BSEP 17-0058, Revision to Radiological Emergency Response Plan Implementing Procedure
| ML17171A407 | |
| Person / Time | |
|---|---|
| Site: | Brunswick |
| Issue date: | 06/20/2017 |
| From: | Wooten B Duke Energy Progress |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| BSEP 17-0058 OPEP-02.6.28, Rev. 15 | |
| Download: ML17171A407 (25) | |
Text
(_~ DUKE ENERGY JUN 2 0 2017 Serial: BSEP 17-0058 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Brunswick Nuclear Plant P.O. Box 10429 Southport, NC 28461 1 O CFR 50.4(b )(5)(iii) 10 CFR 50.54(q)(5) 10 CFR 72.4 Renewed Facility Operating License Nos. DPR-71 and DPR-62 Docket Nos. 50-325 and 50-324 Revision to Radiological Emergency Response Plan Implementing Procedure Ladies and Gentlemen:
In accordance with 1 O CFR 50.4(b)(5)(iii); 1 O CFR 50.54(q)(5); and 1 O CFR 72.4; Duke Energy Progress, LLC (Duke Energy), is submitting a revision to Radiological Emergency Response Plan Implementing Procedure OPEP-02.6.28, Off-Site Protective Action Recommendations, Revision 15, which became effective May 31, 2017.
Duke Energy has evaluated this revision, in accordance with 10 CFR 50.54(q), and determined that the revision is not a reduction in the effectiveness of the Radiological Emergency Response Plan and that the Plan, as changed, continues to meet the standards of 1 O CFR 50.47(b) and the requirements of 1 O CFR 50, Appendix E. Enclosure 1 provides a 1 O CFR 50.54(q)(5) summary for the revised Radiological Emergency Response Plan implementing procedure. contains a copy of the revised Radiological Emergency Response Plan implementing procedure.
This document contains no regulatory commitments.
Please refer any questions regarding this submittal to Mr. Lee Grzeck, Manager - Regulatory Affairs, at (910) 457-2487.
Sincerely, 17_. t,J~
Bryan Wooten Director - Organizational Effectiveness Brunswick Steam Electric Plant
U.S. Nuclear Regulatory Commission Page 2 of 2
Enclosures:
- 1. 1 O CFR 50.54(q)(5} Summary for OPEP-02.6.28, Revision 15
- 2. Copy of OPEP-02.6.28, Revision 15, Off-Site Protective Action Recommendations cc (with Enclosures 1 and 2):
U.S. Nuclear Regulatory Commission, Region II ATIN: Ms. Catherine Haney, Regional Administrator 245 Peachtree Center Ave, NE, Suite 1200 Atlanta, GA 30303-1257 cc (with Enclosure 1 only):
U.S. Nuclear Regulatory Commission ATIN: Ms. Michelle P. Catts, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U.S. Nuclear Regulatory Commission ATIN: Mr. Andrew Hon ~Mail Stop OWFN 8G9A) (Electronic Copy Only) 11555 Rockville Pike Rockville, MD 20852-2738 Andrew.Hon@nrc.gov U.S. Nuclear Regulatory Commission ATIN: Mr. John Nguyen (Mail Stop 3WFN 14A) (Electronic Copy) 11555 Rockville Pike Rockville, MD 20852-2738 cc (without enclosures):
Chair - North Carolina Utilities Commission (Electronic Copy Only) 4325 Mail Service Center Raleigh, NC 27699-4300 swatson@ncuc.net U.S. Nuclear Regulatory Commission ATIN: Director, Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Washington, DC 20555-0001
10 CFR 50.54(q)(5) Summary for OPEP-02.6.28, Revision 15 BSEP 17-0058 In accordance with 1 O CFR 50.54(q)(5), Duke Energy Progress, LLC, is providing a summary of the revised Radiological Emergency Response Plan implementing procedure being submitted with this letter. Radiological Emergency Response Plan implementing procedure OPEP-02.6.28, Off-Site Protective Action Recommendations, Revision 15, a copy of which is provided in of this letter, became effective on May 31, 2017.
