation
SUBJECT:
FORTHCOMING MEETING TO DISCUSS THE DRAFT SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT FOR THE LICENSE RENEWAL OF PILGRIM NUCLEAR POWER STATION DATE AND TIME:
Wednesday, January 24, 2007, (Two identical sessions)
First session:
1:30 p.m. - 4:30 p.m. (as necessary)
Second session:
7:00 p.m. - 10:00 p.m. (as necessary)
LOCATION:
Radisson Plymouth Harbor Ballroom 180 Water Street Plymouth, Massachusetts 02360 CATEGORY 3:*
This is a Category 3 Meeting. The public is invited to participate in this meeting by providing comments and asking questions throughout the meeting.
PURPOSE:
To meet with the public to receive comments on the draft Supplemental Environmental Impact Statement (DSEIS) 29 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (NUREG-1437) for Pilgrim Nuclear Power Station issued on December 8, 2006. The DSEIS is available on the NRCs Website at http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr1437/
supplement29/ and in the NRCs publicly available Agencywide Document Access and Management System (ADAMS). The ADAMS Accession Number is ML063260173. See the attached agenda and Federal Register Notice 71 FR 75280.
CONTACTS:
Alicia Williamson, NRR Andrew Stuyvenberg, NRR 301-415-1878 301-415-4006 ARW1@nrc.gov ALS3@nrc.gov
- Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings," 67 Federal Register 36920, May 28, 2002.
PURPOSE (Cont.):
Both formal sessions will be preceded by an informal ?open house beginning one hour prior to each session for those who wish to attend.
The open house will provide members of the public with an opportunity to talk informally one-on-one with NRC staff. Members of the public may register to present oral comments at this meeting by contacting Alicia Williamson, at (800) 368-5642, ext. 1878, or by email at ARW1@nrc.gov by January 17, 2007. Those who wish to make comments may also register at the meeting within 15 minutes of the start of each session.
Individual oral comments may be limited by the time available, depending on the number of persons who register.
If special equipment or accommodations are needed to attend or present information at the meeting, the need should be brought to the attention of Ms. Williamson at 800-368-5642, ext. 1878 or via e-mail at arw1@nrc.gov, no later than January 10, 2007, to provide the NRC staff adequate notice to determine whether the request can be accommodated.
PARTICIPANTS:
NRC EarthTech C. Cameron R. Hurley R. Franovich A. Williamson R. Palla Members of the Public Who Register to Speak Docket No.: 50-293
Enclosures:
- 1. Agenda
- 2. Federal Register Notice cc w/enclos: See next page PURPOSE (Cont.):
Both formal sessions will be preceded by an informal ?open house beginning one hour prior to each session for those who wish to attend.
The open house will provide members of the public with an opportunity to talk informally one-on-one with NRC staff. Members of the public may register to present oral comments at this meeting by contacting Alicia Williamson, at (800) 368-5642, ext. 1878, or by email at ARW1@nrc.gov by January 17, 2007. Those who wish to make comments may also register at the meeting within 15 minutes of the start of each session.
Individual oral comments may be limited by the time available, depending on the number of persons who register.
If special equipment or accommodations are needed to attend or present information at the meeting, the need should be brought to the attention of Ms. Williamson at 800-368-5642, ext. 1878 or via e-mail at ARW1@nrc.gov, no later than January 10, 2007, to provide the NRC staff adequate notice to determine whether the request can be accommodated.
PARTICIPANTS:
NRC EarthTech C. Cameron R. Hurley R. Franovich A. Williamson R. Palla Members of the Public Who Register to Speak Docket Nos.: 50-293
Enclosures:
- 1. Agenda
- 2. Federal Register Notice cc w/enclos: See next page DISTRIBUTION: See next page Adams Accession No.: ML070050153 OFFICE LA:DLR GS:DLR:REBB PM:DLR:REBB NAME S. Figueroa A. Stuyvenberg A. Williamson DATE 1/5/07 1/5/07 1/8/07 OFFICIAL RECORD COPY
Memo to R. Franovich from A. Williamson Dated January 8, 2007
SUBJECT:
FORTHCOMING MEETING TO DISCUSS THE DRAFT SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT FOR THE LICENSE RENEWAL OF PILGRIM NUCLEAR POWER STATION DISTRIBUTION:
Hard Copy Public Service List A. Williamson E-Mail PMNS B. Boger (RidsNrrAdro)
P.T. Kuo (RidsNrrDlr)
R. Franovich (RidsNrrDlrRebb)
E. Benner (RidsNrrDlrReba)
R. Schaaf R. Palla S. Hoffman bobbie.hurley@earthtech.com john.szeligowski@earthtech.com F. Cameron OGC (RidsOGCMailRoom)
S. Uttal M. Barkman P. Buckberg J. Shea R. Shane, OCA B. Keeling, OCA T. Combs, OCA OPA (RidsOpaMail)
D. McIntyre, OPA R. Powell, Region 1 W. Raymond, Region 1 N. Sieller, Region 1 RI N. Sheehan C. Harbough, ADM S. Sanders, NRR Technical Communications Assistant Samuel Lee, EDO Contact, Region I DLR Staff AGENDA FOR PUBLIC MEETING TO DISCUSS THE DRAFT SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT FOR THE LICENSE RENEWAL OF PILGRIM NUCLEAR POWER STATION WEDNESDAY, JANUARY 24, 2007 Two Meeting Sessions - 1:30 p.m. to 4:30 p.m. and 7:00 p.m. to 10:00 p.m.*
I.
