Text

November 24, 2003 Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

ST. LUCIE UNITS 1 AND 2 - CORRECTIONS TO RENEWED OPERATING LICENSE AND TECHNICAL SPECIFICATIONS

Dear Mr. Stall:

On October 2, 2003, the U.S. Nuclear Regulatory Commission (NRC) issued the renewed operating licenses for St. Lucie Units 1 and 2. Subsequently, a member of the St. Lucie staff informed the NRC Project Manager that on page 4 of the Unit 2 renewed operating license, the last two lines of Condition 3.F, Physical Protection, had been omitted. We have determined that the complete paragraph is included in the official agency record (ADAMS Accession No. ML032870081), but the two lines were inadvertently omitted from paper copies during the reproduction process. Please insert the enclosed replacement page into your copy of the license.

The St. Lucie staff also reported that the copy of the Unit 1 Technical Specifications (TSs) enclosed with the renewed operating license included pages 3/4 7-32 through 3/4 7-39a from Amendment No. 83. These pages, which were marked Deleted, were subsequently removed by Amendment No. 134 and should be removed from the TSs. The NRC authority files have also been updated.

Prior to issuance of the renewed operating licenses, the St. Lucie licenses and TSs were reviewed as part of an effort to compare the NRCs license authority files with licensees records to ensure errors in licenses and TSs are identified and corrected for all units. A list of discrepancies identified in the review is enclosed for information. Corrections to the TSs were included in the copies of the TSs enclosed with the renewed operating licenses. The discrepancies noted in the Unit 2 original license were rendered moot by issuance of the renewed operating license. I have discussed the corrections with Mr. George Madden of your staff.

J. A. Stall The St. Lucie staff should be commended for their alertness in identifying the errors noted above. We apologize for any inconvenience they may have caused. If there are questions or comments, please contact me at 301-415-3974.

Sincerely,

/RA/

Brendan T. Moroney, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos: 50-335 and 50-389

Enclosures:

As stated cc w/encl: See next page

J. A. Stall The St. Lucie staff should be commended for their alertness in identifying the errors noted above. We apologize for any inconvenience they may have caused. If there are questions or comments, please contact me at 301-415-3974.

Sincerely,

/RA/

Brendan T. Moroney, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos: 50-335 and 50-389

Enclosures:

As stated cc w/encl: See next page Distribution PUBLIC PD II-2 R/F RLEP R/F AHowe BMoroney RAnand OGC ACRS JMunday, RII SBloom BClayton (Paper Copy)

GHill (4 Copies)

SLee ADAMS: ML033280516 OFFICE PM/PD II-2 PM/RLEP LA/PD II-2 SC/RLEP SC/PD II-2 NAME BMoroney RAnand BClayton SLee AHowe DATE 11/18/03 11/18/03 11/18/03 11/20/03 1121/03 OFFICIAL RECORD COPY Renewed License No. NPF-16 the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection.

The Updated Final Safety Analysis Report supplement as revised on March 28, 2003, described above, shall be included in the next scheduled update to the Updated Final Safety Analysis Report required by 10 CFR 50.71(e)(4), following issuance of this renewed license. Until that update is complete, FPL may make changes to the programs described in such supplement without prior Commission approval, provided that FPL evaluates each such change pursuant to the criteria set forth in 10 CFR 50.59 and otherwise complies with the requirements in that section.

D.

Antitrust Conditions FPL shall comply with the antitrust conditions in Appendices C and D to this renewed license.

E.

Fire Protection FPL shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report (The fire protection program and features were originally describe in the Final Safety Analysis Report, and supplemented by FPL submittals L-82-282 dated July 14, 1982, L-83-89 dated February 25, 1983, L-83-425 dated July 22, 1983, L-83-603 dated December 27, 1983, L-84-347 dated November 28, 1984, L-84-389 dated December 31, 1984, and L-85-72 dated February 21,1985, for the facility) and as approved in the NRC Safety Evaluation Report, Supplement 3 dated April 1983 and supplemented by NRC letter dated December 5, 1986, subject to the following provision:

FPL may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

F.