The changes to the Radiological Emergency Response Plan implementing procedure include correction of typographical errors and editorial/administrative changes for referenced documents, enhanced guidance for Staged evacuation following a Rapidly Progressing Severe Accident during Non-Summer months, additional direction for the selection of upper or lower meteorological data for determination of affected zones, and corrected guidance and logic for Expanded PARs based on a change in affected zones.
Reference:
EREG AR Number 2124514
Copy of OPEP-02.6.28, Revision 15, Off-Site Protective Action Recommendations BSEP 17-0058
0PEP-02.6.28 Rev. 15 Page 1 of 21 BRUNSWICK NUCLEAR PLANT R
Reference Use PLANT OPERATING MANUAL VOLUME XIII PLANT EMERGENCY PROCEDURE 0PEP-02.6.28 OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS REVISION 15
TABLE OF CONTENTS 0PEP-02.6.28 Rev. 15 Page 2 of 21 SECTION PAGE 1.0 PURPOSE................................................................................................ 3
2.0 REFERENCES
.......................................................................................... 3 3.0 GENERAL INFORMATION.......................................................................... 4 4.0 DEFINITIONS/ABBREVIATIONS.................................................................. 4 5.0 RESPONSIBILITIES................................................................................... 6 6.0 PROCEDURE........................................................................................... 7 7.0 RECORDS............................................................................................... 9 ATTACHMENTS 1
PAR Flowchart - INITIAL Non-Summer (September 1 - May 31)......................... 10 2
PAR Flowchart - INITIAL Summer (June 1 - August 31)...................................... 12 3
PAR Flowchart - EXPANDED Non-Summer (September 1 - May 31)................. 14 4
PAR Flowchart - EXPANDED Summer (June 1 - August 31).............................. 17 5
10 Mile EPZ Map.................................................................................................. 20
0PEP-02.6.28 Rev. 15 Page 3 of 21 1.0 PURPOSE The purpose of this procedure is to describe the process for making initial Protective Action Recommendations (PARs) and Expanded PARs to off-site agencies during a declared General Emergency.
2.0 REFERENCES
2.1 0ERP Radiological Emergency Response Plan (ERP) 2.2 0PEP-02.1.1, Emergency Control - Unusual Event, Alert, Site Area Emergency, and General Emergency 2.3 0PEP-02.6.21, Emergency Communicator 2.4 0PEP-02.6.26, Activation and Operation of the Technical Support Center (TSC) 2.5 0PEP-02.6.27, Activation and Operation of the Emergency Operations Facility (EOF) 2.6 0PEP-03.4.8, Offsite Dose Projections for Monitored Releases 2.7 AD-EP-ALL-0202, Emergency Response Offsite Dose Assessment 2.8 NUREG-0654 Rev. 1 Supp. 3, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants - Guidance for Protective Action Strategies 2.9 EPA-400-R-92-001, Manual of Protective Action Guides and Protective Actions for Nuclear Incidents, U. S. Environmental Protection Agency, May 1992.
2.10 State of North Carolina Radiological Emergency Response Plan for Nuclear Power Facilities, Annex K - Radiological Protective Drugs 2.11 Brunswick Nuclear Power Plant Development of Evacuation Time Estimates prepared by KLD Associated, November 2012.
(RMS Number 1284620) 2.12 Brunswick Nuclear Power Plant Development of Protective Action Strategy, Final Report Revision 1, prepared by KLD Engineering dated January 30, 2015 2.13 NRC Regulatory Issue Summary 2005-08, Endorsement of Nuclear Energy Institute (NEI) Guidance Range of Protective Actions for Nuclear Power Plant Incident
2.0 REFERENCES
0PEP-02.6.28 Rev. 15 Page 4 of 21 2.14 NRC Letter 09-0198, Dated 12/24/2009,
Subject:
Brunswick Steam Electric Plant, Units 1 and 2 -Proposed Changes to the Emergency Planning Zones of the Emergency Response Plan (TAC NOS. ME1640 AND ME1641) 2.15 CP&L Letter, Response to Request for Additional Information Regarding Emergency Response Plan Revision - Modification of the Emergency Planning Zones, dated November 11, 2009 (ADAMS Accession No. ML093220067).