Welcome and Purpose of Meeting 10 minutes (C. Cameron)
II.
Overview of License Renewal Process 10 minutes (R. Franovich)
III.
Results of the Environmental Review 30 minutes (A. Williamson, R. Hurley)
IV.
How Comments can be Submitted 5 minutes (A. Williamson)
V.
Public Comments As Required (C. Cameron)
VI.
Closing/Availability of Transcripts, etc.
5 minutes (C. Cameron)
- The NRC staff will host informal discussions one hour prior to each meeting session. No formal comments on the Draft Supplemental Environmental Impact Statement (DSEIS) will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meetings (see agenda, above) or in writing, as described in the attached Federal Register Notice.
Federal Register Notices: December 14, 2006 (Volume 71, Number 240)
Page 75280-75281
============================================================
Pilgrim Nuclear Power Station; Notice of Availability of The Draft Supplement 29 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants, and Public Meeting for the License Renewal of Pilgrim Nuclear Power Station Notice is hereby given that the U.S.
Nuclear Regulatory Commission (NRC, Commission) has published a draft plant-specific supplement to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GEIS), NUREG-1437, regarding the renewal of operating license DPR-35 for an additional 20 years of operation for the Pilgrim Nuclear Power Station (Pilgrim). Pilgrim is located on the western shore of Cape Cod in the Town of Plymouth, Plymouth County, Massachusetts. It is 38 miles southeast of Boston, Massachusetts, and 44 miles east of Providence, Rhode Island. Possible alternatives to the proposed action (license renewal) include no action and reasonable alternative energy sources.
The draft Supplement 29 to the GEIS is publicly available at the NRC Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike, Rockville, Maryland, 20852, or from the NRCs Agencywide Documents Access and Management System (ADAMS).
The ADAMS Public Electronic Reading Room is accessible at http://adamswebsearch.nrc.gov/dologin.htm. The Accession Number for the draft Supplement 29 to the GEIS is ML063260173. Persons who do not have access to ADAMS, or who encounter problems in accessing the documents located in ADAMS, should contact the NRCs PDR reference staff by telephone at 1-800-397-4209, or 301-415-4737, or by e-mail at pdr@nrc.gov. In addition, the Plymouth Public Library, 132 South Street; Duxbury Free Library, 77 Alden Street; and the Kingston Public Library, 6 Green Street, has agreed to make the draft supplement to the GEIS available for public inspection.
Any interested party may submit comments on the draft supplement to the GEIS for consideration by the NRC staff. To be certain of consideration, comments on the draft supplement to the GEIS and the proposed action must be received by February 28, 2007.
Comments received after the due date will be considered if it is practical to do so, but the NRC staff is able to assure consideration only for comments received on or before this date.
Written comments on the draft supplement to the GEIS should be sent to: Chief, Rules and Directives Branch, Division of Administrative Services, Office of Administration, Mail Stop T-6D59, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. Comments may be hand-delivered to the NRC at 11545 Rockville Pike, Room T-6D59, Rockville, Maryland, between 7:30 a.m. and 4:15 p.m. on Federal workdays. Electronic comments may be submitted to the NRC by e-mail at PilgrimEIS@nrc.gov. All comments received by the Commission, including those made by Federal, State, local agencies, Native American Tribes, or other interested persons, will be made available electronically at the Commissions PDR in Rockville, Maryland, and through ADAMS.
