EPID:L-2022-LLQ-0003
From kanterella
Jump to navigation
Jump to search
EPID - L-2022-LLQ-0003, Bellefonte Nuclear Plant, Units 1 and 2, Status Update and Request for Extension of Construction Permits (CPPR-122 and CPPR-123) (Open) 31 August 2021 - 17 June 2022 | |
|---|---|
Request for: - LLQ Open | |
Questions Answers | |
| From: | |
MONTHYEARCNL-21-077, Bellefonte Nuclear Plant, Units 1 and 2, Status Update and Request for Extension of Construction Permits (CPPR-122 and CPPR-123)2021-08-31031 August 2021
[table view]Title: Bellefonte Nuclear Plant, Units 1 and 2, Status Update and Request for Extension of Construction Permits (CPPR-122 and CPPR-123) CNL-21-082, Bellefonte Nuclear Plant, Units 1 and 2 - Withdrawal of Request for Extension of Unit 1 and Unit 2 Construction Permits (CPPR-122 and CPPR-123)2021-09-10010 September 2021 Title: Bellefonte Nuclear Plant, Units 1 and 2 - Withdrawal of Request for Extension of Unit 1 and Unit 2 Construction Permits (CPPR-122 and CPPR-123) CNL-22-019, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Reduction in Commitment2022-02-0404 February 2022 Title: Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Reduction in Commitment CNL-22-027, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 40 - Annual Update and Proposed Changes to Revision 402022-04-28028 April 2022 Title: Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 40 - Annual Update and Proposed Changes to Revision 40 ML22147A1362022-06-17017 June 2022 Title: Tennessee Valley Authority Nuclear Quality Assurance Plan, Revision 40 2022-02-04 | |