3.0 GENERAL INFORMATION 3.1 Protective Action Recommendations (PARs) shall be made by the Emergency Response Manager in the EOF.
3.2 The Site Emergency Coordinator shall make Protective Action Recommendations, if necessary, prior to EOF becoming Operational.
3.3 This procedure provides the process for making Protective Action Recommendations (PARs) and communicating Protective Action Recommendation (PARs) to Offsite Response Organizations (OROs) within 15 minutes of a declared General Emergency.
3.4 PARs shall be transmitted to the OROs on an approved notification form.
3.5 The Protective Action Recommendation (PAR) is subject to acceptance or modification by state or county decision makers.
3.6 The state/counties shall assume the responsibility for implementing protective actions taken to protect the health and safety of the general public.
3.7 The development of recommended actions for protection of the public involves the evaluation of risks inherent in evacuation of the public against the risks associated with events at the plant. This includes factors such as proximity to the plant, meteorological conditions, plant conditions and events, radiological release potentials and durations, evacuation time estimates, radiological shielding factors of buildings and vehicles, and others.
4.0 DEFINITIONS/ABBREVIATIONS
4.1 Impediment
An offsite condition (i.e., flooding, bridge/road closures, traffic control not yet in place) for which offsite agencies had provided prior communication to the site AND specifically requested that the site NOT issue an evacuation PAR.
4.0 DEFINITIONS/ABBREVIATIONS 0PEP-02.6.28 Rev. 15 Page 5 of 21 4.2 Offsite Response Organization (ORO): Any State and local government, supporting private industry and voluntary organizations and licensee offsite response organizations that are responsible for carrying out emergency functions during a radiological emergency (e.g., Brunswick and New Hanover Counties, State of North Carolina, and US Coast Guard).
4.3 Protective Action Guide (PAG): The projected dose to a reference person, or other identified individual, from an accidental release of radioactive material at which a specific protective action to reduce or avoid that dose is warranted. Within the context of this procedure, the PAGs for the general public for the early phase of an Atmospheric Release correspond to projected exposures of greater than or equal to 1 Rem TEDE or greater than or equal to 5 Rem CDE.
4.4 Rapidly Progressing Severe Accident (RPSA): A General Emergency (GE) with rapid/immediate loss of containment integrity and loss of ability to cool the core. An RPSA is more severe than other GEs, and different protective actions are appropriate.
4.5 Sea Breeze Effect: Coastal wind circulation pattern that develops during the daytime, when the land temperature is hotter than the ocean, causing surface winds to blow inland from the sea. A line of thunderstorms often forms along the Sea Breeze Effect front during summer afternoons. The consequence of a release traveling inland and then returning back to sea can increase the projected dose by a factor of up to 2.5. The Sea Breeze Effect can exist with wind direction from 16° to 269°.
4.6 Short Term Release: A radiological release that is controlled and that can be accurately projected to be less than 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> in duration.
Categorizing a release as Short Term is a tool implemented to simplify the review and comparison to Evacuation Time Estimate values such that the PAR logic can be reduced to Yes or No responses.
4.7 Staged Evacuation: A protective action strategy that reduces traffic congestion to emphasize protection of those members of the public most at risk and reduce the overall impact upon the public in the event of the General Emergency.
4.8 Summer
The months of June, July, and August during which the transient population is elevated and has an impact on the Evacuation Time Estimates. The remainder of the year including January, February, March, April, May, September, October, November, and December (i.e.,
September 1 - May 31 of the following year) is categorized as Non-summer for evaluation of PARs.
0PEP-02.6.28 Rev. 15 Page 6 of 21 5.0 RESPONSIBILITIES 5.1 The Emergency Response Manager (ERM) shall:
5.1.1 Use the guidance in this procedure to ensure Protective Action Recommendations (PARs) are communicated within 15 minutes of the declaration of a General Emergency.
5.1.2 Verbally communicate this information to off-site decision makers (OROs).
5.1.3 Approve the Emergency Notification Form.
5.1.4 Maintain an awareness of the state/county acceptance or modification of the Protective Action Recommendations (PARs).