The NRC staff will hold a public meeting to present an overview of the draft plant-specific supplement to the GEIS and to accept public comments on the document. The public meeting will be held on January 24, 2007, at the Radisson Plymouth Harbor Ballroom, 180 Water Street, Plymouth, Massachusetts 02360. There will be two sessions to accommodate interested parties. The first session will convene at 1:30 p.m. and will continue until 4:30 p.m., as necessary. The second session will convene at 7 p.m. with a repeat of the overview portions of the meeting and will continue until 10 p.m., as necessary. Both meetings will be transcribed and will include: (1) A presentation of the contents of the draft plant-specific supplement to the GEIS, and (2) the opportunity for interested government agencies, organizations, and individuals to provide comments on the draft report. Additionally, the NRC staff will host informal discussions one hour prior to the start of each session at the same location. No comments on the draft supplement to the GEIS will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meeting or in writing. Persons may pre-register to attend or present oral comments at the meeting by contacting Ms. Alicia Williamson, the NRC Environmental Project Manager at 1-800-368-5642, extension 1878, or by e-mail at PilgrimEIS@nrc.gov, no later than January 17, 2007. Members of the public may also register to provide oral comments within 15 minutes of the start of each session. Individual, oral comments may be limited by the time available, depending on the number of persons who register. If special equipment or accommodations are needed to attend or present information at the public meeting, the need should be brought to Ms. Alicia Williamson attention no later than January 10, 2007, to provide the NRC staff adequate notice to determine whether the request can be accommodated.
For Further Information
Contact:
Ms. Alicia Williamson, Environmental Branch B, Division of License Renewal, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Mail Stop O-11F1, Washington, DC, 20555-0001. Ms. Alicia Williamson may be contacted at the aforementioned telephone number or e-mail address.
Dated at Rockville, Maryland, this 8th day of December, 2007.
For The Nuclear Regulatory Commission.
Robert Schaaf, Acting Branch Chief, Environmental Branch B, Division of License Renewal, Office of Nuclear Reactor Regulation.
[FR Doc. E6-21272 Filed 12-13-06; 8:45 am]
BILLING CODE 7590-01-P
Pilgrim Nuclear Power Station cc:
Mr. Gary J. Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213 Mr. John T. Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Christopher Schwarz Vice President, Operations Support Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Michael A. Balduzzi Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Kevin H. Bronson General Manager, Plant Operations Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Stephen J. Bethay Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Oscar Limpias Vice President, Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. John F. McCann Director, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Ms. Charlene D. Faison Manager, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Colomb Director of Oversight Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Bryan S. Ford Manager, Licensing Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. James H. Sniezek 5486 Nithsdale Drive Salisbury, MD 21801-2490 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Mr. Garrett D. Edwards 814 Waverly Road Kennett Square, PA 19348
Pilgrim Nuclear Power Station cc:
Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Senior Resident Inspector U. S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station Post Office Box 867 Plymouth, MA 02360 Chairman, Board of Selectmen 11 Lincoln Street Plymouth, MA 02360 Chairman Nuclear Matters Committee Town Hall 11 Lincoln Street Plymouth, MA 02360 Chairman, Duxbury Board of Selectmen Town Hall 878 Tremont Street Duxbury, MA 02332 Office of the Commissioner Massachusetts Department of Environmental Protection One Winter Street Boston, MA 02108 Office of the Attorney General One Ashburton Place 20th Floor Boston, MA 02108 Director, Radiation Control Program Commonwealth of Massachusetts Executive Offices of Health and Human Services 174 Portland Street Boston, MA 02114 Secretary of Public Safety Executive Office of Public Safety One Ashburton Place Boston, MA 02108 Director, Massachusetts Emergency Management Agency Attn: James Muckerheide 400 Worcester Road Framingham, MA 01702-5399 Mr. William D. Meinert Nuclear Engineer Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056-0426 Plymouth Public Library Attn: Ms. Dinah OBrien 132 South Street Plymouth, MA 02360 Duxbury Free Library Attn: Mr. David Murphy 77 Alden Street Duxbury, MA 02332 Kingston Public Library Attn: Librarian Susan Olin 6 Green Street Kingston, MA 02364
Pilgrim Nuclear Power Station cc:
Mark Sylvia Town Manager Town of Plymouth 11 Lincoln Street Plymouth, MA 02360 Todd Callaghan Office of Coastal Zone Management 251 Causeway Street, Suite 800 Boston, MA 02114 Ms. Becky Chin, Vice Chair Duxbury Nuclear Advisory Committee 31 Deerpath Trail North Duxbury, MA 02332 Mr. Thomas Bott 1 Maple Place Plymouth, MA 02360 Mr. Andre Martecchini Duxbury - Selectman 110 Heritage Lane Duxbury, MA 02332 Mr. David Leonardi 120 Bay State Drive Braintree, MA 02178 Mr. Jeff Berger Chairman - Plymouth Nuclear Matters Committee P.O. Box 1812 Plymouth, MA 02362-1812 Mr. Paul Smith 122 Ellisville Road Plymouth, MA 02360 Mr. Jerry Benezra 26 Island Rock Plymouth, MA 02360 Mr. Brian DuBois Carpenters L.V. 424 6 Skylark Avenue Plymouth, MA 02360 Mr. Jim Burba New England Regional Coordinator of Carpenters 129 Pearl Street Stoughton, MA 02072 Ms. Mary Shevory MEMA 650 East Street Brockton, MA 02302 Ms. Kate Francini 23 Driftwood Lane Plymouth, MA 02360 Mr. Richard A. Rothstein Plymouth Nuclear Matters Committee 32 Webster Reach Plymouth, MA 02360 Mr. Mark Serrano 19415 Deerfield Avenue Lansdowne, VA 20176 Ms. Mary Ellen Burns 13 Tavern Path Plymouth, MA 02360 Mr. Rick Buckley Entergy Nuclear P.O. Box 31995 Jackson, MS 39286
Pilgrim Nuclear Power Station cc:
Ms. Joyce McMahon Mass AREA 15 1/2 Rowell Avenue Beverly, MA 01915 Mr. Jim OConnell Llennoco, Inc.
P.O. Box 653 Chatham, MA 02633 Mr. Pine DuBois Jones River Watershed Association P.O. Box 73 Kingston, MA 02364 Ms. Mary Lampert Duxbury Nuclear Advisory Committee 148 Washington Street Duxbury, MA 02332 Ms. Nancy Landgren 625 Washington Street Duxbury, MA 02332 Mr. Keith Maxwell 19 Old Meeting House Green Norton, MA 02766 Mr. Rick Anderson Carpenters Local 624 21 Mazzeo Drive Randolph, MA 02368 Ms. Molly Barlett 52 Crooked Lane Duxbury, MA 02332 Ms. Megan Dempster 18 Bartlett Road Plymouth, MA 02360 Ms. Marie Fehlow 9 Coles Lane Plymouth, MA 02360 Mr. Larry Harrington MDPH Radiation Coordinator 175 Route 6A Sandwich, MA 02563 Mr. Robert Hillman 63 Cooke Road Plymouth, MA 02360 Ms. Casey Meserve Plymouth Bulletin 165 Enterprise Drive Marshfield, MA 02050 Mr. Joseph Prall 26 Sushala Way Plymouth, MA 02360 Ms. Mary Valliere 12 Harvest View Carver, MA 02330 Mr. Robert R. Ruddock General Counsel Associated Industries of Massachusetts 22 Berkeley Street / P.O. Box 763 Boston, MA 02117-0763 Ms. Anne D. Geller 13 Vernon Street Plymouth, MA 02360 Mr. Frank Collins P.O. Box 713 Manomet, MA 02345-0712 Mr. Congressman Delahunt 1250 Hancock Street, 8th Floor Quincy, MA 02169 Mr. J. Tarney-Manuel 11 Elm Street Plymouth, MA 02360
Pilgrim Nuclear Power Station cc:
Alba C. Thompson 11 Westwood Rd.
Plymouth, MA 02360 Office of the Attorney General One Ashburton Place 20th Floor Boston, MA 02108 Diane Curran, Esq.
Harmon, Curran, Spielberg
& Eisenberg, L.L.P.
1726 M Street, NW, Suite 600 Washington, DC 20036 Matthew Brock, Esq.
Assistant Attorney General Office of the Massachusetts Attorney General Environmental Protection Division One Ashburton Place, Room 1813 Boston, MA 02108-1598 Ms. Shelia Hollis Suite 700 1667 K Street, NW Washington, DC 20006 Ms. Molly Barlett 52 Crooked Lane Duxbury, MA 02332 David R. Lewis, Esq.
Paul A. Gaukler, Esq.
Pillsbury Winthrop Shaw Pittman LLP 2300 N Street, NW Washington, DC 20037-1128 Chief Kevin M. Nord Fire Chief and Director, Duxbury Emergency Management Agency 688 Tremont Street P.O. Box 2824 Duxbury, MA 02331