Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JAN 1 5 2004 LR-N04-0012 o PSEG NuclearLLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT I DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 1 Technical Specifications, the operating statistics for December 2003 are being forwarded.
Sincerely arl ricker Sa m Plant Manager Attachments C Distribution j5-:7aq 95-2168 REV. 7/99
.r, -,
e DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-272 Salem 1 1/9/04 F. Todd (856) 339-1316 Reporting Period December 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 A d 1111111
_11___11 11 11 1096
_"1 Month Year-to-date Cumulative 744 8478 150666 744 8402 145953 0
0 0
801774 9096682 149000648 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONI F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)
=
(1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.: 50-272 UNIT: Salem 1 DATE: 1/9/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience Salem 1 entered the month at a reduced power level and reached 100% power on December 1.
On December 5, Salem 1 was reduced to approximately 72% power due to 500KV line outage. Power was restored to 100% on December 6.
On December 24, Salem I was reduced to approximately 91 % power and later to approximately 82% power due to circulators out of service and excessive river grass intrusion.
Power was restored to 100% on December 28.
On December 30, Salem I was reduced to approximately 82% power due to circulators out of service. Power remained at a reduced level to the end of the month.
At the end of the month, Salem 1 completed 73 days of continuous on-line operation.