A 0 An Energy East Company ROCHESERGASANDECIRCCORPORATWON

  • 89EAST AVENUEROCHFESERNY 146494001 585546-2700 vwwwre.om October 9, 2003 US Nuclear Regulatory Commission Document Control Desk Attn:

Robert Clark Project Directorate 1-1 Washington, DC 20555

Subject:

Monthly Report for September 2003 Operating Status Information R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Clark:

Pursuantto Ginna Improved Technical Specifications Section 5.6.4, attached is the monthly operating status report for Ginna Station for the month of September 2003.

Very truly yours, a --

hA. Widay ant Manager xc:

U.S. Nuclear Regulatory Commission Mr. Robert Clark (Mail Stop O-8E9)

Project Directorate 1-1 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector Attachments

OPERATING DATA REPORT 50-244 October 9, 2003 COMPLETED BY:

TL John V. Walden TELEPHONE (585) 771-3588 OPERATING STATUS

1. Unit Name:

R.E. GINNA NUCLEAR POWER PLANT

2. Reporting Period:

September, 2003

3. Design Electric Rating (Net MWe):

470

4. Maximum Dependable Capacity (Net MWe):

480 Notes:

This Month Yr.-to-Date Cumulative*

5. Number of hours Reactor Was Critical
6. Hours Generator On-line
7. Unit Reserve Shutdown Hours
8. Net Electrical Energy Generated (MWH) 340.8 340.3 0.0 151107.0 6104.8 6084.1 0.0 2973607.3 245121.7 241943.2 8.5
  • 110302516.3
  • CUMULATIVE TOTAL COMMENCING NOVEMBER 8,1969

IL DOCKET NO: 50-244 UNIT NAME: R.E. GINNA NUCLEAR POWER PLANT DATE: October 9. 2003 COMPLETED BY: John V. Walden TELEPHONE: (585) 771-3588 UNIT SHUTDOWN REPORTING PERIOD:

September 2003 (Month/Year)

NO.

DATE TYPE DURATION REASON)

METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)

SHUTTING S: SCHEDULED DOWN2)

COMMENTS 4

030915 S

379.7 C

1 Refueling and maintenanc, outage

SUMMARY

End of fuel cycle coastdown began at the start of the month of September. Power gradually decreased from full power to 81% over the time period of September 1 through September 14, 2003. At 2329 on September 14, 2003, the unit began a manual shutdown for refueling and maintenance. The unit was taken off-line at 0420 on September 15, 2003. The shutdown continued through the end of the month.

(1) Reason A-Equipment Failure (Explain)

B - Maintenance or Test C-Refueling D - Regulatory Restriction E - Operator Trainngflicense Examination F-Administrative G - Operational Error (Explain)

H -Other (Explain)

(2) Method 1 - Manuel 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4-Continuation 5 - Other (Explain)