ML033560469
| ML033560469 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 11/28/2003 |
| From: | Ogle C Division of Reactor Safety I |
| To: | Scarola J Carolina Power & Light Co |
| References | |
| FOIA/PA-2003-0358 IR-02-011 | |
| Download: ML033560469 (24) | |
See also: IR 05000400/2002011
Text
Carolina Power & Light Company
ATTN: Mr. James Scarola
Vice President - Harris Plant
Shearon Harris Nuclear Power Plant
P. 0. Box 165, Mail Code: Zone 1
New Hill, North Carolina 27562-0165
SUBJECT:
SHEARON HARRIS NUCLEAR PLANT - NRC INSPECTION REPORT
50-400/02-11
Dear Mr. Scarola:
On December 20, 2002, the Nuclear Regulatory Commission (NRC) completed a triennial fire
protection inspection at your Shearon Harris Nuclear Plant. The enclosed integrated inspection
report documents the inspection findings which were discussed on that date, with you and other
members of your staff.
The inspection examined the effectiveness of activities conducted under your license relating to
implementation of your NRC-approved fire protection program. The inspectors reviewed
selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, the inspectors identified eight issues of very low safety
significance (Green). Each of these issues was determined to involve a violation of NRC
requirements. However, because of their very low safety significance and because they have
been entered into your corrective action program, the NRC is treating these issues as Non-
Cited Violations (NCVs), in accordance with Section VI.A.1 of the NRC's Enforcement Policy.
In addition, since two of these findings are related to your corrective action for the previous
violation associated with the Thermo-Lag fire barrier assembly between the 'B' train switchgear
room/auxiliary control panel room and the A train cable spreading room, that violation will
remain open. If you deny any NCV in this report, you should provide a response with the basis
for your denial, within 30 days of the date of this inspection report, to the Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001; with copies to the
Regional Administrator, Region II; Director, Office of Enforcement, United States Nuclear
Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at
the Shearon Harris Nuclear Plant.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be publicly available in the NRC Public Document Room or from the Publicly
2
Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is
accessible from the NRC Web site at htto:/lwww.nrc.cov/reading-rm/adams.html (the Public
Electronic Reading Room).
Sincerely,
Charles R. Ogle, Chief
Engineering Branch 1
Division of Reactor Safety
Docket No.: 50-400
License No.: NPF-63
Enclosure: NRC Inspection Report 50-400/02-11
w/Attachment
cc w/encl:
Distribution w/encl:
PUBLIC
{OFFICE
RI1:DRS
RII:DRS
RII:DRS
RII:DRP
RII:DRS
RII:DRS
RII:DRP
SIGNATURE
NAME
RSchin
GWiseman
PFilfion
RHagar
SWalker
DCPayne
- PFredrickson
DATE
1/J2003
1/_J2003
1/__J2003
1/_J2003
1/IJ_003
1/_J2003
1/_J2003
E-MAIL COPY?
YES
NO
YES
NO
YES
NO
-YES
N
NO
YES
NO
PUBLIC DOCUMENT
YES
NO
.
UFCA HU
_UP
lXXMN
NAE P:AMKISl-l '02- _ HO
- _A.wpd
e
OFFICIAL RECORDI
COUPY
UOUUMLINJ NAML: F.XHAKKI5W0Z-11R0.WP(J
U.S. NUCLEAR REGULATORY COMMISSION
REGION II
Docket No.:
License No.:
50-400
Report No.:
Licensee:
Facility:
Location:
Dates:
Inspectors:
50-400/02-11
Carolina Power & Light (CP&L)
Shearon Harris Nuclear Plant
5413 Shearon Harris Road
New Hill, NC 27562
October 21 - 25, 2002 (Week 1)
November 4 - 8, 2002 (Week 2)
December 16 - 20, 2002 (Week 3)
P. Fillion, Reactor Inspector, Region II
R. Hagar, Resident Inspector, Shearon Harris (Week 3 only)
D. C. Payne, Fire Protection Team Leader, Region II (Week 3 only)
R. Schin, Senior Reactor Inspector, Region II (Lead Inspector)
S. Walker, Reactor Inspector (Week 3 only)
G. Wiseman, Senior Fire Protection Inspector, Region II (Weeks 1
&2)
Accompanying Personnel:
H. Christensen, Deputy Director, Division of Reactor
Safety, Region II (Week 3 only)
C. Ogle, Chief, Engineering Branch 1, Division of Reactor
Safety, Region II
N. Staples, Inspector Trainee, Region II (Weeks 1 & 2)
Approved by:
Charles R. Ogle, Chief
Engineering Branch 1
Division of Reactor Safety
Enclosure
SUMMARY OF FINDINGS
IR 05000400-02-11; Carolina Power & Light; on 10/21/2002 - 12120/2002, Shearon Harris
Nuclear Plant, Triennial Baseline Inspection of the Fire Protection Program.
The inspection was conducted by a team of regional engineering inspectors and the Shearon
Harris resident inspector. Nine Green findings, each a Non-Cited Violation (NCV), were
identified. The significance of issues is indicated by their color (Green, White, Yellow, Red)
using IMC 0609 "Significance Determination Process" (SDP). Findings for which the SDP does
not apply may be "Green" or be assigned a severity level after NRC management review. The
NRC's program for overseeing the safe operation of commercial nuclear power reactors is
described in NUREG-1 649, "Reactor Oversight Process," Revision 3, dated July 2000.
Inspection Identified Findings
Cornerstones: Mitigating Systems and Initiating Events
Green. An NCV of Shearon Harris Operating License Condition (OLC) 2.F, Fire
Protection Program; and Technical Specification (TS) 6.8.1, Procedures and Programs,
was identified for failing to protect equipment [motor-operated valve (MOV) 1 CS-1 65,
volume control tank (VCT) outlet to charging pumps (CSIPs)] from maloperation due to
a fire. Consequently, a fire in any of three different plant areas could result in a reactor
coolant pump (RCP) seal loss of coolant accident (LOCA) with no operable CSIP.
This finding had a credible impact on safety because it could result in a loss of
equipment that was relied upon for safe shutdown from a fire and could initiate a LOCA
event. However, the finding was of very low safety significance because of the low fire
initiation frequency and probability of spurious actuations, and the effectiveness of
automatic sprinklers, fire brigade, and remaining SSD equipment to limit the effects of a
fire and to shut down the nuclear reactor. Therefore, this finding is characterized as
Green (Section 1 R05.-).
