April 2, 2015
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NRC EXAMINATION REPORT 05000445/2015301; 05000446/2015301
Dear Mr. Flores:
On March 9, 2015, Garry Struble, Simulator and Licensing Examination Manager, notified the U.S. Nuclear Regulatory Commissions (NRC) Region IVs staff via electronic mail that the initial retake examination scheduled at Comanche Peak Nuclear Power Plant for the week of March 23, 2015, was no longer needed. This retake examination included a written examination for two reactor operator applicants.
Mr. Kenneth Peters of your staff formally cancelled the examination by letter to Marc Dapas, Regional Administrator, dated March 12, 2015. Per the request, applications for the two reactor operator applicants have been withdrawn. The examination development process was cancelled after the completion of the draft examination review process at your request; however, the portions of the examination that were reviewed with comments provided to your staff will be included in the NRCs Agencywide Documents Access and Management System (ADAMS).
No findings were identified during this examination.
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E LAMAR BLVD ARLINGTON, TX In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA/
Vincent G. Gaddy, Chief Operations Branch
Division of Reactor Safety
Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89
cc: Electronic Distribution to Comanche Peak Nuclear Power Plant In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA/
Vincent G. Gaddy, Chief Operations Branch
Division of Reactor Safety
Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89
cc: Electronic Distribution to Comanche Peak Nuclear Power Plant
Distribution See next page
CP-201503 Exam Report-sdh.docx
ADAMS Accession Number: ML15093A110 SUNSI Review By: VGG ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive Keyword:
RGN-002 OFFICE
SOE:OB
OE:OB NAME SHedger
VGaddy SIGNATURE
/RA/
/RA/
DATE 4/1/15
4/2/15 OFFICIAL RECORD COPY
Letter to Rafael Flores from Vincent G. Gaddy, dated April 2, 2015
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NRC EXAMINATION REPORT 05000445/2015301; 05000446/2015301
DISTRIBUTION:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
Acting DRP Deputy Director (Thomas.Farnholtz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (John.Kramer@nrc.gov)
Senior Resident Inspector (Jeffrey.Josey@nrc.gov)
Resident Inspector (Rayomand.Kumana@nrc.gov)
Administrative Assistant (Rhonda.Smith@nrc.gov)
Branch Chief, DRP/A (Wayne.Walker@nrc.gov)
Senior Project Engineer, DRP/A (Ryan.Alexander@nrc.gov)
Project Engineer, DRP/A (Thomas.Sullivan@nrc.gov)
Project Engineer, DRP/A (Margaret.Tobin@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Balwant.Singal@nrc.gov)
Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (Michael.Waters@nrc.gov)