MONTHYEARLR-N04-0021, Units I and 2 - Implementation of Alternative Source Term (AST) Request for Changes to Technical Specifications and Updated Final Safety Analysis Report2004-04-26026 April 2004 Units I and 2 - Implementation of Alternative Source Term (AST) Request for Changes to Technical Specifications and Updated Final Safety Analysis Report Project stage: Request ML0416103102004-07-0606 July 2004 PSEG Nuclear, LLC, Withholding from Public Disclosure, NEDC-33066P, Hope Creek Generating Station Aprm/Rbm/Technical Specifications/Maximum Extended Load Line Limit Analysis (Arts/Mellla), Revision 1 Project stage: Other ML0423701062004-08-24024 August 2004 Request for Additional Information Implementation of Alternate Source Term Project stage: RAI LR-N04-0417, LCR S03-05, Implementation of Alternate Source Term Request for Additional Information (TAC Nos. MC3094 & MC3095)2004-09-23023 September 2004 LCR S03-05, Implementation of Alternate Source Term Request for Additional Information (TAC Nos. MC3094 & MC3095) Project stage: Request LR-N04-0431, Request for License Amendment Arts/Mella Implementation - Schedule Update2004-09-30030 September 2004 Request for License Amendment Arts/Mella Implementation - Schedule Update Project stage: Request ML0429406752004-10-29029 October 2004 Delay in Submission of Fuel Dependent Analyses (Tac No. Mc 3390) Project stage: Other ML0431303612004-11-16016 November 2004 Request for Additional Information Amendment to Implement Alternative Source Term Project stage: RAI ML0504901532005-03-0808 March 2005 Facsimile Transmission, Draft Request for Additional Information to Be Discussed in an Upcoming Conference Call Project stage: Draft RAI ML0510803412005-05-0505 May 2005 RAI, Amendment to Implement Alternative Source Term Project stage: RAI LR-N05-0314, May 2005 Monthly Operating Report for Salem Generating Station, Unit 12005-06-14014 June 2005 May 2005 Monthly Operating Report for Salem Generating Station, Unit 1 Project stage: Request ML0522105012005-07-25025 July 2005 E-Mail Miller, NRR, to Duke, PSEG, Hope Creek Arts/Mellla Draft RAIs Project stage: Draft Other ML0525102402005-08-10010 August 2005 Implementation of Alternate Source Term (AST) Request for Changes to Technical Specifications and Updated Final Safety Analysis Report Project stage: Request ML0523004982005-08-18018 August 2005 RAI - Request for Change to Technical Specifications, Implementation of Arts/Mellla Operating Domain Project stage: RAI 05000354/LER-2005-007, Re B Control Room Emergency Filtration (CREF) Train Inoperable Greater than Allowed by Technical Specifications2005-08-18018 August 2005 Re B Control Room Emergency Filtration (CREF) Train Inoperable Greater than Allowed by Technical Specifications Project stage: Request LR-N05-0448, Response to Request for Additional Information Re Request for Change to Technical Specifications Arts/Mellla Implementation2005-09-23023 September 2005 Response to Request for Additional Information Re Request for Change to Technical Specifications Arts/Mellla Implementation Project stage: Response to RAI ML0530000292005-10-31031 October 2005 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance LR-N05-0520, Response to Request for Additional Information Request for Change to Technical Specifications Arts/Mellla Implementation2005-11-16016 November 2005 Response to Request for Additional Information Request for Change to Technical Specifications Arts/Mellla Implementation Project stage: Response to RAI JAFP-06-0015, Application for Technical Specification Amendment to Support Implementation of Arts/Meod2006-01-26026 January 2006 Application for Technical Specification Amendment to Support Implementation of Arts/Meod Project stage: Request ML0605301292006-02-17017 February 2006 Issuance of Amendments Alternate Source Term - Technical Specification Pages Project stage: Approval ML0600403222006-02-17017 February 2006 Issuance of License Amendments 271 and 252 Alternate Source Term Project stage: Approval ML0606204702006-03-0303 March 2006 Re-Issuance of Safety Evaluation for Amendment 163 Implementation of Arts/Mellla Project stage: Approval ML0606205002006-03-0303 March 2006 SE Related to Amendment No. 163 - Non-Proprietary Project stage: Other ML0610700392006-05-0202 May 2006 Corrections to Safety Evaluation for Amendment No. 271 and No. 252, Respectively, Alternate Source Term Project stage: Approval 2005-03-08
[Table View] |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236
§ PSEG SEP 3 0 2004 Nu4iclearLLC LR-N04-0431 LCR H04-01 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 REQUEST FOR LICENSE AMENDMENT ARTS/MELLLA IMPLEMENTATION - SCHEDULE UPDATE HOPE CREEK GENERATING STATION FACILITY OPERATING LICENSE NPF-57 DOCKET NO. 50-354
Reference:
LR-N04-0062, "Request for License Amendment: ARTS/MELLLA Implementation," dated June 7, 2004 This letter provides an update on the status of the fuel dependent analyses being performed to justify operation in the ARTS/MELLLA condition. By the referenced letter, PSEG Nuclear LLC (PSEG) requested a revision to the Technical Specifications for the Hope Creek Generating Station to reflect an expanded operating domain resulting from implementation of Average Power Range Monitor/Rod Block Monitor/Technical Specifications/Maximum Extended Load Line Limit Analysis (ARTS/MELLLA).
The referenced letter stated that PSEG would submit the Hope Creek fuel dependent analyses results and, if required, any additional Technical Specification changes associated with the fuel dependent evaluations, by September 30, 2004. These analyses are not yet complete. PSEG now expects to complete the analyses and submit the results by November 30, 2004.
Should you have any questions regarding this transmittal, please contact Mr. Paul Duke at 856-339-1466.
Sincerely, Christina L. Perino Director - Licensing and Nuclear Safety 9ZVDDI 95-2168 REV. 7199
Document Control Desk
SEP 3 0 2004 LR-N04-0431 C
Mr. S. Collins, Administrator - Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. D. Collins, Project Manager - Hope Creek U. S. Nuclear Regulatory Commission Mail Stop 08C2 Washington, DC 20555 USNRC Senior Resident Inspector - Hope Creek (X24)
Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering PO Box 415 Trenton, NJ 08625