IR 05000424/2022010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams) Inspection Report 05000424/2022010 and 05000425/2022010
ML22334A231
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 12/02/2022
From: James Baptist
NRC/RGN-II/DRS/EB1
To: Gayheart C
Southern Nuclear Operating Co
References
IR 2022010
Download: ML22334A231 (18)


Text

December 2, 2022

SUBJECT:

VOGTLE ELECTRIC GENERATING PLANT, UNITS 1&2 - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000424/2022010 AND 05000425/2022010

Dear Cheryl A. Gayheart:

On October 21, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Vogtle Electric Generating Plant, Units 1&2 and discussed the results of this inspection with Mr. R. Norris and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, James B. Baptist, Chief Engineering Br 1 Division of Reactor Safety Docket Nos. 05000424 and 05000425 License Nos. NPF-68 and NPF-81

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000424 and 05000425

License Numbers:

NPF-68 and NPF-81

Report Numbers:

05000424/2022010 and 05000425/2022010

Enterprise Identifier:

I-2022-010-0047

Licensee:

Southern Nuclear Company, Inc.

Facility:

Vogtle Electric Generating Plant, Units 1&2

Location:

Waynesboro, GA

Inspection Dates:

October 03, 2022 to October 21, 2022

Inspectors:

P. Braxton, Reactor Inspector

T. Fanelli, Senior Reactor Inspector

C. Franklin, Reactor Inspector

J. Lizardi-Barreto, Reactor Inspector

A. Ruh, Resident Inspector

T. Su, Reactor Inspector

Approved By:

James B. Baptist, Chief

Engineering Br 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Vogtle Electric Generating Plant, Units 1&2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance (DBA) Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (7 Samples)

(1)4160 VAC bus 1AA02, transformer 1BB07X

Material condition and configuration during a walkdown

Operating environment

Corrective and preventive maintenance effectiveness

Protective relay setting and calibration

Overcurrent protection and coordination

Alignment of Plant Wilson after station blackout

(2) Nuclear service cooling water spray header and cold weather bypass butterfly valves HV-1668A, HV-1669A, HV-1668B and HV-1669B

Thrust, set-point, weak-link, maximum differential pressure calculations

Required capability during normal, abnormal, and emergency operating procedures, including loss of nuclear service cooling water system

Results of recent surveillance tests and procedure adequacy

Material condition of valves and associated equipment during a walkdown

Corrective action effectiveness

Control circuit scheme and periodic verification of electrical interlocks

(3) Main steam isolation valve 2HV3016B

Thrust, set-point, weak-link, maximum differential pressure calculations

Air supply sizing (time, and pressure)

Required capability during normal, abnormal, and emergency operating procedures, including faulted steam generator, steam generator tube rupture, and station blackout

Results of recent surveillance tests and procedure adequacy

Material condition of valves and associated equipment during a walkdown Corrective action effectiveness

(4) Containment purge valves 1/2HV-2624A/B, 2626A/B, 2627A/B, 2628A/B, 2629A/B

Material condition and configuration during a walkdown

Effectiveness of corrective and preventative maintenance to ensure containment isolation capability

Maintenance of seismic qualification

(5) Auxiliary feedwater system pumps and valves 1/2-1302-P4-001, P4-002, P4-003, HV5132

Material condition and configuration during a walkdown

Correlation of flowrate acceptance criteria to accident conditions considering instrument inaccuracies and diesel generator voltage and frequency uncertainties

Surveillance testing results and compliance with inservice testing code requirements (instrumentation selection, reference values, documentation)

System capability and protection during flooding from high energy line breaks

Modifications to safety analysis design basis cases and system assumptions

Control valve closing capability under reverse flow conditions described in failure modes and effects analysis

(6) Residual heat removal system pumps 1/2-1205-P6-002

Material condition and configuration during a walkdown

Design bases and design assumptions have been appropriately translated into design calculations, drawings, and procedures.

Corrective actions and preventative maintenance effectiveness

Maintenance of seismic qualification

Results of recent surveillance tests in accordance with applicable procedures

Termination of inadvertent safety injection

(7) Residual heat removal to safety injection discharge motor operated gate valves 1/2-1205-HV-8804B

Material condition and configuration during a walkdown

Design bases and design assumptions have been appropriately translated into design calculations, drawings, and procedures.