Green. An NCV of OLC 2.F and TS 6.8.1 was identified for failing to protect equipment
(MOVs 1CC-208, CC supply to RCP seals; and 1CC-251, CC return from RCP seals)
from maloperation due to a fire. Consequently, a fire in one plant area could potentially
This finding had a credible impact on safety because it could result in a loss of
equipment that was relied upon for safe shutdown from a fire and could potentially
initiate a LOCA event. However, the finding was of very low safety significance because
of the low fire initiation frequency and probability of spurious actuations, and the
effectiveness of automatic sprinklers, fire brigade, and remaining SSD equipment to limit
the effects of a fire and to shut down the nuclear reactor. Therefore, this finding is
characterized as Green (Section 1 R05..).
Green. An NCV of OLC 2.F and TS 6.8.1 was identified for failing to provide a fire
barrier to protect equipment [MOVs 1 CS-1 66, VCT outlet to CSIPs and I CS-1 68, CSIP
2
suction cross-connect] from maloperation due to a fire. Consequently, a fire in one
plant area could result in a loss of all charging and high pressure safety injection.
This finding had a credible impact on safety because it could result in a loss of
equipment that was relied upon for safe shutdown from a fire. However, the finding was
of very low safety significance because of the low fire initiation frequency and probability
of spurious actuations, and the effectiveness of automatic sprinklers, fire brigade, and
remaining SSD equipment to limit the effects of a fire and to shut down the nuclear
reactor. Therefore, this finding is characterized as Green (Section 1 R05._).
Green. An NCV of OLC 2.F and TS 6.8.1 was identified for failing to provide a fire
barrier to protect equipment [MOVs 1 CS-1 69, CSIP suction cross-connect; 1 CS-214,
CSIP mini-flow isolation; 1CS-218, CSIP discharge cross-connect; and 1CS-219, CSIP
discharge cross-connect] from maloperation due to a fire. Consequently, a fire in one
plant area could result in a loss of all charging and high pressure safety injection.
.
This finding had a credible impact on safety because it could result in a loss of
equipment that was relied upon for safe shutdown from a fire. However, the finding was
of very low safety significance because of the low fire initiation frequency and probability
of spurious actuations, and the effectiveness of automatic sprinklers, fire brigade, and
remaining SSD equipment to limit the effects of a fire and to shut down the nuclear
reactor. Therefore, this finding is characterized as Green (Section 1 R05._).
Green. An NCV of TS 6.8.1 was identified for inadequate procedural steps. For a fire in
fire area 1-A-ACP, AOP-36 steps 2.C and 14.A (which involved removing fuses from
transfer panel 1 B near the door to the fire area) involved excessive challenges to
operators. Challenges included exposure to smoke that would leak past the door and to
the fire brigade who would be opening the door, entering a narrow energized electrical
cabinet, and using a metal screwdriver inside the cabinet and seven feet above the floor
with poor visibility and poor labeling. There was not reasonable assurance that all
auxiliary operators (AOs) could perform the steps during a fire. Consequently, operators
may not be able to manually start the auxiliary feedwater pump that was relied upon for
SSD.
This finding had a credible impact on safety because it could result in inability to operate
equipment that was relied upon for SSD from a fire. However, the finding was of very
low safety significance because of the low fire initiation frequency, fire brigade, and
remaining SSD equipment to limit the effects of a fire and to shut down the nuclear
reactor. Therefore, this finding is characterized as Green (Section 1 R05._).
Green. An NCV of TS 6.8.1 was identified for an inadequate procedure for SSD from a
fire. For a fire in areas l-A-BAL-B or l-A-ACP, there too many AOP-36 contingency
actions, to respond to potential spurious actuations, for the one available SSD AO to
perform. Examples included continuously locally manually throttling the charging
system flow control valve bypass valve while at the same time locally manually closing a
steam generator power operated relief valve that could stick open in a different area of
3
the plant; or at the same time locally manually controlling auxiliary feedwater flow in
another area of the plant. Consequently, a main steam line break event may not be
stopped or auxiliary feedwater may be lost.
This finding had a credible impact on safety because it could result in inability to prevent
an initiating event or to operate equipment that was relied upon for SSD from a fire.
However, the finding was of very low safety significance because of the low fire initiation
frequency, automatic sprinklers, fire brigade, and remaining SSD equipment to limit the
effects of a fire and to shut down the nuclear reactor. Therefore, this finding is
characterized as Green (Section 1 R05_).
Green. An NCV of TS 6.8.1 was identified for an inadequate procedure for SSD from a
fire. For a fire in area 1-A-BAL-B, AOP-36 directed operators to take CSIP suction from
the boric acid tank (BAT) even if BAT level indication were lost. However, the charging
volume needed for reactor coolant system (RCS) cooldown would have emptied the
BAT and damaged the CSIP.
This finding had a credible impact on safety because it could result in loss of equipment
that was relied upon for SSD from a fire. However, the finding was of very low safety
significance because of the low fire initiation frequency, automatic sprinklers, fire
brigade, and remaining SSD equipment to limit the effects of a fire and to shut down the
nuclear reactor. Therefore, this finding is characterized as Green (Section 1 R05L.
Green. An NCV of OLC 2.F and TS 6.8.1 was identified for failing to provide battery-
backed emergency lights for operators to perform actions for SSD from a fire. For a fire
in SSA areas 1 -A-BAL-B-B1, 1 -A-BAL-B-B2, 1 -A-BAL-B-B4, 1 -A-BAL-B-B5, 1-A-EPA, 1-
A-BATB, or 1-A-ACP; many operator actions had no adequate battery-backed
emergency lights. Some of those actions had no emergency lights at all. However,
some had fluorescent lights that would be powered by the emergency diesel generators
during a LOOP, but those lights had not been approved by the NRC as an exemption
from the requirement for battery-backed emergency lights.
This finding has a credible impact on safety because it could result in operators failing to
perform SSD actions in an accurate and timely manner. However, the finding was of
very low safety significance because operators had flashlights available which would
have enabled them to perform the actions. Therefore, this finding is characterized as
Green (Section 1 R05_).
Report Details
1.
REACTOR SAFETY
Cornerstones: Initiating Events and Mitigating Systems
1R05 FIRE PROTECTION
.01
Systems Required To Achieve and Maintain Post-Fire SSD Circuit Analysis
a.
Inspection Scope
The team evaluated the licensee's approved fire protection program (FPP) against
applicable requirements, including Operating License NFP-63, License Condition 2.F,
Fire Protection Program (FPP); Branch Technical Position (BTP) Chemical Engineering
Branch (CMEB) 9.5-1 (NUREG-0800), July 1981; related NUREG 1038, NRC Safety
Evaluation Reports (SERs); and plant Technical Specifications (TS). The team evaluated
all areas of this inspection, as documented below, against these requirements.