Physical Protection FPL shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The plans, which contain Safeguards Information protected under 10 CFR 73.21, are entitled: St. Lucie Plant Security Plan, with revisions submitted through April 11, 1988; St. Lucie Plant Training and Qualification Plan, with revisions submitted through August 8, 1985; and St. Lucie Plant Safeguards Contingency Plan, with revisions submitted through December 8, 1986. Changes made in accordance with 10 CFR 73.55 shall be implemented in accordance with the schedule set forth therein.

Authority File Review St. Lucie Unit 1 Technical Specifications Page Comments Action Required XIII Page number missing on licensees copy.

Replace with page from Amendment No. 142 (ADAMS ML013600135).

3/4 3-3 Licensees copy just shows Amendment No. 27 at the bottom of the page. It should show 15 crossed out, followed by

27. The text is correct.

Replace with page from Amendment No. 27 (ADAMS ML013530336).

3/4 3-5 Licensees copy just shows Amendment No. 27 at the bottom of the page. It should show 15 crossed out followed by

27. The text is correct.

Replace with page from Amendment No. 27 (ADAMS ML013530336).

3/4 3-36 Licensees copy is missing this page.

This page was deleted by Amendment No. 57 (ML013530400). It is Xed out in authority copies. Page 36 is not accounted for in the licensees copy, which has page 37 following page 35.

Add filler page to indicate that the page was deleted by Amendment No. 57.

3/4 7-19 The page number is illegible on the licensees copy.

Replace with page from Amendment No. 142 (ADAMS ML013600135).

5-1 Page number missing on licensees copy Replace with page from Amendment No. 142 (ADAMS ML013600135).

Authority File Review St. Lucie Unit 2 Technical Specifications Page Comments Action Required 2-3 Licensees copy missing "Figure No 2.1-1" label.

"Amendment No. 8" and page number are handwritten.

Replace with page from Amendment No. 8 (ADAMS ML013600092).

3/4 0-1 Licensees copy missing the word "corrected" after Amendment number. The text is the same.

Replace with page from correction letter for Amendment No. 33 (ADAMS ML013540511).

3/4 3-27 Licensees copy is missing this page.

Replace with page from Amendment No.73 (ADAMS ML013610006).

3/4 8-1 Licensees copy has page from Amendment No. 123 instead of corrected page from correction letter dated January 4, 2002.

Replace with page from correction letter for Amendment No.123 (ADAMS ML020070275).

5-4B through 5-4F Licensee's copy has a parenthetical reference to an electronic file that is different from the reference in the authority file. The curves appear to be the same.

Replace with pages from Amendment No.101 (ADAMS ML013610012).

St. Lucie Unit 2 (Original) License Appendix C, page 13 Parts of the right side of paragraph of IX (a) and (c) are cut off on the licensees copy.

Replace with page from the authority file.

Appendix C, page 16 Parts of the right side of paragraph of X(d) are cut off on the licensees copy.

Replace with page from the authority file.

Mr. J. A. Stall ST. LUCIE PLANT Florida Power and Light Company cc:

Senior Resident Inspector St. Lucie Plant U.S. Nuclear Regulatory Commission P.O. Box 6090 Jensen Beach, Florida 34957 Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 M. S. Ross, Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Douglas Anderson County Administrator St. Lucie County 2300 Virginia Avenue Fort Pierce, Florida 34982 Mr. William A. Passetti, Chief Department of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741 Mr. William Jefferson, Jr.

Site Vice President St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957-2000 Mr. G. L. Johnston Plant General Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Mr. Terry Patterson Licensing Manager St. Lucie Nuclear Plant 6351 South Ocean Drive Jensen Beach, Florida 34957 Vice President, Nuclear Operations Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. J. Kammel Radiological Emergency Planning Administrator Department of Public Safety 6000 SE. Tower Drive Stuart, Florida 34997