5.2 Prior to the EOF becoming operational, the Site Emergency Coordinator (SEC) shall:
5.2.1 Use the guidance in this procedure to ensure Protective Action Recommendations (PARs) are made within 15 minutes of the declaration of a General Emergency.
5.2.2 Verbally communicate this information to off-site decision makers.
5.2.3 Approve the Emergency Notification Form.
5.2.4 Maintain an awareness of the state/county acceptance or modification of the Protective Action Recommendations (PARs).
5.3 The Radiological Control Manager (RCM) shall:
5.3.1 Recommend Protective Action Recommendations (PARs) to the Emergency Response Manager (ERM).
5.3.2 Continually assess dose assessment results on radiological conditions and advise the Emergency Response Manager (ERM) if the initial Protective Action Recommendation (PAR) should be expanded.
5.3.3 Immediately provide radiological and meteorological information to the Communications Manager for inclusion on the Emergency Notification Form.
5.4 The Communications Managers, Communications Director, and Emergency Communicator (as applicable) shall:
5.4.1 Ensure an Emergency Notification, which includes the Protective Action Recommendation (PAR), is made to off-site agencies within 15 minutes of the declaration of a General Emergency.
0PEP-02.6.28 Rev. 15 Page 7 of 21 6.0 PROCEDURE NOTE:
The population within the 10-mile EPZ is significantly larger during the summer months of June through August. As such, the estimated evacuation times for potentially impacted zones is significantly higher during the summer. It is important that the proper attachment is selected for PAR determination based on the time of year and if the evaluation is the initial PAR or if evaluating ongoing conditions for potential expanded PARs.
NOTE:
The initial Protective Action Recommendations (PARs) made to the Off-site Response Organizations (OROs) will be based upon current meteorological data such as wind direction, speed and stability class, and other factors (e.g.,
impediments to evacuation, Rapidly Progressing Severe Accident, or dose in excess of PAGs).
NOTE:
Releases affecting off-site areas may not be of the magnitude requiring evacuation. Areas within the 10-mile EPZ that do not evacuate may be recommended to shelter.
6.1 Consider sheltering for special populations or hazardous environmental conditions.
6.1.1 Special populations may include institutionalized or infirm persons.
6.1.2 Hazardous environmental conditions may include the presence of severe weather or competing disasters (e.g., hostile actions, impediments to evacuation, or a Rapidly Progressing Severe Accident).
6.2 Perform the following actions for making Protective Action Recommendations (PARs) when a General Emergency has been declared.
6.2.1 Protective Action Recommendations (PARs) will be recommended by the Radiological Control Manager (RCM) and approved by the Emergency Response Manager (ERM).
6.2.2 The Radiological Control Manager (RCM) should obtain the current wind direction from the Dose Projection Coordinator or use the EOF Meteorology Status Board.
6.2.3 The Radiological Control Manager (RCM) will use either, PAR Flowchart - INITIAL Non-Summer (September 1 - May 31) or Attachment 2, PAR Flowchart - INITIAL Summer (June 1 - August 31), for determining Protection Action Recommendations.
6.0 PROCEDURE 0PEP-02.6.28 Rev. 15 Page 8 of 21 6.3 The Radiological Control Manager (RCM) should continually monitor the following changes and then review and recommend an Expanded Protective Action Recommendation (PAR), as necessary, using, PAR Flowchart - EXPANDED Non-Summer (September 1 -
May 31) or Attachment 4, PAR Flowchart - EXPANDED Summer (June 1 -
August 31) for guidance:
Increase in dose assessment projected values Increase in field measurement values Shift in 15-minute average wind direction resulting in additional sectors being affected Offsite agencies inform the site that offsite impediments no longer exist or that most (approximately 90%) of previous evacuations have been completed Termination of active hostile action against the site 6.3.1 Protective Action Recommendations (PARs) should be extended to the point (beyond the 10 mile EPZ, as necessary) where PAG doses (i.e., greater than or equal to 1 Rem TEDE or greater than or equal to 5 Rem CDE [thyroid]) will no longer be exceeded.
6.3.2 The Communication Managers should ensure Protective Action Recommendations (PARs) are included on the Emergency Notification Form and issued within 15 minutes from the General Emergency declaration or ERM approval of Expanded PAR development.
