Text
% I Ia*If am--
4, TM Richard L. Anderson Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem /Boulevard Berwick, PA 18603 Tel. 570.542.3883 Fax 570.542.1504 RLAnderson@ pplweb.com October 13,2004 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop O-P1-17 Washington, D.C. 20555-0001 SUSQUEHANNA STEAM ELECTRIC STATION MONTHLY OPERATING REPORTS Dockei Nos. 50-397/NPF-14 and 50-388/NPF-22 PLA-005829 The September 2004 Monthly Operating Reports for Susquehanna SES Units I and 2 are attached.
Very truly yours,
?4e6 Richarl. Anderson JJH/cmm cc: NRC Region 1 NRC Sr. Resident Inspector, Mr. A. Blarney NRC Project Manager, Mr. R V. Guzman
, OPERATING DATA REPORT DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-387 One 10/13/2004 J. J. Hennings (570) 542-3747 OPERATING STATUS 1.
2.
3.
4.
Unit Name:
Suspuehanna Steam Electric Station (UP)
Reporting Period:
September 2004 Design Electrical Rating (Net MWe):
1177*
Maximum Dependable Capacity (Net MWe):
1135*
5.
6.
7.
8.
9.
Hours in Reporting Period Number of Hours Reactor Was Critical Hours Generator On-Line Unit Reserve Shutdown Hours Net Electrical Energy Generated (MWH)
This Month 720 720 720 0
807,882 Yr.-to-Date 6575 5294.2 5244.4 0
5,680,239 Cumulative 186,864 155,779.0 153,484.0 0
158,293,677 NOTES:
- Design Electrical Rating (DER) and Maximum Dependable Capacity (MDC) has been changed starting with the May reporting period due to turbine modifications that were completed in April.
Page 1 of 1
I :
I UNIT SHUTDOWNS DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-387 One 10/13/2004 J. J. Hennings (570) 542-3747 REPORT MONTH September 2004 No.
Date Type Duration Reason Method of Cause & Corrective Action (Hours) 2 Shutting To Prevent Recurrence Down Reactor 3 No shutdowns this month Summary: The only significant power reduction this month was down to 68% power on 9/10/04 for a Control Rod Sequence Exchange. 100% power was achieved on 9/13/04.
1.
F. Forced S. Scheduled
- 2.
3.
Reason:
Method:
A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continuation from previous month E - Operator Training & Licensee Exam 5 - Other F - Administrative G - Operational Error (Explain)
Page 1 of 1
SUSQUEHANNA STEAM ELECTRIC STATION Docket Number:
50-387 Completed by: J. J. Hennings Challenges to Main Steam Safety Relief Valves None.
Date:
10/13/04 Telephone:
(570) 542-3747
OPERATING DATA REPORT DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-388 Two 10/13/04 J. J. Hennings (570) 542-3747 OPERATING STATUS
- 5.
Unit Name:
Susguehanna Steam Electric Station (U2)
- 6. Reporting Period:
September 2004
- 7.
Design Electrical Rating (Net MWe):
1182
- 8. Maximum Dependable Capacity (Net MWe):
1140 5.
6.
7.
8.
9.
Hours in Reporting Period Number of Hours Reactor Was Critical Hours Generator On-Line Unit Reserve Shutdown Hours Net Electrical Energy Generated (MWH)
This Month 720 720 720 0
814,938 Yr.-to-Date 6,575 6,575 6,575 0
7,525,737 Cumulative 172,104
.150,470.8
.148,483.6 0O 156,283,748 NOTES:
Page 1 of I
T I IO UNIT SHUTDOWNS DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-388 Two 10/13/04 J. J. Hennings (570) 542-3747 REPORT MONTH September 2004 No.
Date Type Duration Reason Method of Cause & Corrective Action I
(Hours) 2 Shutting to Prevent Recurrence Down Reactor 1<'3 X
No shutdowns this month.
Summary: The only power reduction greater than 20% this month, was down to 68% power on 9/17/04 for a planned Control Rod Sequence Exchange. 100% power was achieved on 9/19/04.
1.
2.
3.
F. Forced S. Scheduled Reason:
A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction Method:
1 - Manual 2 -Manual Scram 3 - Automatic Scram 4 - Continuation from previous month 5 - Other E - Operator Training & Licensee Exam F - Administrative G - Operational Error (Explain)
Page 1 of 1
SUSQUEHANNA STEAM ELECTRIC STATION Docket Number:
50-388 Completed by: J. J. Hennings Date:
10/13/2004 Telephone:
(570) 542-3747 Challenges to Main Steam Safety Relief Valves None.