The team used the licensee's Individual Plant Examination for External Events (IPEEE)
and in-plant tours to select four risk significant fire areas/zones for inspection. The four
fire areas/zones selected were:
Fire Zone 1-A-4-CHLR; part of Fire Area 1-A-BAL-B:
This fire zone was located on the 261 foot level (ground level) of the auxiliary building. It
was further subdivided in the licensee's SSA into SSA areas 1-A-BAL-B-B1 [including
the "A" chiller and motor-driven AFW pumps flow control valves (FCVs)] and SSA area 1-
A-BAL-B-B2 (including the "B" chiller and turbine-driven TDAFW pump FCVs). A
significant fire in either of these areas would require shutdown of the unit from the main
control room (MCR) and additional manual operator actions in various areas of the plant.
Fire Zone 1-A-4-COM-E; part of Fire Area 1-A-BAL-B:
This fire zone was located on the 261 foot level (ground level) of the auxiliary building. It
was further subdivided in the licensee's SSA into SSA areas 1-A-BAL-B-B4 (including
480V MCC 1B35-SB) and 1-A-BAL-B-B5 (including 480V MCC 1A35-SA). A significant
fire in either of these areas would require shutdown of the unit from the main control
room (MCR) and additional manual operator actions in various areas of the plant.
Fire Area 1-A-EPA:
This fire zone was located on the 261 foot level (ground level) of the auxiliary building. It
included electrical penetration room 'A'. A significant fire in this area would require
shutdown of the unit from the MCR and additional manual operator actions in various
areas of the plant.
Fire Area 1-A-BATB:
This fire zone was located on the 286 foot level (above ground level) of the auxiliary
building. It included the 'B' electrical battery room. A significant fire in this area would
require shutdown of the unit from the MCR and additional manual operator actions in
various areas of the plant.
2
The team reviewed the post-fire SSD capability and the fire protection features to verify
that at least one post-fire safe shutdown success path would be maintained free of fire
damage during a fire in any of the selected fire areas/zones. The team reviewed the
licensee's fire protection program, including the SSA and supporting calculations, to
determine the systems required to achieve post-fire SSD. The team also reviewed the
safe shutdown equipment list (SSEL), system flow diagrams, and the fire area hazards
analysis in the Updated Final Safety Analysis Report (UFSAR) for each of the selected
fire areas to evaluate the completeness and adequacy of the SSD analysis and the
systems relied upon to mitigate fires in the selected fire areas. Specific licensee
documents and drawings reviewed during the inspection are listed in the Attachment.
b.
Findings
The team found that the licensee's SSA method for dealing with problem cables, that
were required for control room operation of safe shutdown equipment during a fire in a
certain area but were not physically protected from that fire, was primarily to rely on
operator manual actions (e.g., locally open the breaker to an MOV and locally operate
the MOV using the handwheel.) Only if no operator action could be found would Harris
physically protect the cables. Consequently, the licensee had over 100 local manual
operator actions that they relied on for hot shutdown. The licensee did not request
deviations from the NRC for these operator actions. This SSD methodology contributed
to the findings that are described in the following sections of this report.
.02
Fire Protection of SSD Capability
a.
Inspection Scope
The team reviewed UFSAR Section 9.5.1, Appendix 9.5A, Fire Hazards Analysis (FHA);
the FPP manual; and plant administrative fire prevention/combustible hazards-ignition
source control procedures. This review was to verify that the objectives established by
the NRC-approved FPP were satisfied. The team also toured the selected plant fire
areas observing the licensee's implementation of these procedures. The team also
reviewed the FPP transient combustible permit logs, and fire emergency/incident
investigation reports, for the years 2000-2002. Corrective action program Action
Requests (ARs) resulting from fire, smoke, sparks, arcing, and equipment overheating
incidents for the same period were also reviewed to assess the effectiveness of the fire
prevention program and to identify any maintenance or material condition problems
related to fire incidents.
The team reviewed flow diagrams and engineering calculations associated with the B'
battery room heating ventilation and air conditioning (HVAC) systems. This review was
done to verify that systems used to accomplish safe shutdown would not be inhibited by
a potential hydrogen gas fire in the 'B' battery room due to inoperable ventilation supply
and exhaust fans. The team also reviewed the TS LCO requirements for loss of
ventilation in the 'B' battery room to verify that appropriate timely actions were specified
to ensure that hydrogen gas concentrations generated by the station batteries remained
below explosive limits.
3
The team also toured the plant's primary fire brigade staging and dress-out areas to
assess the condition of fire fighting and smoke control equipment. Fire brigade personal
protective equipment located in brigade staging area lockers was reviewed to evaluate
equipment accessibility and functionality. Additionally, the team examined whether
backup emergency lighting was provided for access pathways to and within the fire
brigade staging and dress-out areas in support of fire brigade operations should a power
failure occur during the fire emergency. The team also observed whether emergency
exit lighting was provided for personnel evacuation pathways to the outside exits as
identified in the National Fire Protection Association (NFPA) 101, Life Safety Code and
Occupational Safety and Health Administration (OSHA) Part 1910, Occupational Safety
and Health Standards. The adequacy of the fire brigade self-contained breathing
apparatus (SCBAs) was reviewed as well as the availability of supplemental breathing air
tanks. Team members also toured the selected fire areas and compared the associated
fire pre-plans with as-built plant conditions. This was done to verify that they were
consistent with the fire protection features and potential fire conditions described in the
UFSAR. Additionally, the team reviewed drawings and engineering flood analysis
associated with the 261' elevation reactor auxiliary building floor and equipment drain
system to verify that those actions required for ASD would not be inhibited by fire
suppression activities or leakage from fire suppression systems.
The team reviewed the fire brigade response procedure, fire brigade organization,
training and drill program administration procedures. Fire drill critiques of operating shifts
for the period of March 2001 through October 2002 were reviewed to verify that fire
brigade drills had been conducted in high fire risk plant areas. Fire brigade training/drill
records for 2002 were also reviewed to verify that the fire brigade personnel
qualifications, brigade drill response time, and brigade performance met the
requirements of the licensee's approved FPP. Additionally, the team observed a fire drill
to verify the licensee's implementation of the fire brigade organization, training, and drill
program administration procedures. The team observed the actions of the site fire
brigade, offsite fire department, and fire drill monitors; and attended the drill critique.
b.
Findings
No findings of significance were identified.
.03
Post-Fire SSD Circuit Analysis
a.