6.3.3 The Radiological Control Manager (RCM) should communicate the Local Planning Zones being recommended for evacuation and Local Planning Zones being recommended for sheltering to the Emergency Response Manger (ERM), Communications Managers, and State Liaison.
6.3.4 The Communications Managers and Emergency Response Manager (ERM) will ensure Off-site Response Organizations are contacted verbally. Phone Talkers will normally make this contact in accordance with 0PEP-02.6.21, Emergency Communicator.
6.3.5 The Radiological Control Manager (RCM) should ensure Protective Action Recommendations (PARs) are posted on the status board in the EOF.
6.0 PROCEDURE 0PEP-02.6.28 Rev. 15 Page 9 of 21 6.3.6 The Radiological Control Manager (RCM) and Emergency Response Manager (ERM) should continually work with the EOF State Representatives to ensure an understanding of off-site recommendations.
6.3.7 The following guides apply prior to reducing the initial Protective Action Recommendations (PARs):
- 1. Long term weather forecast conditions are obtained with a high degree of confidence in the forecast. No sea-breeze in effect.
- 2. Radiological environmental conditions are defined.
- 3. Plant conditions are stabilized and no additional release as a result of the initiating accident is anticipated.
- 4. Population dose savings is quantifiable as a result of the Expanded PAR and the decision is ALARA.
6.3.8 A Protective Action Recommendation (PAR) shall not be reduced from the initial recommendation for any Local Planning Zones until the release is terminated and the decision is coordinated with the state/county decision makers.
7.0 RECORDS Documentation generated from implementation of this procedure should be forwarded to the Manager - Nuclear Emergency Planning for submittal to Document Services for retention.
0PEP-02.6.28 Rev. 15 Page 10 of 21 ATTACHMENT 1 Page 1 of 2 PAR Flowchart - INITIAL Non-Summer (September 1 - May 31)
0PEP-02.6.28 Rev. 15 Page 11 of 21 ATTACHMENT 1 Page 2 of 2 PAR Flowchart - INITIAL Non-Summer (September 1 - May 31)
General Note: Protective Action Recommendations for Zones C, D, K, L, M, N includes offshore waterways 2 to 10 miles downwind.
KI Recommended for Public Table 1 Table 2 Table 3 WIND FROM
[NOTE 4]
RAPID PROGRESSING SEVERE ACCIDENT (RPSA)
HOSTILE ACTION OR IMPEDIMENT DEFAULT PARs EVACUATE ZONES 2-10 MILES DOWNWIND SHELTER ZONES 0-2 MILE RADIUS
[NOTE 3]
SHELTER ZONES 0-2 MILE RADIUS 2-10 MILES DOWNWIND EVACUATE ZONES 0-2 MILE RADIUS 2-10 MILES DOWNWIND 180° - 195° G,H,J,K A,B A,B,G,H,J,K,L A,B,G,H,J,K 196° - 236° H,J,K,L A,B A,B,H,J,K,L A,B,H,J,K,L 237° - 271° J,K,L,M A,B A,B,J,K,L,M A,B,J,K,L,M 272° - 288° J,L,M A,B A,B,J,L,M A,B,J,L,M 289° - 316° L,M,N A,B A,B,L,M,N A,B,L,M,N 317° - 327° M,N A,B A,B,M,N A,B,M,N 328° - 009° C,M,N A,B A,B,C,M,N A,B,C,M,N 010° - 021° C,D,M,N A,B A,B,C,D,M,N A,B,C,D,M,N 022° - 038° C,D,E,M,N A,B A,B,C,D,E,M,N A,B,C,D,E,M,N 039° - 051° C,D,E A,B A,B,C,D,E A,B,C,D,E 052° - 090° C,D,E,F A,B A,B,C,D,E,F A,B,C,D,E,F 091° - 112° D,E,F A,B A,B,C,D,E,F A,B,D,E,F 113° - 179° E,F,G,H,J A,B A,B,E,F,G,H,J A,B,E,F,G,H,J Note 3: During the Non-Summer, a discussion should be held with the OROs regarding subsequent staged evacuation of sheltered zones A and B, but ONLY when safe to do so.
