Public Meeting on with Nuclear Management Company, Llc to Discuss Performance Improvement Commitments
ML040860583
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/26/2004
From: Louden P
NRC/RGN-III/DRP/RPB7
To: Middlesworth G
Nuclear Management Co
References
IP 95003 IR-03-007
Download: ML040860583 (5)


Text

March 26, 2004 Mr. Gary D. Van Middlesworth Site Vice-President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

PUBLIC MEETING ON MARCH 16, 2004, TO DISCUSS PERFORMANCE IMPROVEMENT COMMITMENTS

Dear Mr. Van Middlesworth:

On March 16, 2004, a public meeting was held between Mr. James McCarthy and other members of the Nuclear Management Company (NMC) and NRC Regional Administrator, James Caldwell and other NRC officials at the Region III Office. The purpose of the meeting was to discuss commitments made by NMC in its February 13, 2004, letter submitted to the NRC in response to Inspection Report 05000266/2003007; 05000301/2003007, the Supplemental Inspection Procedure 95003 inspection report.

At the meeting, discussion details regarding the commitment letter included clarifying summary statements and performance verification objectives to some of the individual commitment items to ensure that a common understanding of NMCs actions was reached.

As a result of that meeting, NMC submitted a revised listing of commitments in a letter dated March 22, 2004. We are reviewing those revised commitments and will inform you in a separate correspondence of the results of our review.

A listing of principal NMC and NRC meeting attendees is enclosed with this letter.

In accordance with 10 CFR 2.390 of the NRCs Rule of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

G. Van Middlesworth If you have any questions regarding this meeting, please contact me at (630) 829-9627.

Sincerely,

/RA/

Patrick Louden, Chief Reactor Projects Branch 7 Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27

Enclosure:

List of Principal Attendees cc w/encl:

R. Kuester, President and Chief Executive Officer, We Generation J. Cowan, Executive Vice President Chief Nuclear Officer D. Cooper, Senior Vice President, Group Operations D. Weaver, Nuclear Asset Manager Plant Manager Regulatory Affairs Manager Training Manager J. Rogoff, Vice President, Counsel & Secretary K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin State Liaison Officer

DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML040860583.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII RIII NAME MKunowski/trn PLouden DATE 03/26/04 03/26/04 03/ /04 03/ /04 OFFICIAL RECORD COPY

G. Van Middlesworth ADAMS Distribution:

WDR DFT DWS RidsNrrDipmIipb GEG HBC PGK1 C. Ariano (hard copy)

C. Pederson, DRS (hard copy - IRs only)

DRPIII DRSIII PLB1 JRK1

Enclosure PUBLIC MEETING PRINCIPAL ATTENDEES March 16, 2004 Nuclear Management Company, LLC (NMC)

James McCarthy Site Director, Point Beach James Connolly Regulatory Affairs Manager, Point Beach Douglas Johnson Director of Life Cycle Issues, NMC Fritzie Flentje Principal Regulatory Affairs Analyst, Point Beach Monica Ray Emergency Preparedness Manager, Point Beach NRC James Caldwell Regional Administrator Steve Reynolds Acting Director, Division of Reactor Projects Roy Caniano Deputy Director, Division of Reactor Safety Lakshminaras Raghavan Chief,Section III, Project Directorate III, Office of Nuclear Reactor Regulation Patrick Louden Chief, Branch 7, Division of Reactor Projects Anton Vegel Chief, Systems Branch, Division of Reactor Safety Ken Riemer Chief, Plant Support Branch, Division of Reactor Safety R. Michael Morris Acting Senior Resident Inspector, Point Beach John Jacobson Senior Reactor Engineer Tom Ploski Senior Emergency Preparedness Inspector Mike Kunowski Project Engineer