Inspection Scope
The team reviewed the adequacy of separation and fire barriers provided for the power
and control cabling of equipment relied on for SSD during a fire in any of the selected fire
areas/zones. On a sample basis, the team reviewed the electrical schematics for power
and control circuits of SSD components and looked for the potential effects of open
circuits, shorts to ground, and hot shorts. This review focused on the cabling of selected
components for the charging/safety injection system, AFW system, and component
cooling water (CC) system. The team traced the routing of cables by using the cable
schedule and conduit and tray drawings. Walkdowns were performed to compare 1-hour
and 3-hour barriers (conduit and tray wraps) to barriers indicated on the drawings.
Circuits and cabling routings were reviewed for the following equipment: 1 CS-169,
4
charging/safety injection pump (CSIP) suction cross connect MOV; 1CS-168, CSIP
suction cross connect MOV; 1CS-214, CSIP minimum flow MOV; 1CS-217, CSIP
discharge cross connect MOV; 1CS-218, CSIP discharge cross connect MOV; 1CS-219,
CSIP discharge cross connect MOV; 1CS-1 65, volume control tank (VCT) outlet MOV;
1 CS-1 66, VCT outlet MOV; 1 CS-278, boric acid tank (BAT) to CSIP MOV; BAT level
instrumentation; 1 CC-207, CC supply to RCP seals MOV; 1 CC-208, CC supply to RCP
seals MOV; 1 CC-252, CC return from RCP seals MOV; 1 CC-251, CC return from RCP
seals MOV; 1CC-249, CC return from RCP seals MOV; 1 RC-1 17, pressurizer power-
operated relief valve (PORV) block valve; 1 Sl-310, containment sump to 'A' RHR pump
MOV; 1SI-311, containment sump to 'B' RHR pump MOV; motor-driven AFW pump 1A;
motor-driven AFW pump 1 B; and turbine-driven AFW pump.
The team also reviewed studies of overcurrent protection on both AC and DC systems to
check whether fire induced faults could result in defeating the safe shutdown functions.
b.
Findinas
(1)
MOV 1CS-165. VCT Outlet to CSIPs
Introduction
The team identified an NCV of OLC 2.F, Fire Protection Program; and Technical Specification (TS) 6.8.1, Procedures and Programs; for failing to provide a fire barrier to
protect equipment (MOV 1CS-165), that was relied upon for safe shutdown (SSD), from
maloperation due to a fire; and for failing to provide procedural guidance for operators to
prevent or mitigate the maloperation.
Description
The team found that the control power cable for charging system MOV 1 CS-165, which
was relied upon to remain open for SSD during a fire in SSA areas 1-A-BAL-B-B1 and 1-
A-BAL-B-B2, and in fire area 1-A-EPA, was routed through those areas with no fire
barrier. This lack of a required fire barrier was not recognized in the SSA and no
procedural guidance was included in AOP-36, Safe Shutdown Following a Fire, Rev. 21,
for operators to prevent or mitigate maloperation of 1 CS-165 prior to damage occurring
to SSD equipment. Consequently, a fire in one of the three areas could cause 1CS-1 65
to spuriously close, stop all CSIP suction, and immediately damage the operating SSD
CSIP.
The SSD analysis for a fire in areas 1 -A-BAL-B-B1, 1 -A-BAL-B2, or 1-A-EPA was to rely
on SSD division 2 equipment. This included reliance on CSIP 'B' for RCS makeup water,
RCP seal cooling, reactivity control by boration, and high pressure safety injection. CSIP
'A' was not assured to be unaffected by the fire and CSIP 'C' was not assured to be
available. Consequently, a failure of CSIP 'B' could result in a loss of all charging and
high pressure safety injection. Also, for a fire in any of these three areas, CC to the RCP
seals was not protected. The team found that the control power cable to MOV 1 CC-207,
CC flow to RCP seals, was also routed through the same three areas and in the same
cable tray with the control power cable to 1 CS-165. Spurious closure of MOV 1 CC-207
would stop all CC flow to the seals of all three RCPs. Thus the potential consequences
5
of a fire in any of the three areas could be an RCP seal LOCA with no operable CSIP.
In addition, the team found that the control power cable for MOV 1 CC-252, CC return
from RCP seals, was routed through SSA area 1-A-BAL-B-B2 and could be affected by a
fire in that area. AOP-36 included an operator action to prevent spurious actuation of
1 CC-252 for a fire in SSA area 1 -A-BAL-B-B2. That action included opening the breaker
to the MOV on MCC 1 E12. However, the SSD AO would likely not be able to safely do
that during a fire in SSA area 1 -A-BAL-B-B2 because MCC 1 El2 was located in that
area. Spurious closure of 1CC-252 would stop all CC to the RCP seals. The team noted
that, while this operator action may not be needed for a fire in SSA area 1 -A-BAL-B-B2
because the charging system was supposed to provide RCP seal cooling, this
inappropriate procedural action (sending an operator into an area on fire) could delay the
SSD AO from performing other actions that were needed.
The team found that modification ESR 01-00087, which was installed in about January
2002, had affected this condition and missed an opportunity to correct it. ESR 01-00087
changed the CSIP mini-flow path so that it would go to the VCT instead of bypassing the
VCT and going directly to the CSIP suction. Prior to the ESR, if 1 CS-1 65 spuriously
closed, the running CSIP would still have some suction although probably not enough to
prevent pump damage. After the ESR, if 1CS-165 spuriously closed, the running CSIP
would have no suction and its failure would be more certain and more immediate. ESR
01 -00087 failed to recognize this effect and missed an opportunity to identify and correct
the condition.
Analysis
This finding had more than minor safety significance because it affected the Mitigating
Systems and Initiating Events objectives of the Reactor Safety Cornerstone. The finding
affected the availability and reliability of systems that mitigate initiating events to prevent
undesirable consequences. It also affected the likelihood of occurrence of initiating
events that challenge critical safety functions. However, the finding was of very low
safety significance because of the low fire initiation frequency and probability of spurious
actuations, and the effectiveness of automatic sprinklers, fire brigade, and remaining
SSD equipment to limit the effects of a fire and to shut down the nuclear reactor.
Therefore, this finding is characterized as Green.
Enforcement
OLC F. required that the licensee implement and maintain in effect all provisions of the
approved fire protection program as described in the Final Safety Analysis Report. The
UFSAR, Section 9.5.1, Fire Protection Program, stated that outside containment, where
cables or equipment (including associated non-essential circuits that could prevent
operation or cause maloperation due to hot shorts, open circuits, or shorts to ground) of
redundant safe shutdown divisions of systems necessary to achieve and maintain cold
shutdown conditions are located within the same fire area outside of primary
containment, one the redundant divisions must be ensured to be free of fire damage.