Note 4: Elevation associated with dose projection results (actual or most likely release points), otherwise use lower.
0PEP-02.6.28 Rev. 15 Page 12 of 21 ATTACHMENT 2 Page 1 of 2 PAR Flowchart - INITIAL Summer (June 1 - August 31)
0PEP-02.6.28 Rev. 15 Page 13 of 21 ATTACHMENT 2 Page 2 of 2 PAR Flowchart - INITIAL Summer (June 1 - August 31)
General Note : Protective Action Recommendations for Zones C, D, K, L, M, N includes offshore waterways 2 to 10 miles downwind.
KI Recommended for Public Table 1 Table 2 Table 3 WIND FROM
[NOTE 4]
RAPID PROGRESSING SEVERE ACCIDENT (RPSA)
HOSTILE ACTION OR IMPEDIMENT DEFAULT PARs EVACUATE SELECTED ZONES 2-10 MILES DOWNWIND SHELTER ZONES 0-2 MILE RADIUS OTHER 2-10 MILES DOWNWIND[NOTE 3]
SHELTER ZONES 0-2 MILE RADIUS 2-10 MILES DOWNWIND EVACUATE ZONES 0-2 MILE RADIUS SELECTED 2-10 MILES DOWNWIND SHELTER OTHER ZONES 2-10 MILES DOWNWIND[NOTE 3]
180° - 195° G,H,J A,B,K,L A,B,G,H,J,K,L A,B,G,H,J K,L 196° - 236° H,J,L A,B,K A,B,H,J,K,L A,B,H,J K,L 237° - 271° J,L,M A,B,K A,B,J,K,L,M A,B,J K,L,M 272° - 288° J,L,M A,B A,B,J,L,M A,B,J L,M 289° - 316° L,M,N A,B A,B,L,M,N A,B L,M,N 317° - 327° M,N A,B A,B,M,N A,B M,N 328° - 009° C,M,N A,B A,B,C,M,N A,B C,M,N 010° - 021° C,M,N A,B,D A,B,C,D,M,N A,B C,D,M,N 022° - 038° C,M,N A,B,D,E A,B,C,D,E,M,N A,B,E C,D,M,N 039° - 051° C
A,B,D,E A,B,C,D,E A,B,E C,D 052° - 090° C,F A,B,D,E A,B,C,D,E,F A,B,E,F C,D 091° - 112° F
A,B,C,D,E A,B,C,D,E,F A,B,E,F C,D 113° - 179° F,G,H,J A,B,E A,B,E,F,G,H,J A,B,E,F,G,H,J Note 3: During the summer with higher transient populations and longer evacuation times, a discussion should be held with the OROs regarding subsequent staged evacuation of sheltered zones that are most at risk, but ONLY when safe to do so.
Note 4: Elevation associated with dose projection results (actual or most likely release points), otherwise use lower.
0PEP-02.6.28 Rev. 15 Page 14 of 21 ATTACHMENT 3 Page 1 of 3 PAR Flowchart - EXPANDED Non-Summer (September 1 - May 31)
0PEP-02.6.28 Rev. 15 Page 15 of 21 ATTACHMENT 3 Page 2 of 3 PAR Flowchart - EXPANDED Non-Summer (September 1 - May 31)
General Note: Protective Action Recommendations for Zones C,D, K, L, M, N includes offshore waterways 2 to 10 miles downwind.
