I t=ELtergy Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
James A. Fitzpatrick NPP RO. Box 1 1 0 Lycoming, NY 13093 Tel 315 349 6024 Fax 315 349 6480 T.A. Sullivan Site Vice President -JAF June 3, 2005 JAFP-05-0087 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
SUBJECT:
References:
James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Request Exiient Processing of License Amendment Request Dated April 27, 2005
- 1) Entergy Letter dated 27 April, 2005 (JAFP-05-0082), Technical Specification Amendment to DC Electrical System Requirements
Dear Sir:
In accordance with 10 CFR 50.90 Entergy Nuclear Operations Inc., submitted a request for amendment to the James A. FitzPatrick Nuclear Power Plant (JAF) Technical Specifications (Reference 1) dated April 27, 2005. This amendment request was submitted to revise the Technical Specification requirements for the plant DC electrical power system as described in Technical Specification Task Force (TSTF) Change Traveler, TSTF-360 Revision 1, which has been approved generically for the boiling water reactor (BWR) Standard TS, NUREG-1433 (BWR/4).
In accordance with 10 CFR 50.91(a)(6) JAF is requesting that this amendment be processed on an exigent basis. This exigent processing is being requested because the existing Technical Specifications potentially do not provide enough time to maintain conditions for 100% power operation and perform detailed trouble shooting activities for spurious intermittent alarms associated with a station battery charger. The station battery chargers are operable; this exigent amendment is being requested as a contingency in the event that the troubleshooting identifies additional work.
There are no commitments contained in this letter. If you have any questions, please contact Mr. Richard Plasse at (315) 349-6793.
I declare under penalty of perjury that the forgoing is true and correct.
Executed on this the 3rd day of June 2005.
Very truly yours, W--
CL v
F.
I A.
.a.
T. A. Sullivan Site Vice President TAS:ed cc:
Mr. Samuel Collins Regional Administrator U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Resident Inspector U.S. Nuclear Regulatory Commission J.A. FitzPatrick Nuclear Power Plant P.O. Box 136 Lycoming, NY 13093 Mr. John Boska, Project Manager Project Directorate 1 Division of Licensing Project Management U.S. Nuclear Regulatory Commission Mail Stop 0 8-B1I Washington, DC 20555 Mr. Peter R. Smith, President NYSERDA 17 Columbia Circle Albany, NY 12203-6399