Section 9.5.1 further stated that one division is to be protected from fire damage by one
of three methods: 1) a three-hour fire barrier, 2) a one-hour fire barrier plus automatic
detection and suppression, or 3) a 20-foot separation with no intervening combustibles
6
and with automatic detection and suppression.
TS 6.8.1 required procedures as recommended by Regulatory Guide (RG) 1.33 and
procedures for fire protection program implementation. RG 1.33 recommended
procedures for combating emergencies, including fires. The licensee's interpretation of
their fire protection program was that they could and would rely on operator actions in
place of physical protection of SSD equipment (see Section
).
However, the
licensee had failed to provide procedural guidance in AOP-36 for operators to prevent
the maloperation of MOV 1CS-165.
Contrary to the above requirements, the licensee failed to protect MOV 1 CS-165 from
maloperation due to a fire where it was relied on for SSD. Because the licensee entered
the finding into the corrective action program as AR76260, this item is being treated as
an NCV in accordance with Section VI.A.1 of the NRC's Enforcement Policy. This item is
identified as NCV 50-400/02-11 -01, Failure to Protect MOV 1 CS-1 65, VCT Outlet to
CSIPs, From Maloperation Due To a Fire.
(2)
MOV 1CC-251. CC Return From RCP Seals:
and MOV 1 CC-208. CC Supply To RCP Seals
Introduction
The team identified an NCV of OLC 2.F and TS 6.8.1 for failing to provide a fire barrier
to protect equipment (MOV 1 CC-251 and MOV 1 CC-208) that was relied upon for SSD
from maloperation due to a fire, and for failing to provide procedural guidance for
operators to prevent or mitigate the maloperation.
Description
The team found that the control power cables for CC system MOVs 1 CC-251 and 1 CC-
208, which were relied upon to remain open for SSD during a fire in area 1-A-BAL-C,
were routed through that area with no fire barrier. Fire area 1-A-BAL-C was located on
the 286 foot level of the auxiliary building, above electrical penetration room 'B'. This
lack of a required fire barrier was not recognized in the SSA and no procedural guidance
was included in AOP-36 for operators to prevent or mitigate maloperation of these
valves. Consequently, a fire in this area could cause 1 CC-251 or 1 CC-208 to spuriously
close, which would stop all CC to the RCP seals.
The SSD analysis for a fire in area 1-A-BAL-C was to relyon SSD division 1 equipment.
This included reliance on CC to cool the RCP seals. CSIP supply to the RCP seals was
not assured to be unaffected by the fire. Consequently, a loss of CC to the RCP seals
could result in a loss of all RCP seal cooling which could in turn result in an RCP seal
failure and a LOCA.
Analysis
This finding had more than minor safety significance because it affected the Initiating
Events objective of the Reactor Safety Cornerstone. The finding affected the likelihood
of occurrence of initiating events that challenge critical safety functions. However, the
7
finding was of very low safety significance because of the low fire initiation frequency and
probability of spurious actuations, and the effectiveness of automatic sprinklers, fire
brigade, and remaining SSD equipment to limit the effects of a fire and to shut down the
nuclear reactor. Therefore, this finding is characterized as Green.
Enforcement
As described in Section .03.b.1 above, OLC F. required equipment relied upon for SSD
be physically protected against maloperation due to the fire. Also, TS 6.8.1 required
procedures for implementing the fire protection program and for combating fires.
Contrary to the above requirements, the licensee failed to protect MOV I CS-1 65 from
maloperation due to a fire where it was relied on for SSD. Because the licensee entered
the finding into the corrective action program as AR 80089, this item is being treated as
an NCV in accordance with Section VI.A.1 of the NRC's Enforcement Policy. This item is
identified as NCV 50-400/02-11-02, Failure to Protect MOVs 1 CC-251 and 1 CC-208, CC
for RCP Seals, From Maloperation Due To a Fire.
(3)
MOV 1CS-169, CSIP Suction Cross-connect: MOV 1CS-214. CSIP Mini-flow Isolation:
MOV 1CS-218. CSIP Discharge Cross-connect: and MOV 1CS-219. CSIP Discharge
Cross-connect
Introduction
The team identified an NCV of OLC 2.F and TS 6.8.1 for failing to provide a fire barrier to
protect equipment (MOVs 1 CS-1 69,1 CS-214,1 CS-218, and 1 CS-219) that was relied
upon for SSD from maloperation due to a fire, and for failing to provide procedural
guidance for operators to prevent or mitigate the maloperation.
Description
The team found that the control power cables for charging system MOVs 1 CS-1 69, 1 CS-
214,1 CS-218, and 1 CS-219, which were relied upon to remain open for SSD during a fire
in area 1-A-BAL-B-B5, were routed through that area with incomplete fire barriers. The
control cables were unprotected for about one foot above MCC 1-A35-SA and inside the
MCC.
This lack of a required fire barrier was recognized in the SSA for 1 CS-I 69,1 CS-214, and
ICS-218, and procedural guidance was included in AOP-36 for operators to prevent
maloperation of these valves. However, the procedural guidance was not adequate.
AOP-36 directed operators to go to MCC 1 -A35-SA and open the breakers for 1 CS-169
and 1 CS-214 to prevent spurious operation. However, operators would not be able to
safely do that because the actions were in the area of the fire that could cause the
spurious operation. AOP-36 directed operators to go to MCC 1-B35-SB, in another
room, to open the breaker for 1 CS-218. However, operators would not be able to do that
because the breaker for 1 CS-218 was actually located on MCC 1 -A35-SA. AOP-36
included no operator guidance for 1 CS-219.
AOP-36 did include the following guideline for operators: "Monitor for spurious valve and
8
pump operation which may result in equipment damage (for example, CSIP suction
valves.)" The team noted that closure of a CSIP suction valve could result in pump
damage within seconds; before operators could respond to an annunciator, analyze the
condition, and take action to prevent pump damage. Another AOP-36 guideline was:
'When directed by the Unit SCO, then shut down equipment and de-energize electrical
busses located within the fire area." Operators stated that they would de-energize MCC
1-A35-SA if the fire brigade team leader or another operator told them that the MCC was
on fire or if they observed spurious actuations that could be initiating from the MCC.
However, the team noted that the fire brigade would not arrive at the fire until about 22
minutes after the control room sounded the fire alarm, and spurious actuations could well
occur before that. By procedure, control room operators would respond to a single fire
detector annunciator by sending an AO to verify that there was a fire and that the fire was
large enough to warrant sounding the fire alarm and calling out the fire brigade.
However, if the control room received annunciation from two or more fire detectors,
which would be very likely in the event of fire large enough to present an operational
safety concern, then they would not send an AO but instead would immediately sound
the fire alarm and call out the fire brigade. So it was likely that the first visual report on
the fire would not be received in the control room until about 22 minutes after the fire
alarm. By that time, the fire would likely have filled the room with smoke so that the fire
brigade may not be able to see if the MCC was on fire.