KI Recommended for Public Table 1 Table 2 Table 3 Table 4 WIND FROM
[NOTE 4]
HOSTILE ACTION OR IMPEDIMENT OR SHORT TERM RELEASE
(> 2 hr 40 min)
SHORT TERM RELEASE
( 2 hr 40 min)
EVACUATE AFFECTED ZONES (list _______
__________________ )
EVACUATE ZONES 0-2 MILE RADIUS AND 2-10 MILES DOWNWIND SHELTER ZONES 0-2 MILE RADIUS 2-10 MILES DOWNWIND EVACUATE ZONES 0-2 MILE RADIUS 2-10 MILES DOWNWIND SHELTER ZONES 0-2 MILE RADIUS 2-10 MILES DOWNWIND 180° - 195° A,B,G,H,J,K,L A,B,G,H,J,K,L A,B,G,H,J,K 196° - 236° A,B,H,J,K,L A,B,H,J,K,L A,B,H,J,K,L 237° - 271° A,B,J,K,L,M A,B,J,K,L,M A,B,J,K,L,M 272° - 288° A,B,J,L,M A,B,J,L,M A,B,J,L,M 289° - 316° A,B,L,M,N A,B,L,M,N A,B,L,M,N 317° - 327° A,B,M,N A,B,M,N A,B,M,N 328° - 009° A,B,C,M,N A,B,C,M,N A,B,C,M,N 010° - 021° A,B,C,D,M,N A,B,C,D,M,N A,B,C,D,M,N 022° - 038° A,B,C,D,E,M,N A,B,C,D,E,M,N A,B,C,D,E,M,N 039° - 051° A,B,C,D,E A,B,C,D,E A,B,C,D,E 052° - 090° A,B,C,D,E,F A,B,C,D,E,F A,B,C,D,E,F 091° - 112° A,B,C,D,E,F A,B,C,D,E,F A,B,D,E,F 113° - 179° A,B,E,F,G,H,J A,B,E,F,G,H,J A,B,E,F,G,H,J Note 4: Elevation associated with dose projection results (actual or most likely release points), otherwise use lower.
0PEP-02.6.28 Rev. 15 Page 16 of 21 ATTACHMENT 3 Page 3 of 3 PAR Flowchart - EXPANDED Non-Summer (September 1 - May 31)
A. Expanded PARs developed based on:
Approved revised Dose Projection results (includes changes in Meteorological conditions)
Change in plant conditions Information from OROs (e.g., Impediments or status of Evacuation activities)
Environmental Monitoring Results > PAG D. If projected or actual measured off-site dose is > 5 Rem CDE (thyroid), recommend use of KI by the public.
E. PARs should be extended beyond the 10 mile EPZ, as necessary, to where protective action guideline doses (i.e., 1 Rem TEDE or 5 Rem CDE [thyroid]) will no longer be exceeded.
Describe:
Expanded PAR Recommended By:
Radiological Controls Manager:
Time:
Date:
Evacuate A B C D E F G H J K L M N Shelter A B C D E F G H J K L M N
- 2. Mark zones identified on Tables 1, 2, 3, or 4 from the previous page.
Evacuate A B C D E F G H J K L M N Shelter A B C D E F G H J K L M N B. EXPANDED PAR - Evacuation Zones - Include previous identified (Line 1 and any new zones identified on Line 2 or 3)
Evacuate A B C D E F G H J K L M N C. EXPANDED PAR - Shelter Zones - Include previous identified (Line 1 and any new zones identified on Line 2 if not Evacuated)
Shelter A B C D E F G H J K L M N
0PEP-02.6.28 Rev. 15 Page 17 of 21 ATTACHMENT 4 Page 1 of 3 PAR Flowchart - EXPANDED Summer (June 1 - August 31)
0PEP-02.6.28 Rev. 15 Page 18 of 21 ATTACHMENT 4 Page 2 of 3 PAR Flowchart - EXPANDED Summer (June 1 - August 31)
General Note: Protective Action Recommendations for Zones C,D, K, L, M, N includes offshore waterways 2 to 10 miles downwind.
