January 5, 2006

Duke Energy Corporation

ATTN:

Mr. G. R. Peterson

Vice President

McGuire Nuclear Station

12700 Hagers Ferry Road

Huntersville, NC 28078-8985

SUBJECT:

NOTIFICATION OF MCGUIRE NUCLEAR STATION COMPONENT DESIGN

BASES INSPECTION-NRC INSPECTION REPORT 05000369/2006007 AND

05000370/2006007

Dear Mr. Peterson:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region II staff will conduct a component design bases inspection at your McGuire Nuclear

Station during the weeks of March 20-24, 2006, April 3-7, 2006, and April 17-21, 2006. The

inspection team will be led by Larry Mellen, a Senior Reactor Inspector from the NRC's

Region II Office. This inspection will be conducted in accordance with the baseline inspection

procedure, Procedure 71111.21, Component Design Bases Inspection, issued December 2,

2005.

The inspection will evaluate the capability of risk significant / low margin components to function

as designed and support proper system operation. The inspection will also include a review of

selected operator actions, operating experience, and modifications.

During a telephone conversation on January 4, 2006, I confirmed with Ms. K. Crane of your

staff, arrangements for an information gathering site visit and the three-week onsite inspection.

The schedule is as follows:

Information gathering visit: Week of March 6, 2006.

Onsite weeks: March 20, 2006; April 3, 2006; and April 17, 2006.

The purpose of the information gathering visit is to meet with members of your staff to identify

risk-significant components and operator actions. Information and documentation needed to

support the inspection will also be identified. Mr. Rudy Bernhard, a Region II Senior Reactor

Analyst, may accompany Mr. Mellen and the inspection team during the information gathering

visit to review probabilistic risk assessment data and identify risk significant components which

will be examined during the inspection.

The enclosure lists documents that will be needed prior to the information gathering visit.

Please contact Mr. Mellen prior to preparing copies of the materials listed in the enclosure.

DEC

2

The inspectors will try to minimize your administrative burden by specifically identifying only

those documents required for the inspection preparation.

During the information gathering visit, the team leader will also discuss the following inspection

support administrative details: office space, suplemental documents requested to be made

available to the team in the Region II office prior to the inspection preparation week of March

13, 2006; arrangements for site access; and the availability of knowledgeable plant engineering

and licensing personnel to serve as points of contact during the inspection.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding the

information requested or the inspection, please contact Mr. Mellen at (404) 562-4531 or me at

(404) 562-4605.

Sincerely,

/RA/

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-369, 50-370

License Nos.: NPF-9, NPF-17

Enclosure

cc w/enc/: (See page 3)

DEC

3

cc w/encl:

C. J. Thomas

Regulatory Compliance Manager (MNS)

Duke Energy Corporation

Electronic Mail Distribution

R. L. Gill, Jr., Manager

Nuclear Regulatory Issues

and Industry Affairs

Duke Energy Corporation

526 S. Church Street

Charlotte, NC 28201-0006

Lisa Vaughn

Associate General Counsel

Duke Energy Corporation

526 South Church Street

Mail Code EC 07H

Charlotte, NC 28201-1244

Anne Cottingham

Winston & Strawn LLP

Electronic Mail Distribution

Beverly Hall, Acting Director

Division of Radiation Protection

N. C. Department of Environmental

Health & Natural Resources

Electronic Mail Distribution

County Manager of Mecklenburg County

720 East Fourth Street

Charlotte, NC 28202

Peggy Force

Assistant Attorney General

N. C. Department of Justice

Electronic Mail Distribution

_________________________

OFFICE

RII:DRS

RII:DRS

RII:DRS

SIGNATURE

NAME

C. Ogle

M. Ernstes

R. Moore

DATE

1/ /2006

1/ /2006

1/ /2006

1/ /2006

1/ /2006

1/ /2006

1/ /2006

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

Enclosure

INFORMATION REQUEST FOR MC GUIRE NUCLEAR STATION

COMPONENT DESIGN BASES INSPECTION

Please provide the information electronically in .pdf files, Excel, or other searchable format on

CDROM. The CDROM should be indexed and hyperlinked to facilitate ease of use.

Information in lists should contain enough information to be easily understood to someone

who has a knowledge of pressurized water reactor technology.

1.

Risk ranking of components from your site specific probabilistic safety analysis (PSA)

sorted by Risk Achievement Worth (RAW) and sorted separately by Birnbaum

Importance. If possible, please provide a correlation between actual plant components

in plain language, and RAW values.

2.

Provide a list of the top 500 cutsets from your PSA.

3.

Risk ranking of operator actions from your site specific PSA sorted by RAW. Provide

copies of your human reliability worksheets for these items.

4.

If you have an External Event or Fire PSA Model, provide the information requested in

Items 1 and 2 for external events and fire.

5.

Any pre-existing evaluation or list of components and calculations with low design

margins (i.e., pumps closest to the design limit for flow or pressure, diesel generator

close to design required output, heat exchangers close to rated design heat removal,

MOV risk-margin rankings, etc.).

6.

A list of the last two years of operating experience evaluations, modifications, and

corrective actions sorted by component or system.

7.

Information of any common cause failure of components experienced in the last 5 years

at your facility.