Inspection/Activity Plan - 03/04/2002 - 03/31/2003
ML020650629
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 03/04/2002
From:
Division Reactor Projects II
To:
References
Download: ML020650629 (1)


Text

Watts Bar Inspection / Activity Plan 03/04/2002 - 03/31/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 1 03/04/2002 16:34:21 Report 22 1

EB2-ISI

- INSERVICE INSPECTION Baseline Inspections 03/06/2002 03/08/2002 Inservice Inspection Activities IP 7111108 1

3 PS-RP

- RADIATION PROTECTION Baseline Inspections 03/11/2002 03/15/2002 Access Control to Radiologically Significant Areas IP 7112101 1

Baseline Inspections 03/11/2002 03/15/2002 ALARA Planning and Controls IP 7112102 1

Baseline Inspections 03/11/2002 03/15/2002 Radioactive Material Processing and Transportation IP 7112202 1

Baseline Inspections 03/11/2002 03/15/2002 Performance Indicator Verification IP 71151 1

2 PS-SEC

- SECURITY Baseline Inspections 04/29/2002 05/03/2002 Response to Contingency Events (Protective Strategy and Implementation of Protective Strategy)

IP 7113003 1

1 PS-RP

- RADIATION PROTECTION AT MUSCLE SHOALS Baseline Inspections 07/10/2002 07/12/2002 Radiological Environmental Monitoring Program IP 7112203 1

2 OL-RQ

- REQUAL INSPECTION Baseline Inspections 08/12/2002 08/16/2002 Licensed Operator Requalification IP 7111111B 1

1 PS-SEC

- SECURITY Baseline Inspections 10/07/2002 10/11/2002 Access Authorization Program (Behavior Observation Only)

IP 7113001 1

Baseline Inspections 10/07/2002 10/11/2002 Access Control (Search of Personnel, Packages, and Vehicles: Identification and Authorization)

IP 7113002 1

Baseline Inspections 10/07/2002 10/11/2002 Performance Indicator Verification IP 71151 1

1 PB6LAYUP

- UNIT 2 SYSTEM LAYUP Other Routine 10/21/2002 10/24/2002 Review Of Quality Assurance For Extended Construction Delays IP 92050 1

1 OL-EP

- EMERGENCY PLANNING INSPECTION Baseline Inspections 11/04/2002 11/08/2002 Alert and Notification System Testing IP 7111402 1

Baseline Inspections 11/04/2002 11/08/2002 Emergency Response Organization Augmentation Testing IP 7111403 1

Baseline Inspections 11/04/2002 11/08/2002 Emergency Action Level and Emergency Plan Changes IP 7111404 1

Baseline Inspections 11/04/2002 11/08/2002 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1

Baseline Inspections 11/04/2002 11/08/2002 Performance Indicator Verification IP 71151 1

1 PB6-AWP

- FREEZE PROTECTION Baseline Inspections 11/11/2002 11/15/2002 Adverse Weather Protection IP 7111101 1

3 OL-EXAM

- INITIAL EXAM Not Applicable 12/02/2002 12/06/2002 WATTS BARR 1/INITIAL EXAMS AT POWER FACILITIES V23161 1

1 PB6-FP

- FLOOD PROTECTION Baseline Inspections 02/10/2003 02/14/2003 Flood Protection Measures IP 7111106 1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.