NRC FORM 591M PART 1 U.S. NUCLEAR REGULATORY COMMISSION (07-2012)
1ocFR2.201 SAFETY INSPECTION REPORT AND COMPLIANCE INSPECTION 1. LICENSEE/LOCATION INSPECTED:
Toledo Cardiology Consultants, In Cherry Street Suite 100 Toledo, OH 43608 REPORT NUMBER(S) 201800 l 2. NRC/REGIONAL OFFICE Region III U.S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 3. DOCKET NUMBER($)
150-00034 4. LICENSE NUMBER(S)
5. DATE(S) OF INSPECTION OH-02220490000 July 19, 2018 LICENSEE:
The inspection was an examination of the activities conducted under your license as they relate to radiation safety and to compliance with the Nuclear Regulatory Commission (NRC) rules and regulations and the conditions of your license. The inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspector. The inspection findings are as follows:
[ZJ 1, 0.
04, Based on the inspection findings, no violations were identifie Previous violation(s) close The violations{s), specifically described to you by the inspector as non-cited violations, are not being cited because they were self-Identified, non-repetitive, and corrective action was or is being taken, and the remaining criteria in the NRC Enforcement Policy, to exercise discretion, were satisfie Non-cited violation(s) were discussed involving the following requirement(s):
During this inspection, certain of your activities, as described below and/or attached, were in violation of NRC requirements and are being cited in accordance with NRC Enforcement Policy. This form is a NOTICE OF VIOLATION, which may be subject to posting in accordance with 10CFR 19.1 (Violations and Corrective Actions)
Statement of Corrective Actions I hereby state that, within 30 days, the actions described by me to the Inspector will be taken to correct the violations identified. This statement of corrective actions is made in accordance with the requirements of 1 O CFR 2.201 (corrective steps already taken, corrective steps which will be taken, date when full compliance will be achieved). I understand that no further written response to NRC will be required, unless specifically requeste TITLE PRINTED NAME SIGNATURE DATE LICENSEE'S REPRESENTATIVE NRC INSPECTOR Edward F. Harvey BRANCH CHIEF Aaron T. Mccraw NRC FORM 591M PART 1 (07-2012)
8/2/2018
NRC FORM 591M PART 3 (07-2012)
10CFR 2.201 U.S. NUCLEAR REGULATORY COMMISSION Docket File Information SAFETY INSPECTION REPORT AND COMPLIANCE INSPECTION 1. LICENSEE/LOCATION INSPECTED:
Toledo Cardiology Consultants, In Cherry Street Suite 100 Toledo, OH 43608 REPORT NUMBER(S} 2018001 3. DOCKET NUMBER(S)
150-00034 6. INSPECTION PROCEDURES USED 87130 2. NRC/REGIONAL OFFICE 4. LICENSE NUMBER(S)
OH-02220490000 Region III U.S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 5 DATE(S) OF INSPECTION July 19, 2018 7 INSPECTION FOCUS AREAS All SUPPLEMENTAL INSPECTION INFORMATION 1. PROGRAM CODE(S)
02220 2. PRIORITY
D Main Office Inspection
1 Field Office Inspection 3. LICENSEE CONTACT Tim Depinet, CNMT Next Inspection Date:
iv' I Temporary Job Site Inspection 15450 Northline Road, Southgate, MI PROGRAM SCOPE 4. TELEPHONE NUMBER (419) 251-3700 NIA This was an unannounced inspection of a mobile nuclear medicine service based in Toledo, Ohio that was performing work under reciprocity at a temporary job site in Southgate, Michigan. The licensee provided nuclear stress test services to its client approximately once per month. A licensed radiopharmacy delivered unit doses of Tc-99M to the licensee's main office in Toledo. The nuclear medicine technologist (NMT) then transported all radioactive material to their client's location to perform the administrations. The client provided dedicated space for the licensee to perfonn stress test The inspector toured the area where administrations were performed and evaluated the licensee's measures for material security, hazard communication, and exposure control. The two licensee personnel on site maintained constant surveillance of all radioactive material and had the ability to lock it in their vehicle if needed. The inspector observed two administrations of Tc-99M for stress tests and noted that the NMT wore appropriate dosimetry and decay corrected the dose to ensure that it was within the acceptable range prior to administration. All potentially contaminated waste generated on site was stored in a receptacle and taken to the licensee's main office for decay-in-storage. The NMT possessed a calibrated survey meter to perform area surveys upon completion of administrations for the day. Licensee staff also demonstrated and discussed procedures for package receipt, area surveys, spill response, and waste handlin Through these observations and discussions, the inspector found the licensee's staff to be knowledgeable ofradiation protection principle The inspector conducted independent and confirmatory surveys of the facility and found no residual contamination or exposures to members of the public in excess ofregulatory limit No violations ofNRC requirements were identified during this inspectio NRC FORM 591M PART 3 (07-2012)