The team concluded that it was unlikely that the control room would de-energize MCC 1-
A35-SA before spurious actuations could occur. Consequently, a fire in this area, near
MCC 1A35-SA, could cause any of the four MOVs to spuriously close. Closure of 1CS-
214 would stop all mini-flow from all CSIPs. Closure of 1CS-218 or 1CS-219 would stop
charging flow from SSD CSIP 'B'.
If such a loss of charging flow or CSIP mini-flow
occurred, operators would receive an alarm in the control room and would probably have
time to diagnose the condition and initiate recovery action. However, closure of 1 CS-1 69
would stop all suction to SSD CSIP 'B' and immediately damage the pump.
The SSD analysis for a fire in area 1-A-BAL-B-B5 was to rely on SSD division 2
equipment. This included reliance on CSIP 'B' for RCS makeup water, RCP seal cooling,
reactivity control by boration, and high pressure safety injection. CSIP 'A' was not
assured to be unaffected by the fire and CSIP 'C' was not assured to be available. The
team noted that MOVs powered from MCC 1-A35-SA could affect CSIP 'A' and CSIP 'C".
Consequently, a failure of CSIP 'B' could result in a loss of all charging, RCP seal
cooling, and high pressure safety injection. Thus the potential consequences of a fire in
SSA area 1 -A-BAL-B5 could be an RCP seal LOCA with no operable CSIP.
Analysis
This finding had more than minor safety significance because it affected the Mitigating
Systems and Initiating Events objectives of the Reactor Safety Cornerstone. The finding
affected the availability and reliability of systems that mitigate initiating events to prevent
undesirable consequences. It also affected the likelihood of occurrence of initiating
events that challenge critical safety functions. However, the finding was of very low
safety significance because of the low fire initiation frequency and probability of spurious
actuations, and the effectiveness of automatic sprinklers, fire brigade, and remaining
SSD equipment to limit the effects of a fire and to shut down the nuclear reactor.
9
Therefore, this finding is characterized as Green.
Enforcement
As described in Section .03.b.1 above, OLC F. required equipment relied upon for SSD
be physically protected against maloperation due to the fire. Also, TS 6.8.1 required
procedures for implementing the fire protection program and for combating fires.
Contrary to the above requirements, the licensee failed to protect MOVs 1CS-169,1 CS-
214,1CS-218, and 1CS-219 from maloperation due to a fire where they were relied on for
SSD. Because the licensee entered the finding into the corrective action program as
ARs 76260 and 80212, this item is being treated as an NCV in accordance with Section
Vl.A.1 of the NRC's Enforcement Policy. This item is identified as NCV 50-400/02-11-03,
Failure to Protect Charging System MOVs 1CS-169, 1CS-214, 1CS-218, and 1CS-219
From Maloperation Due To a Fire.
(4)
MOV 1CS-166. VOT Outlet to QSIPs: MOV 1CS-1 68. CSIP Suction Cross-connect: and
MOV 1CS-217. CSIP Discharge Cross-connect
Introduction
The team identified an NCV of OLC 2.F and TS 6.8.1 for failing to provide a fire barrier to
protect equipment (MOVs 1 CS-1 66, 1CS-168, and 1CS-217) that was relied upon for
SSD from maloperation due to a fire, and for failing to provide procedural guidance for
operators to prevent or mitigate the maloperation.
Description
The team found that the control power cables forcharging system MOVs 1CS-1 66, 1CS-
168, and 1CS-217, which were relied upon to remain open for SSD during a fire in area
1 -A-BAL-B-B4, were routed through that area with incomplete fire barriers. The control
cable for MOV I CS-1 66 was unprotected for about one foot above MCC 1 B35-SB and
inside the MCC. The control power cables for MOVs 1CS-168 and 1CS-217 were
unprotected inside MCC 1 B35-SB. This lack of a required fire barrier was not recognized
in the SSA and no procedural guidance was included in AOP-36 for operators to prevent
or mitigate maloperation of these valves. Consequently, a fire in this area, near MCC
1 B35-SB, could cause 1 CS-1 66 or 1 CS-1 68 to spuriously close, which would stop all
suction to SSD CSIP 'A', and immediately damage the pump. If CSIP 'C' were aligned to
be used in place of CSIP 'A', then the fire could cause spurious closure of 1CS-217 and
stop charging flow from CSIP C.
The SSD analysis for a fire in area 1 -A-BAL-B-B4 was to rely on SSD division 1
equipment. This included reliance on CSIP 'A' for RCS makeup water, reactivity control
by boration, and high pressure safety injection. CSIP 'B' was not assured to be
unaffected by the fire and CSIP 'C' was not assured to be available. Consequently, a
failure of CSIP 'A' could result in a loss of all charging and high pressure safety injection.
If CSIP 'C' were aligned to be operating in place of CSIP 'A', and a maloperation of 1CS-
217 caused a loss of charging flow, operators would receive a loss of charging flow alarm
and would have time to diagnose and recover from the loss of charging flow.
10
Analysis
This finding had more than minor safety significance because it affected the Mitigating
Systems objectives of the Reactor Safety Cornerstone. The finding affected the
availability and reliability of systems that mitigate initiating events to prevent undesirable
consequences. However, the finding was of very low safety significance because of the
low fire initiation frequency and probability of spurious actuations, and the effectiveness
of automatic sprinklers, fire brigade, and remaining SSD equipment to limit the effects of
a fire and to shut down the nuclear reactor. Therefore, this finding is characterized as
Green.
Enforcement
As described in Section .03.b.1 above, OLC F. required equipment relied upon for SSD
be physically protected against maloperation due to the fire. Also, TS 6.8.1 required
procedures for implementing the fire protection program and for combating fires.
Contrary to the above requirements, the licensee failed to protect MOVs 1 CS-1 66, 1 CS-
168, and 1CS-217 from maloperation due to a fire where they were relied on for SSD.
Because the licensee entered the finding into the corrective action program as AR
76260, this item is being treated as an NCV in accordance with Section VI.A.1 of the
NRC's Enforcement Policy. This item is identified as NCV 50-400/02-11-04, Failure to
Protect Charging System MOVs 1 CS-166,1 CS-168, and 1 CS-217 From Maloperation
Due To a Fire.
(5) Design of MO~s 1A35-SA and 1B35-SB
Introduction
The team identified an unresolved item (URI) regarding whether the design of MCCs
1 A35-SA and 1 B35-SB met the requirements for fire barriers to protect SSD components
from maloperation.
