SAFEGUARDS INFORMATION November 19, 2004 Mr. Paul D. Hinnenkamp Vice President, Operations Entergy Operations, Inc.
River Bend Station, Unit 1 5485 U.S. Highway 61 P.O. Box 220 St. Francisville, LA 70775
SUBJECT:
RIVER BEND STATION, UNIT 1 - CORRECTION TO ADMINISTRATIVE CHANGE TO FACILITY OPERATING LICENSE AND SAFETY EVALUATION PURSUANT TO COMMISSION ORDER EA-03-086 REGARDING REVISIONS TO PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN (TAC NO. MC2963)
Dear Mr. Hinnenkamp:
By letter dated October 28, 2004, the Nuclear Regulatory Commission (NRC) issued an administrative change to Facility Operating License (FOL) NPF-47 for River Bend Station, Unit 1, to incorporate the reference to the recently-revised physical security plan, training and qualification plan, and safeguards contingency plan. Your staff identified errors in the revised license page and in the Safety Evaluation (SE) provided in the October 28, 2004, letter.
Therefore, the NRC is issuing a corrected page to the FOL and to pages 14 and 49 of the SE, which contain Safeguards Information. The revised license and SE pages for River Bend Station, Unit 1, are enclosed. We regret any inconvenience this may have caused.
Sincerely,
/RA/
John A. Nakoski, Chief Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-458
Enclosures:
- 2. Revised pages of SE cc w/encl 1 only: See attached page cc w/encls 1 and 2: Mr. Andre James, Site Security Manager SAFEGUARDS INFORMATION NOTICE: Enclosure 2 to this letter contains Safeguards Information. Upon separation from Enclosure 2, this letter and Enclosure 1 are DECONTROLLED.
River Bend Station cc w/o encl.:
Winston & Strawn 1400 L Street, N.W.
Washington, DC 20005-3502 Manager - Licensing Entergy Operations, Inc.
River Bend Station 5485 US Highway 61N St. Francisville, LA 70775 Senior Resident Inspector P. O. Box 1050 St. Francisville, LA 70775 President of West Feliciana Police Jury P. O. Box 1921 St. Francisville, LA 70775 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Ms. H. Anne Plettinger 3456 Villa Rose Drive Baton Rouge, LA 70806 Mr. Michael E. Henry, State Liaison Officer Department of Environmental Quality Permits Division P. O. Box 4313 Baton Rouge, LA 70821-4313 Wise, Carter, Child & Caraway P. O. Box 651 Jackson, MS 39205 Executive Vice President and Chief Operating Officer Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 General Manager - Plant Operations Entergy Operations, Inc.
River Bend Station 5485 US Highway 61N St. Francisville, LA 70775 Director - Nuclear Safety Entergy Operations, Inc.
River Bend Station 5485 US Highway 61N St. Francisville, LA 70775 Vice President - Operations Support Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Attorney General State of Louisiana P. O. Box 94095 Baton Rouge, LA 70804-9095 Brian Almon Public Utility Commission William B. Travis Building P. O. Box 13326 1701 North Congress Avenue Austin, TX 78701-3326
SAFEGUARDS INFORMATION November 19, 2004 Mr. Paul D. Hinnenkamp Vice President, Operations Entergy Operations, Inc.
River Bend Station, Unit 1 5485 U.S. Highway 61 P.O. Box 220 St. Francisville, LA 70775
SUBJECT:
RIVER BEND STATION, UNIT 1 - CORRECTION TO ADMINISTRATIVE CHANGE TO FACILITY OPERATING LICENSE AND SAFETY EVALUATION PURSUANT TO COMMISSION ORDER EA-03-086 REGARDING REVISIONS TO PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN (TAC NO. MC2963)
Dear Mr. Hinnenkamp:
By letter dated October 28, 2004, the Nuclear Regulatory Commission (NRC) issued an administrative change to Facility Operating License (FOL) NPF-47 for River Bend Station, Unit 1 to incorporate the reference to the recently-revised physical security plan, training and qualification plan, and safeguards contingency plan. Your staff identified errors in the revised license page and in the Safety Evaluation (SE) provided in the October 28, 2004, letter.
Therefore, the NRC is issuing a corrected page to the FOL and to pages 14 and 49 of the SE, which contain Safeguards Information. The revised license and SE pages for River Bend Station, Unit 1, are enclosed. We regret any inconvenience this may have caused.
Sincerely,
/RA/
John A. Nakoski, Chief Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-458
Enclosures:
- 2. Revised pages of SE cc w/encl 1 only: See attached page cc w/encls 1 and 2: Mr. Andre James, Site Security Manager SAFEGUARDS INFORMATION DISTRIBUTION:
PUBLIC SPRT R/F OGC ACRS DJohnson MWebb RGramm HBerkow GHill (2)
DLPM DPR TBoyce AHowell, RIV Accession No.:
OFFICE SPRT/PM SPRT/TL NRR/PM PDIV/LA SPRT/PL NRR/SC NAME MChernoff PPeduzzi MWebb DJohnson JPeralta JNakoski DATE 11/17/04 11/15/04 11/18/04 11/18/04 11/17/04 11/17/04 DOCUMENT NAME: A:\\ML043240436.wpd OFFICIAL RECORD COPY NOTICE: Enclosure 2 to this letter contains Safeguards Information. Upon separation from Enclosure 2, this letter and Enclosure 1 are DECONTROLLED.
CHANGES TO FACILITY OPERATING LICENSE NO. NPF-47 DOCKET NO. 50-458 Replace the following page of the Facility Operating License NPF-47 with the attached revised page as indicated. The revised page is identified by revision date and contains marginal lines indicating the area of change.
Remove Page Insert Page 7
7 D.
The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to the provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21, is entitled: "Physical Security, Safeguards Contingency and Training and Qualifications Plan" submitted by letter dated September 30, 2004.
E.
Except as otherwise provided in the Technical Specifications or Environmental Protection Plan, EOI shall report any violations of the requirements contained in Section 2, Items C.(1); C.(3) through (9); and C.(11) through (16) of this license in the following manner: initial notification shall be made within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to the NRC Operations Center via the Emergency Notification System with written followup within 60 days in accordance with the procedures described in 10 CFR 50.73 (b), (c) and (e).
F.
The licensee shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
G.
This license is effective as of the date of issuance and shall expire at midnight on August 29, 2025.
FOR THE NUCLEAR REGULATORY COMMISSION Original signed by Harold R. Denton, Director Office of Nuclear Reactor Regulation
Enclosures:
- 1. Attachments 1-5
- 2. Appendix A - Technical Specifications (NUREG-1172)
- 3. Appendix B - Environmental Protection Plan
- 4. Appendix C - Antitrust Conditions Date of Issuance: November 20, 1985 Revised: December 16, 1993 Amendment No. 70, 79, 85, 119, 135 Revised by letter dated October 28, 2004 Revised by letter dated November 19, 2004