Results of recent surveillance tests in accordance with applicable procedures

Corrective actions and preventative maintenance effectiveness

Maintenance of seismic qualification Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

(1)125 VDC panel 1BD11/1BD1 and circuit breaker 1BD105

Corrective and preventive maintenance effectiveness Battery capacity calculation

Effectiveness of corrective actions

Periodic verification of electrical interlocks

Modification Review - Permanent Mods (IP Section 02.03) (4 Samples)

(1) SNC959023, SNC959025 - Unit 1 and 2 Solid State Protection System Bridging Strategy: Low Margin, Increase Under-Voltage Trip Attachment Coil Circuit Voltage

Post-modification testing and operability

Coil voltage

(2) SNC922254, SNC922258 - Unit 1 and 2 Auxiliary Feedwater Orifice Replacements

Orifice installation orientation

Post-modification flow tests and hydraulic model assumptions

Pumphouse internal flooding scenario impacts

(3) SNC1046656 - Unit 2 A-train Main Steam Isolation Valve Actuator Replacements

Design drawings, installation adequacy and post-modification testing

Pipe stress analysis

Updated Technical Requirements Manual curves

Stroke times during high-and low-pressure operations

(4) SNC1062134, SNC1062133 - Eliminate Single Point Vulnerabilities from Main Steam Isolation Valve Control Circuits for Normally Energized MDR Relays and Micro Switches

Design inputs and elementary drawing logic

Post-modification testing

Review of Operating Experience Issues (IP Section 02.06) (3 Samples)

(1) Information Notice 2021-01, Lessons Learned from NRC Inspections of Design-Basis Capability of Power-Operated Valves at Nuclear Power Plants
(2) Information Notice 2020-02, Flex Diesel Generator Operational Challenges
(3) Information Notice 2019-10, Failures Reported in Eaton/Cutler Hammer A200 and Freedom Series Contactors

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On October 21, 2022, the inspectors presented the design basis assurance inspection (teams) inspection results to Mr. R. Norris and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

GP-17105

Weak Link Analysis for Valves 8804 A & B

05/11/2000

1/2X6AA06-661-4

Valve 4G Seismic Upgrade Evaluation Report

11/09/1988

AX5AC01-00365

HV5132 Weak Link AFW Discharge Valve

09/03/1987

AX5C03-00722-1

Fisher Weak Link Analysis and Calculation Procedure for

280 Series Butterfly Valves

3/17/2000

DC-1000-M

General Design Criteria (Mechanical)

DC-1005

Seismic - Interdiscipline

DC-1007

Environment - Interdiscipline

DC-1009

Plant Single-Failure Criteria

DC-1018

Pipe Break Criteria - Interdiscipline

DC-1204

Safety Injection System

DC-1205

Residual Heat Removal System

SNC143798

NMP-ES-050-F01, RER Response Form to Fleet NMP-MA-

010 Meets the Sites Seismic Criteria

C110878101

VNP-1HV8804B

Thrust and Torque Calculation 1HV8804B (VNPS-1) AC

Motor Operated GL-96-05 Gate Valve

VNP-2HV8804B

Thrust and Torque Calculation 2HV8804B (VNPS-2) AC

Motor Operated GL-96-05 Gate Valve

2.3

X2CQ10.04

Civil/Seismic Requirements of Scaffolding in Safety Related

Area per Procedure NMP-MA-010

X3CA18

Evaluate Station Auxiliary System Loads

X3CF02

Determine Class 1E Battery Sizing per IEEE STD 485-1983

25.0

X3CT08

Fire Event Safe Shutdown Circuit Analysis

X4C1000U01

Differential Pressure Calculations for REA VG-9049

(Generic Letter 89-10)

X4C1000U01

Differential Pressure Calculations for REA VG-9049

(Generic Letter 89-10)

X4C1202S26

Ultimate Heat Sink Analysis

X4C1202V02

NSCW Cooling Tower Fan Performance - After SBO

71111.21M

Calculations

X4C1202V03

Verification of NSCW Constant Heat Loads and Flows and

Cooldown Heat Loads

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

X4C1204S07

ECCS Reference Summary

X4C1204V23

Generic Decay Heat Power Curve Calculation

X4C1205V01

Residual Heat Removal System Design

11/08/1983

X4C1205V02

Cooldown Transient with One RHR Train

2/1/1993

X4C1205V03

RHR Pump Runout

11/10/1987

X4C1205V04

One and Two Train Cooldown of RCS

07/11/2013

X4C1205V04

One and Two Train Cooldown of RCS

X4C1301S00F1

FMEA - Main Steam System

X4C1301U01

Main Steam Line Pressure Safety Valve Forces

X4C1302S00F1

FMEA - Auxiliary Feedwater and Condensate Storage

System

X4C1302V15

AFW Hydraulic Analysis

X4CPS.0075.411

Qualification of Valves for Generic Letter 89.10 (FQP-11AB-

9)