Description
The team had observed that MCCs 1A35-SA and 1 B35-SB included control and power
cables and breakers for MOVs that were relied upon to remain open for SSD during a fire
in the MCCs (See Sections .03.b.3 and .03.b.4 above.) These breakers were located in
the MCCs next to breakers that were not relied upon for SSD during such a fire. Since
there were no qualified fire barriers inside the MCCs, the team considered whether a fire
starting inside the MCCs could credibly cause spurious actuation (i.e., maloperation) of
SSD components.
The team noted that the licensee's IPEEE assumed that the most limiting condition
resulting from a fire starting inside one of these MCCs was a loss of power to the MCC
due to tripping of the power supply to the MCC. However, the team noted that a spurious
actuation resulting in a loss of the charging system would be a more limiting condition
that loss of power to the MCC. A licensee engineering manager considered that it was
not credible that a fire starting inside an MCC could result in spurious actuations of
11
breakers in the MCC, because the power supply to the MCC would automatically trip
before such spurious actuations could occur.
The team reviewed design drawings and descriptions of the MCCs. Each MCC
contained breakers that were arranged in vertical columns. Each column was separated
from the adjacent columns by solid sheets of steel. Each column included about four
breaker cubicles and a vertical cable pathway. Each breaker cubicle was separated from
the cubicles above and below it by solid sheets of steel, but each breaker cubicle had an
opening to the vertical cable pathway. The power and control cables for the breakers in
a column generally entered the MCC at the top, but some entered at the bottom. In
some columns, all power and control cables for all breakers in the column were in close
proximity near the top of the MCC, with essentially no physical separation or fire barrier.
Licensee engineers stated that the design of these MCCs, with SSD breakers co-located
with non-SSD breakers, was common at Shearon Harris and at other nuclear power
plants. This breaker arrangement resulted from the design requirements for internal
events, where there were two separate trains of electrical power such that the plant could
safely shut down with only one train being powered. Consequently, where two MOVs in
series had a safety function to be able to close, each was powered from a different
electrical train of power to ensure that at least one would be able to close. Two MOVs in
series were used in many applications, including containment isolation, CSIP suction
cross-connects, CSIP discharge cross-connects, and the VCT outlet to the CSIPs. Each
of the two MOVs in series was powered from a different electrical train and a different
MCC . However, for SSD during a fire, these same MOVs had a different safety function
- to remain open. If either one spuriously closed, it would shut off a required SSD
flowpath. Licensee engineers contended that they could not design the plant to preclude
having breakers for MOVs in the same fire area for which they were relied upon to
remain open for SSD.
Analysis
If a fire initiating in an MCC could credibly cause spurious actuations of SSD equipment
in the MCC, the observed condition could have more than minor safety significance
because it could affect the Mitigating Systems objectives of the Reactor Safety
Cornerstone. The condition could affect the availability and reliability of systems that
mitigate initiating events to prevent undesirable consequences. The condition could also
have generic applicability.
FollowuD Action
URI 50-400/02-11-05, Credibility of a Fire Inside an MCC Causing Spurious Actuations,
is opened for further NRC review of this design condition.
12
.04
Operational Implementation of SSD Capabilitv
.05
Emergency Communications
The guidelines established by BTP CMEB 9.5-1, Section C.5.g, "Lighting and
Communication,' paragraph (4), required that a portable communications system should
be provided for use by the fire brigade and other operations personnel required to
achieve safe plant shutdown. This system should not interfere with the communications
capabilities of the plant security force. Fixed repeaters installed to permit use of portable
radio communication units should be protected from exposure fire damage.
a.
Inspection Scope
The team reviewed the adequacy of the communication systems relied upon to
coordinate the shutdown of the unit and fire brigade duties, including the site paging
(PA), portable radio, and sound-powered phone systems. The team reviewed the
licensee's portable radio channel features to assess whether the system and its
repeaters were protected from exposure fire damage. During walkdowns of sections of
the post-fire SSD procedure, the team checked if adequate communications equipment
would be available for the personnel performing the procedure. The team also reviewed
the periodic testing of the site fire alarm and PA systems; maintenance checklists for the
sound-powered phone circuits and amplifiers; and inventory surveillance of post-fire SSD
operator equipment to assess whether the maintenance/surveillance test program for the
communications systems was sufficient to verify proper operation of the systems.
b.
Findinas
No findings of significance were identified.
.06
a.
Inspection Scope
The team reviewed the design and operation of, and examined the manufacturer's
information for the direct current (DC) emergency lighting system self-contained, battery
powered emergency lighting units (ELUs) as described in UFSAR Sections 9.5.1.2.2.e
and 9.5.3. During plant walk downs of selected areas where operators performed local
manual actions defined in the post-fire SSD procedure, the team inspected area ELUs for
operability and checked the aiming of lamp heads to determine if adequate illumination
was available to correctly and safely perform the actions required by the procedures.
The team inspected emergency lighting features along access and egress pathways
used during SSD activities for adequacy and personnel safety. The locations and
identification numbers on the ELUs were compared to design drawings to confirm the as-
13
built configuration. The team also checked if these battery power supplies were rated
with at least an 8-hour capacity. In addition, the team reviewed licensee periodic
maintenance tests to verify that the ELUs were being maintained in an operable manner.
b.
Findings
No findings of significance were identified.
.07
Cold Shutdown Repairs
a.
Inspection Scope
The team reviewed existing procedures and examined plant equipment to establish that
the licensee had dedicated repair procedures, equipment, and materials to accomplish
repairs of damaged components required for cold shutdown, that these components
could be made operable, and that cold shutdown could be achieved within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The
team examined cold shutdown repair equipment and replacement electrical power and
control cables for systems needed to take the plant to cold shutdown following a large
fire. The team evaluated the estimated manpower and the time required to perform post-
fire repairs for reasonableness.
b.
Findings
No findings of significance were identified.
.08
Fire Barriers and Fire Area/Zone/Room Penetration Seals
a.
Inspection Scope
The team walked down the selected fire zones/areas to evaluate the adequacy of the fire
resistance of barrier enclosure walls, ceilings, floors, and cable protection. This
evaluation also included fire barrier penetration seals, fire doors, fire dampers, cable tray
fire stops, and fire barrier partitions to ensure that at least one train of SSD equipment
would be maintained free of fire damage from a single fire. The team observed the
material condition and configuration of the installed fire barrier features and also
reviewed construction details and supporting fire endurance tests for the installed fire
barrier features. The team compared the observed fire barrier penetration seal
configurations to the design drawings and tested configurations. The team also
compared the penetration seal ratings with the ratings of the barriers in which they were
installed. In addition, the team reviewed licensing documentation, engineering
evaluations of Generic Letter 86-10 fire barrier features, and NFPA code deviations to
verify that the fire barrier installations met design requirements and license commitments.
b.
