Inspection/Activity Plan for 03/01/2002 - 03/31/2003
ML020670201
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 03/04/2002
From: Plisco L
Division Reactor Projects II
To: Dennis Morey
Southern Nuclear Operating Co
References
Download: ML020670201 (2)


Text

Farley Inspection / Activity Plan 03/01/2002 - 03/31/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/04/2002 09:54:27 Report 22 5

EB1-SSDI

- SSDI - INSPECTION Baseline Inspections 03/04/2002 03/08/2002 Safety System Design and Performance Capability IP 7111121 1, 2 5

EB1-SSDI

- SSDI - INSPECTION Baseline Inspections 03/18/2002 03/22/2002 Safety System Design and Performance Capability IP 7111121 1, 2 1

PS-SEC

- SECURITY Baseline Inspections 05/13/2002 05/17/2002 Access Authorization Program (Behavior Observation Only)

IP 7113001 1, 2 Baseline Inspections 05/13/2002 05/17/2002 Access Control (Search of Personnel, Packages, and Vehicles: Identification and Authorization)

IP 7113002 1, 2 Baseline Inspections 05/13/2002 05/17/2002 Performance Indicator Verification IP 71151 1, 2 1

BR2-BI

- FLOOD PROTECTION Baseline Inspections 06/24/2002 06/27/2002 Flood Protection Measures IP 7111106 1, 2 2

OL RQ

- REQUAL INSPECTION Baseline Inspections 07/15/2002 07/19/2002 Licensed Operator Requalification IP 7111111B 1, 2 4

EB1-FP

- FP - PRE-INSPECTION VISIT Baseline Inspections 07/22/2002 07/26/2002 Fire Protection IP 7111105T 1, 2 1

EB2-HS

- EB2-HS Baseline Inspections 08/05/2002 08/09/2002 Heat Sink Performance IP 7111107B 1, 2 3

EB1-FP

- FP - INSPECTION Baseline Inspections 08/12/2002 08/16/2002 Fire Protection IP 7111105T 1, 2 2

OL EP

- EMERGENCY EXERCISE Baseline Inspections 08/19/2002 08/23/2002 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 08/19/2002 08/23/2002 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 08/19/2002 08/23/2002 Performance Indicator Verification IP 71151 1, 2 3

EB1-FP

- FP - INSPECTION Baseline Inspections 09/09/2002 09/13/2002 Fire Protection IP 7111105T 1, 2 1

EB2-ISI

- EB2-ISI Baseline Inspections 09/16/2002 09/20/2002 Inservice Inspection Activities IP 7111108 2

3 PS-RP

- RADIATION PROTECTION Baseline Inspections 09/16/2002 09/20/2002 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 09/16/2002 09/20/2002 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 09/16/2002 09/20/2002 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 09/16/2002 09/20/2002 Performance Indicator Verification IP 71151 1, 2 1

2515/145

- TI 2515/145 (U2) RE: BULLETIN 01-01 Safety Issues 09/23/2002 09/29/2002 Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles (NRC Bulletin 2001-01)

IP 2515/145 2

3 PS-RP

- RADIATION PROTECTION Baseline Inspections 09/30/2002 10/04/2002 Access Control to Radiologically Significant Areas IP 7112101 1, 2 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Farley Inspection / Activity Plan 03/01/2002 - 03/31/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/04/2002 09:54:27 Report 22 3

PS-RP

- RADIATION PROTECTION Baseline Inspections 09/30/2002 10/04/2002 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 09/30/2002 10/04/2002 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 09/30/2002 10/04/2002 Performance Indicator Verification IP 71151 1, 2 1

PS-RP

- RADIATION PROTECTION-@ SMYRNA ENV. LAB Baseline Inspections 10/30/2002 11/01/2002 Radiological Environmental Monitoring Program IP 7112203 1

3 EB2-MODS - EB2-MODS/50.59 Baseline Inspections 02/10/2003 02/14/2003 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 02/10/2003 02/14/2003 Permanent Plant Modifications IP 7111117B 1, 2 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.