CY-06-146, Submittal of Haddam Neck Plant, Final Status Survey (FSS) Final Report - Phase IV
| ML063400421 | |
| Person / Time | |
|---|---|
| Site: | Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png |
| Issue date: | 11/29/2006 |
| From: | Gerard van Noordennen Connecticut Yankee Atomic Power Co |
| To: | Document Control Desk, NRC/FSME |
| References | |
| CY-06-146 | |
| Download: ML063400421 (3) | |
Text
CONNECTICUT YANKEE ATOMIC POWER COMPANY HADDAM NECK PLANT 362 INJUN HOLLOW ROAD
- EAST HAMPTON, CT 06424-3099 November 29, 2006 Docket No. 50-213 CY-06-146 Re: 10 CFR 50.82(a)(11)
U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555-0001 Haddam Neck Plant Final Status Survey (FSS) Final Report - Phase IV The Haddam Neck Plant (HNP) License Termination Plan (LTP) (Section 1.4) describes the process of releasing land from the HNP Operating License. The HNP LTP Section 5.9.2 states that the FSS Final Report will be prepared and submitted in a phased approach.
CYAPCO is hereby submitting the FSS Final Report - Phase IV (Attachment 1).
This Phase IV FSS Final Report addresses sixteen (16) water covered survey units comprising the discharge canal and permanent wetland areas. This report contains a compilation of all 16 Survey Unit Release Records that are within the Phase IV scope. Table 1-1 of the report provides a listing of all the survey units including the classification and general description for each unit.
Based on the current schedule, Phase V, Phase VI and Phase VII FSS Final Reports will be submitted to the NRC in December 2006, February 2007 and May 2007, respectively.
CYAPCO hereby requests the NRC review this Phase IV FSS Final Report for acceptance of this portion of the HNP site final radiological survey by March 30, 2007.
"m~)'s'&cT
U.S. Nuclear Regulatory Commission CY-06-146/ Page 2 If you should have any questions regarding this submittal, please contact me at (860) 267-3938.
Sincerely, G. P. van Noordennen Date Director, Nuclear Safety and Regulatory Affairs : Final Status Survey (FSS) Final Report - Phase IV cc:
S. J. Collins, NRC Region 1 Administrator T. B. Smith, NRC Project Manager, Haddam Neck Plant M. Roberts, Acting Chief, Decommissioning Branch, NRC Region 1 E. L. Wilds, Jr., Director, CT DEP Radiation Division
Docket No. 50-213 CY-06-146 Haddam Neck Plant Final Status Survey (FSS) Final Report - Phase IV November 2006