X5CP1668

NSCW Cooling Tower Spray Header Shutoff and Bypass

Valve Controls Train "A" & Train "B"

X5CP5150

Aux Feedwater Supply to SG Flow Indication

X6CAJ.08

Main Steam Line Break Offsite Doses

1.0

X6CXC36

Flooding Analysis - VNP Auxiliary Feedwater Pumphouse -

Unit 1 & 2

10648087

Adverse trend previously identified in 2B RHR Pump dP

09/20/19

10667477

SI "B" Boric Acid buildup

11/26/19

10667479

SI Accumulator Local Sample valve Boric Acid leak

11/26/19

10698551

U1 CNMT Penetration 84 CNMT PURGE EXH LLRT 1HV-

28A failed

03/25/20

10730669

2R21 Outage Scheduling MOV Delay Starts Lesson

Learned

08/16/20

10740052

14" Flexible connection on the U2 CTB Normal Purge

exhaust line degraded

09/19/20

10748136

SI Accumulator Local Sample valve & Swagelock Fitting

Boric Acid leak

10/22/20

Corrective Action

Documents

10748140

SI Accumulator Local Sample valve & Swagelock Fitting

Boric Acid leak

10/22/20

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

10828191

Unit 1 Containment Mini-Purge Exhaust Tripped

09/18/21

10829955

Unit 1 Train A RHR pump issue observed during start

following maintenance

09/25/21

10861521

2HV0607 - Minor to Moderate Dry Boric Acid on Flange and

bolting

2/23/22

10865776

Valve Needed for 2R22 N2 SI

03/11/22

10866977

2-HIC-607A has no light indication

03/16/22

10881597

Mini Purge Supply Fan trips on low flow causing QHVC

alarm ALB52-F06

05/17/22

276875, 277066,

10698290,

10698575,

10735584,

10651765,

10677066,

10694969,

10695405,

10695498,

10706799,

10731564,

10742075,

1070318,

1074681,

10702730,

10770466,

10777711,

10781950,

10799120,

10787581,

10708502,

10656219,

10719559,

10804425,

10811954,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

10816524,

10819167,

10847364,

10852544,

10736252,

10727859,

10868529,

10774529,

10840714,

10840885,

10899662,

10826914,

10802172,

10797827,

10740785,

10856612,

10789981,

10788415,

10777575,

10746820,

10730606,

10725202,

10723290,

10868818,

10866094,

10834601,

10740784,

10735561,

10878409,

10821009,

10799528,

10768308,

10701339,

10695396,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

10669859,

10656214,

10878379,

10870460,

10859659,

10792727,

10741214,

10690643,

10906295,

10870727,

10833215,

10775867,

10901500,

10902970

10912618

Incorrect dP recorded for TDAFW in surveillance 14748-

103-SNC788814

10912619

Minor oil residue 1B MDAFW pump motor

10912896

Aux building C46 overhead lighting not operating

10912898

Auxiliary building C46 floor degradation

10913164

Inconsistent use of of elbows on solenoid exhaust ports

10913181

Sections of flexible conduit do not have grounding cable

installed

10913183

HVAC damper limit switch missing FME cover

10913184

Scaffold with outdated tag

10913185

Housekeeping around U1 and U2 containment purge valve

actuators

10913186

Minor oil leak on 1HV2629B valve actuator

10913187

Scaffold clamp to be removed

10913188

Review installation of permanent scaffold underneath

1HV2629A/B

10913189

Flex joint tie rod missing nut

10913190

Coating peeling on containment purge valve actuator

Corrective Action

Documents

Resulting from

Inspection

10916850

NMP-MA-010 provides insufficient guidance for particular

cases

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