KI Recommended for Public WIND FROM
[NOTE 5 Table 1 Table 2 Table 3 Table 4 HOSTILE ACTION, IMPEDIMENT, OR SHORT TERM RELEASE EVACUATE AFFECTED ZONES (list __________
____________________)
EVACUATION OF PREVIOUSLY SHELTERED AREAS DEFAULT PARs SHELTER ZONES 0-2 MILE RADIUS 2-10 MILES DOWNWIND EVACUATE ZONES 0-2 MILE RADIUS AND 2-10 MILES DOWNWIND 180° - 195° A,B,G,H,J,K,L A,B,G,H,J,K A,B,G,H,J,K 196° - 236° A,B,H,J,K,L A,B,H,J,K,L A,B,H,J,K,L 237° - 271° A,B,J,K,L,M A,B,J,K,L,M A,B,J,K,L,M 272° - 288° A,B,J,L,M A,B,J,L.M A,B,J,L,M 289° - 316° A,B,L,M,N A,B,L,M,N A,B,L,M,N 317° - 327° A,B,M,N A,B,M,N A,B,M,N 328° - 009° A,B,C,M,N A,B,C,M,N A,B,C,M,N 010° - 021° A,B,C,D,M,N A,B,C,D,M,N A,B,C,D,M,N 022° - 038° A,B,C,D,E,M,N A,B,C,D,E,M,N A,B,C,D,E,M,N 039° - 051° A,B,C,D,E A,B,C,D,E A,B,C,D,E 052° - 090° A,B,C,D,E,F A,B,C,D,E,F A,B,C,D,E,F 091° - 112° A,B,C,D,E,F A,B,D,E,F A,B,D,E,F 113° - 179° A,B,E,F,G,H,J A,B,E,F,G,H,J A,B,E,F,G,H,J Note 5: Elevation associated with dose projection results (actual or most likely release points), otherwise use lower.
0PEP-02.6.28 Rev. 15 Page 19 of 21 ATTACHMENT 4 Page 3 of 3 PAR Flowchart - EXPANDED Summer (June 1 - August 31)
A. Expanded PARs developed based on:
Approved revised Dose Projection results (includes changes in Meteorological conditions)
Change in plant conditions Information from OROs (e.g., Impediments or status of Evacuation activities)
Environmental Monitoring Results > PAG D. If projected or actual measured off-site dose is > 5 Rem CDE (thyroid), recommend use of KI by the public.
E. PARs should be extended beyond the 10 mile EPZ, as necessary, to where protective action guideline doses (i.e., 1 Rem TEDE or 5 Rem CDE [thyroid]) will no longer be exceeded.
Describe:
Expanded PAR Recommended By:
Radiological Controls Manager:
Time:
Date:
Evacuate A B C D E F G H J K L M N Shelter A B C D E F G H J K L M N
- 2. Mark zones identified on Tables 1, 2, 3 or 4 from the previous page.
Evacuate A B C D E F G H J K L M N Shelter A B C D E F G H J K L M N B. EXPANDED PAR - Evacuation Zones - Include previous identified (Line 1 and any new zones identified on Line 2)
Evacuate A B C D E F G H J K L M N C. EXPANDED PAR - Shelter Zones - Include previous identified (Line 1 and any new zones identified on Line 2 if not Evacuated)
Shelter A B C D E F G H J K L M N
0PEP-02.6.28 Rev. 15 Page 20 of 21 ATTACHMENT 5 Page 1 of 1 10 Mile EPZ Map
REVISION
SUMMARY
Page 1 of 1 0PEP-02.6.28 Rev. 15 Page 21 of 21 Revision 15:
PRR 2124472 added zone L to first row and zone C to next to last row on Attachment 2 page 2 of 2 Table 1 Shelter Zones, corrected greater than or equal symbol and less than symbol in Tables 1 and 2 of Attachment 3 and moved the zones in line 7 of Table 2 from Shelter to Evacuate and added Note 3, changed "G" to "B" for evacuation zones in Table 2 next to last row.
PRR 2113501 Changed the title of 0PEP-02.1.1 in Step 2.2, PRR 2074469 added (OROs) at the end of Step 5.1.2, reworded Step 5.2 to correct grammar, PRR 2049317 Added Notes to Attachments 1, thru 4 for wind direction elevation to use.
Other: Removed Step 6.3.1 and it's 2 sub steps; modified Attachment 3 page 1 flowchart to include note 3, note 4 and actions for "Do GE conditions still exist" and "Initial 'Staged Evacuation' complete"; added Table 4 to Attachment 3 page 2; added note "3" to Attachment 3 page 3 Step A.2; modified Attachment 4 page 1 flowchart to include note 4 and actions for Do GE conditions still exist; added Table 2 to Attachment 4 page 2. Corrected Note 3 of page 2.
Prepared by Fred Litten