ML052430046

From kanterella
Jump to navigation Jump to search

Withholding from Public Disclosure, Setpoint Methodology Portion of the Response to (NRC) Request for Additional Information, Questions 1 and 2 (CAW-05-1998)
ML052430046
Person / Time
Site: Callaway Ameren icon.png
Issue date: 09/07/2005
From: Donohew J
NRC/NRR/DLPM/LPD4
To: Gresham J
Westinghouse
Donohew J N, NRR/DLPM,415-1307
References
CAW-05-1998, TAC MC4437
Download: ML052430046 (4)


Text

September 7, 2005 Mr. James A. Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company P.O. Box 355 Pittsburgh, PA 15230-0355

SUBJECT:

REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (CAW-05-1998) (TAC NO. MC4437)

Dear Mr. Gresham:

By letter dated May 26, 2005, AmerenUE submitted an affidavit dated May 26, 2005, executed by you, requesting that information in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390.

Setpoint Methodology Portion of the Response to [NRC] Request for Additional Information, Questions 1 and 2 A nonproprietary copy of the document was provided for placement in the NRC's Public Document Room and for addition to the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room.

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(i)

The information sought to be withheld from public disclosure is owned and has been held in confidence by Westinghouse.

(ii)

The information is of a type customarily held in confidence by Westinghouse and not customarily disclosed to the public.

(a)

The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouse's competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.

(c)

Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.

J. Gresham We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the information in Attachment 1 to the AmerenUE letter dated May 26, 2005, "Setpoint Methodology Portion of the Response to [NRC] Request for Additional Information, Questions 1 and 2," marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at (301) 415-1307.

Sincerely,

/RA/

Jack Donohew, Senior Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-483 cc: See next page

J. Gresham We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the information in Attachment 1 to the AmerenUE letter dated May 26, 2005, "Setpoint Methodology Portion of the Response to [NRC] Request for Additional Information, Questions 1 and 2," marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at (301) 415-1307.

Sincerely,

/RA/

Jack Donohew, Senior Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-483 DISTRIBUTION:

PUBLIC cc: See next page PDIV-2 Reading RidsNrrDlpmPdiv (HBerkow)

RidsNrrDlpmPdiv2 DCollins RidsNrrPMJDonohew RidsNrrLALFeizollahi RidsOgcRp HLi AHowe ADAMS ACCESSION NO.: ML052430046 NRR-084 OFFICE PDIV-2/PM PDIV-2/LA EEIB:SC/A PDIV-2/SC(A)

NAME JDonohew LFeizollahi AHowe DCollins DATE 9/2/05 9/1/05 9/2/2005 9/7/05 OFFICIAL RECORD COPY

Updated: July 2005 Callaway Plant, Unit 1 cc:

Professional Nuclear Consulting, Inc.

19041 Raines Drive Derwood, MD 20855 John ONeill, Esq.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, N.W.

Washington, D.C. 20037 Mr. Mark A. Reidmeyer, Regional Regulatory Affairs Supervisor Regulatory Affairs AmerenUE P.O. Box 620 Fulton, MO 65251 U.S. Nuclear Regulatory Commission Resident Inspector Office 8201 NRC Road Steedman, MO 65077-1302 Mr. Les H. Kanuckel Manager, Quality Assurance AmerenUE P.O. Box 620 Fulton, MO 65251 Missouri Public Service Commission Governor Office Building 200 Madison Street Jefferson City, MO 65102-0360 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Mr. Mike Wells, Deputy Director Missouri Department of Natural Resources P.O. Box 176 Jefferson City, MO 65101 Mr. Rick A. Muench President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KA 66839 Mr. Dan I. Bolef, President Kay Drey, Representative Board of Directors Coalition for the Environment 6267 Delmar Boulevard University City, MO 63130 Mr. Lee Fritz, Presiding Commissioner Callaway County Court House 10 East Fifth Street Fulton, MO 65151 Mr. David E. Shafer Superintendent, Licensing Regulatory Affairs AmerenUE P.O. Box 66149, MC 470 St. Louis, MO 63166-6149 Mr. Keith D. Young Manager, Regulatory Affairs AmerenUE P.O. Box 620 Fulton, MO 65251 Mr. Scott Clardy, Director Section for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570 Certrec Corporation 4200 South Hulen, Suite 630 Fort Worth, TX 76109 Director, Missouri State Emergency Management Agency P.O. Box 116 Jefferson City, MO 65102-0116 Mr. Charles D. Naslund Senior Vice President and Chief Nuclear Officer Union Electric Company Post Office Box 620 Fulton, MO 65251