UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 March 2, 2006 Mr. James H. Lash Site Vice President First Energy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077
SUBJECT:
ANNUAL ASSESSMENT LETTER - BEAVER VALLEY POWER STATION UNITS 1 AND 2 (REPORTS 05000334/2006001 and 05000412/2006001)
Dear Mr. Lash:
On February 7, 2006, the NRC staff completed its performance review of the Beaver Valley Power Station Units 1 and 2. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period January 1 through December 31, 2005. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan.
Overall, Beaver Valley Power Station Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2007. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
J. Lash 2
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5200 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Ronald R. Bellamy, Ph.D., Chief Reactor Projects Branch 7 Division of Reactor Projects Docket Nos.
50-334, 50-412 License Nos. DPR-66, NPF-73
Enclosure:
Beaver Valley Power Station Inspection/ Activity Plan cc w/encl:
R. Mende, Direction of Site Operations T. Cosgrove, Director, Maintenance P. Sena, Director, Engineering L. Freeland, Director, Site Performance Improvement and Manager, Regulatory Compliance D. Jenkins, Attorney, FENOC B. Sepelak, Supervisor, Nuclear Compliance M. Clancy, Mayor, Shippingport, PA D. Allard, PADEP C. OClaire, State Liaison to the NRC, State of Ohio Z. Clayton, EPA-DERR, State of Ohio Director, Utilities Department, Public Utilities Commission, State of Ohio D. Hill, Chief, Radiological Health Program, State of West Virginia J. Lewis, Commissioner, Division of Labor, State of West Virginia W. Hill, Beaver County Emergency Management Agency J. Johnsrud, National Energy Committee, Sierra Club
J. Lash 3
Distribution w/encl:
S. Collins, RA M. Dapas, DRA R. Bellamy, DRP R. Fuhrmeister, DRP B. Sosa, RI OEDO R. Laufer, NRR T. Colburn, PM, NRR R. Guzman, NRR P. Cataldo - Senior Resident Inspector P. Garrett - Resident OA DRS Director and Deputy Director, Region I DRS Branch Chiefs (5)
P. Kaufman, DRS J. McFadden, DRS G. Smith, DRS D. Silk, DRS R. Marziale, DRP Region I Docket Room (with concurrences)
RidsNrrDirsIpab@nrc.gov Institute of Nuclear Power Operations (INPO)
DOCUMENT NAME: S:\\ROP-6 EOC Review\\ROP-6 Annual Assessment Letters\\BV EOC.wpd SISP Review Complete: DMK (Reviewers Initials)
After declaring this document An Official Agency Record it will/will not be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP RI/DRP RI/DRP NAME PCataldo/DMK Furhmeister/DMKDKern/DMK BHolian/BEH RBellamy/RRB DATE 02/24/06 02/27/06 02/28/06 03/01/06 03/02/06 OFFICIAL RECORD COPY
Beaver Valley Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/02/2006 16:36:49 Report 22 3
50001
- U1 SG REPLACEMENT Other Routine 01/09/2006 05/01/2006 1
50001 IP Steam Generator Replacement Inspection 3
71007
- U1 RX HEAD REPLACEMENT Other Routine 01/23/2006 04/28/2006 1
71007 IP Reactor Vessel Head Replacement Inspection 1
7112101
- OCC RAD SAFETY - ACCESS Baseline Inspections 02/27/2006 03/03/2006 1, 2 7112101 IP Access Control to Radiologically Significant Areas 1
7112102
- OCC RAD SAFETY - ACCESS Baseline Inspections 04/03/2006 04/07/2006 1, 2 7112101 IP Access Control to Radiologically Significant Areas 1
7112102
- OCC RAD SAFETY - ALARA Baseline Inspections 04/24/2006 04/28/2006 1, 2 7112102 IP ALARA Planning and Controls 3
7111111B
- L.O. REQUAL PROG.(FOCUS U1)+P/F RSLT Baseline Inspections 07/31/2006 08/03/2006 1, 2 7111111B IP Licensed Operator Requalification Program 7
7111121
- CDBI (COMPONENT DESIGN BASES INSPECTION)
Baseline Inspections 06/12/2006 06/16/2006 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 06/26/2006 06/30/2006 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 07/10/2006 07/14/2006 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 07/17/2006 07/20/2006 1, 2 7111121 IP Component Design Bases Inspection 7
7111401
- EXERCISE EVALUATION & EP PI VERIFICATION Baseline Inspections 06/26/2006 06/30/2006 1, 2 7111401 IP Exercise Evaluation Baseline Inspections 06/26/2006 06/30/2006 1, 2 71151 IP Performance Indicator Verification 1
7112202
- PUB RAD SAFETY - RADWASTE Baseline Inspections 06/26/2006 06/30/2006 1, 2 7112202 IP Radioactive Material Processing and Transportation 2
7111112B
- MAINTENANCE RULE Baseline Inspections 09/11/2006 09/15/2006 1, 2 7111112B IP Maintenance Effectiveness 1
7112102
- OCC RAD SAFETY - ALARA Baseline Inspections 10/02/2006 10/06/2006 1, 2 7112102 IP ALARA Planning and Controls 1
7111108P
- INSERVICE INSPECTION - UNIT 2 Baseline Inspections 10/02/2006 10/20/2006 2
7111108P IP Inservice Inspection Activities - PWR 1
7112103
- OCC RAD SAFETY - INSTRUMENTS Baseline Inspections 12/11/2006 12/15/2006 1, 2 7112102 IP ALARA Planning and Controls 3
TRI FIRE
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 01/22/2007 01/26/2007 1
7111105T IP Fire Protection [Triennial]
Baseline Inspections 02/05/2007 02/09/2007 1
7111105T IP Fire Protection [Triennial]
1 71114
- EP PRGM INSP Baseline Inspections 02/05/2007 02/09/2007 1, 2 7111402 IP Alert and Notification System Testing This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Beaver Valley Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/02/2006 16:36:49 Report 22 1
71114
- EP PRGM INSP Baseline Inspections 02/05/2007 02/09/2007 1, 2 7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 02/05/2007 02/09/2007 1, 2 7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 02/05/2007 02/09/2007 1, 2 7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 02/05/2007 02/09/2007 1, 2 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 02/05/2007 02/09/2007 1, 2 71151-EP02 IP ERO Drill Participation Baseline Inspections 02/05/2007 02/09/2007 1, 2 71151-EP03 IP Alert & Notification System 1
7112101
- OCC RAD SAFETY Baseline Inspections 03/05/2007 03/09/2007 1, 2 7112101 IP Access Control to Radiologically Significant Areas 4
- PI&R Baseline Inspections 03/26/2007 03/30/2007 1, 2 71152B IP Identification and Resolution of Problems Baseline Inspections 04/09/2007 04/13/2007 1, 2 71152B IP Identification and Resolution of Problems 1
7112201
- PUB RAD SAFETY - RETS Baseline Inspections 05/14/2007 05/18/2007 1, 2 7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 3
7111117B
- MODS AND 50.59 Baseline Inspections 06/04/2007 06/08/2007 1, 2 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 06/04/2007 06/08/2007 1, 2 7111117B IP Permanent Plant Modifications 1
7112203
- PUB RAD SAFETY - REMP Baseline Inspections 08/06/2007 08/10/2007 1, 2 7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.