Findings
No findings of significance were identified.
.09
Fire Protection Svstems. Features, and Eauipment
14
a.
Inspection Scope
The team reviewed flow diagrams, electrical schematic diagrams, periodic test
procedures, engineering technical evaluations for NFPA code deviations, operational
valve lineup procedures, and cable routing data for the power and control circuits of the
motor-driven fire pump, the diesel-driven fire pump, and the fire protection water supply
system yard mains. The review evaluated whether the common fire protection water
delivery and supply components could be damaged or inhibited by fire-induced failures of
electrical power supplies or control circuits and subsequent possible loss of fire water
supply to the plant. Additionally, team members walked down the fire protection water
supply system in selected fire areas to assess the adequacy of the system material
condition, consistency of the as-built configuration with engineering drawings, and
operability of the system in accordance with applicable administrative procedures and
NFPA standards.
The team examined the adequacy of installed fire protection features in accordance with
the fire area and system spatial separation and design requirements in BTP CMEB 9.5-1.
The team walked down accessible portions of the fire detection and alarm systems in
the selected fire areas to evaluate the engineering design and operation of the installed
configurations. The team also reviewed engineering drawings for fire detector spacing
and locations in the four selected fire areas for consistency with the licensee's fire
protection plan and the requirements in NFPA 72E.
The team also walked down the selected fire zones/areas with automatic sprinkler
suppression systems installed to assure proper type, placement and spacing of the
heads/nozzles and the lack of obstructions. The team examined vendor information,
engineering evaluations for NFPA code deviations, and design calculations to verify that
the required suppression system density for each protected area was available.
The team reviewed the adequacy of the design, installation and operation of the manual
suppression standpipe and fire hose system for the selected fire areas. The team
examined design calculations and evaluations to verify that the required fire hose water
flow and sprinkler system density for each protected area were available. The team
checked a sample of manual fire hose lengths to determine whether they would reach
the SSD equipment. Additionally, the team observed placement of the fire hoses and
extinguishers to assess consistency with the fire fighting pre-plan drawings.
b.
Findings
No findings of significance were identified.
.10
Compensatory Measures
a.
Inspection Scope
The team reviewed the licensee's Fire Protection System Engineering Status Reviews
which identifies each fire protection system's performance problems and regulatory
issues. The team also reviewed the Fire Protection Out of Service Log generated for the
last 18 months and associated compensatory measures. The review was performed to
15
verify that the risk associated with removing fire protection and/or post-fire systems or
components was properly assessed and adequate compensatory measures were
implemented in accordance with the approved fire protection program.
b.
Findings
No findings of significance were identified.
4.
OTHER ACTIVITIES (OA)
40A2 Identification and Resolution of Problems
a.
Inspection Scone
The team reviewed the corrective action program procedures and a selected sample of
condition reports associated with the Harris FPP to verify that the licensee had an
appropriate threshold for identifying issues. The team also reviewed licensee audits and
assessments of fire protection and safe shutdown. The team evaluated the
effectiveness of the corrective actions for the identified issues.
b.
Findings
The team found that licensee audits and self-assessments in the area of SSD were
weak. They had not identified the types of findings that this inspection found.
Contributing factors included a lack of attention to detail; for example, not tracing cable
routings or walking down operator actions as was done in this inspection. In addition, the
CP&L corporate Nuclear Assessment Section (NAS) audits of fire protection at Shearon
Harris did not look at SSD. A Peer Report included in the November 2000 NAS audit of
Shearon Harris fire protection stated: uHarris NAS Fire Protection Program Audits of
recent past have not included fire events safe shutdown within the scope of the audits
due to a reliance on engineering self-assessments. It is the opinion of the auditor that
the scope of future Harris NAS Fire Protection assessments should include fire events
safe shutdown related documentation and activities." However, the team noted that
subsequent NAS audits of Harris fire protection did not audit SSD.
40A6 Meetings
Exit Meeting Summary
The team presented the inspection results to you and members of your staff at the
conclusion of the inspection on December 20, 2002. You acknowledged the findings
presented. Proprietary information is not included in this inspection report.
16
SUPPLEMENTAL INFORMATION
Partial List of Persons Contacted
Licensee
D. Baksa, Supervisor, Equipment Perfromance
J. Caves, Licensing Supervisor
R. Duncan, Director of Site Operations
M. Fletcher, Manager, Fire Protection Program
P. Fulford, Superintendent, Design Engineering
C. Georgeson, Supervisor, EI&C Design
W. Gregory, Operations Fire Protection Specialist
W. Gurganion, Manager, NAS
T. Hobbs, Manager, Operations
A. Khanpour, Manager, Engineering
F. Lane, Jr., Senior Nuclear Work Management Specialist
J. Laque, Manager, Maintenance
T. Morton, Site Services Manager
J. Scarola, Site Vice President
B. Waldrep, Plant General Manager
NRC
J. Brady, Senior Resident Inspector, Shearon Harris
H. Christensen, Deputy Director, Division of Reactor Safety (DRS), Region II (RiI)
C. Ogle, Chief, Engineering Branch 1, DRS, RiI
Items Opened. Closed, and Discussed
Opened
50-400/02-11-01
50-400/02-11-02
50-400/02-11-03
50-400/02-11-04
NCV
NCV
Failure to Protect Charging System MOV 1CS-1 65, VCT
Outlet to CSIPs, From Maloperation Due To a Fire (Section
1 R05.03.b.1)
Failure to Protect Component Cooling MOVs 1CC-251 and
1 CC-208, CC for RCP Seals, From Maloperation Due To a
Fire (Section 1 R05.03.b.2)
Failure to Protect Charging System MOVs 1CS-1 69, 1CS-
214, 1 CS-218, and 1 CS-219 From Maloperation Due To a
Fire (Section 1 R05.03.b.3)
Failure to Protect Charging System MOVs 1 CS-1 66, 1 CS-
168, and 1CS-217 From Maloperation Due To a Fire
(Section 1R05.03.b.4)
50-400/02-11-05
Credibility of a Fire Inside an MCC Causing Spurious
17
Actuations (Section 1 R05.03.b.5)
50-400/02-11-06
50-400/02-11-07
50-400/02-11-08
50-400/02-11-09
50-400/02-11-10
Closed
None
Discussed
50-400/02-08-01
VIa
Failure to Implement and Maintain NRC Approved Fire
Protection Program Safe Shutdown System Separation
Requirements (Section
)
18