10916866

Capability of AFW discharge MOV function not

demonstrated

1X3D-AA-A01A

Main One Line Unit 1

1X3D-AA-D02A

One Line Diagram, 4160 Switchgear 1AA02

1X3D-AA-E07A

One Line Diagram-480V Switchgear 1BB07

1X3D-AA-M)8A-56

Unit 1 Relaying Data

1X3D-AA-M08A-

034

Unit 1 Relaying Data

1X3D-AA-M08A-

035

Unit 1 Relaying Data

1X3D-AA-MO8A-

Unit 1 Relaying Data

1X3D-BD-K05U

Elementary Diagram for 1HV-1668A

1X3D-BD-K05V

Elementary Diagram for 1HV-1668B

1X3D-BD-K05W

Elementary Diagram for 1HV-1669A

1X3D-BD-K05X

Elementary Diagram for 1HV-1669B

1X4AR17-00208-2

Air and Hydraulic System Schematic & Actuator Control

Wiring Diagram for Gate Valve 1HV-3026B

1.0

1X4DB121

P&I Diagram Safety Injection System No. 1204

1X4DB122

P&I Diagram Safety Injection System No. 1205

1X4DB133-1

P&ID Nuclear Service Cooling Water System No. 1202

1X4DB133-2

P&ID Nuclear Service Cooling Water System No. 1202

1X4DB161-1

P & I Diagram Auxiliary Feedwater System, Condensate

Storage & Degasifier System, System No. 1302

1X4DB161-2

P & I Diagram Auxiliary Feedwater System, System No.

1302

1X4DB161-3

P & I Diagram Auxiliary Feedwater System, (Aux

Feedwater Pump Turbine Driver), System No. 1302

1X4DB168-3

P & I Diagram Condensate & Feedwater System, System

No. 1305

1X6AA06-00411

Motor Op. Gate Valve Mod 08002GM84FEB010

2X4DB159-1

PI&D Main Steam System No. 1301

Drawings

39A2461

Body NT316-SR2-M3-9280 Bettis Actuated Control

C

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Valve CW to Close Valve Shaft Rotation Horiz Pipe, Vert

Shaft

39A2462

Body NT316-SR2-M3-9280 Bettis Actuated Control

Valve CW to Close Valve Shaft Rotation Horiz Pipe, Vert

Shaft

C

AX6AF02-20007-4

Pump Size 8X20WDF Coupled Design

D

AX6AU01-00526

Westinghouse Process I&C Volume 1

AX6D025

Control Building Floor Plan Elevation 2200 Level 1 Seismic

Category Areas

AX6D030

Control Building and Equipment Building Floor Plan EL. 220

FT. -0 IN. Level 1 Seismic Category Areas

3.0

CX3DE001

Grounding - General Notes, Symbols & Details

DC-1018

Design Criteria - Pipe Break Criteria - Interdiscipline

DC-1302

Design Criteria - Auxiliary Feedwater System

SNC1062133E001

Elementary Diagram Main Steam System1HV-3006A

1.0

SNC1062133E002

Elementary Diagram Main Steam System 1HV-3016A

1.0

SNC1046656

U2 A-train MSIV Actuator Replacements

A

SNC1046656

U2 A-Train MSIV Actuator Replacement

SNC1062133

Eliminate SPVs from MSIV control circuits for Normally

Energized MDR relays and micro switches

SNC1062134

Eliminate SPVs from MSIV control circuits for Normally

Energized MDR relays and micro switches

SNC922254

U1 AFW Orifice Replacement

Engineering

Changes

SNC922258

U2 AFW Orifice Replacement

AX5AG02-00103

Test Report of Flow Determination Testing on Orifices

Performed for Plant Vogtle

DC-1000-E

General Design Criteria ( Electrical)

DC-1804

4160-V AC System

DC-1805

480V AC System

FCP-7

Butterfly Valve Sizing and Internal Component Calculation

Procedures

B

Miscellaneous

GP-19473

Transmittal of LTR-TA-16-148, Vogtle Units 1 and 2:

Auxiliary Feedwater Flow

Assumptions Modeled in the Feedwater System Pipe Break

11/07/2016

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

(Feedline Break) Analysis

NSAL-19-2

NSAL-19-2 Revision 0, "Contactors Failing to

Release/Open When De-energized"

