ML033020186

From kanterella
Jump to navigation Jump to search

Y020030173 - Alex Marion Ltr Re Generic Request for Order EA-03-009
ML033020186
Person / Time
Site: Nuclear Energy Institute
Issue date: 10/29/2003
From: Barrett R
Division of Engineering
To: Marion A
Nuclear Energy Institute
Collins J, NRR/EMCB, 415-4038
Shared Package
ML033020195 List:
References
EA-03-009, TAC MC1031, Y020030173
Download: ML033020186 (2)


Text

October 29, 2003 Mr. Alexander Marion Director, Engineering Nuclear Generation Division Nuclear Energy Institute 1776 I Street, N.W., Suite 400 Washington, DC 20006-3708

Dear Mr. Marion:

By letter dated September 26, 2003, Nuclear Energy Institute (NEI) submitted a generic request for relaxation from certain provisions of Order EA-03-009, which established interim inspection requirements for reactor pressure vessel heads at pressurized water reactors. By letter dated October 15, 2003, NEI provided additional information in response to staff questions raised during its initial review of the September 26, 2003 request.

The additional information will be considered as part of the generic relaxation technical basis report provided by the Materials Reliability Program Generic Evaluation of Examination Coverage Requirements for Reactor Pressure Vessel Head Penetration Nozzles (MRP-95).

If you have any questions regarding this matter, please contact me or Bill Bateman (301-415-2795 or WHB@NRC.GOV.

Sincerely,

/RA C. I. Grimes for/

Richard J. Barrett, Director Division of Engineering Office of Nuclear Reactor Regulation

October 29, 2003 Mr. Alexander Marion Director, Engineering Nuclear Generation Division Nuclear Energy Institute 1776 I Street, N.W., Suite 400 Washington, DC 20006-3708

Dear Mr. Marion:

By letter dated September 26, 2003, Nuclear Energy Institute (NEI) submitted a generic request for relaxation from certain provisions of Order EA-03-009, which established interim inspection requirements for reactor pressure vessel heads at pressurized water reactors. By letter dated October 15, 2003, NEI provided additional information in response to staff questions raised during its initial review of the September 26, 2003 request.

The additional information will be considered as part of the generic relaxation technical basis report provided by the Materials Reliability Program Generic Evaluation of Examination Coverage Requirements for Reactor Pressure Vessel Head Penetration Nozzles (MRP-95).

If you have any questions regarding this matter, please contact me or Bill Bateman (301-415-2795 or WHB@NRC.GOV.

Sincerely,

/RA C. I. Grimes for/

Richard J. Barrett, Director Division of Engineering Office of Nuclear Reactor Regulation DISTRIBUTION:

PUBLIC EMCB RF JDyer/WBorchardt BSheron KJohnson RBarrett/CGrimes WBateman TChan JCollins NRR Mailroom (YT# 020030173)

Package: ML033020195 Document

Title:

Alex Marion Ltr Re Generic Request Incoming:ML032900977 for Order EA-03-009 Response: ML033020186 OFFICE EMCB:DE EMCB:DE EMCB:DE DE:D NAME JWCollins TLChan WHBateman RJBarrett DATE 10/29/03 10/29/03 10/29/03 10/29/03 OFFICIAL RECORD COPY