09/24/2019

RAL 5168

Main Steam Isolation Valve Maintenance Manual

RAL-7094

Fatigue Analysis for MSIV Actuator Assembly

TE1051341

Westinghouse NSAL-19-2 Contactors Failing to

Release/Open When Deenergized

9/6/2019

Unit 1 SHR CTMT

CTMT System Health Report # 2101 Vogtle Unit 1

09/30/2022

Unit 1 SHR RHR

RHR System Health Report # 1205 Vogtle Unit 1

09/30/2022

Unit 1 SHR SI

SI System Health Report # 1204 Vogtle Unit 1

09/30/2022

Unit 2 SHR CTMT CTMT System Health Report # 2101 Vogtle Unit 2

09/30/2022

Unit 2 SHR RHR

RHR System Health Report # 1205 Vogtle Unit 2

09/30/2022

Unit 2 SHR SI

SI System Health Report # 1205 Vogtle Unit 2

09/30/2022

WCAP-17308-NP-

A

Treatment of Diesel Generator (DG) Technical Specification

Frequency and Voltage Tolerances

Operability

Evaluations

AX6AA15-00002

Vogtle Electric Generating Plant - Unit 1/2, Pump and Valve

Operability Report

11882-1

Unit 1 Outside Area Rounds

106

14150A-1

Train A NSCW Fan/Spray Valve Surveillance

14150B-1

Train B NSCW Fan/Spray Valve Surveillance

14721C-1

ECCS Subsystem Flow Balance and Checkvalve Refueling

Inservice Test

14721D-1

ECCS Subsystem Flow Balance and Checkvalve Refueling

Inservice Test

14748-1

AFW Pump and Check Valve Cold S/D IST and TDAFWP

Auto Start Test

35.1

14805B-1

Train B Residual Heat Removal Pump IST and Response

Time Test

5.3

14807A-1

Train A Motor Driven Auxiliary Feedwater Pump / Check

Valve Inservice and Response Time Test

10.1

14807B-1

Train B Motor Driven Auxiliary Feedwater Pump / Check

Valve Inservice and Response Time Test

5.2

Procedures

14825-1

Quarterly Inservice Valve Test

106.5

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

14850-1

Cold Shutdown Valve Inservice Test

60.0

14850-2

Cold Shutdown Valve Inservice Test

17061-1

Annunciator Response Procedures for ALB 61 on Process

Control Panel

19.4

18021-C

Loss of Nuclear Service Cooling Water System

19020-1

E-2 Faulted Steam Generator Isolation

1.1

19030-1

E-3 Steam Generator Tube Rupture

26007-C

Bettis Actuator Maintenance (Track Series)

13.3

AX5AC03-10001

Vogtle Electric Generating Plant - Unit No. 1/2 Operating

and Maintenance Instructions Disassemble and Assembly

for Nuclear Series Actuators

2.0

AX6AF02-20030

Vogtle Electric Generating Plant - Unit No. 1/2 Installation

Operation & Maintenance Manual & Supplement RHR

Pumps

18.0

MIS-17-009

Vogtle Electric Generating Plant Fourth 10-Year Interval

Inservice Testing Program

13.0

NMP-AD-028

CFR 21 Evaluations and Reporting Requirements

7.0

NMP-AD-028

CFR 21 Evaluations and Reporting Requirements

7.0

NMP-ES-006

Preventive Maintenance Implementation and

Continuing Equipment Reliability Improvement

13.0

NMP-ES-006-001

PM Template Management and PM Optimization

Guidance

4.1

NMP-ES-006-002

Preventive Maintenance Change Requests

11.0

NMP-ES-006-003

Preventive Maintenance Feedback

6.1

NMP-ES-006-004

Preventive Maintenance Oversight Group

6.0

NMP-GM-002

Corrective Action Program

16.0

NMP-GM-002-001

Corrective Action Program Instructions

43.0

NMP-MA-010-001

Permanent Scaffolding Installation, Modification, and

Removal Process

1.3

SNC1158288

B-RHR IST (Q) - I&C Support Req.

Work Orders

SNC1171119,

SNC1142967,

SNC622778,

SNC970653,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SNC832642,

SNC795416,

SNC979326,

SNC832139,

SNC832138,

SNC1030647,

SNC1030645,

14748-101T-

38119, 14748-

101-1101737801,

SNC351861,

SNC788814,

SNC905686,

SNC1159355,

SNC1174182,

SNC1189035,

SNC1163251,

SNC1178133,

SNC1193831,

SNC1105655,

SNC1233676,

SNC 396689,

SNC494595,

SNC731534,

SNC904311,

SNC909433,

SNC913849,

SNC981075,

SNC377678,

SNC774779,

SNC832143,

SNC856543,

SNC972592,

SNC1089908

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SNC1172960

B-RHR IST (Q) - I&C Support Req.

SNC1187666

B-RHR IST (Q) - I&C Support Req.

SNC1258537

205, 2HIC607A, Investigate and Correct Cause of no light

Indication

SNC809832

ECCS Flow/Bal-14721-C-1

SNC809837

ECCS Flow/Bal-14721-C-1

0